COFRENTES UNDERVESSEL PROJECT IN RFO 16 (2007)
[ Replacement of all the CRDH undervessel piping]
COFRENTES UNDERVESSEL COFRENTES UNDERVESSEL PROJECT IN RFO 16 (2007)PROJECT IN RFO 16 (2007)
[ Replacement of all the CRDH [ Replacement of all the CRDH undervessel piping]undervessel piping]
IRPA 1212th International Congress of the International Radiation Protection Association Buenos Aires , Argentina – October 19-24Eduardo Sollet ([email protected])COFRENTES NPP (SPAIN)
2
3
1.- BACKGROUND AND ROOT CAUSE
• Background- Events in RFO 15: – Leaks detected in 8 CRDH small pipes (2”) in sector 2 within the reactor
bioshield in the drywell– No access available for repair so it was necessary to replace all sector 2
CRDH pipes inside the drywell bioshield
• Root cause analysis conclusions: – Leaks were produced by Transgranular
Stress Corrosion Cracking (TGSCC) induced by external agents acting from the outside of the pipes
– Three necessary factors are involved: Residual stress (curves pipes), Humidity (normal working conditions) and a Chemical Agent (chlorides on the pipes from dust + small deposits of carbon steel)
4
- CRDH Pipe :• Sectors 1, 3 & 4 in DW through
bioshield• Sectors 1, 2, 3 & 4 inside UV• Supports modifications
- Cables:• Replacement nuclear instrumentation
cablesMaterial improvements
- Control Rod Drives (CRDs):• Remove & installation of all 145 CRDs• Decontamination & reuse of internal
filters- Nuclear Instrumentation IRMs, SRMs:
• Removal & Inspection
2.- WORK SCOPE
5
WORKING ENVIRONMENT
6
Main “ALARA” techniques implemented in the project:
1. Preparation and planning all activities with the contract2. Reduction of most radiation fields (shielding, cleaning
and decontamination)3. Design of automatic tools for pipe cutting, machining and
welding4. Mock-up training5. Continuous radiological monitoring by RPpersonnel6. Selection of a high qualified and experienced contractor
in the nuclear field
3.- ALARA PROGRAM
7
The ALARA Plan covered the following major tasks with dedicated ALARA techniques:
Removal and installation of 145 CRDs (50 CRD’s maintained & rebuilt)Removal and substitution of 145 LPRM & 290 RPIS cables (all)Inspection and removal of SRM’s & IRM’sReplacement of 290 CRDH piping.
3.- ALARA PROGRAM
8
PLANNING AND PREPARATION • Creation of a working group (Mant., Operations, QC, Eng.,
RP, Purchases, Chemistry & main Contractor) with periodic meetings for planning and work preparation.
• Detailed working planning by activity in order to reducetime and dose
• Setup of a low radiation waiting area outside the Drywell• Total scope of the project planned in 45 days (in critical
path)• Total number of workers involved in the field: 490• Total time in RCA during project execution: 27.970 h• Nuclear safety: All fuel unloaded from vessel prior
starting of activities
3.- ALARA PROGRAM
9
3.- ALARA PROGRAM
DOSE CONTROL LEVELS:
Individual Dose Control Levels: – 4 mSv / day–18 mSv / outage
Individual Dose Legal Limits:– 50 mSv / year– 100 mSv / 5 years
10
CONTINUOUS MONITORING OF INDIVIDUAL AND COLLECTIVE DOSES OF THE PROJECT:
• DRDs (electronic dosemeters)• Tele dosemeters • Continuous radiological surveillance of the workplace • CCTV
3.- ALARA PROGRAM
11
Two 1:1 mock-ups (one quarter in plant and one eighth in contractor facility) of the undervessel area were constructed for training and qualification of both workers and the new tools
CRDH PIPES
CRDS TUBES
SISMIC SUPPORTS
SRMs-IRM’s TUBES
3.- ALARA PROGRAMMOCK-UP TRAINING AND QUALIFICATION
12
MASSIVE SHIELDING INSTALLATION•DRY WELL:
3.- ALARA PROGRAM
TEMPORARY SHIELDS
13
MASSIVE SHIELDING INSTALLATION•DRY WELL:
3.- ALARA PROGRAM
PERMANENT SHIELDS
14
SOURCE TERM REDUCTIONShielding and cutting of the reactor bottom drain line and thermometric collector
3.- ALARA PROGRAM
REACTOR VESSELBOTTOM DRAIN LINE
HOT SPOTS IN ELBOWS AND
PIPE
TERMOMETRICCOLECTOR
HOT SPOT
BEFORE MODIFICATION
10 mSv/h
0,5 Sv/h
0,3 Sv/h
15
SOURCE TERM REDUCTIONShielding and cutting of the reactor bottom drain line and thermometric collector
3.- ALARA PROGRAM
AFTER MODIFICATION
THERMOMETRIC COLECTOR, DRAIN LINE ELBOWS AND
HOT SPOTS ELIMINATED
NEW VALVE
NEW FLANGE
General area dose rate ≈ 1 mSv/h
