City of Greater Geraldton Coastal Hazard Risk Management and Adaptation Plan (CHRMP)
Transcript

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Acknowledgement of Country

Welcome

Mayor

Shane Van Styn

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Welcome & Project Introduction

Project Team - Consultants

Statutory & Strategic Planning

Community Engagement

Coastal Hazard and Risk Baird Australia

Jim Churchill – Project Manager / Senior Coastal Hazard and Risk

TPG+Place match

Cath Blake-Powell – Director/Community Engagement

Mike Davis – Associate Planner

Jessica Black – Senior Community Engagement

Realm

Leo Drynan – Economic Assessment of Adaptation Options

Rhys Thompson – Economic Assessment of Adaptation Options

Economic Analysis

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Welcome & Project Introduction

Coastal Erosion and Inundation Studies

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

• The delivery of the CHRMAP will include:

• Evaluation of the coastal hazard risks identified in the CVS in terms of likelihood and

consequence;

• Identification of adaptation options to mitigate the identified risk; and

• Assessment of the adaptation options identified to select preferred options.

• Community and stakeholder engagement will occur throughout the process to

understand community values, gauge community tolerance of risk, identify adaptation

options to manage risk and understand which options are acceptable.

• This information will be used to meet legislative requirements and plan future monitoring,

development and investments in our coastal areas.

Welcome & Project Introduction

CHRMAP Process

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Hazard Risk Assessment

CHRMAP Process

July – Oct 17

Identify Coastal Issues

Community Consultation

Draft CHRMAP

Public Advertising of Draft CHRMAP

Final CHRMAP

October 17 Feb – April 18 April - May 18 June 18

Welcome & Project Introduction

City will provide updates during this process.

Coastal Adaptation

Oct – Nov 17 Nov 17– Jan 18

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

1. Identification of key coastal infrastructure/assets that hold economic,

social and environmental value;

2. Consequence scale for the identified coastal hazards;

3. Define risk tolerances to the identified coastal hazard risks; and

4. Feedback on proposed adaptation options that could address the risks

(and identify additional).

CHRMAP Workshop Goals

Welcome & Project Introduction

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

CHRMAP Workshop Goals

Welcome & Project Introduction

Workshop One (9am – 12pm)

Coastal zone from Cape Burney to Town Beach.

Workshop Two (1pm – 4pm)

Coastal zone from the Marina to Drummond Cove.

SurveyThe deadline to complete the survey is 8am, Monday 23 October 2017.

www.surveymonkey.com/r/GeroCAP

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Housekeeping

Community Workshop - Agenda

Introductions and Welcome

Project Introduction

Workshop Agenda

Project Background

Task One: Coastal Assets Identification

Consequence Scale Overview

Task Two: Consequence Scale

Short Break

Task Three: Asset Priorities

Preliminary Adaptation Options Presentation

Task Four: Adaptation Strategy

Wrap up and Next Steps

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Community Workshop - Etiquette

Please Consider…

• Let’s keep on topic, specific to the CHRMAP process;

• One speaker at a time;

• You are here so lets all participate and contribute;

• We are all different so lets respect each others views;

• No suggestions are wrong, all ideas/questions will be considered; and

• The more you put in the more you will get back – guaranteed!

Housekeeping

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Community Workshop - Housekeeping

Please Consider…

• Facilities are located…

• Tea and coffee

• Please put your mobile phones on silent or vibrate

Housekeeping

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Community Workshop – Questions and Parking Lot

• Questions that occur to you during the

presentation, please write on the sticky

notes.

• If time permits we will answer these.

• Otherwise if we can’t answer them all,

leave your details and we will follow up

with responses after the session.

Housekeeping

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Context

• Coastal Hazard Risk Management and Adaptation Planning

(CHRMAP) a key focus for Western Australian coastal

communities.

Hurricane Sandy, NJ, US 2012 (www.businessinsider.com)

Sydney ECL2016 (www.abc.net.au/news)

Hembsby, Norfolk UK 2013 (www.bbc.com/news)

CHRMAP Projects WA 2013 – 2018 (DoP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

State Planning Policy SPP2.6

• Key guiding document for coastal planning in Western Australia

• Policy Objectives• sustainable development which recognises the need to balance competing economic, social and

environmental demands.

• Places of unique landscape, scientific and cultural significance should be conserved and managed.

