1
Comments on August 2017 DS496
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
1 103.8
through
103.15
Some new text is proposed below.
However, it is recommended that
the text of 103.8 through 103.15 be
reviewed and edited by an English
expert.
Need text to be edited
throughout for proper
English
2 103.8 Proposed revised text:
103.8, 2nd
sentence, suggest the
following change:
“It established the basic principles
and framework of the Regulations
that has have been inherited to
incorporated into the later editions,
such as:”
Proposed changes to
correct poor English.
3 103.8(a) Proposed revised text:
“Radionuclides were divided
classified into 3 groups (I, II and III)
to specify activity limits per
package.”
Proposed change to
properly reflect the
wording in para. 6.1 of
the 1961 edition.
4 103.8(b) Proposed revised text:
“Radioactive material were
classified divided into 9 8
categories including Special Form,
Materials of Low Specific Activity
Material (LSA),Fissile Material
(Class I, II and III) and Large
Radioactive Sources.
Suggest using the term
“categories” since that is
what is used in para. 14.1
of the 1961 edition.
Also suggest dropping
“LSA” since that
acronym was not used in
the 1961 edition.
Also, should drop
2
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
“special form” since that
term was not used in the
1961 edition. As a result,
that results in only 8
categories being
specified.
5 103.8(d) Proposed revised text:
Suggest the following text so as to
accurately reflect the 1961 text:
“Two conditions of transport were
considered specified, i.e. Normal
and Accident. No specific test
conditions were specified except
that, for Type B packages, ‘the
maximum credible accident
relevant to the mode of transport’
was required.”
Suggest changes for
clarity and accuracy.
The conditions were
specified not considered.
Also I suggested to add
that, for this initial
edition, “maximum
credible accident” was
specified (see para.
5.1.3(b) of the 1961
edition).
6 103.10 Proposed revised text:
“The 1964 Revised Edition of the
Regulations defined four important
principles – containment, shielding,
criticality and heat transfer:
a) extended the radionuclide groups
to 8 (I to VIII);
b) eliminated the concept of
applying ‘maximum credible
accident’ to Type B package
designs, and replaced it with
Containment and
radiation shielding were
specifically addressed in
Part II. Criticality is
addressed, but mostly in
an indirect fashion.
Heat transfer is not
addressed per se.
Therefore suggest
deletion shown (it is
addressed later with
proposed added text for
3
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
specific accident conditions of
transport test requirements
including a 9 m drop and
exposure to an 800oC, 30-
minutes thermal test;
c) added special form radioactive
material as a category of
material, and included tests for
qualifying a material as special
form.”
the 1996 Edition.
Other changes proposed
are:
Item (a) retained from
draft text
Item (b) expanded for
accuracy. For example,
it does not say “fire”
test. Also suggested
additional text points
out elimination of
‘maximum credible
accident’.
Item (c) – this is the
first edition that added
‘special form
radioactive material’.
7 103.12 Proposed revised text:
“The 1967 Edition of the
Regulations was issued in the
current formation of sections
(Sections I to VIII) with a new
format of 7 sections and
appendixes rather than Parts and
Annexes, containing with the
following major changes.”
Although the format
changed, it is not correct
to say “the current
formation of sections”
since the document was
restructured in 1985 and
has since changed a
number of times since.
Although the number of
sections has remained
constant, the flow of the
document changed
significantly in 1985, and
4
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
has changed since then.
8 103.12 (a) Proposed revised text:
“Specifically defined A1 and A2
activity limits (in para. 109), and
then individually listed activity
limit values for a large number of
radionuclides.”
Proposed change for
accuracy. This is the first
edition where A1 and A2
values were used.
9 103.12 (b) Proposed revised text:
Change “for” to “for”.
Fix typographical error
10 103.12 (c) Proposed revised text:
“The concept of unilateral and
multilateral approvals (B(U) and
B(M)) was introduced, and the
meaning of each was defined.”
Suggested addition for
completeness.
11 103.13 Proposed revised text:
“The 1985 Edition of the
Regulations incorporated one a
fundamental change – the use of
the Q system as the basis for the
A2 and A2 values; a foundation
stone for all editions thereafter.
Other major additional changes
were:”
The A1 and A2 values in
the 1985 Edition are
based upon the Q system,
but the Regulations do
not mention the Q-system
per se; that system is
addressed in detail in, and
fully documented in SS7
(1985).
Thus the proposed text
change makes this
statement accurate.
12 103.13(a) Proposed revised text:
“Radiation protection principles to
satisfy IAEA Safety Series No. 9
Change is proposed for
proper grammar (were
versus was) and to also
5
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
“Basic Safety Standards for
Radiation Protection (1982 Edition)
was were incorporated in the
Foreword to the 1985 Edition.”
make note that, for this
edition, the radiation
protection standards were
not fully incorporated as
provisions in the
Regulations. This then is
in concert with 103.14(a).
13 103.13(e) Proposed revised text:
“Low Specific Activity (LSA)
Material and Low Level Solid
(LLS) Radioactive Material were
changed to three levels of LSA
(i.e. to LSA-I, LSA-II and LSA-III
material) and two levels of
Surface Contaminated Object
(SCO) (i.e. to SCO-I and SCO-
II).”
Propose this text change
for accuracy and
completeness.
14 103.13(g) Proposed revised text:
“A third mechanical test, the
dynamic crush test, was added for
low density, light weight packages
with contents exceeding 1000 A2;
and an enhanced water immersion
test was added for packages
containing irradiated nuclear fuel
was introduced.”
Propose this text change
for accuracy and
completeness.
15 103.13(i
bis)
Proposed revised text (as an added
subpara):
“The terminology of excepted
Previously, these
excepted packages (i.e.
limited quantities of
6
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
packages was introduced.” materials, instruments,
and articles, and empty
packages) were exempted
from multiple provisions
except for the general
design requirements; but
they were not specifically
identified as ‘excepted
packages’.
16 103.13(i
bis2)
Proposed revised text (as an added
subpara):
“Schedules that had been added in
the 1973 Edition of the
Regulations were removed from
the 1985 Edition.”
Since schedules were
mentioned for the 1973
edition, it should be
mentioned here that they
were not included. The
2nd
page of the Foreword
of the 1985 Edition
addresses why they were
removed.
17 103.14(a
bis)
Proposed revised text (as an added
subpara):
“(a bis) The objective of the
Regulations, specifying that
protection is achieved through
four principle features was first
specified in this Edition. Those
four are:
(a) Containment of the
radioactive contents;
The 1964 edition
specifically mentions
containment and radiation
shielding design
principles in Annex II,
Part II, criticality control
is address in text but not
specifically called out as
a key principle, and heat
transfer is not addressed
at all. The same is
7
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
(b) Control of external radiation;
(c) Prevention of criticality; and
(d) Prevention of damage caused
by heat.”
essentially true for the
1967, 1973 and 1985
Editions. The first time
these four were coupled
together in an
“Objective” was in the
1996 Edtion (para. 104).
Thus for accuracy, this
should be stated in the
discussion of the 1996
Edition.
18 103.14 (g
bis)
Proposed revised text (as an added
subpara):
“The requirement for the dynamic
crush test extended to all non-
exempted fissile material packages
that are defined as low density,
light weight packages, irrespective
of the activity of the fissile
material contents.”
To ensure it is understood
that the dynamic crush
test applies to all low
density, light weight
fissile material packages
not just those with
activity exceeding 1000
A2.
19 103.15 Proposed revised text:
Propose changing the first part of
the first sentence to read:
“Since 2000, the Regulations were
revised reviewed in on a biennial
cycle to match……:.”
As stated, the current text
infers that there has been
a new edition every two
years since 2000. This is
not correct. The review is
every two years, the
revision occurs when
needed (e.g. 2000 to
2003, 2005 to 2009, 2009
8
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
to 2012; these are not
every two years).
20
103.15/6 “One important set of changes may
be was the revision of fissile
exemption provisions introduced in
the 2012 Edition of the
Regulations.”
Current draft reads as
though 2012 changes
have not been made yet.
21 104.1 Proposed revised text:
Change second sentence to read as
follows:
“By placing primary reliance on the
package design and preparation, the
need for any special actions during
carriage (i.e. by the carrier) is
minimized reduced.”
Can it be demonstrated
that by placing reliance
on design and preparation
truly minimizes the need
for any special actions
during carriage, or does it
in fact reduce but not
minimize the need for
special actions during
carriage?
22 106.2 Proposed revised text:
“’In-transit storage’ is a part of
shipment that is regulated by the
provisions of SSR-6. Storage in a
transport package, which may be
over time span of several years or
decades, as defined in the IAEA
Safety Glossary means the holding
of radioactive material in a
package that provides for its
containment, with the intention of
retrieval (for spent fuel see also
Revised for clarity.
9
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
SSG-15, and for radioactive waste
see also WS-G-6.1). Storage that
precedes shipment is regulated by
international and/or national
storage regulations and is out of
the scope of the transport
regulations. Such ‘shipment after
storage’ will also be regulated by
the provisions of SSR-6; but is a
specific shipment operation which
requires consideration of ageing
phenomena of package
components, as well as changes in
the transport regulations and
changes of technical knowledge
during the period of storage.”
