Chaffey Community College District Measure “L” Program Program Update September 2010 Projects under Construction Page 1 of 18 1. Rendering of exterior and landscaping for the Michael Alexander Campus Center. Michael Alexander Campus Center Architect: MDA Johnson Favaro Original Contract: $6,686,215 Construction Manager: Bernards Approved Change Orders: $0 Contractor: See Multi-Prime Contracts Revised Contract: $6,686,215 Contract Start: June 21, 2010 Multi-Prime Contracts (19): See Below Contract Completion: July 31, 2011 BP 01 – General Construction: USS Cal Builders, Inc.. ……………………………………………………………… $648,000 BP 02 – Earthwork, Grading & Paving: Crew, Inc. …………………………………………………………….………. $724,900 BP 03 – Concrete: ASR Constructors, Inc. ………………………………………………………..……………………….. $563,000 BP 04 – Masonry: ASR Constructors, Inc. ……………………………………………………………………………….…. $178,000 BP 05 – Structural Steel: KCB Towers, Inc. ………………………………………………………………………….….. $574,290 BP 06 – Casework: K & Z Cabinet Co., Inc. ……………………………………………………………………………….…$130,500 BP 07 – Roofing & Sheet Metal: Chapman Coast Roof Co., Inc. .………………………………………..………$220,449 BP 08 – Aluminum Storefront & Glazing: E & R Glass Contractors, Inc……….………………………….. $162,920 BP 09 – Framing, Drywall, Fireproofing, Lath & Plaster: Caston Plastering & Drywall, Inc. …... $685,585 BP 10 – Ceramic Tile: Continental Marble and Tile Company ……………………..……………………………. $74,104 BP 11 – Acoustical Ceilings: Commercial Interiors Acoustics, Inc.. ……………………………..………..…….$44,998 BP 12 – Flooring: Donald M. Hoover Company…………………….…………………………………………………………$89,905 BP 13 – Painting: Triumph Painting………………….…………………………………………………………………………….$62,800 BP 14 – Plumbing: Nile ASR/Duke Constructors…………………..……………………………………………………. $451,000 BP 15 – HVAC: West-Tech Mechanical, Inc. ………………….……………………………………………………………..$664,975 BP 16 – Electrical: Daniel’s Electric Construction Co., Inc. …………………….……………………………………$878,000 BP 17 – Landscape & Irrigation: Martinez Landscaping Co., Inc. ……….…………………………………….. $116,789 BP 18 – Fire Protection: JPI Development, Inc. …………………………………….…………………………………….. $92,000 BP 19 – Kitchen Equipment: R.W. Smith & Co., Inc. …………………..…………………………………………….. $324,000 Scope: Demolition of the existing Campus Center West Building and the construction of a new 16,400 sq. ft. two story Campus Center Building, including a student cafeteria, faculty dining room, health services, career services resource center, extended opportunity programs and services, and student government offices. Renovation of approximately 1,700 sq. ft. of the existing Campus Center East Building.
Transcript

