of 43
COMPARISON BETWEEN PWD
203A (REV. 1/2010)&PWD 203 A
(2007)
Prepared By:
Nurfidatul Ema bt Saaidin
Bsc (Hons) QS UiTM
Penolong Pengarah Kanan (Ukur Bahan)
1
Hanawati bt. Hashim
Bsc (Hons) QS UiTM
Penolong Pengarah Kanan (Ukur Bahan)
COMPARISON BETWEEN PWD 203A
(2007) / PWD 203A (REV. 1/2010) (CONTD)
PWD 203A (Rev. 1/2010) consist of 81 clauses compared with PWD 203A (Rev. 2007) with only 78 clauses.
Additional 3 new clauses, pertinent ones being:
i. Events & Consequences of Default by the Government (Cl. 55)
ii. Safety At The Site (Cl. 68)
iii. Advance Payment (Cl. 69)
Additional of sub-clauses under clause 12 & clause 40
1.0 INTRODUCTION
1.1 Background
The JKR.PWD Forms were last revised in 1983: almost a quarter of
century ago.
Since then, numerous changes have occurred legally and in practice.
The Forms became anachronistic and out of tandem wit
contemporary practice
Steps were initiated a number of years ago to revise these Forms: a
process formally approved by the AGs chambers
These resulted first in the JKR /PWD Forms(Rev.2007) which were
officially launched in 2008
These new Forms, were further revised with the JKR/PWD
Forms(Rev.1/2010) and officially launched on 24th June 2011
Current, these are the Forms that have to be used for all Public
Sector Projects and apparently for other applications involving
statutory bodies and the like.
1.2 FORMS REVISED
For Traditional General Contracts
For Package Deal Types Of Contrtact
Old Forms New Form Application
1. JKR 203A(Rev.83) JKR 203(Rev.1/2010) COC for BQ Contracts
2. JKR 203(Rev.83) JKR 203(Rev.1/2010) COC for Contracts based
on Drawings &
Specifications
3.JKR 203N(Rev.83) JKR 203N(Rev.1/2010) COC for NSC where Main
Contract is based on JKR
203 &203A
4.JKR 203P(Rev.83) JKR 203P(Rev.1/2010) COC for nominated
supplier where Main
Contractor is based on JKR
203&203A
Old Forms New Form Application
PWD DB/T(2002 Edn) PWD DB(Rev.1/2010) COC for Design & Build
Contract
Old Form New Form Change
Rev.2007 Rev.1/2010
56 78 81 Additonal 22
Clauses (3)
1.3 NUMBER OF CLAUSES JKR 203A
JKR 203
JKR DB
Old Form New Form Change
Rev.2007 Rev.1/2010
56 78 81 Additonal 22
Clauses (3)
Old Form New Form Change
Rev.2007 Rev.1/2010
62 76 79 Additonal 14
Clauses (3)
Old Form New Form Change
Rev.2007 Rev.1/2010
37 50 50 Additonal 13
Clauses (3)
JKR 203N
JKR 203
Note: For the JKR 203N, the clause 41.0 in the Rev.2007 Forms has been
deleted and a new Clause 5.0 added in the Rev. 1/2010 Form.
Old Form New Form Change
Rev.2007 Rev.1/2010
37 37 37 No Change
COMPARISON BETWEEN PWD 203A
(REV. 2007) / PWD 203A (REV. 1/2010)
(CONTD)
PWD 203A (1/2010)
Consist only of 1 Addendum
- Termination on Corruption.
PWD 203A (2007)
Consist only of 1 Addendum
- Termination on Corruption.
Addendum to COC
COMPARISON BETWEEN PWD 203A (REV.
