Date post: | 20-Jan-2016 |
Category: |
Documents |
Upload: | sharyl-park |
View: | 215 times |
Download: | 0 times |
Coal Mine ConnectionsCoal Mine Connections
Lessons from ExperienceLessons from Experience
Why are we talking about Coal Why are we talking about Coal mine connectionsmine connections
Because we had a situation where the Because we had a situation where the customer wanted a service that was out of customer wanted a service that was out of our standards and therefore caused our standards and therefore caused confusion and eventually a problem.confusion and eventually a problem.
Here was the planHere was the plan
1.47 mi
LIVINGSTON
PODISH
0.13
mi
0.90 mi
0.50
mi
SUMMIT
JCT.
3.15 mi
ELLSWORTH
CALVIN
JCT.
1.30 mi
0.69
mi
WEIRN.O.
LITTLE
A
25 kVANDREWS
SHAFT
RICHARDSON
0.19
mi
4.71 mi
556.5
25 kV
0.01
mi
3/0
AA
AC
556.
5
3/0
AC
SR
4/0,
1/0
4/0 CU,1/0 CU
LONGFARMSHAFT
0.17
mi
3/0
AC
SR
3/0 ACSR3/0 ACSR
3/0
AC
SR
0.60
mi
3/0
AC
SR
100
ft.
1/0
AL
U
LONG FARM BLEEDER SUBSTATION
U
100
ft.
3/0
AC
SR
CONSTRUCT 100 FEET OF 1/0 AL,UNDERGROUND 25 kV LINE
INSTALL A 25 kV AIR SWITCH AT TAP
INSTALL A 1.5 MVA, 25-4.16 kV PAD-MOUNTEDTRANSFORMER PACKAGE WITH 4 kV METERING 1.5 MVA,
25-4.16 kVPAD-MOUNT
LFB54173
LONG FARM BLEEDER
TAP
LFBT53773
LSMJ-EPJ (400)
What HappenedWhat Happened
The transformer was energized with no load The transformer was energized with no load and the low side arrester failed. The high and the low side arrester failed. The high side fuse failed and launched upwards and side fuse failed and launched upwards and stuck into the roof of the transformer.stuck into the roof of the transformer.
Blown Arrester
Neutral ungrounded
3 CT’s
2 VT’sHigh Side VT’s Grounded
The situation developed because
1. Planning not aware that coal mine wanted ungrounded service at 4160. They were told that this customer want 4160 service nothing was said about ungrounded service
2. Planning issued a plan for 4 wire service
3. Pad mount transformer was shipped with arresters installed, this is not what the T&D manual wants
4. 3 element metering specified, but only 2 VT’s showed up
5. It was a rush job so a decision was made to use 2.5 element metering
6. When the transformer was ready to be energized, the Coal company inspector told our people to remove the ground
7. Our crew was confused and called their boss and he checked
8. The metering people said they would have to change the metering
9. Our crew was told to disconnect the metering, they did by opening the low side metering switches
10. They were instructed to remove the ground
11. They were told to go ahead and energize
12. Arrester failed causing a phase to phase fault and failed the high side transformer fuse
Metering opened
Why did it happenWhy did it happen
Here is the Schematic of how everything Here is the Schematic of how everything was hooked up when energized.was hooked up when energized.
No Ground on Transformer
High side on metering VT’s Grounded for 2.5 element metering
No Ground on Transformer
High side on metering VT’s Grounded for 2.5 element metering
This arrester saw a voltage of 1.5p.u. and failed, when it failed it blew stuff all over the place. This stuff caused a phase to phase fault in the transformer, also when the arrester failed, it would fail in the shorted mode, causing line to line voltage across the VT’s putting them into saturation, which would cause a high current to flow through them
This transformer used Cooper fuses which was an old design as it did not provide positive latching, using the right hand rule the fuse could have been forced out of the holder and the expelled gas would have launch it upwards into the lid. As it would see maximum fault current at this point.
So what do coals mines want?So what do coals mines want?
There are two types of mines we encounter There are two types of mines we encounter on our system.on our system.
Above Ground mines, I like to call them Above Ground mines, I like to call them strip mines.strip mines.