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects under Construction

Page 1 of 18

1. Rendering of exterior and landscaping for the Michael Alexander Campus Center.

Michael Alexander Campus Center Architect: MDA Johnson Favaro Original Contract: $6,686,215 Construction Manager: Bernards Approved Change Orders: $0 Contractor: See Multi-Prime Contracts Revised Contract: $6,686,215Contract Start: June 21, 2010 Multi-Prime Contracts (19): See Below Contract Completion: July 31, 2011BP 01 – General Construction: USS Cal Builders, Inc.. ……………………………………………………………… $648,000 BP 02 – Earthwork, Grading & Paving: Crew, Inc. …………………………………………………………….………. $724,900 BP 03 – Concrete: ASR Constructors, Inc. ………………………………………………………..……………………….. $563,000 BP 04 – Masonry: ASR Constructors, Inc. ……………………………………………………………………………….…. $178,000 BP 05 – Structural Steel: KCB Towers, Inc. ………………………………………………………………………….….. $574,290 BP 06 – Casework: K & Z Cabinet Co., Inc. ……………………………………………………………………………….…$130,500 BP 07 – Roofing & Sheet Metal: Chapman Coast Roof Co., Inc. .………………………………………..………$220,449 BP 08 – Aluminum Storefront & Glazing: E & R Glass Contractors, Inc……….………………………….. $162,920 BP 09 – Framing, Drywall, Fireproofing, Lath & Plaster: Caston Plastering & Drywall, Inc. …... $685,585 BP 10 – Ceramic Tile: Continental Marble and Tile Company ……………………..……………………………. $74,104 BP 11 – Acoustical Ceilings: Commercial Interiors Acoustics, Inc.. ……………………………..………..…….$44,998 BP 12 – Flooring: Donald M. Hoover Company…………………….…………………………………………………………$89,905 BP 13 – Painting: Triumph Painting………………….…………………………………………………………………………….$62,800BP 14 – Plumbing: Nile ASR/Duke Constructors…………………..……………………………………………………. $451,000 BP 15 – HVAC: West-Tech Mechanical, Inc. ………………….……………………………………………………………..$664,975 BP 16 – Electrical: Daniel’s Electric Construction Co., Inc. …………………….……………………………………$878,000BP 17 – Landscape & Irrigation: Martinez Landscaping Co., Inc. ……….…………………………………….. $116,789 BP 18 – Fire Protection: JPI Development, Inc. …………………………………….…………………………………….. $92,000 BP 19 – Kitchen Equipment: R.W. Smith & Co., Inc. …………………..…………………………………………….. $324,000 Scope: Demolition of the existing Campus Center West Building and the construction of a new 16,400 sq. ft. two story Campus Center Building, including a student cafeteria, faculty dining room, health services, career services resource center, extended opportunity programs and services, and student government offices. Renovation of approximately 1,700 sq. ft. of the existing Campus Center East Building.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects under Construction

Page 2 of 18

1. Forming and rebar and placement of footings. 2. Installation of storm drain at Oak Drive.

3. Placement of concrete at building foundations. 4. Campus Center Building pad and site.

Michael Alexander Campus Center Continued

Status: The excavation of the building footings has been completed, and the rebar has been placed in the footings. The concrete foundations have been placed. The site 24-inch storm drain installation at Oak Drive is on going, and the fabrication of structural steel has begun. The new masonry seat walls at the west fire lane extension have been installed, and the concrete contractor is continuing to screen all on site footing spoils of rocks in an effort to prepare backfill material. The contractor is forming the poured in place walls, and the building under slab plumbing is complete. The under slab electrical is almost complete, and lighting conduit has been replaced at the west fire lane. The fire lane has been surveyed, and the lower manhole at Oak Drive is complete. The catch basin walls at Oak Drive have been placed.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects under Construction

Page 3 of 18

1. Map of the future Omnitrans Transit Center.

2. Looking west- New bus turnabout, and concrete curbs. 3. Looking North- Installation of light pole bases.

Omnitrans Transit CenterArchitect: HMC Architects Original Contract: $1,681,000 Construction Manager: Bernards Approved Change Orders: $0Contractor: Young Contractors, Inc. Revised Contract: $1,681,000Contract Start: June 4, 2010Contract Completion: October 31, 2010 Scope: Design and construction of a new transit bus center for the loading and unloading of the Omnitrans buses on the Rancho Cucamonga campus.Status: Young Contractors, Inc. is continuing with the installation of the storm drain and bio-swale system. The electrical subcontractor has energized the light poles in the parking lot area, and Young Contractors is continuing with the concrete walkways in and around the bus shelter. Landscape irrigation has begun in the planters, and boulder placement is on going.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects under Construction

