Date post: | 03-Jun-2018 |
Category: |
Documents |
Upload: | krmcharigdc |
View: | 217 times |
Download: | 0 times |
of 25
8/12/2019 coles_lfp_11_04
1/25
Planning and Oversight of NSFs Large Facility
Projects
Mark Coles
Deputy Director for Large Facility Projects
Office of Budget, Finance and Award Management
8/12/2019 coles_lfp_11_04
2/25
2
Introduction
National Academies study Setting Priorities for Large Research FacilityProjects (Brinkman report) makes specific recommendations forprioritizing, planning, and overseeing the construction and operation oflarge facilities supported by NSF.
The report cites the need to make greater resources available for pre-award planning of a projects workscope, and
Implement rigorous post-award oversight through periodic externalreview
National Science Board and National Science Foundation joint responseembraces this recommendation.
Purpose of this presentation is to discuss howthis should be implemented and solicit input
8/12/2019 coles_lfp_11_04
3/25
3
Summary of the NAS Study Recommendations
Development of a 10-20 year facility roadmap
Three levels of criteria for ranking:
Scientific and technical merit
Agency Strategic Criteria National Criteria
New starts ranked in annual budget request using clear rationale basedon roadmap
Enhanced project pre-approval planning and budgeting
Greater independent oversight and review needed Review effectiveness of Deputy Director for Large Facilities in two years
OSTP should coordinates roadmaps across agencies
NSF Leadership and NSB should pay careful attention toimplementation of proposed reforms
8/12/2019 coles_lfp_11_04
4/25
4
NAS Study Findings
There is a lack of funding for disciplines toconduct idea-generating and project-ranking
activities and, once ideas have some level ofapproval, a lack of funding for conceptualdevelopment, planning, engineering, anddesigninformation needed when judging
whether a project is ready for funding in lightof its ranking and for preparing a project forfunding if it is selected.
8/12/2019 coles_lfp_11_04
5/25
5
NSB defines a new process for approvingreadiness of a project:
Project plans are judged to be construction ready bythe Large Facility Deputy,
The budget for construction and for operations costs
has been justified to the satisfaction of the ChiefFinancial Officer
From: Attachment 5 to NSB-04-92, NSB-04-97
What are the criteria for ascertaining readinessof plans and budget?
8/12/2019 coles_lfp_11_04
6/25
6
Readiness certification process needs to be defined
Goal: NSB approves projects that are well definedand that have thorough cost estimates
Present situation:
Project baseline, including well scrutinized bottoms-upcontingency estimate, is established after construction.
Many projects are de-scoped during construction (examples:LIGO, Gemini, IceCube, likely ALMA)
Development of a project baseline (planning, costing,enabling R&D, PMCS, risk assessment, staffing)requires ~5-10% of total project cost.
8/12/2019 coles_lfp_11_04
7/25
7
Recommendation: Develop project baselineprior to approval of construction award
Project baseline:
Detailed technical workscope flowdown from sciencerequirements
Bottoms-up budget estimate
Resource loaded schedule with realistic budget profile andcritical path
Thorough risk assessment and item-by-item contingencyestimate
Robust project execution plan for project management, andstaffing commitments for key work package managers
8/12/2019 coles_lfp_11_04
8/25
8
Benefits of defining project baseline prior toconstruction award
Development of a robust project baseline reduces uncertainty inproject workscope.
Need to make an earlier commitment of significant developmentfunding to a project, with expectation that construction approvalis likely if pre-defined development criteria are satisfied.
Internal Management Plan (aka Project Development Plan)could lay out predefined criteria that must be satisfied. Forexample: Completion and successful review of preparatory research
Satisfactory demonstration of enabling technology Develop of detailed bottoms-up cost and contingency estimates,
resource loaded schedule, recruitment of key personnel, ProjectManagement Plan, and other components of Project Baseline,followed by successful external baseline review.