23
107.4 Proposed revised text:
Revise the lead-in text of the new
material (i.e. second sentence) in
this paragraph as follows:
“Natural materials and ores are any
physical ….”
The preceding sentence
makes material and ore
plural. This sentence
should do the same, or
the first sentence should
make them singular.
Also, since two items are
discussed “is” should be
changed to “are”.
24 107.4 Proposed revised text:
Revise the lead in part of the 2nd
sentence in the new material in this
paragraph in a manner consistent
See “Reason” provided
for comment 23.
10
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
with comment 22; i.e.
“Examples of natural materials and
ores include…..”.
25 107.4 Proposed revised text:
Revise the lead in part of the 3rd
sentence in the new material in this
paragraph in a manner consistent
with comment 22; i.e.
“’Natural materials’ does do not
include…..”.
See “Reason” provided
for comment 23.
26 109.1,
First
Sentence
Proposed revised text:
“Additional measures may be required
by regulatory agencies to provide
appropriate physical protection in the
transport of radioactive material and to
prevent unlawful acts involving
without lawful authority which
constitute the receipt, possession, use,
transfer, alteration, disposal and/or
dispersal of radioactive material and
which cause, or are likely to cause,
death or serious injury to any person or
substantial damage to property.
For proposed text on relevant
references see Comments 27 and 30.
First sentence: changes
are proposed for clarity:
(a) stating “unlawful acts
involving” seems to
communicate better than
“acts without lawful
authority which constitute”;
and (b) suggest the use of
and/or since an unlawful
act by an malicious
individual or entity could
involve more than just
receipt, etc.
27 109.1,
Second
Sentence
Proposed revised text for
parenthetical part of para. 109.1:
“(See the Convention on the Physical
Protection of Nuclear Material,
Parenthetical part of para.
201: The listing of
relevant, security-related
documents should be
11
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
INFCIRC/274 Rev.1, IAEA, Vienna
(1980) [9]; Amendments to the
Convention on the Physical
Protection of Nuclear Material,
IAEA (2005) [10]; IAEA Nuclear
Security Series No. 13, Nuclear
Security Recommendations on
Physical Protection of Nuclear
Material and Nuclear Facilities
(INFCIRC/225/Revision 5), (2011)
[11]; IAEA Nuclear Security
Series No. 26-G, Security of
Nuclear Material in Transport
(2015) [12]; IAEA Nuclear Security Series No. 9, Security in the
Transport of Radioactive Material
(2008) [13]; and IAEA Nuclear
Security Series No. 14, Nuclear
Security Recommendations on
Radioactive Material and
Associated Facilities, (2011) [14]).”
For proposed correct listing of these
references, see Comment 30.
made complete and up to
date. For example, the
Amendment to the
CPPNM is now in force,
and other related Nuclear
Security Series
documents as noted in the
column to the left.
28 109.2 Proposed revised text:
“See also, Code of Conduct on the
Safety and Security of Radioactive
Sources, IAEA, Vienna (2004) [1215]
and Guidance on the Import and Export
of Radioactive Sources, IAEA, Vienna
Change to reference
numbers caused by
addition of up-to-date
listing of security-related
documents (see
12
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
(2005) [1316].”
For proposed corrections to
reference number see Comment 30.
29 References
to Section
I
Proposed revised text for References
2, 3 and 4:
See recommendation in the column
to the right.
References [2, 3, and 4]
cite editions that are out
of date. These documents
are revised every two
years. For consistency
and accuracy, and to
avoid confusion, would it
not be better to make a
statement with respect to
these 3 documents similar
to footnote 1- i.e.
indicating that
“Throughout this
publication, reference to
these modal regulatory
documents always
refers to the latest
edition.”?
30
References
to Section
I
Proposed revised text for references
referring to security in redraft of
para 109.1:
“[9] The Convention on the Physical
Protection of Nuclear Material,
INFCIRC/274/Rev.1, IAEA, Vienna
To make the listing of
IAEA documents relevant
to transport security
accurate and up to date.
13
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
(1980).
[10] Amendment to the
Convention on the Physical
Protection of Nuclear Material,
GOV/INF/2005/10-GC(49)INF/6,
IAEA, Vienna, 2005).
[11] INTERNATIONAL
ATOMIC ENERGY AGENCY,
Nuclear Security
Recommendations on Physical
Protection of Nuclear Material
and Nuclear Facilities
(INFCIRC/225/Revision 5), IAEA
Nuclear Security Series No. 13,
IAEA, Vienna (2011).
[12] INTERNATIONAL
ATOMIC ENERGY AGENCY,
Security of Nuclear Material in
Transport, IAEA Nuclear
Security Series No. 26-G, IAEA,
Vienna (2015).
[13] INTERNATIONAL
ATOMIC ENERGY AGENCY,
Security in the Transport of
Radioactive Material, IAEA
Nuclear Security Series No. 9,
IAEA, Vienna (2008).
14
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
[14] INTERNATIONAL
ATOMIC ENERGY AGENCY,
Nuclear Security
Recommendations on Radioactive
Material and Associated Facilities,
IAEA, Nuclear Security Series No.
14, IAEA, Vienna (2011).”
31 References
to Section
I
Proposed revised text for references referring to security in redraft of para
109.2:
“[15] INTERNATIONAL ATOMIC
ENERGY AGENCY, Code of Conduct
on the Safety and Security of
Radioactive Sources, IAEA, Vienna
(2004).
[16] INTERNATIONAL ATOMIC
ENERGY AGENCY, Guidance on the
Import and Export of Radioactive
Sources, IAEA, Vienna (2012).”
To adjust the reference
numbering accounting for
the addition of new
transport-security-related
IAEA documents
discussed in preceding
comments.
32 207.3 Proposed revised text:
Change the URL for the listing of
competent authorities to the
following: http://www-
ns.iaea.org/downloads/rw/transport-
safety/competent-authorities-list.pdf
The listing of competent
authorities can now be
found on the Transport
Safety Unit’s website at
the URL shown in
column 3.
33 209.1/6-7 … The confinement system could be
(i) an inner receptacle with defined
dimensions, (ii) an inner structure
Editorial comment to
provide a more accurate
example of a package
15
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
maintaining the outer dimension of
a fuel assembly and any interstitial
fixed poisons, or (iii) a complete
package, such as an irradiated
nuclear fuel a waste package, with
no inner container. …
which could be
considered a confinement
system. Note that (iii),
"irradiated nuclear fuel
package", is not a good
example of a system
where the confinement
boundary is the same as
the containment
boundary. Criticality
safety evaluations for
irradiated nuclear fuel
packages often rely on the
confinement capability of
the fuel itself, as well as
the basket structure for
assuring geometry control
of the fuel and neutron
absorber panels, making
it a better fit as an
example under (ii). A
better example would be
a Type B waste package,
where there may be no
internal geometry control
features, and the
confinement boundary
and containment
boundary are identical.
16
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
34 220A.1 –
220A.7
These paragraphs should be
renumbered 221.1 – 221.7.
For consistency with draft
DS495 which has Dose
Rate as para 221.
35
220A.1 “One of the limiting quantities in
radiological protection with respect to
the exposure of people is effective
dose (the others being equivalent dose
to the lens of the eye and to the skin
(e.g. see Section II-8 of Ref. [1]). As
protection quantities are not directly
measurable quantities, operational
quantities, which are measurable, had
to be created which are measurable.
Operational These quantities are
‘ambient dose equivalent’ for strongly
penetrating radiation and ‘directional
dose equivalent’ for weakly
penetrating radiation. The dose rate
should be taken as the value of the
operational quantity ‘ambient dose
equivalent’ or ‘directional dose
equivalent,’, as appropriate.”
In addition, paragraph 220A should
be renumbered as 221.1 to be
consistent with the numbering in the
draft DS495 document.
Editorial.
36 220A.7 (to
become
221.7)
“To reduce discrepancies of
measured dose equivalent dose rate
in different surrounding areas, the
Edited for clarity and to
update term from “dose
equivalent” to “dose
17
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
dose equivalent to determine the
relevant values dose rate for
packages, ove23cks, vehicles etc.
shall be determined as the absolute
values caused by the radioactive
material consignment only. Dose
equivalent rate caused by
surrounding areas shall be
subtracted from measured values of
packages, ove23cks, vehicles etc.”
rate”.
37 221.1 –
232.3
The paragraphs in this range should
be renumbered 222.1 – 233.3
With the insertion of dose
rate in DS495 as para
221 and the deletion of
radiation level, these
corresponding paragraph
numbers have changed.
38 223.1 (to
be 224.1)/
last line
“Platform” and “flat rack” may be
called as “open-sided”.
Editorial
39 225.1 (to
be 226.1)
Proposed revised text:
“The concept of LDRM applies only
to the qualification of the
radioactive contents of a package
for exemption from the requirements
for Type C packages in the air
transport mode.