Page 4 of 18

1. Interior view of completed classroom, and lighting upgrades.

1. Interior view of completed lighting upgrades and classroom.

Physical Science RenovationArchitect: DLR Group WWCOT Original Contract: $2,094,591 Construction Manager: Bernards Approved Change Orders: $0 Contractor: Southland Industries Revised Contract: $2,094,591Contract Start: June 1, 2010Contract Completion: July 31, 2010Scope: This is an energy project services contract, which includes energy efficient lighting and HVAC systems and controls, along with interior renovations. Status: Building was completed and ready for use for the fall 2010 semester. Accessible ramps were completed and ready for use. Lights in Parking Lot 14 are installed, and functioning. Exterior display cases have been installed. Completion of punch list items is in process.

Math Success CenterArchitect: DLR Group WWCOT Original Contract: $893,698 Construction Manager: Bernards Approved Change Orders: $0 Contractor: Southland Industries Revised Contract: $893,698Contract Start: June 1, 2010 Contract Completion: July 31, 2010Scope: This is an energy project services contract, which includes energy efficient lighting and HVAC systems and controls, along with interior renovations. Status: Building was completed and ready for use for the fall 2010 semester. Exterior display cases have been installed. Completion of punch list items is in process.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects under Construction

Page 5 of 18

1. View looking west of new sod, concrete curbs, and shrubs.

1. View looking east of the convenience store.

VPA Landscape Addition Architect: Soltis Landscape Services Original Contract: $247,770 Construction Manager: Bernards Approved Change Orders: $0 Contractor: Elite Landscaping, Inc. Revised Contract: $247,770Contract Start: April 19, 2010 Contract Completion: July 16, 2010Scope: The project includes the landscaping and irrigation of the areas adjacent to the Visual and Performing Arts Complex.Status: The punch list was issued September 16, 2010, in which Elite Landscaping, Inc. will have 30 days to complete the items on the list. The 90-day maintenance period has also begun as of September 14, 2010 and will be completed December 12, 2010.

Panther Express Convenience Store Architect: HMC Architects Original Contract: $275,000 Construction Manager: Bernards Approved Change Orders: $0Contractor: KAR Construction/Mobile Modular Revised Contract: $275,000Contract Start: July 26, 2010Contract Completion: October 31, 2010 Scope: The installation of a new modular unit for a convenience store for Auxiliary Services located in parking lot no. 12, near the Health Science Building. Status: The modular building units were placed on the foundation September 24, 2010. The exterior plaster system installation has begun, and the foundation preparation work for the shade structures is on going. Site improvements and utility connections will begin in October 2010.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects under Construction

Page 6 of 18

Fontana Phase III-Academic Building Architect: HMC Architects Original Contract: $7,305,036 Construction Manager: Bernards Approved Change Orders: $0 Contractor: See Multi-Prime Contracts Revised Contract: $7,305,036Contract Start: March 16, 2010 Multi-Prime Contracts (17): See Below Contract Completion: April 23, 2011FABP 01 – General Construction: ISEC, Inc. ………………………………………………………………………………. $568,259 FABP 02 – Earthwork, Grading & Paving: Crew, Inc. …………………………………………………………………. $188,000 FABP 03 – Concrete: Rossi Concrete, Inc. ………………………………………………………………………………….. $529,000 FABP 04 – Fire Protection: Kincaid Industries, Inc. ……………………………………………………………………. $161,000 FABP 05 – Structural, Misc. Steel & Metal Decking: Columbia Steel, Inc. ……………………………….. $646,800 FABP 06 – Casework & Millwork: ISEC, Inc. …………………………………………………………………………………$234,937 FABP 07 – Roofing & Sheet Metal: Waterproofing Experts, Inc. …………………………………………………$516,546 FABP 08 – Aluminum Storefront & Glazing: Best Contracting Services, Inc. ………………………….. $571,184 FABP 09 – Framing, Drywall, Fireproofing, Lath & Plaster: Caston Plastering & Drywall, Inc. .. $965,585 FABP 10 – Ceramic Tile: J. Colavin & Son, Inc. ……………………………………………………………………………. $54,850 FABP 11 – Acoustical Ceilings: KHS&S Contractors, Inc. ……………………………………………………………….$85,483 FABP 12 – Flooring: Donald M. Hoover Company…………………………………………………………………………$122,000 FABP 13 – Painting: AJ Fistes Corporation …………………………………………………………………………………….$69,792 FABP 14 – Plumbing: Nile Advanced Construction, Inc. ……………………………………………………………. $398,600 FABP 15 – HVAC: West-Tech Mechanical, Inc. ……………………………………………………………………………..$910,000 FABP 16 – Electrical: R.I.S. Electrical Contractors, Inc. ……………………………………………………………$1,177,000 FABP 17 – Landscape & Irrigation: ASR Constructors, Inc. ……………………………………………………….. $106,000 Scope: Comprised of 30,400 sq ft., this will be a new academic building with four classrooms, two labs with prep rooms, a library, a bookstore, student lounge, dance studio, and administration offices.