8/12/2019 coles_lfp_11_04
9/25
9
More planning resources will:
Reduce uncertainties in construction and operations budgets
Reduce uncertainty in construction schedule
Reduce likelihood of de-scoping
Thorough pre-construction risk assessment will create a more robustProject Execution Plan
Create an appropriate framework for cooperation for activities involvinginternational and inter-agency partnerships as an integral part of in-depth planning.
Make project oversight during construction more straightforward, add
more definition to the proposed workscope and decision points. Allow more in-depth consideration of transition to operations and
greater certainty in predicted O&M costs.
Avoid a funding hiatus.Overlap some development activities beyondNSB approval and inclusion in annual NSF budget submission.
8/12/2019 coles_lfp_11_04
10/25
10
Other factors to consider
Greater involvement by NSF OD, NSB, OMB, Congress, in theearly stage of a project - prior to entry into Readiness Stage.
Need to provide visible, but not risk-free, level of commitment
to a project during the readiness phase so that a project canrecruit engineering and managerial staff and undertake enablingR&D, detailed plans, cost estimates.
Need to set an expectation that a project will go forward intoconstruction from the readiness phase if it meets the criteria
established in its Internal Management Plan (and that if can fallout, or terminate, if unsuccessful)
8/12/2019 coles_lfp_11_04
11/25
11
Suggested Implementation
Prior to entering Readiness phase a project musthave: Scientific merit satisfying the first two NAS criteriascientific
merit and NSF priority
Preliminary Project Plan: Top down estimates of technical scope, budget, contingency,
Detailed plan for enabling R&D, planning, technicaldemonstrationsProject Development Plan
Detailed schedule with identified decision point and plan fordetermining construction readiness.
Prioritization of readiness activities with window for constructionapproval, to provide latitude for timing of construction approval
Approval by Facilities Panel of Project Development Plan
Approval by MREFC Panel of overall activity, timing, decisionpoints, etc.
8/12/2019 coles_lfp_11_04
12/25
12
Implementation:Requirements to enter Readiness Phase
Review and approval of: Preliminary technical scope,
Top-down budget and contingency estimates,
Project development plan
Project development schedule, including proposed decision point window Presentation and approval to NSF OD and NSB of project for entry into
Readiness phase
Determination by NSF OD and NSB that project meets third level NAScriterianational importance
Inform OMB and Congress of:
Projects potential construction scope
Development schedule
Window for construction approval (and allow for tuning to meet futurebudget envelope expectations)
8/12/2019 coles_lfp_11_04
13/25
13
While in the Readiness Phase
Regular status reports to NSF and NSB
Periodic updates to OMB and Congress of project status
External reviews of development milestones as appropriate
Baseline review to establish construction readiness and budgetreadiness
Request to NSF OD and NSB to exit Readiness Phase uponsuccessful completion of baseline review
Inform OMB and Congress of successful completion of baseline
review and request inclusion of projects construction budgetwithin window
Projects that fail to meet development milestones may bedelayed or terminated, as appropriate.
8/12/2019 coles_lfp_11_04
14/25
14
Exiting Readiness Phase
Construction activity begins
Construction oversight by NSF begins:
Monthly status reports
Periodic external reviews of construction activity
Development activities conclude
Periodic updates to inform NSF OD, NSB, OMB,Congress of project status
8/12/2019 coles_lfp_11_04
15/25
15
Summary Impacts on NSF
Greater commitment of R&RA funds for extensiveplanning
Involvement of NSF Director, OMB, Congress frombeginning of the intensive planning stage, rather thanat the end
Implementation of formally approved projectdevelopment plans
Greater responsibility for evaluation of projecttechnical plans and budget by CFO and DeputyDirector for Large Facilities
8/12/2019 coles_lfp_11_04
16/25
16
Oversight during construction
Practices for post-award oversight vary greatly across foundation
External review by slowly varying panels with a great breadth ofrelevant experience are used mostly in Physics.
