Unit code Unit code :- CPCCSP3001A,CPCCSP3004A &CPCCSP3003A • Job role :- Helper mason • Out come :- After completing this unit, trainees will be able to apply float and render , restore solid plasterwork and apply trowelled texture coat finishes.
Transcript
Page 1: Coat and finishes c3

Unit code

• Unit code :- CPCCSP3001A,CPCCSP3004A &CPCCSP3003A

• Job role :- Helper mason• Out come :- After completing this unit,

trainees will be able to apply float and render , restore solid plasterwork and apply trowelled texture coat finishes.

Page 2: Coat and finishes c3

Introduction

Name - Rameshwar Lal Jat

Designation -Trainer

Company-Leighton India Contractor Pvt. Ltd.

Page 3: Coat and finishes c3

•Communication skills to:

•Follow instructions

•Read and interpret:

•Documentation from a variety of sources

•Drawings and specifications

•Recognize procedures

•Report faults

•Enable clear and direct communication,

•Use and interpret non-verbal communication, such as hand signals

•Written skills to record results of checks and tests and relevant work completion procedures

•Identifying and accurately reporting to appropriate personnel any faults in tools, equipment or materials

•Respond to change and contribute to workplace responsibilities, such as current work site environmental and sustainability frameworks and management systems

•Teamwork skills to work with others to action tasks and relate to people from a range of cultural and ethnic backgrounds and with varying physical and mental abilities

•Technological skills to:

•Use a range of mobile technology, such as two-way radio and mobile phones

•Voice and hand signals to access and understand site-specific instructions.

Required skills

Page 4: Coat and finishes c3

• Adjusting work activity to maintain quality standards

• Application of product and process knowledge to predict consequences and identify

improvements

• Identifying and applying appropriate safety precautions to safely use equipment, and

shift and handle products and materials

• Identifying and reading manufacturers' product installation procedures and

nominated specifications for mixing adhesives, and fixing and cutting cornices

• Identifying by name and general application paper-faced and handmade cornices

• Identifying faults in materials

• Identifying from workplace information and labels the type and purpose of materials

and potential for health and safety risks for cornices and adhesives

• Requirements to plan own work using a systematic approach to allow for efficient and

safe handling of cornices and safe access to work at heights.

Required knowledge

Page 5: Coat and finishes c3

• Application of product and process knowledge to identify problems and predict

consequences

• Identifying faults in operation of equipment or materials quality

• Identifying from workplace information and labels the type and purpose of materials and

potential for health and safety risks

• Implications on work quality requirements for instruction to be followed

• Manufacturers' product installation procedures and nominated specifications for the work

process

• Names and functions of equipment, components and materials

• Requirements for a systematic approach to planning own work

• Safely use equipment, shift and handle products and materials.

• Plastering tools and equipment types, characteristics, uses and limitations

• Processes for the calculation of material requirements

Required knowledge

Page 6: Coat and finishes c3

PPE Required for masonry work

Helmet Safety jacket Safety Shoes

Safety harness Ear plug Goggles

Page 7: Coat and finishes c3

PPE Required for masonry work

Cotton hand gloves Rubber hand gloves Nose mask

Page 8: Coat and finishes c3

Materials Required for Plastering work

Coarse Sand Fine Sand

Cement

Page 9: Coat and finishes c3

Line Dori

Plumbob Brick Hammer

Tools Required for Masonry work

Right angle

Page 10: Coat and finishes c3

Tools Required for Masonry work

Trowel

Sprit level

Measurements Tape

Page 11: Coat and finishes c3

Plastering

• Plastering helps provide better sound and thermal insulation and fire resistance.

• A good plasterer should have a sound knowledge of materials to use and their characteristics.

• A plasterer should identify the correct materials and their suitability for any given situation.

• A good plasterer should be able to put right any problems with their work and that of others.

Page 12: Coat and finishes c3

Backgrounds

• The background is the surface that your first coat of plaster is applied to.

• The background needs to provide a good bond for your plaster.

• Preparation of backgrounds is key to a good standard of finished work.• If a background is not suitable or prepared well, your plaster will not

stick to it properly.

Page 13: Coat and finishes c3

Suction

• A plasterer needs to check the rate of suction of the background before applying plaster.

• Too much suction can cause the material to shrink or crack and loose adhesion.

• It can be difficult to rule in or get flat because of the loss of water in the material.

• The plaster will not reach its full strength and could fall off.

• Too little suction can cause the material to slip down the wall making it hard to rule in.

Page 14: Coat and finishes c3

High Suction Background

• Can include Aerated Block, old brickwork and softer types of brick.

• Can be wetted before plastering to control suction.

• Can be controlled with two coats of PVA , one very wet to seal and a 50 / 50 mix for adhesion.

• Use direct bond, hard wall, render.

Page 15: Coat and finishes c3

Medium Suction Background

• Can include lightweight aggregate concrete blocks and clay brickwork.

• Generally has good suction.• Make sure is dust and

grease free and clear of mortar snots.

• Can use all plaster products.

Page 16: Coat and finishes c3

Extended chicken mesh

• Can be used inside and outside.

• Flexible so can be curved.• Fixed to wall plates to

provide a key and resist movement.

• If fixing rib lath the ribs should be in contact with and at right angles to the support.

• Needs pricking up coat first.• Use Carlite Bonding.

Page 17: Coat and finishes c3

Composite Background

• A background with a range of materials.

• This can have different rates of suction.

• Use different methods to create a key eg pva, gyp bond, spatterdash.