• Ensuring future generations can enjoy the same access to the coast as the present day.

• Coastal Hazard Definition for Future Planning

Source: BMTWhitehill Rd Drummond Cove

Erosion of the Coastline Storm tide Inundation

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Coastal Hazard Risk Management and Adaptation Planning

Guidelines developed by Western

Australian Planning Commission

(WAPC)

• Risk Management approach to

manage coastal hazard risk

• Consult and involve key stakeholders

and wider community

• Consider impacts of Coastal Hazard -

Economic, Environmental, Social,

Cultural.

Adaptation Hierarchy

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Three studies completed by CoGG for Geraldton

Shoreline areas:

1. Point Moore

2. CBD to Drummond Cove

3. Cape Burney to Greys Beach

Studies determine the potential effects of coastal

erosion and inundation based on SPP2.6

requirements.

Coastal hazard assessed across 3 planning

horizons - 2030, 2070 and 2110.

Recommend allowances in foreshore areas for

coastal hazard impacts.

Inundation and Coastal Processes Allowances Studies

Drummond Cove: Coastal Erosion Setback Lines

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

• CHRMAP uses the findings from the studies to

define the coastal hazard for the City of Greater

Geraldton’s coastal foreshore.

• Coastline assessed within 12 coastal

compartments for CHRMAP.

• Coastal inundation and erosion considered

separately.

Inundation and Coastal Processes Allowances Studies

Application of Results

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Focus Area

Cape Burney to

Geraldton

Cape Burney

Point Moore

Tarcoola Beach

Southgate Dunes

Geraldton

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Focus Area

Beresford to

Drummond Cove

Beresford

Drummond Cove

Sunset

Bluff Point

Glenfield

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Inundation and Coastal Processes Allowances Studies

Key Findings

• Coastal Erosion and Inundation hazard will impact a range of coastal assets at

different time scales (Now, 2030, 2070, 2110)

• Key locations for coastal erosion:• Beresford Foreshore;

• Sunset Beach;

• St Georges Beach

• Point Moore (Greys Beach);

• Drummond Cove; and

• Point Moore.

• Key locations for coastal inundation:• Geraldton Town Centre;

• Beachlands;

• Point Moore;

• Chapman River South; and

• Drummond Cove.

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Inundation and Coastal Processes Allowances Studies

Coastal Erosion Hazard Findings

Tarcoola Beach

Beachlands / Mahomet Flats

Southgate Dunes / Cape Burney

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Inundation and Coastal Processes Allowances Studies

Coastal Erosion Hazard Findings

Point Moore Geraldton

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Inundation and Coastal Processes Allowances Studies

Coastal Inundation Hazard Findings

Point Moore

2110 500yr ARI Depth of Inundation

Tarcoola Beach

2110 Inundation Areas – 20yrARI, 100yrARI, 500yr ARI

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Inundation and Coastal Processes Allowances Studies

Coastal Inundation Hazard Findings

Point Moore

2110 500yr ARI Depth of Inundation

Geraldton

2110 Inundation Areas – 20yrARI, 100yrARI, 500yr ARI

2030 500yr ARI Depth of Inundation 2110 500yr ARI Depth of Inundation

2110 = +0.9m

2070 = +0.39m

2030 = +0.07m

Sea Level Rise

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Inundation and Coastal Processes Allowances Studies

Coastal Erosion Hazard Findings

Drummond Cove Glenfield, Sunset Beresford SthBeresford Nth

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Inundation and Coastal Processes Allowances Studies

Coastal Inundation Hazard Findings – 2110 500yr ARI Event

Drummond Cove Glenfield, Sunset Beresford SthBeresford Nth

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Coastal Asset Types

Natural

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Coastal Asset Types

Natural / Environmental Assets Social / Cultural Assets Economic / Physical Assetseg Beaches, dune, flora, fauna eg heritage, meeting places eg roads, buildings, structures

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Questions?

Introductions and Welcome

Project Introduction

Workshop Agenda

Project Background

Task One: Coastal Assets Identification

Consequence Scale Overview

Task Two: Consequence Scale

Short Break

Task Three: Asset Priorities

Preliminary Adaptation Options Presentation

Task Four: Adaptation Strategy

Wrap up and Next Steps

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

TASK ONE: Coastal Assets Identification

1. What are the coastal assets that are important to you?

2. Why is it important to you?

Categorise as:

• Physical/Economic (road, building)

• Natural/Environmental (vegetation or a reserve)

• Social/Cultural (eg walking, meeting place)

work

individually

20min

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Asset Types

TASK ONE: Coastal Assets Identification

1. What are the coastal assets that are important to you?

2. Why is it important to you?

work

individually

20min

Natural

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Assets: Consequence Scale

Lines/Tones On Your Map – What Do They Mean?

