PAGE 1 OF 2 College Park Elementary School Replacement VIRGINIA BEACH CITY PUBLIC SCHOOLS FPC # 295 December 11, 2009 ADDENDUM NO. 3 TO ALL BIDDERS: The following constitute Addendum No. 3 to the Contract Documents dated November 15, 2009. This Addendum shall be attached to the specifications and drawing set and shall be a part thereof to the same extent as if it were originally included. Bidders must acknowledge receipt of this Addendum during the bidding process by signing the Bid Proposal/Contract Forms when submitting proposals. GENERAL: 2.1 General: Permanently installed ceiling hung instructional shapes as manufactured by: (See sketch SKA-15) y Chisel Productions, Inc. 1785 A MacArthur Boulevard Atlanta, GA 30318 (404) 351-8388 y or approved equivalent. 1. Provide eleven (11) 3-dimensional geometric solid ceiling hung, polyurethane coated, EPS shapes as indicated: y Four (4) 6’ x 6’ x 6’ cubes y Three (3) 6’ x 6’ x 6’ tetrahedrons y Three (3) 6’ spheres Each individual shape shall be painted a primary (bright) color, four (4) colors total. Provide three (3) coats minimum or until achieving uniform smooth surface.
Transcript
Microsoft Word - CPES ADDENDUM NO 3.docFPC # 295
December 11, 2009
ADDENDUM NO. 3 TO ALL BIDDERS: The following constitute Addendum No. 3 to the Contract Documents dated November 15, 2009. This Addendum shall be attached to the specifications and drawing set and shall be a part thereof to the same extent as if it were originally included. Bidders must acknowledge receipt of this Addendum during the bidding process by signing the Bid Proposal/Contract Forms when submitting proposals.
GENERAL:
2.1 General: Permanently installed ceiling hung instructional shapes as manufactured by: (See sketch SKA-15)
Chisel Productions, Inc. 1785 A MacArthur Boulevard Atlanta, GA 30318 (404) 351-8388
or approved equivalent.
1. Provide eleven (11) 3-dimensional geometric solid ceiling hung, polyurethane coated, EPS shapes as indicated:
Four (4) 6’ x 6’ x 6’ cubes Three (3) 6’ x 6’ x 6’ tetrahedrons Three (3) 6’ spheres
Each individual shape shall be painted a primary (bright) color, four (4) colors total. Provide three (3) coats minimum or until achieving uniform smooth surface.
PAGE 2 OF 2
2. Product Requirements:
Material: EPS 1-1.5 FR Solid Coating: Fire rated polyurethane 35068 Amature: Steel pipe or channel armature embedded and concealed inside
shape to facilitate handing from a single point at top. Note: Objects shall be hung at finish angle to floor plan as directed by Architect.
Finish: Light (orange peel) texture ASTM C578 for EPS Flame spread: 25, Smoke density: 430, for coating
PERTAINING TO THE DRAWINGS:
2.2 Drawing A601: 1. Replace with attached SKA-16.
2.3 Drawings A801 through A810: 1. Add drawings in their entirety.
2.4 Drawing E501:
1. Provide electrical connection for internally lit, 277V, 1-phase monument sign. Provide a 20-amp, 2-pole disconnect switch in a NEMA 3R enclosure mounted on the side of the sign. Feed the monument sign from a 20-amp, 1-pole spare circuit breaker in panel “H1” via spare contact in lighting contactor “LCEX” with 2 #10, 1 #10 ground in a ¾” conduit (approximately 1,200 LF). Future monument sign shall be located north of bench (indicated by civil key plan note # 39/C106) in grass.
PERTAINING TO THE SPECIFICATIONS:
2.5 Specification Section 084113 – Aluminum-Framed Entrances and Storefronts:
2. Paragraph 2.3, A. – Add the following: “4. Provide Kawneer center glazed IR-501 at all locations receiving missle- impact glazing, or approved equivalent.”