Below ground mines such as QuecreekBelow ground mines such as Quecreek
Above ground mines usually require our Above ground mines usually require our standard service, but below ground mines standard service, but below ground mines are different.are different.
Both above ground mining and below Both above ground mining and below ground mining are govern by the State ground mining are govern by the State Mining Laws. Each State has their own Mining Laws. Each State has their own group that enforces these laws.group that enforces these laws.
www.dep.state.pa.us/dep/deputate/minres/dwww.dep.state.pa.us/dep/deputate/minres/dms/guidelines/ms/guidelines/
Below ground mining operations Below ground mining operations requires special standards from what we requires special standards from what we
are use toare use to Why is below ground so special. Underground Why is below ground so special. Underground
mining deals with methane gas and water. Two mining deals with methane gas and water. Two things that don’t mix well with electric.things that don’t mix well with electric.
For below ground mining there are two For below ground mining there are two componentscomponents
a. Electric that goes underground for operating a. Electric that goes underground for operating equipmentequipment
b. An above ground fan that pushes air b. An above ground fan that pushes air underground for ventilationunderground for ventilation
Lets look at each componentLets look at each component
Above ground air fan.Above ground air fan. If that fan goes off line then the mine must be If that fan goes off line then the mine must be
evacuated immediately. Not easy when you are a evacuated immediately. Not easy when you are a mile or so into a mine.mile or so into a mine.
The operators would like to keep the fan operating The operators would like to keep the fan operating until the end of a shift when the mine is emptied.until the end of a shift when the mine is emptied.
If you have a line to ground fault with a solidly If you have a line to ground fault with a solidly grounded neutral the circuit protection will trip the grounded neutral the circuit protection will trip the fan immediately. But if the fan were to be served fan immediately. But if the fan were to be served from a delta connection then you can have a line to from a delta connection then you can have a line to ground fault and have time to look for the trouble.ground fault and have time to look for the trouble.
Therefore, most operators would like to Therefore, most operators would like to serve there fan from a delta system, so a serve there fan from a delta system, so a line to ground fault does not cause the fan line to ground fault does not cause the fan to shut down and can be corrected not to shut down and can be corrected not immediately, but in a timely manner.immediately, but in a timely manner.
DEP recognizes this and allows either the DEP recognizes this and allows either the fan to be served from a solidly grounded fan to be served from a solidly grounded wye or from a delta connection.wye or from a delta connection.
Most of the fans are in the hundreds of Most of the fans are in the hundreds of horsepower so it requires voltages to horsepower so it requires voltages to operate at 4160 or 2400. operate at 4160 or 2400.
If the mine has a 4160 volt motor they If the mine has a 4160 volt motor they will want to take voltage at 4160 delta.will want to take voltage at 4160 delta.
To give them this delta connection To give them this delta connection requires us to operate the transformer as requires us to operate the transformer as an ungrounded wye.an ungrounded wye.
We have transformers that can be We have transformers that can be connected either 4160 wye or 2400 volts connected either 4160 wye or 2400 volts delta.delta.
However this delta connection is a non However this delta connection is a non standard for us at 4160 volts, so we have standard for us at 4160 volts, so we have to be careful on how we hook it up and the to be careful on how we hook it up and the equipment connected to it.equipment connected to it.
So what does the mines want for So what does the mines want for the surface fanthe surface fan
No ground
Metering 3 wire
Coal mine owns
or
DEP wants this connection between ground grids as they require 4 ohms or less
AP Transformer
Fan and other stuff
So what does the mines want for So what does the mines want for the surface fanthe surface fan
No ground
Metering 3 wire
Coal mine owns
or
DEP wants this connection between ground grids as they require 4 ohms or less
AP Transformer
Fan and other stuff
10 foot min
If arresters are installed they have to be phase to phase rated
So what does the mines want for So what does the mines want for the surface fanthe surface fan
No ground
Metering 3 wire contained in the transformer
Coal mine owns
or
AP Transformer Fan and other stuff
10 foot min
If arresters are installed they have to be phase to phase ratedAs a cost savings for
both us and the coal mine we are using padmounts
They would like us to have a ground ring installed around the padmount with 2 ground rods as a min. If the coal company ever buys the padmount they will have to have a 4 ohms or less resistance.