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Assets: Consequence Scale

What is Coastal Erosion?

Source: Cardno

Shoreline erosion hazard – ‘Setback’ allowance:

• S1 - current risk of storm erosion

• S2 - historical shoreline movement trends

• S3 - erosion caused by future sea level rise

• Uncertainty

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Assets: Consequence Scale

Source: CardnoDrummond Cove: Coastal Erosion Setback Lines

What is Coastal Erosion?

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Assets : Consequence Scale

What is Storm Surge Inundation?

Storm surge is the rise in the level of the ocean, over and above the regular

astronomical tide, caused by a severe storm such as a tropical cyclone.

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Inundation: 2110 - 500 year ARI Event

Coastal Erosion Setback - 2110

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Inundation: 2110 - 500 year ARI Event

Coastal Erosion Setback - 2110

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Assets : Consequence ScaleConsequence Scale

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Coastal Assets : Consequence Scale

Asset Example No.1: Marine Terrace

Community Workshop

Physical/Economic Asset

Erosion: Moderate

Permanent loss or damage $200k - $2

million

Inundation: Minor

Permanent loss or damage $20k - $200k

Loss of connectivity

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Assets : Consequence ScaleAsset Example No.1: Marine Terrace

What is the Consequence of Erosion & Inundation?

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Coastal Assets : Consequence Scale

Asset Example No.2 Foreshore Reserve and Beach

Community Workshop

Environmental Asset

Erosion: Catastrophic

Permanent loss of flora and fauna - will not recover

Inundation: Minor

Short term loss of flora and fauna - strong recovery

Social Asset

Erosion: Catastrophic

Long term or permanent loss of function >75% of

community affected. Loss of recreation space

Inundation: Insignificant

Minimal short term inconvenience <5% of community

affected

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Assets : Consequence ScaleAsset Example No.2 Foreshore Reserve and Beach

What is the Consequence of Erosion & Inundation?

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Coastal Assets : Consequence Scale

Asset Example No.3: Geraldton Surf Life Saving Club

Community Workshop

Social Asset

Erosion: Catastrophic

Long term or permanent loss of function

>75% of community affected loss of

social venue

Inundation: Minor

Permanent loss or damage $20k - $200k

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Assets : Consequence ScaleAsset Example No.3: Geraldton Surf Life Saving Club

What is the Consequence of Erosion & Inundation?

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Coastal Assets : Consequence Scale

Asset Example No.4: The CBD

Community Workshop

Economic Asset

Erosion: Catastrophic

Permanent loss or damage >$5 millionInundation: Catastrophic

Permanent loss or damage >$5 million

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Coastal Assets : Consequence ScaleAsset Example No.4: The CBD

What is the Consequence of Erosion & Inundation?

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

TASK TWO: Coastal Assets Consequence Scale

Examine the coastal assets you identified in Task 1.

For each asset, determine a consequence of erosion and inundation.

Group Work

40min

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

TASK TWO:

Examine the coastal assets you identified in Task 1.

For each asset, determine a consequence of erosion and inundation.

Consequence Scale

Group Work

40min

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Short Break

Please return to your seats in…

5 minutes

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

TASK THREE: Priority Assets

Re-examine your table’s coastal assets from Task 1.

Use your 5 sticky dots to identify priority assets.

You can spread your dots over five individual assets or

place more than one dot on a single asset.

work individually

10min

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Adaptation Options

Consequence ScaleLocate assets in areas not at risk

Avoid foredune / low lying areas

Retreat over time as coastal

hazard realised

Planning Controls

Building design

Emergency Evacuation Planning

Seawalls and Flood Walls

Beach nourishment

Groynes

Offshore Breakwater

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Adaptation Options: Avoid

Development planning approvals

take into consideration

• Coastal Erosion setbacks; and

• 500yr ARI inundation extents.

No new developments on the

shoreline side of the identified coastal

hazard extent.