16
Removal of all nuclear instrumentation cables prior CRDH pipe replacement
TIP PIPES
3.- ALARA PROGRAMSOURCE TERM REDUCTION
RPIS PIPES
• All the nuclear instrumentation cables in the pedestal were removed to reduce interferences, general area dose rate and contamination
• New better cables were installed for RPIS and LPRM without a metallic cover protection to avoid contamination
LPRMS CABLES
17
EXTRACTION OF 145 CRDS3.- ALARA PROGRAM
LEAD CRD FILTHER SHIELD
• Uncuopling CRD’s from Refueling Floor• Continuous radiological surveillance by RP
during CRD extraction (telemetry)• Shielding of each CRD filter after its
removal• Use of “mururuoa suits” for CRD
extraction
18
• Chemical decontamination + cleaning of all CRD filters before reuse
3.- ALARA PROGRAM
EXTRACTION OF 145 CRDS
19
CRDH PIPING REPLACEMENT• Use of special tools for removing the CRDH pipe from the CRD
flange
3.- ALARA PROGRAM
HYDRAULIC TOOL FOR OLD CRDH PIPE EXTRACTION
DRILLING EQUIPMENT FOR PIPE WELDING REDUCTION
20
3.- ALARA PROGRAMCRDH PIPING SUBSTITUTION• Use of special semiautomatic machines for welding
NEW WELDING EQUIPMENT
21
4.- RADIOLOGICAL CONDITIONSDRYWELL CONDITIONS (Chemical decon performed in the 15th outage)•High recontamination of the clean-up system (carbon steel)• Low recontamination of the Recirculation Loops (stainless steal)
BRAC POINT HISTORICAL DATA
0,00
2,00
4,00
6,00
8,00
10,00
12,00
14,00
16,00
6ª REC. 7ª REC. 8ª REC 10ª REC DIC-99 13ª REC(d.d.)
14ª REC 15ª REC(d.d.)
16ª REC
Dos
e Rat
e (m
Sv/h
)
LAZO A LAZO B
Partial Decon A B
DZO jun 96 H2 mar 97
Descon Loop A
Full Decon
22
UNDERVESSEL (PEDESTAL) CONDITIONS•Expected a dose rate decrease after removal all CRDs and
Nuclear Instrumentation cables•Complete shoot-out steel removal needed but this decreased
the shielding inside the area•Both facts cause the opposite effect: Moderate dose rate
increase in the area due to PRM tube dose rate (hot spots in the flange area >100 mSv/h contact). This was an unknown effect with not prior experience in the plant
4.- RADIOLOGICAL CONDITIONS
23
4.- RADIOLOGICAL CONDITIONS
3
14
2
WORKING AREAS
0,7 - 1,20,9 - 1,8POINTS 1 & 2:Pedestal Platform Area
Before shielding and cleaning PRMS
0,7 – 1,60,8 - 2,5POINTS 3 & 4:Pipe working areas in sectors 1,2,3&4
DOSE RATE (mSv/h)
WORKS ON THE PEDESTAL PLATFORM WORKS ABOVE THE CRDs&PRMs FLANGES (2M HIGH FROM THE PEDESTAL PLATFORM)
PEDESTAL CONDITIONS
After shielding and cleaning PRMS
24
4.- RADIOLOGICAL CONDITIONS
DRYWELL MAP
1 2
DRYWELL CONDITIONS
0,3 – 0,80.6 – 1,5AREA OF CRDH PIPE SUBSTITUTION
2.- After Shielding1.- Before Shielding
DOSE RATE (mSv/h)DRYWELL WORKING AREA
0,3 – 0,80.6 – 1,5AREA OF CRDH PIPE SUBSTITUTION
2.- After Shielding1.- Before Shielding
DOSE RATE (mSv/h)DRYWELL WORKING AREA
25
5.- MAIN PROBLEMS FOUNDHIGHER THAN EXPECTED UNDERVESSEL AREA DOSE RATE
1st ALARA technique
• The 33 PRMs flanges were first shielded with a lead cylinders of 1 cm thick and 10 cm High
Result: Local contact dose rate over the flange PRM area decreased to 10 mSv/h (DRF =10). In the UV platform the dose reduction factor was light (-30%)
26
5.- MAIN PROBLEMS FOUNDHIGHER THAN EXPECTED UNDERVESSEL AREA DOSE RATE
2nd ALARA technique
• The 33 PRMs were cleaned and flushed with demin. water to remove hotspots
Result: Contact dose rate over all the PRM tubes decreased to 10 mSv/h (DRF =10)
27
5.- MAIN PROBLEMS FOUNDHIGHER THAN EXPECTED UNDERVESSEL AREA DOSE RATE
3rd ALARA technique
• The peripherical PRMs were reshielded to 1 m height with lead cylinders of 1 cm thick
Benefit: Ambient dose rate in CRDH sectors decreased by a factor of 2
28
5.- MAIN PROBLEMS FOUND
CRDH PIPE WELD IN CRD FLANGE THICKER THAN EXPECTED
• More time expended when machining the original weld. After all new tubes were inserted ready for welding, it was discovered an air gap higher than expected from the front end surface of the tube and the sitting area within the flange. This made impossible the welding causing the re-extraction of all new tubes for a better machining of the old weld. Almost 0,6 additional Sv were expended in this reworking activity. Then the tubes were repositioned again and welded semi automatically.