1. Exterior rendering of the building looking north.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects under Construction

Page 7 of 18

Fontana Phase III-Academic Building Continued

Status: First and second floor slabs were placed, and are complete. Roof parapet framing will take place in October 2010, and domestic water and fire manifolds are installed. Domestic water line installation has been charged, and final tie in by the fire sprinkler contractor is complete. Remaining structural steel at the west stairs was erected, and was followed by a Topping Out ceremony. The Fontana Water Company has completed the water line, concrete sidewalk, and bus turn out. The mechanical, electrical, plumbing, and other trades are continuing with preliminary work prior to fireproofing, which began September 27, 2010. Scaffold has been set at the north side of the building.

3. Placement of first floor concrete – 42 meter pump.

2. Placement of scaffold at the north side of the building.1. Placement of the final piece of structural steel.

4. Roding the concrete.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects under Construction

Page 8 of 18

2. Installation of north hydronic lines.

Physical Ed Facility-Gymnasium Renovation Architect: NTD Architecture Original Contract: $4,694,000 Construction Manager: Bernards Approved Change Orders: $28,297 Contractor: USS Cal Builders, Inc. Revised Contract: $4,722,297Contract Start: February 1, 2010Contract Completion: October 31, 2010Scope: Renovation of the 30,843 sq. ft. existing athletics building. Status: USS Cal Builders, Inc. has begun installation of ceramic tile in the Team Locker Rooms, Faculty Locker Rooms, and Men’s and Women’s Locker Rooms. The toilet partitions, fixtures, and showerhead fixtures have been installed on the east side, and light fixtures have been installed in the three classrooms. The classroom partition wall has been installed, and priming and painting of the east side walls is on going. The footings for the north and south canopies are being prepared, and the columns are scheduled to be placed early October 2010. The gymnasium floor slab has been prepared, and the wood floor is scheduled to be delivered and installed in early October 2010. T-Bar ceiling on the east side is being installed, and T-Bar hangers are being installed on the west side. Glazing on the first and second floor is complete, and the installation of the air-handling units is on going.

1. Installation of toilet partitions and fixtures.

4. Waterproofing and preparation for new metal stud wall infill at the Women’s Locker Room.

3. Placement of rebar in preparation for forming and placement of concrete walkway.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects in Bid and Award

Page 9 of 18

1. View looking east of the Central Plant Building.

Central Plant Build Out-Hot Water Upgrade Engineer: P2S Engineering, Inc. Original Contract: $148,800 Construction Manager: Bernards Approved Change Orders: $0Contractor: Hickman Mechanical, Inc. Revised Contract: $148,800Contract Start: October 10, 2010Contract Completion: November 1, 2010 Scope: The project consists of upgrades to the existing boiler system and expansion tanks at the Central Plant-Phase One.Status: The contract was awarded and approved for Hickman Mechanical, Inc., at the September 2010 Board meeting. The project is scheduled to begin construction in early October 2010.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects in Pre-Bid/Planning

