+ All Categories
Home > Design > Code Q&A: Answers to Common and Challenging Code Questions

Code Q&A: Answers to Common and Challenging Code Questions

Date post: 11-Apr-2017
Category:
Upload: aia-pittsburgh
View: 66 times
Download: 0 times
Share this document with a friend
80
Code Q&A: Answers to Common and Challenging Code Questions Build Pittsburgh - 2017
Transcript
Page 1: Code Q&A: Answers to Common and Challenging Code Questions

Code Q&A:Answers to Common and Challenging Code Questions

Build Pittsburgh - 2017

Page 2: Code Q&A: Answers to Common and Challenging Code Questions

Question:• When does a client need to pull a building permit?

Occupancy permit (New Tenant but same use type)?

Page 3: Code Q&A: Answers to Common and Challenging Code Questions

What is the purpose?• Designs by Licensed Design Professional• Built by Licensed, Insured Contractors• Special Inspections and independent testing

requirements

So why:• Zoning review and approval?• Building Code Plan Review?• Building Inspections?

Page 4: Code Q&A: Answers to Common and Challenging Code Questions

What is the purpose?

• Verification that work complies with the code.

• That a completed project is legal.

Page 5: Code Q&A: Answers to Common and Challenging Code Questions

What is the Process?

Page 6: Code Q&A: Answers to Common and Challenging Code Questions
Page 7: Code Q&A: Answers to Common and Challenging Code Questions

PLI Permit ProcessApplication

• ApplicationPlan Review

• Plan ReviewApproval

• ApprovalPermit

Issuance• Permit Issuance

Inspection• Inspections

Final• Final Inspection

Certificate of

Occupancy

• Certificate of Occupancy

Page 8: Code Q&A: Answers to Common and Challenging Code Questions

Permit review:

1. What is the application for?

2. What code is applied?

3. What is the existing legal use?

Page 9: Code Q&A: Answers to Common and Challenging Code Questions

1. What is the Application for?

•Are the scope of work, and occupancy descriptions accurate? Does it match the drawings?

• Is it also a change in use?

Page 10: Code Q&A: Answers to Common and Challenging Code Questions

2. What code is applied?

• What code was the project designed to? • There are alternatives for existing buildings.

Page 11: Code Q&A: Answers to Common and Challenging Code Questions

3. What is the existing legal use?

• How is this determined?

Page 12: Code Q&A: Answers to Common and Challenging Code Questions

Certificate of OccupancyIs the document issued by the AHJ, City of Pittsburgh, upon completion of a project verifying it is now legal to use.

Means that it has been approved, inspected, and determined compliant with the Codes in effect at the time of construction for a particular use.

Page 13: Code Q&A: Answers to Common and Challenging Code Questions

Certificate of Occupancy• Use of the building / property stays legal -until

changes are made

• Regardless of Ownership• Regardless of Tenant changes• Regardless of Name changes

Page 14: Code Q&A: Answers to Common and Challenging Code Questions

Question:• When does a client need to pull a building permit?

Occupancy permit (New Tenant but same use type)?

Page 15: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Types of occupancy permits (Certificate of

Occupancy / Temporary CO / Partial Occupancy), how each one is used, and application procedures for each.

Page 16: Code Q&A: Answers to Common and Challenging Code Questions

Certificate of OccupancyWhen changes are made to the use of a building, a new Certificate of Occupancy is required – each time.

- Requiring:- Department of City Planning / Zoning approval - PLI / Building Code approval

Page 17: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Interface with Department of City Planning on

applications for CO / TCO / Partial Occupancy. Specifically, hashing out the wording of the occupancy description (this seems to be a constant struggle with Planning).

Page 18: Code Q&A: Answers to Common and Challenging Code Questions
Page 19: Code Q&A: Answers to Common and Challenging Code Questions
Page 20: Code Q&A: Answers to Common and Challenging Code Questions
Page 21: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Discussion about existing Certificates of Occupancy.

What determines if new work can be performed under an existing CO, or if a new one needs to be obtained? How does the wording of the occupancy description impact this?

Page 22: Code Q&A: Answers to Common and Challenging Code Questions
Page 23: Code Q&A: Answers to Common and Challenging Code Questions

When there is no existing Certificate of Occupancy

• This is defined as ‘UNCERTIFIED’ per the PA UCC 403.28

• 403.28 (a) – Structures built prior to April 27, 1927 are deemed legally occupied – until changes are made.

• 403.28 (b) – Structures under the Dept. of Labor and Industry Jurisdiction

• 403.28 (c) – Structures under the jurisdiction of the City of Pittsburgh, and NOT falling under 403.28 (a).

