Odessa Subarea Special Study Appraisal Investigation Columbia Basin Project
Public Information Meeting October 23, 2007 Moses Lake, WA
Meeting Objectives
• Provide update on appraisal investigation analyses
• Provide overview of study process and schedule
• Obtain feedback on appraisal investigation results
Study Purpose
• Continue phased development of the Columbia Basin Project as authorized
• Replace groundwater pumping in the Study area with a surface water supply from the Columbia Basin Project
Blue Lake
Columbia River
Snake River
Columbia River
Crab Creek
Crab Creek
PROSSE R DIVERSION D AM
East Low Canal
Pot
hole
s E
ast C
anal
Main C
anal
W6 4
5 W
a ste
wa y
Winchester
Wasteway
PE 1
6.4
Was
tew
ay
West C
anal
Royal
Branch
Canal
Wes
t Can
al
West Canal
Lind Coulee
Wasteway
Esquatzel Diversion Canal
Eltopia
East Low C
anal
West Canal
Potholes
East Canal
Branch Canal
Poth
oles
Eas
t Can
al
B E N T O N
Odessa Subarea Odessa Ground Water Feeder Canal GRAND COULEE DAM S T E V E N S F E R R Y O K A N O G A N Special Study Area Management Subarea NORTH DAM
Agricultural fields irrigated with groundwater and within Study Area Lake
C H E L A N Roosevelt Reclamation Dam Canal or Wasteway
County River or Stream
Irrigation District Waterbody Represents current and petitioned boundary Banks
Lake 0 5 10 15 20
Miles
DRY FALLS DAM
L I N C O L N
D O U G L A S
Lake Billy Lenore Clapp Lake PINTO DAM
Soap Lake
Sylvan Lake
C H E L A N
Rocky Coulee Wasteway
Odessa Ground Water Management Subarea
G R A N T Moses Lake
Potholes Reservoir
A D A M S Frenchman Hills Lake
Frenchman Hills Wasteway
Frenchman Hills O'SU LLIVAN DAM Tunnel K I T T I TA S
Lower Crab Creek
Scooteney Wahluke Branch Canal Wasteway Wahluke Siphon
Scooteney WH I T M A N Reservoir
YA K I M A
Ringold Wasteway
B EN T O N
F R A N K L I N This reference graphic is intended for informational purposes only. It is meant to assist in feature location relative to other landmarks. Geographic features and boundaries have been intentionally simplified in an attempt to provide a more readable product. No representation is made as to accuracy of this document. Irrigation district boundaries do not represent the true legal boundaries of the districts. They are approximations based on previous hard-copy maps of differing scales and not on any survey data.
Sources: Upper Columbia Area Office, Ephrata Field Office & Pacific Northwest Regional Office
Prepared by Bureau of Reclamation PNGIS
on September 25, 2006 WA L L A W A L L A
StudyArea
Study Process Overview
• Organize and Develop Plan of Study • Pre-appraisal Investigation • Appraisal Investigation (Pre-plan formulation) • Feasibility Investigation (Plan formulation) • Environmental Regulatory Requirements • Alternative Selected • Repayment Contract Discussions Begin • Construction Authority w/Federal Appropriations
• Final Engineering Design and Specifications • Award Construction Contract
PASS Recommendations
• Four Water Delivery Alternatives
Infrastructure to convey surface water togroundwater irrigated lands in Study area
• Water Supply Options
Replacement surface water supply for currentgroundwater irrigation in Study area
Water Delivery Alternatives
Alternative
Groundwater Acreage Supplied
Estimated Water Supply
Needed
acre-feetacres percent of total
Alternative A: Construct East High Canal
140,000 100 515,300
Alternative B: North portion of EHC. Enlarge & extend ELC.