2.6 Specification Section 004000 – Proposal Form:
1. Delete section in its entirety and replace with the revised Proposal Form (attached).
END ADDENDUM NO. 3
PROPOSAL FORM 004000 - 1
SECTION 004000 – PROPOSAL FORM DATE: TO: The School Board of the City of Virginia Beach c/o Mr. Anthony L. Arnold, P.E., Director Facilities Planning & Construction Virginia Beach City Public Schools School Administration Building Post Office Box 6038 Virginia Beach, Virginia 23456 I acknowledge receiving the Contract Documents consisting of Plans, Specifications, Bidding Requirements, General and Supplementary Conditions and also Addenda No. for the project COLLEGE PARK ELEMENTARY SCHOOL REPLACEMENT, Virginia Beach, Virginia. I have examined the site of the proposed work, and being familiar with all conditions surrounding the project, propose to furnish all labor, materials, and supplies and to construct the project in accordance with the Contract Documents for the stipulated lump sums as follows: (Show amounts in words and figures. In the event of discrepancy, the amount shown in words shall govern.) BASE BID Dollars $ ALTERNATE NO. 1 - ADDITIVE
Provide a complete and functioning solar collection photovoltaic (PV) system, roof mounted, and connected into the electrical power distribution system to generate on- site electrical energy from sunlight. The system shall be mounted on the roof from column lines 2 to 20 and between column lines A and F and shall be rated 84KW. The system shall include 230-watt or 315-watt solar PV panels with an efficiency of at least 18% and shall be equal to SunPower style #230/#315 or equal. Provide AC inverters, minimum 6-KW each, and arrange as required to provide a balanced AC power system at 208V, 3-phase. The inverters shall be equal to SMA America, Inc model #ST36. The inverters shall be roof mounted and wired into the school’s electrical distribution system through protective circuit breakers. Provide all wiring, connections and grounding in accordance with the NEC. Provide the capability to monitor the energy output of the system over the internet, including complete internet connection, hardware and software. The system shall also be capable of being integrated into the building’s BMS system.
COLLEGE PARK ELEMENTARY SCHOOL REPLACEMENT
PROPOSAL FORM 004000 - 2
Provide the services of licensed engineers to design the collector mounting brackets, to verify the roof capacity to support the load and to design the electrical system for the collectors. Drawings shall be provided of the final design and shall be signed and sealed by an engineer licensed in Virginia.
Dollars $ ALTERNATE NO. 2 - ADDITIVE
Provide +4’-8” tall from finish floor ceramic tile wainscoat on gypsum wall board above the terrazzo base in areas A136, B128, B137, A125, C141, C142; at entire walkway along A201 to A207, A207, A211, B229, B205, B219, C 228, and C227. Allow for 2050 LF at height indicated. Provide cove trim units at top course, inside and outside corners. Wainscoat is continuous around and trimmed to all door and window frames and openings. Provide Daltile 3” x 6” “White” glazed wall tile in a running bond pattern.
Dollars $
Printed Name:
Individual or Firm Name and Address: Phone: Fax: State Registration Number and Class: If you are physically disabled, hearing or visually impaired and need assistance with the bidding process, please call Mr. Anthony L. Arnold, P.E. at 263-1090 or 263-1240 (TDD) for further assistance. END OF SECTION 004000 Proposal Form (Rev. 2-11-08)
1. H ANGIN G GEO METRIC SHAP ES, TYP ICAL (1 1 TOTA L). HA NG FRO M ROO F STR UCTUR E ABOV E W
ITH BOT TOM O F OBJE CT @
+ 22'-0"
APPROVED:
3
VIRGINIA BEACH CITY PUBLIC SCHOOLS
1/16" = 1'-0 " SE CO ND FLO OR PAR TIA L R EFL ECT ED CE ILIN G P LAN
R EV
IS IO
N S:
D R
AW N
A
FINISH SCHEDULE
NUMBER ROOM NAME FLOOR FINISH BASE FINISH WALL FINISH CEILING
REMARKS COLORMATERIAL HEIGHT C113 KINDERGARTEN
CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5
C114 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 C115 KINDERGARTEN
CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5
C116 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 C117 PALS TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C118 SPECIAL EDUCATION TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C119 EARLY DISCOVERIES
CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5
C120 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 C121 INSTRUCTIONAL
STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3
C122 ELECTRICAL EXPOSED CONC VINYL PAINTED GYP SATC 9'-0" C123 EARLY DISCOVERIES
CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5
C124 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 C125 EARLY DISCOVERIES
OFFICE CARPET VINYL PAINTED GYP SATC 8'-0" 12 2
C126 EARLY DISCOVERIES CLASSROOM
TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5
C127 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 C128 SPEECH TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C129 READING RECOVERY TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C130 EARLY DISCOVERIES
CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5
C140 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 C141 STAIR TERRAZZO TERRAZZO PAINTED GYP SATC 10'-0" 3, 5, 9 C142 CORRIDOR TERRAZZO TERRAZZO PAINTED
GYP/CMU EXPOSED/PAINT ED GYP/SATC
9'-0"
AREA 'D' D101 STAIR TERRAZZO TERRAZZO PAINTED GYP SATC 10'-0" 3, 5, 9 D102 ADMINISTRATION
WAITING CARPET VINYL PAINTED GYP SATC 9'-0" 1, 12 1, 14
D103 ADMINISTRATION CARPET VINYL PAINTED GYP SATC 9'-0" 1, 12 1, 14 SECOND FLOOR AREA 'A' A201 LIBRARY/MEDIA CENTER CARPET WOOD PAINTED GYP SATC/GYP 10'-0"/+8" 6 7, 17 A202 LIBRARIAN OFFICE CARPET WOOD PAINTED GYP SATC 10'-0" 6, 12 17 A203 COMPUTER LAB CARPET WOOD PAINTED GYP SATC 10'-0" 3 8, 18 A204 AV WORKROOM CARPET WOOD PAINTED GYP SATC 9'-0" 6, 12 5, 17 A205 CRS CARPET WOOD PAINTED GYP SATC 9'-0" 5 A206 CRS STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 9'-0" A207 STAIR TERRAZZO TERRAZZO PAINTED GYP SATC 10'-0" 3, 9 A208 MECHANICAL EXPOSED CONC VINYL PAINTED CMU EXPOSED - 4 A209 ELECTRICAL EXPOSED CONC VINYL PAINTED CMU EXPOSED - 4 A210 FACULTY TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 A211 PROFESSIONAL
DEVELOPMENT CARPET VINYL PAINTED GYP SATC 9'-0" 6, 12 7, 17
AREA 'B' B201 BOYS CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 2 10, 12 B202 CUSTODIAL EXPOSED CONC VINYL PAINTED GYP PAINTED GYP 9'-0" 4 B203 GIRLS CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 2 10, 12 B204 MECHANICAL EXPOSED CONC VINYL PAINTED CMU EXPOSED - 4 B205 STAIR TERRAZZO TERRAZZO PAINTED GYP SATC 10'-0" 3, 9 B206 2ND GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 B207 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B208 FACULTY TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 B209 2ND GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 B210 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B211 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B212 2ND GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 B213 2ND GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 B214 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B215 KILN/POTTERY STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B216 ART TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 6 B217 ART STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B218 TEACHER WORK ROOM TERRAZZO TERRAZZO PAINTED GYP SATC 9'-0" 3, 12 5 B219 STAIR TERRAZZO TERRAZZO PAINTED GYP SATC 10'-0" 3, 9 B220 3RD GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 B221 B222 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B223 FACULTY TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 B224 3RD GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 B225 ELECTRICAL EXPOSED CONC VINYL PAINTED GYP EXPOSED - 4 B226 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B227 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B228 3RD GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 B229 CORRIDOR TERRAZZO TERRAZZO PAINTED
GYP/CMU EXPOSED/PAINT ED GYP/SATC
SEE SECTIONS
