Date post: | 15-Jan-2016 |
Category: |
Documents |
Upload: | ibrahim-saner |
View: | 221 times |
Download: | 0 times |
Colorado River Protection Activities on the
Moab UMTRA Project
Ken Pill, HydrogeologistTechnical Assistance Contractor
CMU Upper Colorado River Basin Water Forum
October 31, 2011
Site Setting
2
Matheson Wetlands Preserve
Moab
Colorado River
Well Field
Tailings Pile
Evaporation Pond
Moab Wash
Site Background and Scope
Former uranium ore-processing facility 1956 to 1984 480-acre site, 130 acres covered by mill tailings pile Toe of pile is 750 ft from west bank of Colorado River Relocate 16 million tons
of uranium mill tailings to engineered disposal cell
Actively remediate ground water at Moab site• Endangered fish
species habitat protection
1984
3
4
Ground Water Conditions
Ammonia Plume
June 2011 data Ammonia toxicity
pH and temperature dependent• Toxicity increases
at higher pH values
5
Ground Water Remediation
Currently extracting ground water closer to the toe of the tailings pile
All extracted ground water pumped to a lined evaporation pond located on the top of the tailings pile
Capability to inject diverted Colorado River water into 34 injection wells along the riverbank
Ground Water Extraction
Fresh Water
Injection
Evap Pond Toe of
Tailings Pile
6
7
Mass removal rates have increased over the past 5 years
Evaporators used to replace pile sprinkler system
As of October 2011 have removed• 699,000 lbs of ammonia• 3,200 lbs of uranium
Ground Water Remediation (continued)
0
1
2
3
4
5
0
10
20
30
40
50
Cont
amin
ant M
ass R
emov
al R
ate
Grou
nd W
ater
Ext
ract
ed
Year
Ground Water Extracted (million gal)
Ammonia (NH3) Mass Removal Rate (lbs/1,000 gal)
Uranium (U) Mass Removal Rate (lbs/100,000 gal)
Evaluating Long-Term Treatment Options Treatability study
• Russ Walker, CMU Dept of Physical and Environmental Sciences
Prepared conceptual design for chemical ground water treatment system• Golder and Assoc• pH adjustment with
lime for U ppt• Shallow settling
ponds with aeration at pH = 10.5 for NH3 removal
8
9
Impacts of River Stage on Water Chemistry
Flow ~3,700 cfs
Base flow conditions— Gaining river
Stiff diagrams illustrate differences between water chemistry
10
Impacts of River Stage (continued)
Flow ~35,900 cfs
Peak runoff conditions— Losing river
Fresh water lens migrated ~40 ft bgs and 150 ft laterally
11
Fresh Water Injection
After fresh water lens developed due to runoff, supplemented with injection
Operating consistently since 2010• Have injected
9 million gallons through October 2011
Oct 2011 Ammonia (mg/L)
12
Suitable Habitat Potential
Closed upstream, open downstream
After spring runoff peak through September 30
Base Flow Conditions (~3,250 cfs)
Side Channels
13
Habitat Potential (continued)
27
43
10
51
15
00
10
20
30
40
50
60
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
Num
ber o
f Day
s Hab
itat
Pre
sent
Rive
r Flo
w (c
fs)
Year
Days Habitat Present
Colorado River Flow
2011 Flooding Worked with
Utah Division of Wildlife Resources to rescue native fish from ponded water after river receded
14
June 9, 201148,500 cfs
Moab Project Information
gjem.energy.gov/moab
Webcam view of Moab site
15
Questions?
16