2007) / PWD 203A (REV. 1/2010) (CONTD)
PWD 203A (Rev. 1/2010)
Consist of 1 Sp. Provision - Variation Of Price (Performance Bond, Advance Payment excluded as Sp. Provision)
PWD 203A (Rev. 2007)
Consists of 3 Sp. Provisions
(Performance Bond excluded as Sp. Provision)
Special Provisions to COC
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
1.0 Definitions And Interpretation
1.1 : Definitions
1.2 : Interpretation
1.0 Definitions And
Interpretation
2.0 Contract Period
Clearly define the contract period, D/Possession and
D/Completion.
2.0 Contract Period
3.0 The S.O and S.Os Representative
3.1: Duties of S.O and S.Os Representative 3.2: S.Os Representative 3.3: S.Os Authority to Delegate
3.0 The S.O and
S.Os Representative
4.0 S.Os Right to Take Action
4.0 S.Os Right to Take Action
Difference
5.0 S.Os Instruction Must be in writing Variations, discrepencies ,in contract, removal of mat. from site ,defect work, others. 5% on-cost charges
5.0 S.Os Instruction 9
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
10
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
6.0 Scope of Contract
-Construct and complete,using
materials,goods
and workmanship,quality as specified in
accordance specified making good
defects
- Making good defects
- Poor governing
consequential works under sub clause 6.2
6.0 Scope of Contract
Difference
7.0 Contract Sum
Stipulates the contract sum.
7.0 Contract Sum
8.0 Contract Documents
8.1 : Documents required in 2 sets, one
original with S.O. and contractor
8.2 : S.O will issue instruction regarding any
discrepancies in the contract document.
8.0 Contract Documents
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
11
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
9.0 Representation, Warranties and Undertakings of the
contractor.
9.1 : Representation and warranties.
Listing out the requirements of a contractor before he enters
into a contract with the government, among others,
registered with CIDB, PKK, ROC, technically and financially
competent, no legal litigation, arbitration, tax claim, dispute
9.0 Representation,
Warranties and
Undertakings of
the contractor.
10.0 Obligation of the contractor
Obligation of the contractor:
- construct, complete, test and commission
-comply with all contractual requirements,
-Protect governments interest, provide qualified staffing and workers, supervision, making good defects etc.
-Carry out any other obligations and responsibilities under
this contract.
10.0 Obligation of the
contractor
Difference
11.0 Inspection of Site
Contractor must visit the site, take note of all risk involved,
access roads, working constraints, etc., especially factors
with cost implication. Information given in document may not
be conclusive, may not relieve the contractor of his
obligation under the contract.
11.0 Inspection of Site
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
12
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
12.0 Programme of Work.
Within 14 days from LA, contractor must submit his working
programme to the S.O. for approval.
Need to be adjusted/modified during the construction if
necessary or when EOT is given under the contract.
12.0 Programme of
Work.
Difference
13.0 Performance Bond/ PGB
-5% of the C/Sum,valid until 12 mths after DLP/CMGD
whichever is earlier, failing which, WJP will apply.
-WJP is 10% deduction made on every progress payment
s,up to a max. of 5% C/Sum.
-50% of WJP may be released upon CPC, at the discretion
of S.O. Any claims made during construction, contractor will
be required to top up value at any time must be 5% of
C/Sum.
13.0 Performance Bond/ PGB
14.0 Indemnity in respect of personal injuries and damage to
property.
It is the duty of the contractor to keep the government (and
agents) indemnified against all manners of claims & actions
pertaining to works on site.
14.0 Indemnity in
respect of personal
injuries and
damage to
property.
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
13
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
15.0 Insurance against personal injuries and damage to property.
-Effect and maintain insurance to cover his liabilities
-Bear the excess amount as stipulated in Appendix
-Period of cover until CMGD.
-In case of failure, the Govt may extent the insurances on
behalf of the contractor, the cost of which shall include 5%
(on-cost charges).
-Cancellation of insurance is made 30 days after receipt of
notice by the government.
-Where claims exceed insured amount, the surplus shall
be borne by contractor.