Page 24: Code Q&A: Answers to Common and Challenging Code Questions

When there is no existing Certificate of Occupancy

403.28 (c) – Structures under the jurisdiction of the City of Pittsburgh, and NOT governed under 403.28 (a).

(1) A construction code official shall issue a certificate of occupancy to an uncertified building if it meets the requirements of the latest version of the “International Existing Building Code” or Chapter 34 of the International Building Code”.

Page 25: Code Q&A: Answers to Common and Challenging Code Questions

Question:Can you talk about the various issues around NOT having an occupancy permit:

a. If there is a permit but the building is clearly being used for another purpose. What is the occupancy, can IEBC be used or must Chapter 34 be followed?

Page 26: Code Q&A: Answers to Common and Challenging Code Questions

Question:Can you talk about the various issues around NOT having an occupancy permit:

(b) If there is only a permit for part of the building, for example the upper floor apartments but not the retail use on the ground floor and basement, what is the occupancy, can IEBC be used or must Chapter 34 be followed?

Page 27: Code Q&A: Answers to Common and Challenging Code Questions

Question:Can you talk about the various issues around NOT having an occupancy permit:

How does the age of the building affect questions (a) and (b)?

Does the City of Pittsburgh use a date other than April 27, 1927, as referenced in UCC 403.28(a)?

Page 28: Code Q&A: Answers to Common and Challenging Code Questions

Codes for Existing Buildings:Options given to the Design Professional:

A. IBC Chapter 34 (with accessibility provisions from IEBC)1- Prescriptive2- Compliance Alternative (Scoring method) <Nov 4, 1947

B. IEBC:1 – Prescriptive2 – Work Area3 – Performance (Scoring method) – <Nov 4, 1947

Page 29: Code Q&A: Answers to Common and Challenging Code Questions

Question:• I’m confused by IBC Chapter 34, 3412.6 Evaulation Process,

reading in part, “In applying this section to a building with mixed occupancies, where the separation between the mixed occupancies does not qualify for any category indicated in Section 3412.6.16, the score for each occupancy shall be determined and the lower score determined for each section of the evaluation process shall apply to the entire building.”

• Am I correct that, for example, 3412.6.1 Building Height is evaluated for the lowest score of a mixed, unseparated residential occupancy and then for a mixed, unseparated retail occupancy with the lowest of those two scores then being used in filling out ONE Table 3412.7 for the building?

Page 30: Code Q&A: Answers to Common and Challenging Code Questions

Compliance Alternative Method (IBC Section 3412 or IEBC Chapter 13)

• Yes.

• Mixed Occupancies (Use Group Classifications)–

• Separated – Fill out separate tables for each occupancy group

• Non-Separated – Fill out one table taking the lowest / worst case score in each category

Page 31: Code Q&A: Answers to Common and Challenging Code Questions
Page 32: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Occupancy verses Use: How rooms become assembly

in a business occupancy and how occupant load and construction types are impacted.

Page 33: Code Q&A: Answers to Common and Challenging Code Questions

Occupant Loads and Occupancy Classification

• Occupancy Classification and Occupant Load calculations are related but independently determined by the Use

• (Actual use / purpose / function).

Page 34: Code Q&A: Answers to Common and Challenging Code Questions

Occupancy Classification• Actual use / function / purpose determines Occupancy

Classification

• IBC Chapter 3

Page 35: Code Q&A: Answers to Common and Challenging Code Questions

Use and Occupancy Classification

• IBC Chapter 3

• IBC 304 – Business – includes “…the use of a building or structure, or a portion thereof, for office, professional or service-type transactions…”

• IBC 303.1 – Assembly – includes “… the use of a building or structure, or portion thereof, for the gathering of persons for the purposes such as civic, social or religious functions; recreation, food or drink consumption or awaiting transportation.”

Page 36: Code Q&A: Answers to Common and Challenging Code Questions

Use and Occupancy Classification

• Assembly Areas:• Exceptions under IBC 303.1

• Room / space used for assembly with occupant load of less than 50 people

• Room / space used for assembly that is less than 750 sf and accessory to another occupancy

Page 37: Code Q&A: Answers to Common and Challenging Code Questions

Occupant Loads• Actual use / function / purpose determines Occupant

Load

• Smaller occupant loads may qualify for exceptions to the Occupancy Classification

Page 38: Code Q&A: Answers to Common and Challenging Code Questions
Page 39: Code Q&A: Answers to Common and Challenging Code Questions

What Occupancy Classification / Occupant loads?

• Offices?• Flex spaces for presentations / lectures / training rooms?• Open office areas with 50+ people?• Call centers?• Conference centers / rooms?• Cafeterias?• Roof top decks / Social gathering spaces?

Page 40: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Occupancy verses Use: How rooms become assembly

in a business occupancy and how occupant load and construction types are impacted.