40 231.3 (to
be 232.3)
Proposed revised text:
Modify the second sentence as
follows:
Propose text changes to
make clear what features
the designer must reach
18
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
“In the case of Type B(U), Type
B(M), Type C and packages designed
to carry fissile material, the designer
must reach certification agreement
with the competent authority with
respect to any equipment attached
to the package during transport. for
certification.
agreement on with the
competent authority.
41 Table 1 (currently
located
immediately
following
para. 233.5)
Revision needed:
The header in the table needs to be
corrected, to properly reflect the
topic of the three columns of data:
Column 1: “Distance between
detector centre and package
surface (cm)”.
Column 2:” Half linear dimension
of package (cm)”.
Column 3: “Correction factora.”
Correction needed to
properly display data in
the table.
42 Table 1 Table 1 is currently inserted after
para 232.3, however it is only
referenced in para 220A.5 (to
become 221.5) and should be placed
with it.
To correct misplacement
of Table 1.
43 236.1 Proposed revised text:
Modify the 3rd
sentence as follows:
“The radiological protection criteria
defined in the BSS were therefore
used to establish radionuclide
specific exemption values (as listed
Additional text is
suggested to make clear
to readers where they can
find the radionuclide
specific exemption values
(needed here since this
19
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
in Table 2 of the Transport
Regulations) for transport purposes
(see para. 402.3).
text is not directly related
to Table 2 of SSR-6).
44 236.1 Proposed revised text:
A paragraph number (236.2) needs
to be added at the beginning of the
paragraph of new text that begins
with “The activity concentration
value……”..
Add paragraph number
for completeness.
45 236.3 Proposed revised text:
Add a carriage return before 236.2
and renumber para. 236.2 to become
236.3; and para. 236.3 to become
236.4.
Make change to
accommodate the above
correction for the large,
unnumbered paragraph
following para. 236.1.
46 238.1 Proposed revised text:
Modify text beginning with the 3rd
sentence as follows:
“For example, a special
arrangement might be necessary
for the disposal of old equipment
containing radioactive material
where there is no reasonable way to
ship the radioactive material in an
approved package. The hazard
associated with repackaging and
handling the radioactive material
could outweigh the advantage of
developing and using an approved
Text needed to make the
3rd
sentence complete,
and to ensure the full
paragraph communicates
properly.
20
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
package, assuming a suitable
package were could be made
available. The special arrangement
provisions should compensate for
not meeting all the normal
requirements of the Transport
Regulations by providing an
equivalent level of safety. In
keeping with the underlying
philosophy of the Transport
Regulations, reliance on
administrative measures should be
minimized in establishing the
compensating special arrangement
measures.”
47 244.1 “The TI performs many functions in
the Transport Regulations, including
providing the basis for the carrier to
segregate radioactive material from
persons, undeveloped film, and other
radioactive material consignments,
and to limiting the level of radiation
exposure to members of the public
and to transport workers during
transport and in-transit storage.”
Slight editorial change to
make verb tenses
consistent for each
clause.
48 244.2 Proposed revised text:
Modify the beginning sentence as
follows: “Beginning with In the
1996 Edition of the Transport
Proposed change for
clarity, the text in DS496
reads as though the
current edition of SSG-26
21
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
Regulations, the TI value no longer
makes any contribution to the
criticality safety accumulation
control accumulation control for
criticality safety of packages
containing fissile material.
Accumulation control for criticality
safety is now provided by a separate
CSI (see paras 218.1–218.23).”
is the 1996 edition. Also,
DS496 does not have a
subpara. 218.3 for CSI.
49 References
to Section
II
Proposed revised text for Reference
9:
See recommendation in the column
to the right.
Reference [9] cites an
edition that is out of date.
This document is revised
every two years. For
consistency and accuracy,
and to avoid confusion,
would it not be better to
make a statement with
respect to this document
similar to footnote 1,
Section I- i.e. indicating
that “Throughout this
publication, reference to
the UN Model
Regulations always
refers to the latest
edition.”?
50 301.1 Proposed revised text:
Modify the penultimate sentence as
follows: “In addition, in the case of
Suggest this change to
make it clear that this is
an action required for
22
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
potential exposures, the likelihood
of occurrence of accidents or events
or sequences of events is also to be
taken into account.”
optimization.
51 301.2 Proposed revised text:
Modify the beginning of the first
sentence as follows: “The BSS [4]
defines radiological……”.
Since the BSS is a single
document, “define”
should be singular.
52 301.2 Proposed revised text:
Appropriately number the three
following subparagraphs as follows:
a) “No practice is to be adopted
unless it produces a positive
net benefit (justification of a
practice).
b) All exposures are to be kept
as low as reasonably
achievable, economic and
social factors being taken
into account (optimization of
protection).
c) Total individual exposure is
to be subject to dose limits
or, in the case of potential
exposures, to the control of
risk (individual dose and risk
limits).”
Number subparagraphs
appropriately.
23
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
53 301.4 Proposed revised text:
Revise the 3rd
sentence as follows:
“In the case of workers devoted only
to transport activities, it will be
reasonable to set constraints for
transport of radioactive material. In
other cases, it may be appropriate
for individual users to include dose
constraints in their RPP, in which
case lower constraints would
normally be expected to be set
rather than for transport activity
only since, by definition ……”.
Add this word for clarity.
54 302.1 Proposed revised text:
Edit the sub-paragraphs preceding
the text “The RPP should…” as
follows:
— To provide for adequate
consideration of radiation
protection measures in
transport;
— To ensure that the system of
radiological protection is
adequately applied;
— To enhance a safety culture
in the transport of
radioactive material;
For consistent editorial
style.
24
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
— To provide practical
measures to meet these
objectives.
55 302.1 Proposed revised text:
Have the text beginning with “The
RPP should….” Be numbered as
302.2, and renumber existing 302.2
to 302.6 accordingly.
For consistent editorial
style.
56 303.1 Proposed revised text:
“The BSS [4] sets an effective dose
limit of 1 mSv per year on the
effective dose for members of the
public of 1 mSv in a year, and for
workers of 20 mSv per in a year
averaged over five consecutive years
and not exceeding 50 mSv in a single
year for workers. Dose limits in
special circumstances;, dose limits in
terms of equivalent dose for the lens
of the eye, extremities (hand and
feet), and skin;, and dose limits for
apprentices and pregnant women are
also set out in the BSS and should be
considered in the context of the
requirements of para. 303. These
limits apply to exposures attributable
to all practices, with the exception of
medical exposures and of exposures
Since the BSS is a single
document, “set” should
be singular. To avoid
confusion in the first
sentence, particularly
with respect to worker
doses, the units for the
dose limits were changed
to “per year.” Also, to
avoid repetition in the
second sentence, the
words dose limits were
deleted for the second
and third list items and
the list punctuation was
corrected.
25
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
to certain natural sources.”
57 303.5 “Given that relatively high dose rates
are permitted during carriage under
exclusive use, meaning that it would
be relatively easy to exceed the 1
mSv level, additional care should be
taken to ensure that the requirements
of para. 303 are met by employing ,
since it would be relatively easy to
exceed the 1 mSv level, and
consequently, specific measures
regarding monitoring or control of
exposures should be taken. In the
assessment of the overall individual
exposure, any exposures received
during the carriage phase of transport
should be considered, together with
those received elsewhere, particularly
during loading and unloading.”
The wording in the first
sentence is confusing, so
it was rewritten to add
clarity to the sentence.
58 306.3 Proposed revised text:
Revise the 2nd
sentence as follows:
“Where appropriate, the competent
authority will ensure that such a
management system is
implemented, as part of the timely
adoption and application of the
Transport Regulations.”
Propose adding this text
to make it clear that
ensuring implementation
of the management
system depends upon
more than just adoption
of the Transport
Regulations, it requires
application of the
provisions of the
Transport Regulations by
26
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
the competent authority
and the designers,
fabricators and users of
the packagings. This will
help bridge to this
concept which is
elaborated in para. 306.4.
59 306.4 Proposed revised text:
Modify the second sentence as
follows:
“For packages intended to be used
for shipment after storage, the
management system should also
address an ageing management
programme.
Adding the word “also”
will emphasize that this is
an additional requirement
of a management system
for packages that are
intended to be used for
shipment after storage.
60 307.1 Proposed revised text:
Modify the beginning of the second
sentence as follows; either:
“Emphasis should be placed….”; or
“Emphasis shall be placed….”.
The use of “is” implies
that this is already
accomplished. This is a
guidance document.
61 307.2 A carriage return is missing before
307.2.
62 308.2 “In order to comply with para. 308
of the Transport Regulations,
information on the radiation doses to
workers and to members of the
public should be collected and
reviewed as appropriate. For
Editorial.
27
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
example, Rreviews should be made
if circumstances warrant, for
example, if significant changes in
transport patterns occur or when a
new technology related to
radioactive material is introduced.
The collection of relevant
information may be achieved
through a combination of radiation
measurements and assessments.
Reviews of accident conditions of
transport are necessary in addition to
those of routine and normal
conditions.”