-It stipulates a notification procedure and obligation the
contract to ensure a mandatory procedure is followed any
cancellation process
-It improses a positive duty on the contractor to ensure
that any insurance cover is not vitiated or rendered void or
voidable.
15.0 Insurance against personal injuries and damage to property.
16.0 Indemnities to the government in respect of claims by work men.
16.1 : Workmen Compensation.
Provides coverage for the Govt and officers against
claims by any workman.
16.0 Indemnities to the government in respect of claims by work men.
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
14
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
17.0 Employees Social Security Act 69 (5% on cost-charges) 17.1 Register with SOCSO 17.2 Contribution to SOCSO 17.3 Default in complying with SOCSO
17.0 Employees Social Security Act 69
18.0 Insurance of work
- Effect and maintain insurance to cover against
loss and damage by fire, lightning,
-Bear the excess amount as stipulated in Appendix
-Period of cover until completion of the works.
-In case of failure, the Govt may extent the
insurances on behalf of the contractor, the cost of
which shall include 5% (on-cost charges).
-Cancellation of insurance is made 30 days after
receipt of notice by the government.
-Where claims exceed insured amount, the surplus
shall be borne by contractor.
-It stipulates a notification procedure and obligation
the contract to ensure a mandatory procedure is
followed any cancellation process
18.0 Insurance of work
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
15
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
19.0 Setting out
Contractor is responsible over proper setting out and
for the correctness of positions, levels, dimensions &
alignments. In the event of any error, the contractor
shall rectify at his own expense said errors to the
satisfaction of the S.O.
19.0 Setting out
20.0 Unfixed materials and goods.
- Materials delivered to site cannot be removed
without the consent of the S.O.
- Upon payment, the material & goods become the
property of the GOVT but still remains the
responsibility of the Contractor.
20.0 Unfixed materials and
goods.
21.0 Compliance with the law
- Contractor must comply with any law, regulation or
bye-law that constitutes the current Statutory
Requirements.
- In the event of any change or amendment, the
contractor must obtain the written instruction from
the S.O. so as to enable the consideration of such
variation.
21.0 Compliance with the law
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
16
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
22.0 Cl. 22.0 : Design 22.1 : Design Liability - As requested by Government, NOT proposal from contractor. - Allows stand alone design by the contractor which must be suitable, functional, safe & compatible with the existing design supplied by the Govt.
- This clause emphasizes the contractors liability in ascertaining that his stand-alone design has been undertaken, approved &
endorsed by a competent & registered
professional.
- Contractor to be fully responsible.
-Contractor to provide design G.Bond for the parts of
designed covers incidental issues such as the
amount, duration to cover, conditions of involving,
default provisions.
22.2 : Design Guarantee Bond
- Contractor is to provide a bond equal to 5% of
the said component of works and submitted
once CPC is issued.
- It must have a validity of 5 years.
22.0 Cl. 22.0 : Design
Difference
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
17
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
23.0 Employment of Workmen. 23.1 : Workmen Restricted to Msian citizens unless proven unavailable. Applies to sub-contractors.
23.2 : Compliance Employment
Act 55 (PERKESO) 23.3 : Days and hours of working
Approval for overtime must be
obtained from S.O. the cost borne
by the contractor.
23.4 : Wages Books and Times Sheets.
23.5 : Default in payment of wages.
Any claims by workmen filed to Dept. of
Labour can be paid out by S.O. to be
deducted from monies due to contractor.
23.6 : Discharge of workmen.
S.O has the right to remove from site any
workman he deems incompetent.
23.0 Employment of Workmen.
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
18
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
24.0 Variation
Definition of variation:
A change in the contract Document arising from the alteration or
modification of the design, quality or
quantity of the Works; including
addition, omission or
substitution/removal from site. There is a cross reference to sub-clause 22.1
the effect of the SOs approval of the contractors design.
24.0 Variation
25.0 Valuation of variation
Contract Rates (of similar character or
similar conditions).