B230 ELEVATOR EQUIPMENT EXPOSED CONC VINYL PAINTED GYP EXPOSED - 4 B231 ELEVATOR - - - - - - AREA 'C' C201 3RD GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C202 4TH GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C203 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 C204 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 C205 SPECIAL EDUCATION TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C206 SPECIAL EDUCATION TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C208 4TH GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C209 C210 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 C211 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 C212 4TH GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C213 4TH GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C214 READ 180 TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C215 MATH RESOURCE TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C216 5TH GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C217 ELECTRICAL EXPOSED CONC VINYL PAINTED GYP EXPOSED - 4 C218 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 C219 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 C220 5TH GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C221 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 C222 CLASSROOM STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 C223 5TH GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C224 GUIDED READING TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C225 READING SPECIALISTS TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C226 5TH GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C227 STAIR TERRAZZO TERRAZZO PAINTED GYP SATC 10'-0" 3, 9 C228 CORRIDOR TERRAZZO TERRAZZO PAINTED GYP EXPOSED/PAINT
ED GYP/SATC SEE SECTIONS
AREA 'D' D201 STAIR TERRAZZO TERRAZZO PAINTED GYP SATC 10'-0" 3, 9
FINISH SCHEDULE
NUMBER ROOM NAME FLOOR FINISH BASE FINISH WALL FINISH CEILING
REMARKS COLORMATERIAL HEIGHT FIRST FLOOR AREA 'A' A101 MAIL CARPET VINYL PAINTED GYP SATC 9'-0" 1 A102 COPY/WORK CARPET VINYL PAINTED GYP SATC 9'-0" 5 A103 COPY STORAGE CARPET VINYL PAINTED GYP SATC 9'-0" A104 ADMIN COATS CARPET VINYL PAINTED GYP SATC 9'-0" A105 RECORD STORAGE CARPET VINYL PAINTED GYP SATC 9'-0" A106 GUIDANCE CARPET VINYL PAINTED GYP SATC 9'-0" 12 2 A107 WAITING CARPET VINYL PAINTED GYP SATC 10'-0" 1 A108 ITIN CARPET VINYL PAINTED GYP SATC 9'-0" 12 2 A109 ITIN CARPET VINYL PAINTED GYP SATC 9'-0" 12 2 A110 ISS CARPET VINYL PAINTED GYP SATC 9'-0" 5 A111 HALL CARPET VINYL PAINTED GYP SATC 9'-0" 1 A112 ADMIN TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 2 13 A113 PRINCIPAL STORAGE CARPET VINYL PAINTED GYP SATC 9'-0" A114 PRINCIPAL TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 2 13 A115 PRINCIPAL CARPET VINYL PAINTED GYP SATC 9'-0" 12 2 A116 CONFERENCE CARPET VINYL PAINTED GYP SATC 9'-0" 1, 12 2, 14 A117 ASSISTANT PRINCIPAL CARPET VINYL PAINTED GYP SATC 9'-0" 12 2 A118 DSS OFFICE CARPET VINYL PAINTED GYP SATC 9'-0" 2 A119 CLINIC TERRAZZO TERRAZZO PAINTED GYP SATC 9'-0" 3, 12 16, 3 A120 CLINIC BATH CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 13 A121 CLINIC STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 9'-0" 3 A122 GIRLS CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 11, 12 A123 CUSTODIAL EXPOSED CONC VINYL PAINTED GYP PAINTED GYP 9'-0" 4 A124 BOYS CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 11, 12 A125 STAIR TERRAZZO TERRAZZO PAINTED GYP SATC 10'-0" 3, 5, 9 A126 CUSTODIAL OFFICE PAINTED CONC VINYL PAINTED CMU SATC 9'-0" 4 A127 GIRLS PE TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 2 13 A128 BOYS PE TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 2 13 A129 GYM ATHLETIC FLOORING WOOD PAINTED CMU EXPOSED - 6 A130 GYM STORAGE EXPOSED CONC VINYL PAINTED CMU SATC 10'-0" 4 A131 CUSTODIAL STORAGE EXPOSED CONC VINYL PAINTED CMU SATC 9'-0" 4 A132 IDF EXPOSED CONC VINYL PAINTED CMU EXPOSED - 4 A133 PARKS/RECREATION
STORAGE EXPOSED CONC VINYL PAINTED CMU SATC 9'-0" 4
A134 PARKS/RECREATION OFFICE
ATHLETIC FLOORING VINYL PAINTED CMU SATC 9'-0" 4
A135 ELECTRICAL EXPOSED CONC VINYL PAINTED CMU EXPOSED - 4 A136 ENTRY TERRAZZO TERRAZZO PAINTED GYP - - 3 15 AREA 'B' B101 TABLE/CHAIR STORAGE EXPOSED CONC VINYL PAINTED CMU SATC 9'-0" 4 B102 PHYSICAL EDUCATION
OFFICE ATHLETIC FLOORING VINYL PAINTED CMU SATC 8'-8" 4