So what does the mines want for the So what does the mines want for the
deep mine servicedeep mine service
No ground
Metering 3 wire
Coal mine owns
or
DEP wants this connection between ground grids as they require 4 ohms or less
AP Transformer
Zig-Zag Transformer if being served Delta and a grounding resistor
10 foot minIf arresters are installed they have to be phase to phase rated
Grounding resistor to limit fault to 25 amps
Ground Bed <4 ohms
Zig-zag if delta
Neutral ground bed <4 ohms 25ft away, but no more than 100ft from transformer
Insulated neutral
Transformer connections and Transformer connections and voltagevoltage
The highest voltage allowed is 15kV to The highest voltage allowed is 15kV to serve the coal mineserve the coal mine
Delta wye, delta delta, wye delta are Delta wye, delta delta, wye delta are permitted provided a grounding resistor and permitted provided a grounding resistor and a zig zag on delta connections to provide a zig zag on delta connections to provide phase to ground faults limited to 25 ampsphase to ground faults limited to 25 amps
A Wye Wye is not permitted A Wye Wye is not permitted
DEP requires 4 ohms for the ground grid or DEP requires 4 ohms for the ground grid or
less instead of 5 ohms as some standards less instead of 5 ohms as some standards state, because they want to limit the voltage state, because they want to limit the voltage developed to 100 volts at 25 amps through developed to 100 volts at 25 amps through the neutral resister, so that makes the the neutral resister, so that makes the resistance 4 ohms or less.resistance 4 ohms or less.
The isolated ground grid has to be a The isolated ground grid has to be a minimum of 25 feet away from the power minimum of 25 feet away from the power transformer, but no more than 100 ft from transformer, but no more than 100 ft from the power transformer per the federal the power transformer per the federal mining laws.mining laws.
RememberRemember
Any time the low side is not solidly Any time the low side is not solidly groundedgrounded
A. Phase to Phase Arresters must be usedA. Phase to Phase Arresters must be used B. 3 wire metering must be used.B. 3 wire metering must be used. When you do not solidly ground the low When you do not solidly ground the low
side, line to ground loads can not be served. side, line to ground loads can not be served. So station service must be a phase to phase So station service must be a phase to phase connected load.connected load.
What is 5S, 6S, 9S meteringWhat is 5S, 6S, 9S metering
5S or two element metering is for 3 wire 5S or two element metering is for 3 wire systems ie cannot serve line to ground loadssystems ie cannot serve line to ground loads
6S or 2 ½ element metering is for 4 wire 6S or 2 ½ element metering is for 4 wire systems. Not used as a standard any more.systems. Not used as a standard any more.
9S or 3 element metering is for 4 wire 9S or 3 element metering is for 4 wire systemssystems
3 element, 2 VT’s, 2 CT’s
2 ½ element, 2 VT’s, 3CT’s
3 element, 3 VT’s, 3CT’sVT’s connected to ground
VT’s connected to ground
So what was the problem
Neutral not connected
2 ½ element metering used
2.5 element metering caused
neutral to move here
Arrester connected line to neutral was not rated for 1.5 p.u. overvoltage there fore boom
The situation developed because
1. Planning not aware that coal mine wanted ungrounded service at 4160. They were told that this customer want 4160 service nothing was said about ungrounded service
2. Planning issued a plan for 4 wire service
3. Pad mount transformer was shipped with arresters installed, this is not what the T&D manual wants
4. 3 element metering specified, but only 2 VT’s showed up
5. It was a rush job so a decision was made to use 2.5 element metering
6. When the transformer was ready to be energized, the Coal company inspector told our people to remove the ground
7. Our crew was confused and called their boss and he checked
8. The metering people said they would have to change the metering
9. Our crew was told to disconnect the metering, they did by opening the low side metering switches
10. They were instructed to remove the ground
11. They were told to go ahead and energize
12. Arrester failed causing a phase to phase fault and failed the high side transformer fuse
What can be done in the future to try to prevent these occurrences
On all plans specify whether the service is Delta, Wye, or Grounded Wye.
Specify the voltage, both phase to phase and phase to neutral where appropriate.
Create a single line if it is something outside of our standards.
Then if something does fit the plan or changes in the field do not fit the plan, the job should be stopped until it is reviewed by planning and engineering.