Page 18: Coat and finishes c3

Preparation• 1. Brush down the background to remove all loose

materials and dust etc. to give a good sound background.

• 2. Remove all mortar snots from joints, internal and external angles.

• 3. Make a key, if needed to the background.• 4. Test the background for suction ( splash some

water on the surface and see how quickly it gets sucked into the background).

• 5. Treat if necessary.

Page 19: Coat and finishes c3

Preparation

• 6. Place drop boards at bottom of wall to catch any material that is dropped. This can then be re used.

• 7. Fix EML to any timber wall and sole plates as necessary. This stops the plaster cracking and falling off the wood.

• 8. Fix any angle beads that are required.• 9.Set up the spot board and stand.

Page 20: Coat and finishes c3

Method of work

• BROAD SCREEDS.• Use on small areas.• Does not give the highest

standard of work but better than freehand.

• Apply screed to corner of wall and rule off.

• Keep depth of material to no more than 11mm.

• Place another vertical screed in other corner and rule off.

Page 21: Coat and finishes c3

Broad Screeds

• Don’t place any screed in between the two end ones.

• Form a horizontal screed top and bottom and rule off using the vertical screeds.

• Using the screeds to rule off, fill in between the screeds.

Page 22: Coat and finishes c3

Dot Screed

• Can be used on long or high walls.

• Use if the finished work has to be absolutely plumb.

• Gives the highest standard for tolerance purposes.

Page 23: Coat and finishes c3

Dot Screed

• 1. Place a dot of material near an internal angle, place a lath in the dot.

• Dot should be about 300mm away from adjoining wall.

• 2. Place a second dot at the bottom of the wall, place a lath into the dot.

• Dots should be about 2.5m apart.• 3. Plumb in the two dots using a floating rule. • 4. Either tap in or bring the wood out until the two

dots are in line.

Page 24: Coat and finishes c3

Dot Screed

• 5. Place another two dots at the other end of the wall.

• 6. Place intermediate dots in the middle of the wall.• 7. Line the intermediate dots through horizontally off

the two perimeter dots.• 8. Join the dots together as the Broad screed system.• 9. Fill in between the screeds and rule off.

Page 25: Coat and finishes c3

Finishing

• The finish coat provides the final, smooth coat for decoration.

• Generally not more than 3mm thick but can be up to 5mm.

• Always applied in two coats for the best finish result.• If matching to a lime plastered surface the finish used

will be lime putty / fine sand mix.• Finish coats should not be over trowelled as this can

prevent the paint sticking to it.

Page 26: Coat and finishes c3

Plastering work

Page 27: Coat and finishes c3

Plastering

Page 28: Coat and finishes c3

Plastering work

Page 29: Coat and finishes c3

Plastering work

Page 30: Coat and finishes c3

Nero plastering

Page 31: Coat and finishes c3

Plastering work

Page 32: Coat and finishes c3

Between wall and ceiling

Page 33: Coat and finishes c3

Between door frame and window

Page 34: Coat and finishes c3

Above the door frames

Page 35: Coat and finishes c3

Around the fireplace

Page 36: Coat and finishes c3

Scratch coat begins

Page 37: Coat and finishes c3

Scratch coat finished

Page 38: Coat and finishes c3

A finished ceiling

Page 39: Coat and finishes c3

Finished walls

Page 40: Coat and finishes c3

Method of work

• This is the most commonly used method of work for skimming.

• 1. first coat is the scratch coat.

• 2. each stroke should overlap the previous one.

• 3. fill any hollows, joints etc. with the scratch coat.

Page 41: Coat and finishes c3

Trowel

• 4. Once scratch coat has picked up – apply laying down coat.

• 5. this should be slightly tighter than scratch coat.

• 6. When laying down coat has picked up enough, apply first dry trowel.

• 7. Trowel twice more with just enough water to lubricate the trowel and to work the plaster.

Page 42: Coat and finishes c3

Trowel

• Any hollows, marks etc. should be filled with the first trowel (fat). Any later than this the fat will be too watery and has no strength.

• 8. Clean angles out at final trowel and use brush to clean angles and beads.

• 9. Cross trowel at right angles to trowelling strokes to remove any water or fat marks.

• 10. Clean skirting line of excess plaster material (lips)

Page 43: Coat and finishes c3

TROWEL,FLOAT,TROWEL

• This method is useful on uneven backgrounds.• 1. Apply scratch coat with trowel.• 2. Apply second coat using a float.• Because the float is more rigid than a trowel, it will

straighten out any irregularities in the floating coat.• 3. When the second coat has picked up, apply thin

laying down coat with the trowel.• 4. Trowel the work as before.

Page 44: Coat and finishes c3

Beads

• Float ( angle ) bead.• Used to form external

angles.• Galvanised or stainless

steel.• Fix using dabs of material.• Need to be plumb, level and

straight along their length.• Make sure wings are behind

finished edge.

Page 45: Coat and finishes c3

Stop Bead

• Reinforces and finishes edge of plaster where no other material meets it.

• Can be used to finish plaster if butting up to another material if there is no cover being used eg. No arcitrave.

Page 46: Coat and finishes c3

Features Bead

Used to form shadow gaps along skirting board.

Page 47: Coat and finishes c3

Movement Bead

• Fixed over any movement joints in the background to prevent cracking of the plaster.

• Fix with dabs.

• Can be formed with two back to back stop beads and mastic filler.

Page 48: Coat and finishes c3

Thanks ANY Questions