Fair Rates (of differing nature or
differing conditions).
Pro-rata Rates
Day work + 15%
25.0 Valuation of variation
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
19
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
26.0 Bills of Quantities
- The quality & quantity from the BQ forms the
basis of the Contract Sum.
- The SMM (ISM) & CEMM (IEM) stipulates that
quantity
is considered fixed unless stated as provisional - Error in description or quantity shall be rectified &
adjustment made to Contract Sum.
- S.O.s right to rationalization - Percentage adjustment
26.0 Bills of Quantities
27.0 Measurement of work
Outlines the method to be used in measurement of
variation & provisional quantities to be carried out by
contractors agent & S.O. during joint valuations.
27.0 Measurement of work
28.0 Payment to contractor and interim certificate. - Payment to be made monthly or as stipulated by S.O. - Only 1 payment is allowed without document contract. - Payment of material by NSS can be made up to 100%. -Material delivered TO & ADJACENT to site, not prematurely delivered.
28.0 Payment to contractor
and interim certificate.
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
20
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
29.0 Adjustment of Contract Sum Increase or decrease of contract sum thru variation or others must be certified by S.O. / Representative
29.0 Adjustment of
Contract Sum
30.0 Fluctuation of price
Details of V.O.P. is still explained under (Special
Provision)
30.0 Fluctuation of price
31.0 Final Account and payment certificate
- 3 months after CPC, all claims complete with
details/supporting documents must be submitted to
the S.O.
- Otherwise the S.O. will proceed with the preparation
of Final Account using current info and its issuance 3
months after DLP or CMGD.
- Contractor to submit Statutory Declaration to the
Govt.
31.0 Final Account and
payment certificate
32.0 Effect of S.Os Certificate
No certificate of the S.O. under any provision shall
release the contractor from his obligations under this
contract.
32.0 Effect of S.Os Certificate
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
21
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
33.0 Deduction from money due to contractor
Govt./S.O. is entitled to deduct money owed by the
contractor through other contracts where both are parties
to it.
33.0 Deduction from
money due to
contractor
34.0 Prime Cost/Provisional Sum
Adjustment of Prime Cost/ Provisional Sum allowed in
contract and that of the actual amount must be carried
out.
Provisional Sum can be converted to Prime Cost Sum
when the contractor will be doing the NSC works but he
waivers his right for Profit and Attendance.
34.0 Prime
Cost/Provisional
Sum
35.0 Materials, Goods and Workmanship Additional testing instructed by S.O. that incurs additional cost will be paid unless the results show that the work, materials & goods are not in accordance with the contract.
35.0 Materials, Goods and Workmanship
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
22
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
36.0 Inspection & Testing of Materials, Goods & Equipment.
All cost involved with Inspection & Testing will be borne by the contractor except additional tests as instructed by
the S.O. (depends on the
results/outcome of said tests).
36.0 Inspection & Testing
of Materials, Goods &
Equipment.
37.0 Constructional Plant, Equipment, Vehicle & Machineries. Arrangement pertaining to bringing in equipment & machineries into Malaysia is solely the responsibility & obligation of the contractor. He is to deal directly with the relevant authorities and shall furnish all such documentation & approval to the S.O. when required. All cost arising from this is to be borne by contractor.
37.0 Constructional Plant, Equipment, Vehicle & Machineries.
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
23
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
38.0 Possession Site
Work cannot commence without
Performance Bond/Insurances. For
purposes of starting work, receipts
without policies are acceptable.