63 309.1 Proposed revised text:
Propose revising the text beginning
with the 3rd
sentence as follows:
“It was recommended at these
meetings that text addressing
requirements for actions needed in
the event of non-compliance
be added to the Transport
Regulations. In addition, the May
2000 meeting of the Transport
Safety Standards Committee
(TRANSSC) recommended that
the IAEA undertake a
coordinated research project
(CRP) on contamination. The
The addition of the work
undertaken in the CRP
will assist in providing
additional guidance to
users of SSG-26.
28
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
results of that CRP can be found
in IAEA TECDOC-1449 [15bis].”
The reference to be added at the end
of the Section is:
“[15bis] INTERNATIONAL
ATOMIC ENERGY AGENCY,
Radiological aspects of non-fixed
contamination of packages and
conveyances, IAEA-TECDOC-
1449, IAEA, Vienna (2005).”
64 309.3 Proposed revised text:
Revise the first part of the first
sentence as follows:
“309.3. The term ‘non-compliance’
has a very broad meaning and
includes any and all situations
(except transport accidents or
malicious incidents) ….”.
By stating “and and all
situations”, since the text
excludes accidents, it is
necessary to also include
in the exceptions actions
taken by those with
malicious intent (i.e.
“malicious incidents”).
65 310.1 Proposed revised text:
Modify the 3rd
sentence as follows:
“Special arrangement is based on
the requirement that the overall level
of safety resulting from additional
operational control or other
alternative means must be shown
to be at least ….”.
The addition of “or other
alternative means” is
needed since, as currently
written, it is implied that
special arrangements can
only be accomplished
through the application of
additional operational
controls. Alternatives to
the design of packaging
may also be used to
29
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
demonstrate that an
equivalent level of safety
has been achieved. This
is elaborated in the 2nd
sentence of 310.2 (i.e.
“new controls and
techniques”); and thus
310.1 should reinforce
this concept.
66 References
to Section
III
Proposed revised text for Reference
For Reference 16, see
recommendation in the column to
the right.
Reference [16], as cited,
is an edition that is out of
date. This document is
revised every two years.
For consistency and
accuracy, and to avoid
confusion, would it not
be better to make a
statement with respect to
these documents similar
to footnote 1, Section I-
i.e. indicating that
“Throughout this
publication, reference to
this modal regulation
always refers to the
latest edition.”?
67 References
to Section
III
Proposed revised text for Reference
For Reference 18, see
recommendation in the column to
Reference [18], as cited,
is an edition that is out of
date. This document is
30
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
the right. revised every two years.
For the UN Model
Regulations, Section II
cited the 2011 edition,
whereas Section III cites
the 2015 edition; but in
fact the UN Committee of
Experts has now issued
the 2017 edition. Thus,
for consistency and
accuracy, and to avoid
confusion, would it not
be better to make a
statement with respect to
these documents similar
to footnote 1, Section I-
i.e. indicating that
“Throughout this
publication, reference to
the UN Model
Regulations always
refers to the latest
edition.”?
68 401.1 Proposed revised text:
Recommend changing the text of the
4th
sentence as follows:
“This identification can be is used
for many purposes.”
This proposed changes
strengthens the argument
that the UN numbers are
actually used for the
purposes stated in the
following sentences
31
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
instead of implying that
they “might” be used.
69 401.1 Proposed revised text:
Recommend changing the text of the
penultimate sentence as follows:
“Each UN number can be is
typically associated with a unique
emergency response advice
This proposed changes
strengthens the argument
that the UN numbers are
actually used for
referencing to unique
emergency response
advice instead of
implying that they
“might” be used in this
fashion.
70 402.1 Proposed revised text:
Recommend changing the text of the
last sentence as follows:
“In the 20xx Edition of SSR-6,
seven new radionuclides, Ni-57, Ge-
69, Sr-83, Ba-135m, Ir-193m, Tb-
149 and Tb-161, were added to
Table 2 of the Transport
Regulations, to provide ….”.
This proposed change
would make it clear that
the table being referred to
is in SSR-6 and not in
SSG-26. This is
consistent with the text of
402.3 where Table 2 is
cited.
71 402.4 (and
following
402.x para-
graphs)
Proposed revised text:
Following the two sub-paragraphs
((a) and (b)) of para. 402.4,
recommend that the text then read
“402.5 The exemption values were
derived……”.
And then the following 402.x
paragraph numbers be adjusted
This recommended edit
would simply make the
text flow better.
32
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
accordingly.
72 402.6 Proposed revised text:
Recommend changing the second
sentence as follows: “The same
exemption values are reproduced in
the Transport RegulationsSSR-6,
Table 2, Basic Radionuclide
Values.”
This change would make
the text consistent with
the wording used
elsewhere, i.e. using “the
Transport Regulations”
rather than “SSR-6”.
73 403.1 Proposed revised text:
Recommend changing the text of the
first sentence as follows: “For
individual radionuclides that are not
listed in Table 2 of the Transport
Regulations, activity concentrations
….”.
This proposed change
would make it clear
which table is being
referred to.
74 403.3 Proposed revised text:
Recommend changing the text of the
first sentence as follows:
“Multilateral approval is needed for
alternative activity limits for an
exempt consignment of instruments
and articles.”
The word “instruments”
needs to be plural.
75 405.3 “Calculation of the activity
concentration for exempt material is
only permitted in the case of a
homogeneous mixture, since the
models for determining these activity
concentrations are based on the
assumption that the isotopes are
Changed the words
homogeneously and
homogeneity to uniformly
and uniformity,
respectively, to be
consistent with the
discussions provided in
33
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
distributed uniformly homogeneously
throughout the material. A The
degrees of uniformity homogeneity
can be referred to are further
discussed in paras 409.15 and
409.10–409.14.”
paragraph 409. The
correct reference (409.1)
is added, and the
incorrect reference
(409.5) is removed.
76 409.1 Proposed revised text:
Recommend changing the text of the
first sentence as follows: “The
preamble to the LSA definition
(see para. 226.3) does not …..”.
This is suggested to make
it clear what preamble is
being referred to.
77 409.10/1-3 For material required to be
“distributed throughout”, that is
(LSA-II solids and LSA-III material
not incorporated into a solid
compact binding agent), a simple
method for assessing…
Editorial
78 409.10/5-6 It is suggested that tThe differences
in specific activity between portions
of a factor of less than ten would
should cause no concern if there is
no indication…
Editorial
79 409.13/6-7 It is suggested that sSpecific activity
differences between the portions of
less than a factor of three would
should cause no concern…
Editorial
80 413.5 Proposed revised text:
It is proposed that para. 413.5 be
moved forward and made para.
This would place a key
constraint on SCOs at the
beginning of the
34
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
413.1; and that the remaining 413.x
paragraphs be incremented upward
by one digit.
discussion.
81 413.6 The existing guidance in 413.6 is
proposed to be deleted.
413.6. Examples of inaccessible
surfaces are:
(a) Inner surfaces of pipes, the ends
of which can be securely closed by
simple methods;
(b) Inner surfaces of maintenance
equipment for nuclear facilities
which are suitably blanked off or
formally closed;
(c) Gloveboxes with access ports
blanked off.
And replaced with the following
paragraphs:
413.6 An accessible surface is any
surface which can readily be wiped
by hand, using standard radiation-
measuring techniques. Any other
surface that is not accessible due to
a design feature, barrier or closure
that remains effective during routine
conditions of transport is an
To address the
commitment made at the
SCO-III working group at
TRANSSC 34 to add
guidance to SSG-
26(DS496) to clarify the
terms external, accessible
and inaccessible surfaces
in para. 413 for SCO
since CDN/8 and USA/9
change proposals were
accepted.
35
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
inaccessible surface. A good rule of
thumb is that, if a 300 cm2 area
could be reached by a person’s
hand, it is an accessible surface. The
phrasing “by hand” is not meant to
discourage use of as low as
reasonably achievable tools such as
telescopic sampling instruments.
The phrasing “standard radiation-
measuring techniques” is intended
to imply practices similar to those
used for complying with package
contamination limits in para. 508.
413.6 bis An accessible surface may
be rendered inaccessible for
transport by securely closing or
blanking it off, such as;
a) Large diameter pipes that are
closed off at the ends;
b) A tool box or other
maintenance equipment that
is securely closed;
c) A glovebox with the access
ports blanked off.
413.6 bis For SCO-III, external
inaccessible surfaces, such as the
narrow gap between manway covers
36
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
and the component, are normally
filled or closed out with weld
material or caulk to prevent
contamination leakage during
transport, as shown in the following
illustration:
82 413.11 413.11 For SCO-III, there is no
specific limits for the levels of fixed
contamination on the external
surfaces, since similar to packages,
the external radiation resulting
therefrom will combine with the
penetrating radiation from the
contents, and the net radiation levels
are controlled by other specific
requirements. The fixed
contamination may not be able to be
practically measured due to the dose
To address the
commitment made at the
SCO-III working group at
TRANSSC 34 to add
guidance to SSG-
26(DS496) to clarify why
limits for fixed
contamination are not
specified in para. 413 for
SCO-III, since CDN/9
and USA/7 change
proposals were accepted.