• But during the final pressure tests after all CRD were inserted ready for core load, leaks were detected in several CRD flanges
29
5.- MAIN PROBLEMS FOUND
CRDH PIPE WELD IN CRD FLANGE THICKER THAN EXPECTED
• The plant decided to repair all the 145 CRDs new flanges welds of all the new CRDH pipes. This meant a new extraction of all CRD’s again.
• But this required a new authorization from the Spanish Regulatory Body (CSN) to account for an extra 1,4 man.Sv necessary to finalize the work
30
5.- MAIN PROBLEMS FOUNDCRDH PIPE WELD IN CRD FLANGE THICKER THAN EXPECTED
WHAT HAPPENED?Original designCDR pipe
CDR flangeExtent of the original weld
more than expected
31
5.- MAIN PROBLEMS FOUNDCRDH PIPE WELD IN CRD FLANGE THICKER THAN EXPECTED
WHAT HAPPENED?
Machining the old weld
Incomplete weld removal
32
5.- MAIN PROBLEMS FOUNDCRDH PIPE WELD IN CRD FLANGE THICKER THAN EXPECTED
WHAT HAPPENED?
Mechanical extraction of the old tube
This push-out creates a crack in the old weld
33
5.- MAIN PROBLEMS FOUNDCRDH PIPE WELD IN CRD FLANGE THICKER THAN EXPECTED
WHAT HAPPENED?
New weld
PT after welding did not discover cracks
34
5.- MAIN PROBLEMS FOUNDIMMEDIATE CORRECTIVE ACTIONS IMPLEMENTED
• Diagnostic of the failure (root-cause analysis): – Visual inspection; machining of the old welds; PT; pressure test
at 20 kg/cm2; inspection of the extracted tubes; fabrication of
flange dummies; mock-up tests.
• Criteria to finalize the project :– Final solution.
– Complete scope: (all 145 CRD´s).
– Guaranty that the flanges will not be affected.
– To avoid new failures: (Tests after each phase).
35
5.- MAIN PROBLEMS FOUND2nd PHASE OD THE CRD TUBE-FLANGE WELDINGS
• Machining and welding procedures tested in mock-up before approval.
• Complete flange machining.• Superficial tests (visual and/or PT) on
machined flanges prior welding.• Manual welding at 26 mm lower end.• Visual inspections and PT after each weld.• Pressure test of all tubes before CRD insertion.• Flange flatness check before CRD insertion.• Individual scram test before core load.
More Dose
36
6.- DOSE ESTIMATES AND FINAL RESULTS
CRDH Piping substitution Project
ESTIMATED COLECTIVE DOSES (man.mSv)ACTUAL DOSES
(man.mSv)INITIAL DOSE
ESTIMATE
REESTIMATED DOSES DURING
RFO16
FINAL DOSE ESTIMATE
CRDs works: Removal/Installation of all (145) CRDs and rebuild (50) CRDs, including shoot-out steel disassembly/assembly
470 + 80 550 564,83
LPRMs works: New LPRMs installed, replacement of all cables (132). New ALARA techniques to shield and clean all of the PRM tubes
151 + 70 221 217,57
SRMs-IRMs works: Cable change and inspections 90 90 83,39
Pedestal platform modification (not necessary) 34 34 0,33
CRDH piping substitution works: 290 CRDH pipes were replaced (includes auxiliary works such as cleaning, shielding)
1473 + 600 2073 2125,85
RPIS works: 290 PIPs cables change 382 382 347,5
Welding repair works in CRD Flanges(reworking activity) + 1405 1405 920,13
TOTAL DOSE (man.mSv) 2600 + 2155 4755 4259,6
37
6.- DOSE ESTIMATES AND FINAL RESULTS
0
500
1000
1500
2000
2500
3000
3500
4000
4500
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86
DAYS
man
.mSv
0
10
20
30
40
50
60
70
Nº P
ERSO
NS
Nº WORKERS > 20 mSv (initial estimation was 0)
INITIAL DOSE ESTIM. 2,6 Sv
ACTUAL DOSE 4,26 Sv
56 Days: Outage expected duration
92 Days: Final outage duration
38
7.- CONCLUSIONS (I)
• The project was planned and prepared with the best available ALARA techniques
• The lack of previous industry experience could not anticipate some of the problems
• New ALARA techniques were implemented as the problem arises (shielding, cleaning and decontamination of PRMs, so their final impact in dose was less than 5% of the additional collective dose)
• Welding machining problems (original welds not fully documented) had the greatest impact in project dose outage duration