Delay (whole or in part)
- < 90 days EOT 43.1 (g) and not entitled to claims. Delay (whole) > 90 days - Contractor agreed to proceed later (entitle to EOT & NO CLAIM) or, - Contractor terminate the contract Delay (in part) > 90 days - Contractor agreed to proceed later (entitle to EOT & NO CLAIM) or, - request SO to omit that part. (If SO refuse, entitle to claims)
38.0 Possession Site
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
24
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
39.0 Completion of Work Contractor to notify S.O that work is completed within 14 days, S.O to inspect and issue CPC. What is practical completion? a) Work completed as specified in contract. b) Government have full, proper and beneficial use
of the work for its intended purpose. c) Passed T & C d) Fit for occupation e) Essential services (external work)
39.0 Completion of
Work
40.0 Damages for Non-Completion
S.O is required to issue Notice to the contractor before
LAD is imposed (no time frame to notice) as a
proclamation of his intention.
40.0 Damages for Non-
Completion
Difference
41.0 Sectional Completion
Involves different Completion Dates for ascertained
portions of work as stipulated in the Appendix where the
EOT, CPC, LAD and DLP will also be considered
separately except Insurances, PB, Final Payment.
41.0 Sectional
Completion
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
25
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
42.0 Partial Occupation/ taking over by government. Govt with the consent of contractor shall take possession & occupy the completed component of works. Certificate of PO will be issued, DLP will start from the day of handing over followed by CMGD. LAD amount will be reduced proportionately corresponding to the value of said component. Value & period of insurances remain the same.
42.0 Partial Occupation/ taking over by government.
43.0 Delay & Extension of time Cl. 43(c) Suspension of work under Cl. 50 Reasons: EOT 43 (a) (j) total: 10 Highlight:- -Delay is not brought about by delay of non-performing NSC. -Contractor has proven he has mitigated the delays. -Does not constitute failure on part of contractor.
43.0 Delay & Extension of time
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
26
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
44.0 Claims for loss and expenses
Claims arising from delay (EOT) due to:-
43.1 : (c) Suspension of Works (d) S.O. instructions & neighboring disputes
(e) S.O. instruction under Cl. 5 (f) delay caused by S.O (h) delay by 3rd party appointed by Govt.
44.0 Claims for loss and
expenses
45.0 Investigation by government and other persons
in case of accidents, failure or other event.
Allows 3rd party to investigate where the
contractor is to provide full cooperation,
assistance & facilities as may be required.
45.0 Investigation by
government and other
persons in case of
accidents, failure or
other event.
46.0 Access for work
S.O/ Rep or 3rd party appointed by Govt must be
given access to site, fabrication factories,
warehouses, etc related to material & goods to be
used in project.
46.0 Access for work
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
27
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
47.0 Sub-Contract or Assignment
Contractor must obtain the consent of S.O. before
sub-contracting the work. Contractor still fully
responsible over the contract & the default of his
sub-contractors.
Assignment of contract or part is not allowed
except for banks/institutions as consented by the
S.O.
47.0 Sub-Contract or
Assignment
48.0 Defects After Completion No On-Cost charges
- In case of failure to rectify by Contractor, S.O.
can appoint 3rd party where the cost of rectification
plus 10% on cost charges will be claimed from the
contractor.
-Diminution in value of Defect work
-Certificate of Making Good Defects.
48.0 Defects After Completion
No On-Cost charges
DLP (12 Mths)
14 Days
3 Mths
CMGD Completion
Date
Final list
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
28
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
49.0 Unfulfilled Obligations
Although the CMGD has been issued, contractor
remains liable to fulfill all obligations incurred prior
to the issue of said certificate.
49.0 Unfulfilled
Obligations
50.0 Suspension of Works
50.1 : Suspension and Resumption To overcome
problems arising from PBT & funding.
Officer named can issue instruction to suspend work.
Contractor to continue with his other obligations
including site security, repair of damages and show
initiative in cutting costs within said period.
50.2 : Extension of Time Contractor can apply for EOT
Cl. 43(c).If suspension exceed 12 months mutual
termination can be considered.