127,300 91 453,200
Alternative C: Enlarge East Low Canal
70,100 50 216,800
Alternative D: Use existing East Low Canal
40,700 29 125,900
Water Storage Options • Lake Roosevelt Re-Operation • Banks Lake Drawdown • Banks Lake Raise • Potholes Reservoir Re-operation • Dry Coulee Reservoir • Rocky Coulee Reservoir • Lind Coulee Reservoir • Lower Crab Creek Reservoir • Black Rock Coulee Reservoir • Canal System Efficiency Improvement
Estimated Groundwater AcreageBy Water Supply Option
Water Supply Option Groundwater Acreage Served
acres percent Banks Lake
Draw down to 1563’ Up to 19,000 14
Draw down below 1563’ Up to 140,000 100
Operational raise of 2’ Up to 19,000 14
Potholes Reservoir Reoperation Up to 19,000 14
Dry Coulee Reservoir Up to 140,000 100
Rocky Coulee Reservoir Up to 46,900 34
Lower Crab Creek Reservoir Up to 140,000 100
Engineering Scope and Limitations
• Investigated four water delivery alternatives and sixwater storage options
• Designs and cost estimates based on previousstudies and limited design data
• Maximum 140,000 groundwater irrigated acres
• Columbia River water availability limited – ESA Fish flow objectives must be met – Water only available for diversion in September, October,
December, and January in driest years
• Delivery of 3.0 acre-feet per acre annually
Water Delivery Alternatives
Four water delivery alternatives investigated involving one or both of the following components
• Construction of new East High Canal system (previous feasibility investigation between 1960s and 1980s)
• Using existing East Low Canal system.
Alternative B –
Construct north portion of new East High Canal system.
Expand (south of I-90) and extend (near Connell) existing East Low Canal.
Water Delivery Alternatives Estimated Water Supply Needs
Alternative
Groundwater Acreage Supplied
Estimated Water Supply
Needed
acre-feetacres percent of total
Alternative A: Construct East High Canal
140,000 100 515,300
Alternative B: North portion of EHC. Enlarge & extend ELC.
127,300 91 453,200
Alternative C: Enlarge East Low Canal
70,100 50 216,800
Alternative D: Use existing East Low Canal
40,700 29 125,900
Water Supply Options
Options investigated included:
• Operational modifications to existing storage facilities • Banks Lake (Dry Falls and North Dams) • Potholes Reservoir (O’Sullivan Dam)
• New reservoirs • Dry Coulee Dam and Reservoir • Rocky Coulee Dam and Reservoir • Lower Crab Creek Dam and Reservoir (two size options)
Columbia River: Available Supply Odessa Subarea Special Study - Appraisal Level Analysis
Columbia River 90% Exceedance Monthly Available Flow Volumes Based on BPA Hyd-Sim Results 1929-1998 and Observed 1999-2005
0
0.2
0.4
0.6
0.8
1
1.2
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Volu
me
(Maf
)
Alt A Annual Diversion Irrigation Season
Canal Availability Window
Columbia Available Flow
Operational Modifications
• Reclamation policy - Any proposed operational modification cannot result in appreciable increased risk of dam failure
• Risk analyses conducted to ensure modifications are “risk neutral”
• Detailed risk analyses conducted during next Study phase (feasibility analyses)
Banks Lake Reservoir Proposed Operational Modifications
• Draft reservoir below current drawdown elevations
– Does not increase dam safety threshold risks
• Raise water surface elevation by 2 feet
– Raise in normal high water operating level may increase dam safety threshold risks
Model Results: Banks Low Elevation
Odessa Subarea Special Study - Appraisal Level Analysis
Banks Lake End-of-Month Elevations 10% of Years at or Lower
CBP-RW Model Results for Period-of-Record 1929-2005
1535
1540
1545
1550
1555
1560
1565
1570
1575
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Month
Elev
atio
n (f
eet)
Design Max 1570
Baseline
Alt A
Alt B
Alt C
Alt D
Design Min 1537 Minimum Elevation to Release 10,000 cfs
Banks Lake 2’ Raise Proposed Structural Modifications
• Structural modifications required to both Dry Falls and North Dams and Grand Coulee Feeder Canal
• Dam crest raise of 2 feet
• Install vertical “crackstopper” filter
• Raise Grand Coulee Feeder Canal lining by 2 feet
Potholes Reservoir Proposed Operational Modifications
• Shift portion of spring feed to fall season; storemore water in fall / winter season (earlier thancurrent operation) • Raise winter operating level about 3 feet; requiredownstream evacuation route • No change to normal high pool level • Overall higher pool throughout year and higherannual “average” reservoir elevation may not meetReclamation dam safety risk thresholds
Potholes Reservoir (O’Sullivan Dam) Proposed Structural Modifications
• Modifications limited to section of dam on Lower Crab Creek side
• Raise dam crest by 5 feet
• Install vertical “crackstopper” filter
New Storage Reservoirs
• Dry Coulee (481,000 ac-ft)
• Rocky Coulee (126,000 ac-ft)
• Lower Crab Creek (200,000 ac-ft) (472,000 ac-ft)
I
/
I
{Normal WS
, £I. )" 4115. 0
,
Proposed Lower Reservoir Outlet
Proposed Ou'Uet Control St'vct'u,.'~ Existing
r ;0"
~.'