Page 10 of 18

Measure “L” Build Out Future Projects U

BBBBusiness Education RenovationStatus: This project is in design development. Architect: DLR Group WWCOT

UAviary LandscapeStatus: This project is in preparation for the bid and award phase. Architect: Soltis Landscape Services

USSA-East Door EntrancesStatus: This project is awaiting DSA approval. Architect: HMC Architects

UPE Athletics-Parking Lot and FlagpoleStatus: This project is in design development. Engineer: Associated Engineers

UFire Alarm-Campus Center East, IT, & PlanetariumStatus: This project is in design development. Engineer: P2S Engineering, Inc.

ULiberal Arts and LettersStatus: Awaiting approval of the State funding proposal pending passage of the State Revenue Bond measure.

ULibrary Remodel / ExpansionStatus: Awaiting approval of the State funding proposal pending passage of the State Revenue Bond measure.

UEEC/Museum-ADA Access and Drainage Status: The project is in design development. Architect: DLR Group WWCOT

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects Completed

Page 11 of 18

1. View looking west of the VPA North Fire Lane.

1. New standing seam roof.

VPA Complex-Theater Wing Re Roof Architect: DLR Group WWCOT Original Contract: $148,700 Construction Manager: Chaffey College Approved Change Orders: $0Contractor: Peterson Dean Roofing Revised Contract: $148,700Contract Start: May 21, 2010 Contract Completion: July 31, 2010Scope: Replacement of the existing roof on the two wings of the theater complex, to a new standing seam metal roof.

VPA North Fire Lane Architect: Associated Engineers Original Contract: $135,000 Construction Manager: Bernards Approved Change Orders: ($22,828)Contractor: ASR Constructors, Inc. Revised Contract: $112,172Contract Start: March 15, 2010 Contract Completion: April 28, 2010Scope: The project includes the renovation of the existing fire lane northeast of the EEC Building and south of the Language Arts Building. The project will rework existing contours of the fire lane, while connecting it to the new Visual and Performing Arts Complex fire lane in compliance with the Americans with Disabilities Act requirements.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects Completed

Page 12 of 18

1. Exterior of the Performing Arts Building-south side.

1. Interior view of completed installation of wood flooring, bleachers, and scoreboard.

Sports Center Complex Architect: NTD Architecture Original Contract: $8,560,543 Construction Manager: Bernards Approved Change Orders: $379,545 Contractor: Edge Development, Inc. Revised Contract: $8,940,088 Contract Start: September 29, 2008 Contract Completion: December 23, 2009 Scope: This project consists of a new 22,000 sq. ft. gymnasium, and includes locker rooms and a snack bar.

Visual and Performing Arts Complex/Music BuildingArchitect: Hammel, Green & Abrahamson, Inc. Original Contract: $22,145,000 Construction Manager: Bernards Approved Change Orders: $ 1,297,130 Contractor: ProWest Constructors Revised Contract: $ 23,442,130Contract Start: February 2008 Contract Completion: - Bldg. B & C—Ceramic Lab/Art Studio Summer 2009 - Bldg. F—Art Complex Fall 2009 - Bldg. E—Music Building Summer 2009 Scope: This project is comprised of four buildings—two new buildings and two buildings that will be renovated. The 46,000 sq. ft. Performing Arts Building, is a three-story structure, including an art complex, digital media labs, photo studio, dance studio, and post-production lab, art studio, audio lab, interior design lab, lecture rooms, and faculty offices. Additionally, there is a 5,500 sq. ft. one-story Music Rehearsal Building, and includes instrumental and choral rooms. The two existing buildings were renovated and modernized into a Ceramics lab and Fashion Art Studio.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects Completed