50.3 : Consequences of Mutual Termination Contractor
paid up to works carried out and
no claims made to PB
50.0 Suspension of Works
Difference
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
29
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
51.0 Events and Consequences of Default by Contractor 2 termination scenarios:
51.1.Default of Obligation by Contractor
-Failure to start work within 2 weeks of L.A (new)
-Suspend or abandon work
-Failure to proceed regularly & diligently
-Failure to execute work in accordance to contract
-Persistently/continuously neglects to carry out obligations
-Failure/refusal to comply to S.O.s instructions -Failure to comply with Cl. 47 (Sub-Contract)
The named officer will issue a 14-day notice, failure of which will
effect termination proceedings.
Implications of termination will be similar to Cl. 51 of the old COC.
Contractor must vacate site and Govt will seize PB/ WJP and
initiate retendering & claim of completion cost.
51.2. General Default
- General default includes contractors bankruptcy, winding up orders & court instruction to freeze contractors asset. - Govt can terminate contract by first issuing a 14-day notice.
- Similar in implication with Cl. 51.1
Contractor must vacate site and Govt will seize PB/WJP and
initiate
retendering & claim of completion cost.
51.0 Events and
Consequences of
Default by
Contractor
Difference
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010) (CONTD)
30
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
51.0 Events and Consequences of Default by Contractor (contd) Stop Work Carry out protective work Remove personnel Vacate site Terminate his sub-contractors Return all plans/documents etc Pay losses/damages to the Government.
51.0 Events and Consequences of Default by Contractor (contd)
52.0 Termination on National Interest
What constitutes National Interest?
Must not imply that the Govt is trying to be
relieved of its contractual obligations &
liabilities. (PBT is not national interest and
national security cannot be compromised!).
Govt will not seize Bond upon
termination.Contractor will be paid whatever
works carried out without claims made to the
PB.
Contractor stop work/remove/personnel/vacate site
52.0 Termination on National
Interest
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
31
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
53.0 Termination on Corruption
If the contractor, his personnel or sub-
contractors is proven guilty of corruption
relating to the Works, the contract may be
terminated after notice has been issued.
PB will be forfeited and claim on completion/
retender cost will be made (Cl. 51.1)
53.0 Termination on
Corruption, unlawful &
illegal activities
Difference
54.0 Payments Upon Termination
If termination is due to Cl. 50 (Suspension of
Works) or Cl. 52 (Termination on National
Interest), payment to contractor shall be:
a)Works carried out until date of termination.
b)Inclusive of partly completed works
c)Cost of materials/goods reasonably and
has/will be
delivered to site.
d)Expenses reasonably incurred by contractor in expectation of completing the
works.
e)Costs involved in handing over the project
back to the Govt.S.O to prepare and issue a
Final Account to the contract.
54.0 Payments Upon
Suspension
&Termination On
National Interest
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
32
Claus
e
JKR 203A Rev 2007 Claus
e
JKR 203A Rev. 1/2010
55.0 Certification of Termination Costs.
To be prepared upon termination,
taking into consideration the following:
i) Payments made to contractor
ii. 3rd party payments to complete works
iii. Other costs related to completion
10% On- Cost Charges
55.0
Events & Consequences Of Default by
The Government
(new clause)
Difference
56.0 Surviving Right
In the event of termination, liabilities of both
parties within the contract period will still
stand.
56.0 Certification of Termination Costs.
57.0 Effect of Force Majeure
A situation in which both Govt & Contractor are
unable to fulfill their obligations under
contract e.g.
war, riot, earthquake etc. Contract will be
terminated
with mutual agreement by both parties where
neither
will be entitled to any claims.
57.0 Cl. 57.0 : Surviving Rights
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
33
Clause JKR 203A Rev 2007 Clause
JKR 203A Rev.
1/2010
58.0 Site Agent and Assistants
Contractor to employ a competent, efficient suitability
qualified site agent, able to receive instructions from S.O
on site.
58.0 Effect of Force Majeure
59.0 Nominated Sub-Contractor and Nominated Supplier
S.O shall call tenders for items under Provisional Sum or
P.C sum in the contract. Contractor may object
nominations with valid reason. S.O may appoint sub
contractor and enter into a direct contract by way of
omission or instruct M/Contractor to execute the works.