Proposed Inlet Control SIn",tu," -'
... /
Dry Coulee Dam / Reservoir Site Plan
Appraisal Cost Estimates Assumptions • Based on preliminary engineering designs & analysis
• Relied heavily on previous investigations (from 1960s to 1980s)
• Supplemented with limited additional data – Geology and hydrology data – Preliminary hydrologic models
• Preliminary and not appropriate for determining actual construction costs or seeking construction authority or appropriations from Congress
Appraisal Cost Estimates • Field costs – construction costs only
• Non-contract costs - Costs associated with work or services provided in support of project
• Investigations • Design and specifications development • Construction management • Environmental compliance • Archaeological considerations
• Costs not included, but to be developed duringfeasibility design
• Land Acquisition • Utilities Relocation • Mitigation
Appraisal Cost Estimate Range Water Delivery Alternatives
EHC (140,000 Acres)
Portion of EHC & Expand ELC (127,300 acres)
Expand ELC (70,100 Acres)
Existing ELC (40,700 Acres)
0 1 2 3 4 5
Dollars (in Billions)
Water Supply Options Appraisal Cost Estimate Range
Banks Lake Drawdown
Banks Lake 2' Raise
Potholes Reservoir Reop
Dry Coulee Reservoir
Rocky Coulee Reservoir
Lower Crab Ck (200,000 AF)
Lower Crab Ck (472,000 AF)
0 0.5 1 1.5 2
Dollars (in Billions)
Total Appraisal Cost Estimate Range Water Delivery and Supply Options Combined
EHC (140, 000 acres)
Portion EHC & Expand ELC (127,300 acres)
Expand ELC (70,100 acres)
Existing ELC (40,700 acres)
0 1 2 3 4 5 6 7
Dollars (in Billions)
Total Appraisal Cost Estimate Range Water Delivery and Supply Options Combined Cost per Groundwater Acre Served
0 10 20 30 40 50
Alternative D (40,700 acres)
Alternative C (70,100 acres)
Alternative B (127,300 acres)
Alternative A (140,000 acres)
Dollars (in Thousands)
Appraisal Engineering Investigation Findings
• All alternatives and options technically viable from engineering and operational perspective
• Cost estimates reflect appraisal-level methods, appropriate for relative comparison between alternatives and options
• Additional data collection and analyses required for feasibility-level cost estimates before seeking construction funding
Study Objectives • Replace all or portion of groundwater use with Project surface water.
• Maximize use of existing infrastructure.
• Retain the possibility of full Project development.
• Address Endangered Species Act (ESA) issues.
• Provide environmental and recreational enhancements.
• Minimize potential delay in the study schedule.
• Be developed in phases.
Next Steps Current to 2011 • Public Comment on Appraisal Investigation through Nov. 30 • Select Alternative / Options for Feasibility Investigation • Conduct Feasibility Investigation • Conduct Environmental and Regulatory Compliance • Select Preferred Alternative
• Begin Repayment Contract Negotiations
After 2011 • Obtain Construction Authority and Federal Appropriations • Prepare Final Construction Design & Specifications • Award Contract for Construction
Feasibility Criteria
The agency preferred alternative must . . .
– Be technically viable – Protect Indian Trust Assets – Comply with the National Environmental Policy Act, the Endangered Species Act, and other environmental regulations – Be socially and environmentally acceptable – Be economically justified and financially feasible
Contact Information
Comments by November 30, 2007
By mail: Ellen Berggren Study Manager Bureau of Reclamation 1150 North Curtis Road Boise, ID 83706
By email: [email protected]
Fax: 208-378-5102