B103 RECYCLING STORAGE EXPOSED CONC VINYL PAINTED CMU SATC 8'-8" B104 MECHANICAL EXPOSED CONC - PAINTED CMU EXPOSED - 4 B105 DRY STORAGE QUARRY TILE QUARRY TILE CERAMIC TILE SATC 9'-0" B106 KITCHEN TOILET CERAMIC TILE CERAMIC TILE CERAMIC TILE SATC 9'-0" 13 B107 KITCHEN LOCKERS QUARRY TILE QUARRY TILE CERAMIC TILE SATC 9'-0" B108 WALK-IN FREEZER - - - - - 7 B109 WALK-IN COOLER - - - - - 7 B110 RECEIVABLES QUARRY TILE QUARRY TILE CERAMIC TILE SATC 9'-0" B111 DISH WASH QUARRY TILE QUARRY TILE CERAMIC TILE SATC 9'-0" B112 KITCHEN OFFICE QUARRY TILE QUARRY TILE CERAMIC TILE SATC 9'-0" B113 NON-FOOD STORAGE QUARRY TILE QUARRY TILE CERAMIC TILE SATC 9'-0" B114 KITCHEN QUARRY TILE QUARRY TILE CERAMIC TILE SATC 9'-0" B115 CUSTODIAL QUARRY TILE QUARRY TILE CERAMIC TILE PAINTED GYP 9'-0" B116 STAIR TERRAZZO TERRAZZO PAINTED GYP SATC 10'-0" 3, 5, 9 B117 MDF EXPOSED CONC VINYL PAINTED GYP SATC 9'-0" 4 B118 ELECTRICAL EXPOSED CONC VINYL PAINTED GYP EXPOSED - 4 B119 COVERED EATING - - - - - B120 FACULTY LOUNGE TERRAZZO TERRAZZO PAINTED GYP SATC 9'-0" 3, 12 4, 16 B121 CAFETORIUM TERRAZZO TERRAZZO PAINTED CMU EXPOSED/HUNG - 3, 8 19, 5 B122 RAMP RS VINYL PAINTED CMU SATC 12'-0" B123 STORAGE WOOD WOOD PAINTED CMU PAINTED GYP 9'-0" B124 STORAGE WOOD WOOD PAINTED CMU PAINTED GYP 9'-0" B125 PLATFORM WOOD WOOD PAINTED CMU EXPOSED - 6 20 B126 RAMP RS VINYL PAINTED CMU SATC 12'-0" B127 STORAGE RS VINYL PAINTED CMU SATC 8'-0" B128 CORRIDOR TERRAZZO TERRAZZO PAINTED
GYP/CMU EXPOSED/PAINT ED GYP/SATC
3
B129 BOYS CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 2 9, 12 B130 CUSTODIAL EXPOSED CONC VINYL PAINTED GYP PAINTED GYP 9'-0" 4 B131 GIRLS CERAMIC TILE - CERAMIC TILE PAINTED GYP 9'-0" 2 9, 12 B132 LTC TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B133 ELEVATOR - - - - - - B134 FACULTY
TOILET/SHOWER CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13
B135 MUSIC TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10, 11 5 B136 TEACHER WORKROOM TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3, 12 5 B137 STAIR TERRAZZO TERRAZZO PAINTED GYP SATC 10'-0" 3, 5, 9 B138 1ST GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 B139 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 B140 INSTRUCTIONAL
STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3
B141 IDF EXPOSED CONC VINYL PAINTED CMU EXPOSED - 4 B142 1ST GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 B143 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 B144 ELECTRICAL EXPOSED CONC VINYL PAINTED GYP SATC 8'-0" 2 B145 LTC TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B146 1ST GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 B147 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 B148 MUSIC STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B149 MUSIC STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 B150 LIFE SAFETY ELECTRICAL
ROOM EXPOSED CONC VINYL PAINTED GYP EXPOSED - 4
AREA 'C' C101 1ST GRADE CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C102 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 C103 KINDERGARTEN
CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5
C104 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 C105 FACULTY TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 C106 LTC TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3 C107 GIFTED TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C108 SPECIAL EDUCATION TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5 C109 KINDERGARTEN
CLASSROOM TERRAZZO TERRAZZO PAINTED GYP SATC - 3, 10 5
C110 CLASSROOM TOILET CERAMIC TILE - CERAMIC TILE PAINTED GYP 8'-0" 2 13 C111 IDF EXPOSED CONC VINYL PAINTED GYP EXPOSED - 4 C112 INSTRUCTIONAL
STORAGE TERRAZZO TERRAZZO PAINTED GYP SATC 8'-0" 3
WALL PARTITION TYPES A1 3-5/8" METAL STUDS @ 24" O.C. WITH 5/8" IMPACT RESISTANT GYPSUM BOARD EACH SIDE TO UNDERSIDE OF
DECK/FLOOR ABOVE. PROVIDE CONTINUOUS 3" SOUND ATTENUATING MINERAL WOOL INSULATION. A2 3-5/8" METAL STUDS @ 24" O.C. BRACE TO UNDERSIDE OF DECK/FLOOR ABOVE WITH 5/8" IMPACT RESISTANT
GYPSUM BOARD TO 6" ABOVE FINISH CEILING. PROVIDE CONTINUOUS 3" SOUND ATTENUATING MINERAL WOOL INSULATION IN STUD BAYS.
A3 3-5/8" METAL STUDS @ 24" O.C. WITH 5/8" IMPACT RESISTANT GYPSUM BOARD EACH SIDE TO 6" ABOVE FINISH CEILING. BRACE STUDS TO OVERHEAD STRUCTURE. (WALL BOARD 1 SIDE ONLY FOR CHASES)
C 12" CMU, SEE STRUCTURAL DRAWINGS. C2 TYPE C, UL U905, 1 HOUR FIRE RATED. D 8" CMU WALL TO UNDERSIDE OF DECK/FLOOR ABOVE, SEE STRUCTURAL DRAWINGS. D1 8" CMU WALL PARTITION TO 1 COURSE ABOVE FINISH CEILING. (+8'-8" WITH NO CEILING) D2 TYPE D, 1 HOUR FIRE RATED UL-U905 E 1 5/8" METAL STUD @ 24" O.C. EACH SIDE OF 3 1/2" (STRUCTURAL) AIR SPACE WITH 5/8" IMPACT RESISTANT
GYPSUM BOARD EACH SIDE. STUDS AND WALLBOARD TO UNDERSIDE OF DECK/FLOOR ABOVE. PROVIDE CONTINUOUS 1-1/2" SOUND ATTENUATING MINERAL WOOL INSULATION EACH SIDE AND 3" TO FILL AIR SPACE/VOID. STRAP WALL STUD ACROSS AIRSPACE, UL U420.