59.0 Site Agent and
Assistants
60.0 Payment to NSC and/ NS
Ensure direct payments to NSC.No Deed of assignment
is needed.
60.1 SO shall obtain tenders for NSC/NS in respect the PCS/PS are included in BQ.
- Contractor shall on the written insruction by the
SO enter into such sub contract with the WS/NSC
60.0 Nominated Sub-
Contractor and
Nominated Supplier
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
34
Claus
e JKR 203A Rev 2007 Clause JKR 203A
Rev. 1/2010 61.0 No Liability of government to NSC and NS
There is no warranty of contract between
government and NSC.
61.0 Payment to NSC and/
NS
62.0 Responsibility of Contractor to NSC and NS Contractor is fully responsible over NSC, he may terminate the NSC with consent from S.O. and may appoint a new NSC at no extra cost to the government.
62.0 No Liability of government to NSC and NS
63.0 Intellectual Property Rights
Copyright and proprietary rights ,related to the Works,
shall be the property of Government. Contractor must
indemnify Government from all claims. if any.
63.0 Responsibility of Contractor to NSC and NS
64.0 Antiquities
All discovery of objects of interest or value during
construction shall be the absolute property of the
Government. Contractor to inform S.O. immediately who
in return will issue instruction as what is to be done.
Contractor will be reimbursed
64.0 Intellectual Property
Rights
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
35
Clause JKR 203A Rev 2007 Clause JKR 203A Rev. 1/2010
65 Arbitration
Both parties can now refer any disputes
toArbitration.
65.0 Antiquities
66 Notices Notices shall be effected by; i. Hand delivery or courier,acknowledge
receipt.or ii. Leaving notices at the registered
address in the contract or iii. Registered post,deemed to have
received, 7 days from date of posting.
Onus on Contractor to inform of any change in address.
66.0 Arbitration
67 Amendments
No amendments to be made to this
agreement unless made by mutual consent
by way of a supplementary agreement.
67.0 Notices
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
36
Claus
e JKR 203A Rev 2007 Clause JKR 203A
Rev. 1/2010 68.0 Confidentiality
Contractor must not disclose to third party all matters
pertaining to the contract unless;
- to the bank/financial institution ,raising funds.
- to the consultants appointed for the project.
- as required by law in the country.
68.0 Safety At Site
Difference
69.0 Stamp duty
Now, Contractor is required to pay for all stamp duty
charges.
69.0 Advance Payment
Difference
70.0 Severability
73.0 Severability
71.0 Waiver 74.0 Waiver
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
37
Clause JKR 203A Rev 2007 Clause JKR 203A Rev.
1/2010
72.0 Laws applicable
75.0 Laws applicable
73.0 Successors Bound 76.0 Successors Bound
74.0 Epidemics and medical attendance 77.0 Epidemics and Medical Attendance
75.0 Technology Transfer 78.0 Technology Transfer
76.0 General duties and Performance Standard
-Maintain site clean and sanitary condition
-Comply will all requirement of the
government health and sanitary authorities.
79.0 General duties and Performance Standard
77.0 Restriction on imported materials and
goods
80.0 Restriction on imported
materials and
goods
78.0 Time
81.0 Time
COMPARISON BETWEEN PWD 203A (2007) / PWD 203A (Rev. 1/2010)
(CONTD)
OTHERS
Appendices
Addendum
Special Provisions
39
THANK YOU
40
Clause Differences
4.0
6.0
Clause 4.1(a) is replaced to sentence in clause 4.1(b)
Clause 4.1(b) is replace to sentence 4.1(a) and provisions 40, 43 and 65 has been deleted
and addition of provision 57 and 66 in this clause.
Additional of term in accordance with best industry practice.