37
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
rate emanating from the large object,
the levels of which should be
minimal in nature, and will be
accounted for in label selection, as
with packages. The limit on the
external non-fixed contamination is
conservatively set to that for
packages which, combined with the
controls on radiation levels will
ensure that the risk from fixed
contamination is low. The major
percentage of the component’s
activity (A2 quantity) should be due
to surface contamination on interior
surfaces, rather than on exterior
surfaces or resulting from neutron
activation of the component.
Though a threshold value is not
specified, this is not intended to
allow transport of components with
non-fixed external surface
contamination exceeding the levels
specified in para. 508 of the
Transport Regulations or with overt
activation of material. Transport of
clearly activated components, such
as reactor vessels, are is outside the
scope of SCO-III.
The red text in the
following two paragraphs
of the current draft of
SSG-26 was deleted at
the January 2017 review
meeting, and should be
reinstated, as it now
applies after acceptance
of the Canadian and U.S.
change proposals to SSR-
6. The struck out text was
also deleted at the
January 2017 review
meeting, but should
remain deleted. The blue
text is new proposed text
added for further clarity.
38
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
83 413.12 413.12 For SCO-III, contamination
on the inaccessible surface may be
determined by conservative
estimates and/or analysis by
methods other than direct
contamination measurements. In the
Q system (see Appendix I), five
radiation exposure routes, i.e.
external photon dose (QA),external
beta dose (QB), inhalation dose
(QC), skin and ingestion dose due to
contamination transfer (QD) and
submersion dose (QE) are
considered. Among these, the
inhalation dose (QC) can be taken as
a major exposure route for SCO-III
in the event of an accident, since
most of the activity that is dispersed
is from the surface contamination
that comes from the surfaces of the
object which may be scratched
during an accident. If a SCO-III is
involved in an accident, the
maximum activity intake for a
person in the vicinity of the accident
should be approximately of the same
level as that from Type A packages
(see Appendix VII).
To address the
commitment made at the
SCO-III working group at
TRANSSC 34 to add
guidance to SSG-
26(DS496) to clarify why
limits for fixed
contamination are not
specified in para. 413 for
SCO-III, since CDN/9
and USA/7 change
proposals were accepted.
The red text in the
paragraph of the current
draft of SSG-26 was
deleted at the January
2017 review meeting, and
should be reinstated, as it
now applies after
acceptance of the
Canadian and U.S.
change proposals to SSR-
6.
84 417.1 Proposed revised text: This change is
39
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
Recommend changing the text in the
3rd
sentence to read as follows:
“These provisions are were
incorporated in the 2012 Edition of
the……”.
recommended since this
draft of SSG-26 is
intended to reflect the
20.xx Edition of SSR-6,
not the 2012 Edition.
85 422.3 “In the case of special form solid
material, the probability of release of
any dispersible radioactive material is
very small. Thus, if radiotoxicity
were the only hazard to be
considered, much higher activity
limits could be accepted for special
form solid material in excepted
packages. However, the nature of
special form does not provide any
additional protection where external
radiation is concerned. The limits for
excepted packages containing special
form material are therefore based on
A1
rather than A2. The basic limit
selected for special form solid
material is 10–3
A1. This limits the
external dose equivalent rate from
unshielded special form material to
one thousandth of the rate used to
determine the A1 values.”
Deleted equivalent from
dose equivalent rate.
86 501.5 “In performing the post-fabrication
tests and inspections on packagings
Corrected typos and
punctuation errors.
40
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
following fabrication to assess the
effectiveness of shielding of Type
B(U), Type B(M), and Type C
packages and packages containing
fissile material, the shielding
components may be checked by a
radiation test of the completed
assembly. The radiation source for
this test need not be the material
intended to be transported, but care
should be taken such that shielding
properties are properly evaluated
relative to energy, energy spectrum,
and type of radiation. Particular
attention should also be paid to the
homogeneity of packaging material
and the possibility of increased
localized dose rates at joints. For
methods of testing the integrity of a
package’s radiation shielding, (see
Refs [1, 2] and paras 659.14–
659.19).”
87 520.2 Proposed revised text:
Recommend changing the lead-in
text of the first sentence as follows:
“A written transport plan is should
be used to govern ……”.
The use of “is” implies
that this is already
accomplished. Thus,
propose the change since
SSG-26 is a guidance
document. The use of
“should” is consistent
with the rest of the text in
41
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
this and the following
paragraph.
88 520.1 bis3
first bullet
(to become
520.5)
There is no explicit limit on the
dose rate on the external surface
(there is nevertheless a limit of 10
mSv/h at 3 m of the object and
there is a limit of 2 mSv/h at the
external surface of the vehicle).
Anyway, if the surface dose rate of
the SCO-III is higher than 2
mSv/h, the transport plan should
contain special precautions to
ensure workers and public
radioprotection, including during
loading and unloading phases if
applicable, and control of the
access to the object.
There is no alternative limit on the
dose rate for SCO-III (all existing
radiation dose rate limits apply
such as 10 mSv/h at 3 m from the
unshielded contents as well as
package limits). However, due to
the size of these objects and their
slow movement compared to most
packages, the transport plan should
contain special precautions to
ensure workers and public
The 10 mSv/hr at 3
meters applies to the
unshielded contents as
with any LSA/SCO,
suggest rewording.
42
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
radioprotection, including during
loading and unloading phases if
applicable, and control of the
access to the object.
89 520.1 bis3
second
bullet
(520.5)
Besides, there is no obligation to
label a SCO-III object. Then, the
transport plan should
contain provisions to ensure that the
workers are well-informed of the
dose rate in the vicinity of
the object, so that they can protect
themselves.
SCO-III should be
labeled as any other
package, suggest deleting
bullet.
90 520.1 bis3 “The transport plan should also
address the following points:
- Although There there is no explicit
dose rate limit on the dose rate on the
external surface, (there are is
nevertheless a limits of 10 mSv/h at 3
m of from the object and there is a
limit of 2 mSv/h at the external
surface of the vehicle). Anyway, iIf
the surface dose rate of the SCO-III is
higher than 2 mSv/h, the transport
plan should contain special
precautions to ensure radioprotection
of workers and the public
radioprotection, including during
loading and unloading phases if
applicable, and control of the access
Editorial changes for
clarity.
43
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
to the object.
- Besides, tThere is no obligation to
label a SCO-III object. Thereforen,
the transport plan should contain
provisions to ensure that the workers
are well-informed of the dose rate in
the vicinity of the object, so that they
can protect themselves.
- Any supplementary requirements for
loading, stowage, carriage, handling
or unloading for the SCO-III.”
91 520.3 “As part of the SCO-III transport
plan, special attention should be paid
to the radiation protection programme
since the transport of SCO-III would
be conducted in a different manner
from the routine transport of ordinary
packages and may involve workers
not familiar with transport operations.
As such, it should take into account
all steps and activities of transport
and all relevant transport workers and
members of the public. Radiation
levels Dose rates of the object,
transport and handling methods,
including durations and distances of
workers from the object in each
Changed radiation levels
to dose rates. Also, the
last sentence needs to be
revised because it is
confusing. No suggested
replacement was
provided because the
meaning of the sentence
is unclear.
44
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
operation, should be carefully
examined and doses to workers
should be optimized with the proper
dose constraint.”
92 520.4 Proposed revised text:
Recommend changing this text to
read as follows:
“Requirements for loading, stowage,
carriage, handling and unloading,
including any special stowage
provisions for the safe dissipation of
heat should are to be addressed
in the SCO-III transport plan.
The use of ‘are” should
not be used in a guidance
document.
93 520.1 bis3 AnywayHowever, if the surface
dose rate of the SCO-III is higher
than 2 mSv/h, the transport plan
should…
Editorial
94 520.5 Proposed revised text:
Recommend changing the first
sentence as follows: “The basic
concept of allowing transport of
SCOs unpackaged is that, though
unpackaged, the objects should will
most likely comply with the
applicable Type IP package
requirements, …..”.
Propose this change to
emphasize that this
concept will probably
result in compliance with
the IP requirements (the
use of should seems to be
inappropriate here).
95 520.5 Proposed revised text:
Recommend that the second
sentence be changed to read as
This change is
recommended since this
is an action that those
45
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
follows: “In addition to being
allowed to be transported
unpackaged, certain requirements
for Type IP packages may need to
be excluded, …..”.
preparing the item for
shipment may need to
take.
96 520.7 Proposed revised text:
Recommend the following change
to the beginning of the first
sentence: ‘As addressed in para.
722.6 in this publication, if the ….”.
This is the first time that
a paragraph in SSG-26 is
cited where this
modifying text was
added. Suggest deletion
to be consistent.
97 521.1 Proposed revised text:
Carriage return is missing before
521.1. Recommend changing the 2nd
sentence as follows: “In assessing
the potential hazards, the physical
form of the LSA material should be
has been taken into account.
The use of “has been”
implies that the
Regulations have taken
the physical form into
account. The entity
preparing the material for
shipment should be
responsible for taking the
physical form into
account.