Page 13 of 18

1. Bio-swale and walkway pavers installed.

1. Completed installation of fiber optic cable in the Sumitomo panel.

Data and Telecom Cabling-VPA, New Gym, & Physical Science Architect/Engineer: P2S Engineering Original Contract: $154,882 Construction Manager: Bernards Approved Change Orders: ($5,127)Contractor: T & D Communications, Inc. Revised Contract: $149,755Contract Start: May 14, 2009 Contract Completion: November 6, 2009 Scope: The Data and Telecom Cabling project involves the installation of new data and fiber cabling for the Visual and Performing Arts Complex, New Gymnasium, and the Physical Science Building. The work was seperated into three (3) phases: Phase I-New cabling to the Fashion, Ceramics, and Music buildings in the Performing Arts Complex and the Physical Science Building; Phase II-New cabling to the Stadium Press Box and New Gymnasium; and Phase III-New cabling to the Performing Arts Building in the Performing Arts Complex.

Fontana Phase III Parking Lot Architect: HMC Architects Original Contract: $1,089,000 Construction Manager: Bernards Approved Change Orders: $42,618 Contractor: Bogh Engineering, Inc. Revised Contract: $1,131,618Contract Start: May 11, 2009 Contract Completion: October 5, 2009 Scope: The Fontana Phase III Parking Lot project consists of the construction of a new parking lot, landscaping, driveway/fire lanes, walkways, utilities, lighting, and signage at the Fontana Campus.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects Completed

Page 14 of 18

1.Social Science-Completed view of the classroom.

1.Chino Campus parking lot, view looking west.

Chino Health Science Parking Lot Architect: MDA Johnson Favaro Original Contract: $414,550 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Laird Construction Co., Inc. Revised Contract: $414,550Contract Start: June 15, 2009 Contract Completion: August 15, 2009 Scope: The construction of a 100,000 sq. ft. parking lot with 194 parking stalls south and west of the existing parking lots.The parking lot is adjacent to the existing Main Instructional Building located on the Chino Campus.

Language Arts/Social Science-HVAC Project Architect: P2S Engineering Original Contract: $2,700,000 Construction Manager: Chaffey College Approved Change Orders: $103,828 Contractor: Siemens Revised Contract: $2,803,828Contract Start: May 15, 2009Contract Completion: August 14, 2009Scope: Energy project upgrade to the Language Arts and Social Science buildings, which includes installation of new air handling equipment and new lighting systems.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects Completed

Page 15 of 18

1. Landscaping at the Fontana Campus. 2. Landscaping at the Rancho Cucamonga Campus.

1. Completed roof at the Physical Science building.

Physical Science Complex-Roof Replacement Architect: DLR Group WWCOT Original Contract: $623,636 Construction Manager: Chaffey College Approved Change Orders: $0 Contractor: Cabral Roofing and Waterproofing Corp. Revised Contract: $623,636Contract Start: May 21, 2009 Contract Completion: July 17, 2009 Scope: Replacement of the existing roof at the Physical Science Building with a standing seam metal roof.

Library Lawn/Fontana Phase II LandscapingArchitect: Steve Frenken Landscape Architecture Original Contract: $385,000 Construction Manager: Bernards Approved Change Orders: ($450)Contractor: Land Forms Landscape Construction Revised Contract: $384,550Contract Start: August 20, 2008 Contract Completion: November 25, 2008Scope: This project consists of landscaping and creating the irrigation system for the Fontana Campus Phase II project and the library lawn area at the Rancho Cucamonga Campus.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects Completed

Page 16 of 18

Health and Life Science (HLS) Re-Roofing Architect: DLR Group WWCOT Original Contract: $456,169 Construction Manager: Bernards Approved Change Orders: $16,383 Contractor: Best Contracting Services, Inc. Revised Contract: $472,552 Contract Start: January 1, 2008 Contract Completion: June 13, 2008 Scope: Comprised of the Health Science Building and the two Life Science buildings, the Health and Life Science Re-Roofing Project, consists of the removal of an existing built up roof on all three locations, and the construction of a new standing seam metal roof.