Other disciplines rely on self-assessment, or narrowly constitutedadvisory panels from the target research field
How can we promote implementation of periodic external review by apanel of scientific, engineering, management, and technical experts?(As recommended by NAS report)
8/12/2019 coles_lfp_11_04
17/25
17
Need for further detailed advice
NSFs Facilities Management and Oversight Guide willbe revised as part of NSF/NSB response to NAS study
Other findings from NAS study also present
opportunities to improve NSFs capabilities: Post award oversight
Full life-cycle cost accounting
Need for guidance on how to develop and implementthese policies, particularly in areas where there hasnot been a tradition of: Construction of large facilities
Use of power tools for technical and financial reporting
Periodic post-award external review
8/12/2019 coles_lfp_11_04
18/25
18
Facilities Subcommittee
With approval of Business and OperationsCommittee, propose to establish FacilitiesSubcommittee as a subsidiary of the Business and
Operations Committee to provide specific guidanceon these policy issues
Facilities Subcommittee will report its findings to thefull Business and Operations Committee
Subcommittee will meet twice per year
Plan to have five members of subcommittee, all withsignificant experience with management of largescientific facilities
8/12/2019 coles_lfp_11_04
19/25
19
Facilities Subcommittee Charter
The Facilities Subcommittee will examine the business practicesthe NSF applies to planning and executing major researchfacility projects, including: NSF policies and procedures for pre-construction planning and
evaluation of proposed large facility projects, Non-technical aspects of the oversight practices applied by NSF
during construction of large facilities, and
Practices used to monitor business operations aspects of thefacilities.
The Subcommittee will make recommendations to the Businessand Operations Advisory Committee as to the adequacy ofcurrent practices, and will make recommendations for ways thatthe NSF can improve current practices to enhance theireffectiveness.
8/12/2019 coles_lfp_11_04
20/25
20
Proposed Facilities Subcommittee Membership
The following individuals have agreed to serve on theSubcommittee if approved by the Business and OperationsCommittee: Tom Kirk (Chair of Subcommittee and member of B&O Committee)
Associate Laboratory Director of High Energy and Nuclear Physics,Brookhaven National Laboratory
Jim Yeck Project Director, IceCube Project, Univ. of Wisconsin, Madison
Janos Kirz Acting Director, Advanced Light Source, Lawrence Berkeley National
Laboratory Paul Gilbert
Chairman Emeritus, Parsons Brinckerhoff Quade & Douglas, Inc.
Larry Ramsey Professor of Astronomy and Astrophysics at Penn State, and Project
Scientist on Hobby-Eberly Large Telescope
8/12/2019 coles_lfp_11_04
21/25
21
How the B&O Committee can help
Recommend business processes for ascertainingreadiness of budget and construction plans
Recommend how best to promote theimplementation of periodic external review duringconstruction
Approve charter and membership of FacilitiesSubcommittee
8/12/2019 coles_lfp_11_04
22/25
Backup materials
8/12/2019 coles_lfp_11_04
23/25
23
NSF/NSB Response:
The National Academies Report properly calls attention to thenecessity for considerable pre-approval funding for planning anddevelopment when it questions whether there is sufficient NSFsupport for this "bottom up" process.NSF endorses the Reports
recommendations to provide researchers access to fundingsufficient to develop compelling research agendas, to refine andprioritize their facility requirements, and to complete researchand development on facility designs and needed technologies.The level and form of funding for planning and development willbe reviewed, and an evaluation will be made of how project
funds are best invested to attain robust plans and scheduleswith better cost projections, so that only well-defined andthoroughly-costed projects are brought forward forconsideration by the Board.
8/12/2019 coles_lfp_11_04
24/25
24
More NSF/NSB Response:
The Director and the Board recognize the need tostrengthen oversight of the implementation of largefacility projects, which will require increased
investments of NSF staff time and travel funds. TheReport emphasizes the importance of initial planningand definition of technical scope, budget, andschedule, followed by periodic post-award status
reviews held on-site by external experts, withimplementation of a transparent process formanagement of changes to a projectsimplementation plan.
8/12/2019 coles_lfp_11_04
25/25
25
And more NSF/NSB response
On the basis of merit-reviewed proposals, NSF willfund these planning and project developmentefforts.
In accepting the Facility Plan the NSB will concurthat each of the Readiness List projects has attainedthat status by an appropriate process