98 522.1 “The The Conveyance conveyance
activity limits for LSA material and
SCO have been specified, the account
for potential hazards having been
taken into account, including the
greater hazards presented by liquids,
and gases, and combustible solids as
well as and possible contamination
This is an awkwardly
worded sentence. The
proposed text attempts to
clarify the sentence.
46
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
levels, in the event of an accident.”
99 522.3 Proposed revised text:
Recommend changing this sentence
as follows: “If an SCO-III item is
involved in an accident, an the pre-
shipment equivalent level of safety
assessment should ensure have
demonstrated that the maximum
activity intake for a person in the
vicinity of the accident should
would be approximately of the same
as that from Type A packages (see
Appendix VII).”
As worded, this implies
that the Regulations have
achieved this. However,
the entity preparing the
item for shipment as
SCO-III needs to
demonstrate that “the
maximum activity intake
for a person in the
vicinity of the accident
would be approximately
of the same as that from
Type A packages”.
100 522.4 Proposed revised text:
Recommend to following changes to
the 1st sentence and the beginning of
the 2nd
sentence: “For SCO-III, it is
permitted to exceed the limit of 100
A2 per conveyance, other than for
an inland waterway craft, or to
exceed the limit of 10 A2 per hold
or compartment except for of an
inland waterway craft, provided than
that the transport plan contains
precautions to which are to be
employed during transport to obtain
an overall level of safety at least
equivalent to that which would be
Several typos and
punctuation mistakes
were corrected, and
portions of the
paragraphs were rewritten
to make them clearer.
47
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
provided if the limits had been
applied. For inland waterway craft
crafts, there is a risk of activity
accumulation in the case of a sinking,
as there is are no strong currents in
the inland waterways and as nor are
there is any probably probable human
activities near the waterways. The
limit of the total activity per hold or
compartment allows to addresses this
risk. The precaution to put in the
transport plan can then be: transport
plan can include
- some precautions on the craft to
limit lower the risk of shrinking
sinking; or
- the designation of an organisation
capable of removing to be able to
remove the SCO-III from the water in
the case event of a shrinking sinking;
or
- some features on of the SCO-III that
guaranty guarantee that even in the
case of a realistically long stay in the
water, the activity release into the
water would be limited.
For conveyances other than inland
48
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
waterway craft, since there is a risk of
activity accumulation in the case of
an accident in a confined space (e.g.,
as a tunnel),. The the total activity
limit is lower. limit of the total
activity allows to address this risk. In
this case, the transport plan can
include The precaution to put in the
transport plan can then be:
- some precautions to limit minimize
the risk of an accident; or
- some itinerary limitations to avoid
confined areas; or
- some features on of the SCO-III that
guaranty guarantee that even in the
case of an accident in a confined area,
the activity release into the air would
be limited.”
101 522.4 Proposed revised text:
Recommend the following changes
to the 3rd
sentence: “The limit of the
total activity per hold or
compartment allows to address
addresses this risk.”
Recommend these
changes to improve the
English text and to make
the provision
understandable and
complete.
102 522.4 Proposed revised text:
Recommend the following changes
to the text following the first 3 sub-
Recommend these
changes to improve the
English text and to make
49
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
bullets: “For conveyances other than
inland waterway craft, there is a risk
of activity accumulation in the case
of an accident in confined space (as
a tunnel). The limit of the total
activity allows to address this risk.
The precaution to put in the
transport plan can then be:
- some precautions to limit the risk
of an accident ; or
- some itinerary limitations to avoid
confined areas ; or
some features on the SCO-III that
guaranty that even in the case of an
accident in a confined area, the
activity release in the air would be
limited.
For conveyances other than
inland waterway craft, there is a
risk of activity accumulation in
the event of an accident in a
confined space (e.g. in a tunnel).
The total activity limit addresses
this risk. The transport plan could
provide provisions such as:
controls or features that limit the
risk of an accident;
- routeing constraints that avoid
confined areas; or
the provision
understandable and
complete.
50
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
features on the SCO-III that
guaranty that even in the case
of an accident in a confined
area, the activity release in the
air would be limited.
103 523.1(d) “The TI for a freight container, tank,
unpackaged LSA-I or unpackaged
SCO-I is the maximum dose rate at 1
m from the external surface of the
load, expressed in mSv/h and
multiplied by 100 and then further
multiplied by an additional factor
which that depends on the largest
cross-sectional area of the load. This
additional multiplication factor, as
specified in Table 7 of the Transport
Regulations, ranges from 1 up to 10.
It is equal to 1 if the largest cross-
sectional area of the load is 1 m2 or
less. It is 10 if the largest cross-
sectional area is more than 20 m2
. The
TI for a freight container may be
established alternatively as the sum of
the TIs of all the packages in the
freight container. For an open-sided
or open-top freight container, surfaces
of a rectangular prism encompassing
the container structure and the load
can be considered as the surfaces of
the load, and the largest cross-
Minor editorial changes
were made to the text.
51
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
sectional area of that prism is can
then be used to determine the
additional multiplication factor in
Table 7 of the Transport
Regulations.”
104 523.3 “The multiplication factors in Table 7
are intended to apply the to large
dimensional loads which that cannot
be simulated as a point source but
must be simulated as a surface source
or a volume source since the
radioactive material is distributed
uniformly throughout the load. such
as unpackaged material or
accumulation of packages. As the
dose rate distribution around a
package, which provides enough
shieldings around their its radioactive
source to comply with prescribed TI
limits prescribed (see such as in para.
527 of the Transport Regulations), is
rather similar to that obtained using a
of the point source model, no
multiplication factor need to be
applied to packages.”
The meaning of this
paragraph is unclear.
Minor editorial changes
were introduced to make
the sentence clearer, but
it is uncertain whether the
original intent of the text
has been preserved.
105 525.1 –
536.1
These paragraphs should be
renumbered 526.1 – 537.1
In DS495, para. 524 from
SSR-6 has been divided
into para 524 and 525,
causing following
paragraphs to increment
52
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
by 1.
106 537.1 –
584.1
These paragraphs should be
renumbered 539.1 – 586.1
Same as above and the
addition of para 538 in
DS495 requires adding 2
to each of these para
numbers.
107 546.4 (to
be 548.4)
“Care should be exercised in
selecting the proper shipping name
from Table 1 of the Transport
Regulations. Portions of an entry that
are not highlighted by written in
capital (i.e., uppercase) letters are not
considered part of the proper shipping
name. When the proper shipping
name contains the conjunction ‘or’,
then only one of the possible
alternatives should be used. The
following examples illustrate the
selection of proper shipping names of
the entry for UN numbers 2909 , 2915
and 3332:
For UN No. 2909 RADIOACTIVE
MATERIAL, EXCEPTED
PACKAGE — ARTICLES
MANUFACTURED FROM
NATURAL URANIUM or
DEPLETED URANIUM or
NATURAL THORIUM, The the
proper shipping name is the
Attempted to modify the
text to more clearly
illustrate the selection of
proper shipping names.
53
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
applicable description from the
following:
a.) UN No. 2909 RADIOACTIVE
MATERIAL, EXCEPTED
PACKAGE — ARTICLES
MANUFACTURED FROM
NATURAL URANIUM,
b.) UN No. 2909 RADIOACTIVE
MATERIAL, EXCEPTED
PACKAGE — ARTICLES
MANUFACTURED FROM
DEPLETED URANIUM, or
c.) UN No. 2909 RADIOACTIVE
MATERIAL, EXCEPTED
PACKAGE — ARTICLES
MANUFACTURED FROM
NATURAL THORIUM.
UN No. 2915 RADIOACTIVE
MATERIAL, TYPE A PACKAGE,
non-special form, non-fissile or
fissile-excepted
UN No. 3332 RADIOACTIVE
MATERIAL, TYPE A PACKAGE,
SPECIAL FORM, non-fissile or
fissile-excepted
54
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
For UN No. 2915 RADIOACTIVE
MATERIAL, TYPE A PACKAGE,
non-special form, non-fissile or
fissile-excepted UN No. 3332
RADIOACTIVE MATERIAL, TYPE
A PACKAGE, SPECIAL FORM,
non-fissile or fissile-excepted, The
the proper shipping name is the
applicable description from the
following: UN No. 2915
RADIOACTIVE MATERIAL, TYPE
A PACKAGE UN No. 3332
RADIOACTIVE MATERIAL, TYPE
A PACKAGE, SPECIAL FORM.
As can be seen from the example of
UN No. 3332, the added
characteristic (in this case, “special
form”) is explicitly spelled out, and
the lowercase words “non-fissile or
fissile-excepted” are not part of the
proper shipping name.”
108 546.5 (to
be 548.5)
“Another example related to the
interpretation and use of the UN
number concept relates to empty
packagings which that previously
have contained radioactive material
(i.e., UN No. 2908). If there are
residues or heels in the packaging, for
example, in uranium hexafluoride
Minor editorial changes.