Page 41: Code Q&A: Answers to Common and Challenging Code Questions

Construction Type• Limited by Occupancy Classification• NOT by Occupant Load

Page 42: Code Q&A: Answers to Common and Challenging Code Questions

Question:• I’m confused about Table 503 building heights. If I

have a two story building Type 5B with an R1 occupancy on the first story less than 5,000 sq. ft., but there is a single story A-1 occupancy less than 5,000 sq. ft. on the second story, (where 1 story, 5,500 sq. ft. is permitted) is that OK by Table 503 alone since the A-1 occupancy is only on one story?

Page 43: Code Q&A: Answers to Common and Challenging Code Questions

• NO. A1 Occupancy Classification on a 2nd Story of a Type 5B building is not permitted.

Page 44: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Construction Type and rating requirements in existing

buildings: How to document existing construction to meet building code requirements.

Page 45: Code Q&A: Answers to Common and Challenging Code Questions

Permit review:

1. What is the application for?

2. What code is applied?

3. What is the existing legal use?

Page 46: Code Q&A: Answers to Common and Challenging Code Questions

Existing Construction Type

• What is the first place to look for existing conditions of approval?

• How do we know if the project is a Change in Occupancy?

• What is the scope of work?

Page 47: Code Q&A: Answers to Common and Challenging Code Questions

Determining Fire Ratings• Options for determining fire ratings:

• Listed tested assemblies (such as UL Design)• Prescriptive Fire Resistance (IBC Tables 720)• Calculated Fire Resistance (IBC 721)• Archaic Materials and Assemblies (IEBC Resource A)

Page 48: Code Q&A: Answers to Common and Challenging Code Questions

Question:• If I need a 2 hour or 3 hour horizontal separation for a

building do the beams and columns supporting that separation need a 2 hour or 3 hour fire rating?

Page 49: Code Q&A: Answers to Common and Challenging Code Questions

Supporting Construction?• Yes.

• IBC 712.4 Continuity. “…The supporting construction shall be protected to afford the required fire-resistance rating of the horizontal assembly supported.”

Page 50: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Is the City planning to adopt the entire 2015

International Residential Code? Why or why not?

• Is there any work being done within PLI to advocate for adoption of the most recent ICC Codes within Pennsylvania? As it is my understanding that code inspectors can only test to the most recent version of the ICC Codes, and enforcing to a previous version is onerous for PLI.

Page 51: Code Q&A: Answers to Common and Challenging Code Questions

What are the current codes in effect?

• PA UCC – 2009 base year I-Codes• With 2015 Accessibility provisions

• http://www.dli.pa.gov/ucc/Pages/default.aspx

• What codes were in effect when the design contract was executed?

• Alternatives for Existing buildings

Page 52: Code Q&A: Answers to Common and Challenging Code Questions

Permit Review Times:

Page 53: Code Q&A: Answers to Common and Challenging Code Questions

Question:• A $5 million hospital equipment upgrade (that will

benefit thousands of patients in the area) is placed in the same queue with a residential garage roof replacement. Can the City be asked why this situation exists and what can be done to expedite the Building Permit process?

Page 54: Code Q&A: Answers to Common and Challenging Code Questions

Question:• The backlog for getting a Permit in the last year has

been consistently as long as 6 weeks, particularly for smaller projects that can be a crippling time frame in moving forward with a very simple project. Is there any movement towards separating Projects by size? Or cost? Or a separate Single Family Residential Review Process – given that these projects are typically far more straightforward.

Page 55: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Single Family Residential Additions and Renovations

tend to be far more straightforward than larger projects. It used to be that you could walk in to apply for a Permit for an addition or renovation and move through the process fairly easily. If an engineer was free they would look over the submission right away and provide a review – either issuing a Permit or requesting more information. Will there be any sort of simplification for these types of Projects in the future as opposed to getting in line with the other much larger Projects?

Page 56: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Why did PLI stop the Thursday afternoon walk-through

reviews?...

• Why did the department eliminate (or not have a replacement for) the expedited permit approval for small projects?

Page 57: Code Q&A: Answers to Common and Challenging Code Questions

• Review not Required• Most Residential alterations• Commercial with no drawings required• Same day / over the counter

• Residential – • Initial Application– 15 business days• Re-review– 8 business days

• Commercial – • Initial Application– 30 business days• Re-review – 15 business days

PLI Review times

Page 58: Code Q&A: Answers to Common and Challenging Code Questions

Where am I in the process?• Building Eye:

• http://pittsburghpa.gov/pli/

• Permits Pending Review List:• http://pittsburghpa.gov/pli/

Page 59: Code Q&A: Answers to Common and Challenging Code Questions
Page 60: Code Q&A: Answers to Common and Challenging Code Questions

Preliminary Review / Code Consultations

Page 61: Code Q&A: Answers to Common and Challenging Code Questions

Question:• In the past, PLI (BBI) would meet with project teams to

go over preliminary code reviews to provide guidance early in the project. Our intent in those discussions was to gain any insight that the plan reviewer may be able to provide to point the design team toward a compliant end. Now that PLI will not meet with design tames to provide that initial insight, it places a potential financial burden on project teams and clients…

Page 62: Code Q&A: Answers to Common and Challenging Code Questions

Question:• If the PLI plan reviewer interprets the code differently

after all the detailing is done, then the design team or the client may be responsible for significant redesign costs. Therefore, will PLI put into place a method/process for design teams to get early insight to assist them in moving toward compliance?