Planning Control Examples

Avoid isn’t applicable to existing or historical developments that are at risk.

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Adaptation Options: Planned/Managed Retreat

Eg. notification on title, control of further development, apply easement or planning zones

to allow for rolling change of land use as coastal hazard is realised.

• Time based structures

• Leave assets unprotected

Planning Control Examples

City Asset/ValueRemoval of the Triton Place toilet block

Tourism Asset/ValueTwo part lease to take into account land at risk

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Adaptation Options: Accommodate Inundation

• Set minimum floor levels based on structure type (Dome Café, Batavia Marina

Development)

• Locate development on least hazardous portion of site

Planning Control Examples

• Lower portion of structure flood resistant

materials and designed to withstand forces

• Modify building design to allow for future

relocation of building

Building Design Examples

http://www.coastalconference.com/2012/papers2012/Greg%20Giles%20and%20Heather%20Stevens%20Full%20Paper.pdf

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Adaptation Options: Accommodate/Protect - Erosion

Whitehill Road in Drummond Cove, St Georges Beach

• Maintains beach amenity

• Mitigates further erosion

• Requires sediment source

• Temporary or short term measure

Community Workshop

Beach Nourishment/ Geo Textile Containers Example

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Adaptation Options: Protect - Erosion

• Midalias Beach

• The Foreshore

Community Workshop

Groynes Example

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Adaptation Options: Protect - Erosion

Community Workshop

Beresford Foreshore

http://www.watoday.com.au/

http://www.watoday.com.au/http://www.watoday.com.au/

Erosion Protection - Seawall Example

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

• Many different types, can be

permanent or temporary

• Engineered Rock Seawalls

• Dikes or Levy Banks

www.elitereaders.com/mobile-flood-walls-austria-machlanddamm/

Community Workshop

Adaptation Options: Protect - Inundation

Flood Protection Sea Walls

www.ukflooddefencealliance.com

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

TASK FOUR: Priority Areas Adaptation Ideas

Group Work

20min

Adaptation Strategies

First Focus on:

Geraldton Town Centre

(Coastal Hazard – Inundation)

Then: Your Table’s Priority Location / Asset

(if time allows)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

TASK FOUR: Priority Areas Adaptation Ideas

Group Work

20min

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

TASK FOUR: Priority Areas Adaptation Ideas

Group Work

20min

Adaptation Strategies

First Focus on:

Your Table’s No.1 Priority Location / Asset

Then: Your Table’s No.2 Priority Location / Asset

(if time allows)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

TASK FOUR: Priority Areas Adaptation Ideas

Group Work

20min

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Please watch the City’s Webpage for regular project updates.

SurveyThe deadline to complete the survey is 8am, Monday 23 October 2017.

www.surveymonkey.com/r/GeroCAP

Next Steps

How Can I Be Involved?

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Thank you!

Please take the time to fill out the post workshop survey

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

CHRMAP Adaptation Responses

• Adaptation responses to manage coastal hazard risk are developed using the adaptation hierarchy (WAPC)

Avoid new development within an area of Coastal Hazard

Relocation or Removal of Assets over the planning timeframe

Management Strategies to control the risk (eg Bldg Design, Planning)

Protection of assets (eg seawalls, groynes, sand nourishment)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

Likelihood Probability for ARI Events

Annual Chance of not happpenning 10yrs 20yrs 30yrs 50yrs 100yrs

50 yr 2% 0.02 0.98 18% 33% 45% 64% 87%

100yr 1% 0.01 0.99 10% 18% 26% 39% 63%

500yr 0.20% 0.002 0.998 2% 4% 6% 10% 18%

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

CHRMAP Risk Assessment

• The likelihood of coastal hazard describes the chance of an event occurring in probable terms

• Almost Certain• Likely• Probable• Unlikely

• Recognises likelihood changes over time AND the uncertainty in making future predictions

Almost CertainLikelyPossibleUnlikely

LEGEND: LIKELIHOOD 2070

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

City of Greater

GeraldtonCoastal Hazard Risk Management and

Adaptation Plan (CHRMP)

Community Workshop

Background Information

CHRMAP Risk Assessment

• Risk is a product of Likelihood and Consequence

• The risk assessment identifies coastal risks in highest need of response ie risk level Extreme or High

• Adaptation responses are developed to mitigate risk

• Note it is impossible / impractical to mitigate all risks


Recommended