55
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
packages, the packaging should not
be called an ‘empty packaging’ but
should be shipped as a package (i.e.,
not as a packaging). The quantity
remaining would determine the
package category (see para. 427.4).”
109 562.1 (to
be 564.1)
“Operational controls that are applied
in the transport of radioactive
material can include the use of
segregation distances. Segregation
distances are usually tabulated as a
function of These generally take the
form of tables relating the total TI
with the segregation distance, along
with some time dependence. These
tables are generally derived at a
global or national level (e.g., the
ICAO Technical Instructions [12])
and include the effects of the
operations of many consignors,
shippers and carriers on either the
most exposed worker or a
representative person of the public.”
Minor editorial changes.
110 564.3 “An example of such a review was
carried out during the preparation of
the 1996 Edition of the Transport
Regulations. The model and dose
criteria were examined in light of the
developing philosophy of dose
constraints, as amplified discussed in
The use of the word
amplified seemed
inappropriate, so it was
replaced with the more
generic word discussed.
56
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
Ref. [38] (the methodology of which
is used in Ref. [39]). A dose
constraint of 0.7 mSv was considered
appropriate for exposure of a critical
group of the public to direct radiation
from sources such as radioactive
material in transport. This constraint
was envisaged as being applicable to
global transport operations in general
rather than the operations of one
particular consignor. Over a series of
three technical meetings, information
on assessed exposures to members of
the public was actively collected and
evaluated. The assessment of this
information demonstrated that
exposures being received by members
of the public from these operations
were far below the dose criterion used
in the modelling and the appropriate
dose constraint [40]. The conclusion
of these studies was that the existing
segregation tables and the other
provisions of the Transport
Regulations together provide for an
appropriate level of radiological
safety. However, these evaluations
were not adequately reflected in the
associated guidance publication. It is
considered that the current
57
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
segregation tables are consistent with
the use of appropriate dose
constraints. For example, the
postulated public doses presented in
the tables relate to a 1 mSv dose with
a very pessimistic model (exposures
are actually estimated to be of the
order of tens of microsieverts), not (as
was intimated in the 1996 guidance
publication) a realistic model.”
111 570.2 (to
be 572.2)
570.2. The basis for a 45 g
consignment limit in items (c) and
(e) is given in para. 417.5. A 15 g
consignment limit was set, not for a
technical or a safety reason, but for a
practical reason (physical
protection).
It is not clear how the 15g
consignment limit for
material transported
under para. 417(d)
provides physical
protection. Recommend
removing the sentence. If
retained, provide more
detail about how the limit
ties to physical protection
requirements.
112 575.7, 1st
sentence
For SCO-III, paras. 575(b) and
575(c) apply. The dose rate at the
surface of the SCO-III is limited as
specified in para. 517.
All standard dose rate
limit provisions apply,
such as paras 517, 573
and 575, unless
alternatively addressed
for watercraft to provide
an equivalent level of
safety.
58
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
113 575.7, 2nd
sentence
Proposed revised text:
Recommend the following changes
to the last sentence: “In the case of a
SCO-III with a surface dose rate
greater than 2 mSv/h, the
precautions to control the access by
workers and members of the
public, secure the object, limit risk
during loading or unloading, and
any other relevant precaution
precautions, should be set specified
in the transport plan.”
Proposed change to
provide clarity in the text.
114 575.1 (to
be 577.1)
Proposed revised text:
Recommend the following changes
to the last sentence: “Then, these
controls, and any other relevant
precaution precautions, should be
set specified in the transport plan.”
Proposed change to
provide clarity in the text,
and for consistency with
changes proposed for
573.7 noted above.
115 579.2 (to
be 581.2)
Proposed revised text:
Recommend the following changes
to the last sentence: “Then, these
precautions should be set specified
in the transport plan.”
Proposed change to
provide clarity in the text,
and for consistency with
changes proposed for
575.7 and 577.1 noted
above.
116 581.1 (to
be 583.1)
“When authorization is given to an
organization for the use of the postal
service, one a suitably knowledgeable
and responsible individual should be
appointed to ensure that the correct
Minor editorial change.
59
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
procedures and limitations are
observed.”
117 References
to Section
V
Proposed revised text for References
to Section V:
See recommendation in the column
to the right for References 8, and
10-14.
Please see earlier
comments regarding the
UN Recommendations
and modal regulatory
documents that are
revised every two years.
It is recommended that
similar wording be used
for these references in
this section.
118 602.1 –
613.2
These paragraphs should be
renumbered 601.1 -612.2
In DS495, para 601 from
SSR-6 was deleted,
causing the following
paragraph numbers to
shift 3.
119 605.2/42-
44
It may be possible, with competent
authority approval, to specify that
the material be transported in a
minimum quantity to provide
protection in the case of an accident
(e.g. thermal inertia).
This paragraph appears
redundant, and it is not
clear what is intended by
the “thermal inertia”
example. Recommend
removing it.
120 613A.1 -
613A.5
These paragraphs should be
renumbered 613.1 – 613.5
In DS495, para 613 was
inserted and combined
with above comment,
paragraph numbers now
match.
121 613A.1 Proposed revised text: Proposed changes to
60
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
Recommend the following changes
to this text: “Package components
are subjected to degradation
mechanisms and ageing processes
which depend on the component
itself and its operational conditions.
Thus the design of a package should
take into account ageing
mechanisms commensurate to with
the operational conditions with
following a graded approach
manner. A designer of package
should evaluate the potential
degradation phenomena over time,
such as corrosion, abrasion, fatigue,
crack propagation, changes of
material compositions or
mechanical properties due to
thermal loadings or radiation,
generation of decomposition gas,
and their impact on the functions
important to safety. How to apply
Applying the graded approach to
ageing consideration depends on the
intended use of the package and its
operating conditions.”
provide clarity in the text.
122 613A.2 Proposed revised text: In the last
sentence of this paragraph, reference
should be to para. 613.4.
Need to clarify reference
to another paragraph.
61
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
123 613A.3 Proposed revised text:
In the first two sentences, make the
following change: “For packages
intended for the repeated use, during
the design phase, ageing mechanism
mechanisms should be evaluated
during the design phase to
demonstrate adequate safety in the
safety demonstration. Based on this
evaluation, an inspection and
maintenance programme should be
developed.”
Proposed changes to
provide clarity in the text.
124 613A.4 Proposed revised text:
The following is revised text (not
showing the original text):
“The ageing degradation of
Structure, System, and Components
(SSCs) Important to Safety (ITS)
should be considered in design and
maintenance of packages for
transportation, storage, and
transportation after storage. This
situation recognizes that the
Transport Regulations do not apply
to long-term storage. During long-
term storage of packages containing
radioactive contents, it may be
difficult to perform inspections to
detect ageing effects of SSCs ITS.
Proposed changes to
provide clarity in the text
and to shorten a very long
sentence.
62
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
An ageing management programme
(see e.g. para. 306.4bis, and for
details see Ref. [10bis]) to address
ageing degradation (para. 809.3) and
a gap analysis program (see para.
809.4) to incorporate changes in
current regulations, technical
knowledge and package design
should be provided. These
programmes are required in the
application of the design approval of
packages for shipment after storage
as prescribed in para. 809.1 of the
Transport Regulations. The ageing
management and gap analysis
programmes should be incorporated
into an inspection plan prior to
transport.”
125 613A.5 Proposed revised text:
This new paragraph mentions ISO
7195 and ANSI N14.1 without
reference citation.
Para. 631.1 cites the ISO 7195
standard as Reference 18; and para.
631.2 mentions ANSI N14.1, but
does not provide a reference number
citation. Also, the references at the
end of Section VI cite ANSI N14.5
Need for consistency in
citing references.
63
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
and ANSI N14.6.
Should this be cited by reference
number also?
126 624.4 Proposed revised text:
Recommended change to the
beginning of the 2nd
sentence as
follows: “The compliance to
Compliance with this requirement
can be…..”.
Proposed change to
provide clarity in the text.
127 624.5 Proposed revised text:
Recommend the following change
to the beginning of the first
sentence: “In case when the When
compliance to the requirement….”.
Proposed change to
provide clarity in the text.
128 624.5 Proposed revised text:
Recommend the following change
to the added parenthetical text: “(i.e.
Co-60 or Na-24 for general package
use or specific nuclides for a certain
specific package design and or
appropriate related activities which
that could result the in a detectable
change of dose rate to be
detectable).”
Proposed change to
provide clarity in the text.
129 673.6/4 Typical neutron absorbent absorber
materials used for criticality control
“Absorbent” not typically
used to describe neutron
absorber materials.
Appears to be a
64
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
typographical error.
130 674.1 Proposed revised text:
Recommend changes to the added
sentence as follows: “These
provisions are were incorporated in
the 2012 Edition of the Transport
Regulations, and their technical
background and detail guidance for
application are provided in Ref.
[48bis].”
To properly reflect that
this document is
providing guidance on
the 20xx version of the
Transport Regulations.
131 683.2/3 Paragraph 683.2(a) requires a single
package, …
Typographical error.
132 References
to Section
VI
Proposed revised text for References
to Section VI:
See recommendation in the column
to the right for References 11, 12,
14, and 15.