Page 63: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Why is there no feedback on code questions until we

submit the entire project and wait for 6 weeks?

Page 64: Code Q&A: Answers to Common and Challenging Code Questions

• Typically No preliminary reviews.• Final construction documents are reviewed for

construction permits.

• Use the ICC Code Commentaries• Use Interpretations at ICC / City of Pittsburgh Bulletins

• http://pittsburghpa.gov/pli/

• City of Pittsburgh Major Development Reviews• http://pittsburghpa.gov/dcp/zoning/major-development

Questions during design

Page 65: Code Q&A: Answers to Common and Challenging Code Questions

• Use the Permit Application as a guide:• http://pittsburghpa.gov/pli/

Does this meet code?

Page 66: Code Q&A: Answers to Common and Challenging Code Questions

• Use the Plan Review checklists guide:• http://pittsburghpa.gov/pli/

Does this meet code?

Page 67: Code Q&A: Answers to Common and Challenging Code Questions

• Variances and Appeals• Building Code: Board of Appeals

• http://pittsburghpa.gov/pli/

• Accessibility Requirements: PA Dept. of Labor and Industry Accessibility Board

• When to apply for a variance?• Can apply during design – Do not need to wait for a plan

review denial.

Does this meet code?

Page 68: Code Q&A: Answers to Common and Challenging Code Questions

Third Party Agency Services

Page 69: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Why are 3rd party reviews for architectural portions

not permitted as a compliance path?

Page 70: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Can you clarify for us what inspectors work directly for

the City and which Inspectors are a Third Party?...

Page 71: Code Q&A: Answers to Common and Challenging Code Questions

Third Party Plan Review / Inspections

Temporary Measures currently in place for:• Plan Review:

• Commercial Electrical• Fire Protection Systems (Fire sprinkler, Fire Alarm Sysetms)

• Inspection:• Electrical – Commercial and Residential

Page 72: Code Q&A: Answers to Common and Challenging Code Questions

Question:• Will there be a process that allows for the General

Contractor to call for all of the Inspections to expedite the process? As opposed to the Electrical having to call for Electrical Inspection, the HVAC sub calling for the HVAC inspection, etc.

Page 73: Code Q&A: Answers to Common and Challenging Code Questions

• Permits are issued separately for each discipline• Building Permits• Demolition• Electrical• Mechanical• Fire Protection

• Each permit holder is responsible for the work under their permit, and to provide access for inspections.

Separate permits

Page 74: Code Q&A: Answers to Common and Challenging Code Questions

• Have Copies of all permits• All approved Drawings• Inspection Records

Records on Site

Page 75: Code Q&A: Answers to Common and Challenging Code Questions

How can it be faster?

Page 76: Code Q&A: Answers to Common and Challenging Code Questions

How can it be faster?• Get it right the at first plan review

• Complete Application:• Use the correct application forms• Use the checklists available• Submit all documentation with the application

• Verify that the scope of work and occupancy descriptions are accurate at application

Page 77: Code Q&A: Answers to Common and Challenging Code Questions

How can it be faster?• Application Drawings:

• Are drawings necessary?• Submit Final Construction Drawings – signed/sealed• Provide Code summary sheets and diagrams

• Review process:• Concurrent submission for MEP/FP permits with Building Permit• Phased Permitting• Make formal submission on revisions• Address all comments

Page 78: Code Q&A: Answers to Common and Challenging Code Questions

How can it be faster?• Inspections:

• Be ready for inspections. Pre-test systems before the inspector arrives!

• Have copies of all permits, approved drawings available• Require use of the Job site sign-off cards

• Provide all copies of required documentation at Final Inspection.

Page 79: Code Q&A: Answers to Common and Challenging Code Questions

• Final Inspection• All required documentations submitted:

• TPA final inspection reports• Final special inspection reports• All related sub-permits final / complete• Verify Conditions of approval from other Departments

• Certificate of Occupancy Issuance at completion

How can it be faster?

Page 80: Code Q&A: Answers to Common and Challenging Code Questions

More Questions, and Thank you!


Recommended