Word must replaced by shall
10
COC Rev. 2007
COC Rev. 1/2010
Clause 10.0(a) mentioned the contractor need to comply the works accordance to the
specification, contract dwgs, and other documents specified in contract.
12
COC Rev. 2007
COC Rev. 1/2010
New sub provision 12.1(a), (b) The provision specified the need of contractor to submit
the Work
Programme to the SO that shows detail activities of wk, methods of
construction proposed to adopt.
'New provision 12.2 (i), (ii) & (iii), It stipulates define periods for the submission and
approval of the programme plus consequences for the SOs default. (to approve or reject or request further informations to clarify on the Work
Programme submit by the contractor)
'New Provision 12.3, 12.4, 12.5 requires the contractor to resubmit the Work
Programme if request for. The submission to and approval by the SO does
not relieve the contractor of any his responsibilities under the contract.
69
COC Rev. 2007
COC Rev. 1/2010
New Provision regarding the value of advance payment, conditions to be
followed by the contractor & deduction of advance payment to be made in
interim certificates.
41
Clause Differences
22.1 (a)
22.1(b)
22.1(c)
22.2(a)
22.2(b)
22.2(c)
22.2(d)
COC Rev. 2007
COC Rev. 1/2010
Term intergrates has been added.
A need of contractor to submit the related particulars ie. Dwg, specs, calculation &
other doc. Pertaining to stand alone design.
Rephrase of clause 22.1 (c) & (d). The contractor shall be fully responsible and
guarantee the Govn. Of the Stand Alone Design, integration, execution of the works,
material and workmanship for the works are independent from any fault, suitable,
functional, safe & compatible with Govn's requirement.
'additional term - 'stand alone 'The Design Guarantee Bond Act as a security for the contractor's obligation and
warranties which valid for a period of 5 years from the date of CPC.
'additional term 'imperfection, shrinkage' due to defects in the stand alone design.
'the Govn. has the right to claim from PB the sum of equal to 5% of the value of the
said part of the works or such part thereof as maybe demanded.
New clause The contractor need to extend security if the DGB were to expire.
42
Clause Differences
40.0
40.2
40.3
40.4
COC Rev. 2007
COC Rev. 1/2010
Few sentences related to this provision has been deleted
Provision is improved by mentioned the right of Government to terminate the
contract and recover LAD from the contractor from any money due/become
due/ form Performance Bond/ as a debt due.
New Provision related to LAD that is amount of loss which Government will
suffer because of breach of contract by the contractor.
New Provision which not relieve the contractor from his liabilities and
obligations under the contract even though deduction such LAD has been
made.
50
COC Rev. 2007
COC Rev. 1/2010
The term 'officer named in the appendix' has been replace to SO.
51.1 (a) (ii)
51.2(b) (ii)
COC Rev. 2007
COC Rev. 1/2010
The need to fill in the no of days of work been suspend
Rephrase of previous provision. The clause strictly mentioned that contract
shall not be entitled to any form of losses i.e lost of profit, damage claim etc.
upon termination of the contract.
43
Clause Differences
53.1
53.2
53.2 (c)
COC Rev. 2007
COC Rev. 1/2010
The new term ' unlawful & illegal activities' has been inserted.
53.1 (a) replaced to 53.1
53.1 (a) (i)& (ii) in COC 2007 has been deleted
53.1(b) change to 53.2
53.2(b)(iii) change to 53.2 (c)
Rephrase of previous provision. The clause strictly mentioned that
contract shall not be entitled to any form of losses i.e lost of profit,
damage claim etc. upon termination of the contract.
55
COC Rev. 2007
COC Rev. 1/2010
New Provision allows the contractor to terminate the government because
of fails to fulfill any obligation which affects the works & consequences of
such termination.
68
COC Rev. 2007
COC Rev. 1/2010
COC Rev. 1/2010
New Provision regarding the compliance of safety requirement,
submission of safety report to Govn, appointment of qualified Safety
Officer and to provide safety measure at site.