Physical, Health, Life Science (PHLS) Renovations Architect: DLR Group WWCOT Original Contract: $8,196,500 Construction Manager: Bernards Approved Change Orders: $871,357 Contractor: PW Construction, Inc. Revised Contract: $9,067,857 Contract Start: June 16, 2007Contract Completion: Phase 1: June 18, 2008 Phase 2: August 15, 2008

Scope: Comprised of 22,997 sq. ft., the Physical, Health, and Life Science Project consists of the renovation of five existing buildings.

1. Newly installed metal roof.

1. Completed dental lab at the Physical Science Building.

������������Chaffey Community College District Measure “L” Program

� Program Update September 2010 Projects Completed

Page 17 of 18

New Marquee Sign Architect: Hammel, Green & Abrahamson, Inc. Original Contract: $180,000 Construction Manager: Bernards Approved Change Orders: $1,500 Contractor: Quiel Bros. Electric Sign Revised Contract: $181,500Contract Start: December 27, 2007 Contract Completion: June 2008 Scope: Removal and replacement of the existing marquee sign located at the Haven Avenue entrance. The new marquee sign is a double-sided display board constructed of brushed aluminum and baked enamel surfaces.

Parking Lot #12/ElevatorArchitect: GKK Works Original Contract: $1,897,007 Construction Manager: Bernards Approved Change Orders: $68,534 Contractor: Edge Development, Inc. Revised Contract: $1,965,541Contract Start: May 16, 2007 Contract Completion: November 11, 2007 Scope: This project completely re-constructs Parking Lot 12 (Phase I) including two accessible parking areas, sidewalks, lights and landscaping. An elevator (Phase II) was also constructed connecting the VSS facility to Parking Lot 12.

1. New marquee sign at Haven Avenue

1. Elevator tower and stairs leading to VSS.

������������Chaffey Community College District

Measure “L” Program

September 2010 Program Budget

Page 18 of 18

Program Fund Sources:

Program Committed Costs:

Total Program Funds $372,658,268 100.00% Total Measure L Bond Funds $244,421,685 100.00%

Committed (Expensed or Encumbered)

$280,898,039 75.38%Committed

(Expensed or Encumbered)$209,796,512 85.83%

Remaining Balance $91,760,229 24.62% Remaining Balance $34,625,173 14.17%

Program Funds Measure L Bond Funds(Includes Rancho Cucamonga, Fontana and Chino Campuses) (Includes Rancho Cucamonga, Fontana and Chino Campuses)

Committed (Expensed or Encumbered),

$209,796,512

Remaining Balance, $34,625,173

Committed (Expensed or Encumbered), $280,898,039

Remaining Balance, $91,760,229

Fund Source AmountPercentage of

TotalFund Source Amount

Percentage ofTotal

Original Measure L Bond $229,830,000 61.67% Original Measure L Bond $229,830,000 94.03%

Bond Refinance Proceeds $2,300,000 0.62% Bond Refinance Proceeds $2,300,000 0.94%

Accrued Bond Interest $12,291,685 3.30% Accrued Bond Interest $12,291,685 5.03%

Other Funds $128,236,583 34.41% Total Measure L Bond Funds $244,421,685 100.00%

Total Program Funds $372,658,268 100.00%

Program Funds Measure L Bond Funds(Includes Rancho Cucamonga, Fontana and Chino Campuses) (Includes Rancho Cucamonga, Fontana and Chino Campuses)

OriginalMeasure LBond, $229,830,000

Other Funds $128,236,583

Accrued Bond Interest, $12,291,685

Bond Refinance Proceeds, $2,300,000

Original Measure L Bond, $229,830,000

Accrued Bond Interest, $12,291,685

Bond Refinance Proceeds, $2,300,000