F 6" METAL STUDS @ 24" O.C. WITH 5/8" TYPE 'X' GYPSUM BOARD EACH SIDE TO UNDERSIDE OF DECK/FLOOR ABOVE. PROVIDE CONTINUOUS 5" SOUND ATTENUATING MINERAL WOOL INSULATION. UL #U419.
F1 PROVIDE PARTITION TYPE F ADDING 7/8" RESILIENT CHANNEL FURRING CLASSROOM OR CLASSROOM BATH/CLOSET SIDE.
F2 6" METAL STUDS @ 24" O.C. WITH 5/8" IMPACT RESISTANT GYPSUM BOARD TO 6" ABOVE FINISH CEILING, BRACE STUDS TO OVERHEAD STRUCTURE. PROVIDE CONTINUOUS 5" SOUND ATTENUATING MINERAL WOOL STUD BAYS.
F3 6" METAL STUDS @ 24" O.C., BRACE TO UNDERSIDE OF DECK/FLOOR ABOVE WITH 5/8" IMPACT RESISTANT GYPSUM BOARD TO 6" ABOVE FINISH CEILING. (WALL BOARD 1 SIDE ONLY FOR CHASES)
F4 6" METAL C-T STUDS @ 24" O.C. WITH 1" GYPSUM SHAFT LINER PER MANUFACTURER'S RECOMMENDATION WITH 5/8" TYPE 'X' GYPSUM BOARD OPPOSITE SIDE SEAL/STOP @ DECK ABOVE. UL#-U417
G DOUBLE 12" CMU WALL WITH 3" AIR SPACE (BEJ). FIRE WALL EACH SIDE, THRU ROOF ABOVE TO +30'-0" AND +28'-0" SEE SECTIONS, STRUCTURAL DRAWINGS, AND ROOF PLAN. UL #U905.
FINISH SCHEDULE NOTES:
WALL/PARTITION TYPES NOTES:
2. PROVIDE COVE BASE.
3. TERRAZZO BASE IS 4" TALL, 3/4" MIN THICKNESS - NO BASE ALONG STOREFRONT OR CURTAINWALL SILLS.
4. EPOXY PAINT CONCRETE FLOOR.
5. CEILING HEIGHT INDICATED IS UNDER FLOOR/LANDING ABOVE.
6. 1X4 CLEAR MAPLE WOOD BASE, PLUG FASTENERS, USE NO LENGTHS SHORTER THAN 8' IN RUN.
7. COORDINATE SLAB DEPRESSION DEPTH WITH INSULATION PER MANUFACTURERS RECOMMENDATIONS. PROVIDE CEILING HEAD/STOP FOR SATC CEILING @ UNITS.
8. PAINT HANGING CEILING CLOUDS, PAINT CEILING AND SYSTEMS ABOVE HUNG CEILING CLOUDS BLACK. NOTE: ELEVATIONS IN REFLECTED CEILING PLAN. PAINT INTERIOR OF ROOF WELLS BRIGHT WHITE.
9. RESILIENT SHEET FLOORING ON STAIR/LANDINGS ONLY (DOES NOT INCLUDE SECOND FLOOR ENTRANCE LANDING)
10. SLOPED CEILING, SEE CEILING PLANS.
11. PROVIDE 3" SOUND ATTENUATING MINERAL WOOL INSULATION THROUGHOUT ENTIRE CEILING.
12. PROVIDE 3" SOUND ATTENUATING MINERAL WOOL INSULATION 4'-0" WIDE @ ROOMS ENTIRE PERIMETER.
1. WALLS/ PARTITIONS TO UNDERSIDE OF DECK/FLOOR ABOVE SHALL BE FILLED/SEALED WITH MINERAL WOOL INSULATION TO DECK/FLOOR. (FIRE RATED WALLS SHALL USE FIRESTOPPING SEALANT PER UL.)
2. SOUND ATTENUATING INSULATION SHALL BE INSTALLED CONTINUOUS IN STUD BAYS.
3. COORDINATE RESILIENT CHANNEL WALLS WITH ELECTRICAL, PLUMBING AND MECHANICAL SYSTEMS.
4. RESILIENT CHANNEL FURRING SHALL RUN CONTINUOUS TO CREATE A FLUSH WALL SURFACE ALONG WALL INDICATED.
5. SEE LIFE SAFETY SHEETS. SMOKE PARTITIONS SHALL CARRY WALL TO UNDERSIDE OF DECK ABOVE AND SEAL/FIRESTOP.
6. 5/8" TYPE 'X' RATED GYPSUM BOARD IS ONLY REQUIRED @ FIRE RATED WALLS - 5/8" IMPACT RATED GYPSUM BOARD IS USED TYPICALLY UNLESS OTHERWISE NOTED.
GENERAL FINISH SCHEDULE NOTES: 1. PROVIDE FLOOR TRANSITIONS/REDUCERS AS SPECIFIED AND INDICATED IN DOOR SCHEDULE.
STC = 50 MIN STC = 50 MIN
STC = 56 MIN STC = 56 MIN
STC = 52 MIN
NOT USED
NOT USED
COLOR NOTES:
1. PAINT VERTICAL WALLS AND VERTICAL FACES OF SOFFITS/HEAD WALLS: BENJAMIN MOORE 173 HAPPILY EVER AFTER. 2. PAINT VERTICAL WALLS AND VERTICAL FACES OF SOFFITS/HEAD WALLS: BENJAMIN MOORE 089 TOOTY FRUITY. 3. PAINT VERTICAL WALLS AND VERTICAL FACES OF SOFFITS/HEAD WALLS: BENJAMIN MOORE 1402 SPRING IRIS. 4. PAINT VERTICAL WALLS AND VERTICAL FACES OF SOFFITS/HEAD WALLS: BENJAMIN MOORE 1446 DUSK TO DAWN. 5. PAINT VERTICAL WALLS AND VERTICAL FACES OF SOFFITS/HEAD WALLS: BENJAMIN MOORE 148 PORTER RANCH CREAM. 6. PAINT VERTICAL WALLS AND VERTICAL FACES OF SOFFITS/HEAD WALLS: BENJAMIN MOORE 660 OCEAN FRONT. 7. PAINT VERTICAL WALLS AND VERTICAL FACES OF SOFFITS/HEAD WALLS: BENJAMIN MOORE 145 HONEYBELL. 8. PAINT VERTICAL WALLS AND VERTICAL FACES OF SOFFITS/HEAD WALLS: BENJAMIN MOORE 1457 WHITE WINGED DOVE. 9. CERAMIC WALL TILE: IN A 1 S.F. AREA PROVIDE DALTILE 0138 GOLDEN GRANITE AS FIELD AND (2) OF EACH OF THE FOLLOWING, RANDOMIZED: DALTILE DH 50 SUNFLOWER, Q 097 ORANGE BUST, 0 169 WATER FALL. 10. CERAMIC WALL TILE IN A 1 S.F. AREA PROVIDE DALTILE 0138 GOLDEN GRANITE AS FIELD AND (2) OF EACH OF THE FOLLOWING, RANDOMIZED: DALTILE DM14 COBALT, 0169 WATERFALL, 0197 AQUA GLOW. 11. CERAMIC WALL TILE IN A 1 S.F. AREA PROVIDE DALTILE 0138 GOLDEN GRANITE AS FIELD AND (2) OF EACH OF THE FOLLOWING, RANDOMIZED: DALTILE DH50 SUNFLOWER, QF43 MARINE, 0169 WATERFALL. 12. PROVIDE DALTILE D138 GOLDEN GRANITE FLOOR TILE. 13. PROVIDE DALTILE D138 GOLDEN GRANITE FLOOR TILE AS FIELD WITH 2/ACCENT FLOOR TILES PER 1 S.F. DALTILE Q138 GOLDEN GRANITE WALL TILE AS FILED WITH 1 COURSE CONTINUOUS ACCENT TILE @ 6'-0". 14. CORIAN: WITCH HAZEL COUNTERTOPS. 15. CORIAN: ATLANTIS COUNTERTOP (ENTRY DESK). 16. CORIAN: JUNIPER COUNTERTOPS. 17. CORIAN: TUMBLED GLASS COUNTERS, STANDS AND STOOLS. 18. CORIAN: ELDERBERRY COUNTERTOP. 19. PAINT CEILING CLOUDS: BENJAMIN 778 SKYLARK SONG ON BOTTOM HORIZONTAL FACE. PAINT VERTICAL FACES OF CEILING CLOUDS, AND AREA ABOVE (AND INDLUDING INSIDES OF MONITOR WELLS) BRIGHT WHITE. 20. PAINT ALL BACK STAGE WALLS AND CEILING/EXPOSED STAGE AREAS BLACK.
GENERAL:
KEYED COLOR NOTES:
1. TERRAZZO PATTERN, COLOR, AND BASE IS INDICATED ON FLOOR PATTERN SHEETS. 2. CARPET PATTERN, COLOR, AND VINYL/BASE IS INDICATED ON FLOOR PATTERN SHEETS. 3. COLORS AND PATTERSN NOT SPECIFICALLY INDICATED IN THE DOCUMENTS SHALL BE SELECTED FROM MANUFACTURERS FULL RANGE, AND AS SPECIFIED. 4. PROVIDE "TERRA COLLECTION" FROM CORIAN FOR ALL OTHER SOLID SURFACE LOCATIONS NOT SPECIFICALLY INDICATED. 5. PAINT ALL EXPOSED CEILINGS: BRIGHT WHITE UNLESS OTHERWISE INDICATED.
ADDENDUM NO. 3 SKA-16 REPLACES A601
(REPLACES A601)
AD DE
ND UM
N O.
NTMA # S-04-01
NTMA # S-04-07
NTMA # D-04-41
NTMA # EX-04-45
NTMA # EX-04-48
NTMA # EX-04-52
NTMA # EX-04-44
BORDER: PATCRAFT FLAX 00122 BASE: JOHNSONITE 49 BEIGE PATCRAFT DILEMMA 18665
TERRAZZO CARPET
I G
IV R
A
NO. 013034 CLAY C. DILLS
1. GEOMETRIC SHAPES IN HALLWAY ARE 6'-0" EACH SIDE AND 6'-0" DIAMETER. GRID PATTERN IN CAFETERIA IS MADE UP OF 8'-0" X 8'-0" SQUARES WITH 4'-0" SPACING.
GENERAL NOTES:
1/16" = 1'-0" 5'
ART STO
BORDER: PATCRAFT COLOR CHOICE SUNDRIED 00870 BASE: JOHNSONITE 112 OAKLEY PATCRAFT ADVANCED PLACEMENT BELL CURVE 00957
TERRAZZO CARPET
ACCENT
ACCENT
ACCENT
ACCENT
ACCENT
BORDER: PATCRAFT COLOR CHOICE INK 00401 BASE: JOHNSONITE 18 NAVY PATCRAFT ADVANCED PLACEMENT THINK TANK 00462
R EV
IS IO
N S:
D R
AW N
I G
IV R
A
GRAPHIC SCALE: 0' 10' 20' 40' 80'
1/16" = 1'-0" 5'
PATCRAFT DILEMMA 18665
1/8" = 1'-0" OVERALL FIRST FLOOR - FLOOR PATTERN PLAN AREA 'A'
I G
IV R
A
GRAPHIC SCALE: 0' 1' 5' 10' 20' 40'
1/8" = 1'-0"
PATCRAFT DILEMMA 18665
E
3
12/11/09
1/8" = 1'-0" OVERALL FIRST FLOOR - FLOOR PATTERN PLAN AREA 'B' I
G
A
GRAPHIC SCALE: 0' 1' 5' 10' 20' 40'
1/8" = 1'-0"
PATCRAFT DILEMMA 18665
1/8" = 1'-0" OVERALL FIRST FLOOR - FLOOR PATTERN PLAN AREA 'C'
I G
IV R
A
GRAPHIC SCALE: 0' 1' 5' 10' 20' 40'
1/8" = 1'-0"
PATCRAFT DILEMMA 18665
1/8" = 1'-0" OVERALL FIRST FLOOR - FLOOR PATTERN PLAN AREA 'D'
I G
IV R
A
GRAPHIC SCALE: 0' 1' 5' 10' 20' 40'
1/8" = 1'-0"
BORDER: PATCRAFT COLOR CHOICE SUNDRIED 00870 BASE: JOHNSONITE 112 OAKLEY
BORDER: PATCRAFT COLOR CHOICE INK 00401 BASE: JOHNSONITE 18 NAVY
PATCRAFT ADVANCED PLACEMENT THINK TANK 00462
R EV
IS IO
N S:
D R
AW N
I G
IV R
A
GRAPHIC SCALE: 0' 1' 5' 10' 20' 40'
1/8" = 1'-0"
BORDER: PATCRAFT COLOR CHOICE SUNDRIED 00870 BASE: JOHNSONITE 112 OAKLEY
BORDER: PATCRAFT COLOR CHOICE INK 00401 BASE: JOHNSONITE 18 NAVY
PATCRAFT ADVANCED PLACEMENT THINK TANK 00462
R EV
IS IO
N S:
D R
AW N
1/8" = 1'-0" ENLARGED SECOND FLOOR - FLOOR PATTERN AREA 'B' I
G
A
GRAPHIC SCALE: 0' 1' 5' 10' 20' 40'
1/8" = 1'-0"
BORDER: PATCRAFT COLOR CHOICE SUNDRIED 00870 BASE: JOHNSONITE 112 OAKLEY
BORDER: PATCRAFT COLOR CHOICE INK 00401 BASE: JOHNSONITE 18 NAVY
PATCRAFT ADVANCED PLACEMENT THINK TANK 00462
R EV
IS IO
N S:
D R
AW N
I G
IV R
A
GRAPHIC SCALE: 0' 1' 5' 10' 20' 40'
1/8" = 1'-0"
BORDER: PATCRAFT COLOR CHOICE SUNDRIED 00870 BASE: JOHNSONITE 112 OAKLEY
BORDER: PATCRAFT COLOR CHOICE INK 00401 BASE: JOHNSONITE 18 NAVY