Please see earlier
comments regarding the
UN Recommendations
and modal regulatory
documents that are
revised every two years.
It is recommended that
similar wording be used
for these references in
this section.
133 701.1/3 The intent is to allow the applicant
to use accepted engineering practice
to evaluate a package or of
radioactive material.
Typographical error.
134 809.3 Proposed revised text:
Recommend changing the text of as
follows: “As the package packages
Proposed change to
provide clarity in the text.
65
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
used for shipment after storage will
be may have been put into in
service for a long duration with the
radioactive contents loaded, the
effects of degradation mechanisms
and ageing process processes
should be demonstrated to comply
evaluated to demonstrate that the
packages satisfy the original or
new safety requirements prior to
shipment following storage. safety
justifications throughout the storage
period in order to
maintain transportability after
storage. It This may be
demonstrated through periodic
will be demonstrated by the
periodical safety assessments
assessment together with inspection,
monitoring and surveillance of the
package, its contents, and its
operational and environmental
conditions as well as maintenance
during storage. Such manner will
evaluations should be documented
by the applicant in an Ageing
Management Programme, which
will be is maintained under the
management system (see para.
66
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
306.4). Examples for consideration
on ageing mechanism of the
package used for shipment after
storage can be found in Refs
[1bis12] to [1bis67].”
135 809.4 Proposed revised text:
Recommend changing the text of as
follows:
“A gap analysis programme
should be established. This
programme, which may or may
not be considered as a periodic
safety review of the package
design, is an assessment of
whether the package design
complies with the current storage
and transport regulatory
requirements. It should consider
changes of the regulations,
changes in technical knowledge
and changes of the state of
package design during storage;
identifying existing gaps.
Furthermore, it should describe
the applicant’s procedure for
conducting such an analysis or
review in order to support the
package design approval
certificate renewal process or the
Proposed change to
provide clarity in the text.
The text was revised
without using track
changes.
67
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
validity of existing certificates
throughout the storage period and
transport following storage.
Detailed information relative to
objectives of the gap analysis
programme can be found in
[1bis78], and further references
on gap analysis for package used
for shipment after storage can be
found in Refs [1bis89] and
[1bis1112].”
136 819.1 Following the adoption of the 1985
Edition of the Transport
Regulations, packages not requiring
approval of design by the competent
authority based on the 1973 Edition
of the Transport Regulations and the
1973 (As Amended) Edition of the
Transport Regulations could no
longer be used. Continued
operational use of such packages
required either that the design be
reviewed according to the
requirements of the 1985 latest
Edition of the Transport
Regulations, or that shipments be
reviewed and approved by the
competent authority as special
arrangements, although this was not
Revert back to 2012 text.
Not clear why these
changes were made and
they do not appear to be
needed.
68
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
explicitly stated in the Transport
Regulations.
137 820.3 The 1973 and 1973 (As Amended)
Editions of the Transport
Regulations only required quality
assurance programmes (now
referred to as the management
system)2 to be established for the
manufacture of packagings. The
1985 Edition of the Transport
Regulations properly identified the
need for quality assurance
programmes (now referred to as the
management system) to cover all
aspects of transport from design,
manufacture, testing,
documentation, use, maintenance
and inspection of all packages, to
actual transport and in-transit
storage operations. Following
adoption of the 2018 Edition of the
Transport Regulations these
packages based on the 1973 Edition
of the Transport Regulations and the
1973 (As Amended) Edition of the
Transport Regulations could no
longer be used.
To clarify “these
packages”. As drafted, it
could be read to apply to
1985 designs as well.
Change is to be consistent
with paragraph 820.1.
138 820.6 In the process of developing the
1996 2018 Edition of the Transport
Changed to eliminate
continued use of 1973
69
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
Regulations, it was determined that
there was no need for an immediate
change of the Transport Regulations
following their adoption, but that
changes aiming at a long term
improvement of safety in transport
were justified. Therefore, it was also
decided to accept continued
operational use of certain packages
designed and approved under the
1973, or 1973 (As Amended), or
1985, or 1985 (As Amended 1990),
1996 Edition, 1996 Edition
(Revised), 1996 (As amended
2003), 2005, 2009 and 2012
Edtions of the Transport
Regulations. The continued use of
existing packagings with a 1967,
1973, or 1973 (As Amended),
Edition of the Transport Regulations
based package design approval was
considered to be no longer necessary
or justified.
design packages and to
add transition for 1996-
2012 package designs (as
modified by Feb. 2016
CSM).
139 820.7 The continued use of approved
packages meeting the requirements
of the 1973, or 1973 (As Amended),
or 1985, or 1985 (As Amended
1990), 1996, 1996 (as Amended
2003), 2005, 2009, 2012 Editions
Changed to eliminate
continued use of 1973
design packages and to
add transition for 1996-
2012 package designs (as
modified by Feb. 2016
70
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
of the Transport Regulations is
subject to multilateral approval from
the date that the 1996 Edition of the
Transport Regulations entered into
force, in order to permit the
competent authorities to establish a
framework within which continued
use may be approved. Additionally,
no new manufacture of packagings
to such designs is permitted to
commence. This transition period
was determined on the basis of an
assessment of the time needed to
incorporate the 2012 2018 Edition
of the Transport Regulations into
national and international
regulations, taking into
consideration the experience gained
during implementation of the
transitional arrangements of the
1996 Edition of the Transport
Regulations.
CSM plus correction to
time needed for 2018
edition).
140 820.8 See para. 535.2. Delete paragraph, per
Feb. 2016 CSM.
141 820.9
(should be
revised as
820.8)
For any revision to the original
package design, or increase in
activity of the contained materials,
or addition of other types of
radioactive material, which would
To update from 2012 as
per Feb. 2016 CSM.
71
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
significantly and detrimentally affect
safety, as determined by the
competent authority, the design
should be reassessed and approved
according to the 2012 latest Edition
of the Transport Regulations. Such
factors could include an increase in
the mass of the contents, changes to
the closure, changes to any impact
limiters, changes to the thermal
protection or shielding and changes
in the form of the contents.
142 820.10
(should be
revised as
820.9)
When applying para. 820, the
original competent authority
identification mark and the design
type codes, assigned by the original
competent authority of design,
should be retained both on the
packages and on the competent
authority certificates of design
approval, notwithstanding that these
packages become subject to
multilateral approval of design. This
means that packages originally
designated Type B(U)-85 or Type
B(U)F-85 under the 1973 1985
Edition of the Transport Regulations
should not be redesignated Type
B(M) or Type B(M)F, nor should
Changed to reflect proper
treatment of -85 designs
(as per Feb. 2016 CSM.)
72
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
they be redesignated Type B(M)-96
or Type B(M)F-96, when used under
the provisions of para. 820. This is
to ensure that such packages can be
clearly identified as packages
grandfathered under the provisions
of para. 820, having been originally
approved under the 1973 a previous
Edition of the Transport
Regulations.
143 820.11
(should be
revised as
820.10)
See para. 832.4 832.2 and 832.3. Revised per Feb. 2016
CSM.
144 823.1
(should be
revised as
824.1)
Paragraph 824 provides introduces
transitional arrangements for special
form radioactive material, the design
of which is also subject to
competent authority approval. It
emphasizes the need to apply
management system measures
according to the 2012 Edition of
the Transport Regulations to
ensure that such special form
radioactive material remains in use
only where it continues to meet the
original design intent or regulatory
requirements. This can best be
achieved by ensuring that the latest
Revised per Feb. 2016
CSM.
73
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
management system measures are
applied to post-manufacturing
activities such as servicing,
maintenance, modification and use
of such special form radioactive
material. It should be noted that the
scope of the transitional
arrangements of the Transport
Regulations only extends to the
requirements for certain special
form radioactive material. In all
other aspects, for example,
concerning general provisions, the
requirements and controls for
transport, including consignment
and conveyance limits, and approval
and administrative requirements, the
provisions of the 2012 current
edition of the Transport Regulations
apply.
145 823.2
(should be
revised as
824.2)
In the process of developing the
2012 2018 Edition of the Transport
Regulations, it was determined that
there was no need for an immediate
change of the Transport Regulations
following their adoption, but that
changes aiming at a long term
improvement of safety in transport
were justified. Therefore, it was also
Revised per Feb. 2016
CSM.
74
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
decided to accept continued
operational use of special form
radioactive material designed and
approved under the 1973 or 1985
and 1985 (As Amended 1990),
1996, 1996 (Revised) and 1996 (As
Amended 2003), 2005, 2009, and
2012 Editions of the Transport
Regulations. However, no new
manufacture of such special form
radioactive material is permitted to
commence. The continued use of
existing special form radioactive
material with a 1973, 1973 (As
Amended), or 1967 Edition of the
Transport Regulations based design
approval was considered to be no
longer necessary or justified.
146 823.3 (to
be 824.3)
See para. 832.5 834.2 and 834.3. Revised per Feb. 2016
CSM.
147 823.1 –
826.2
These paragraphs should be
renumbered 824.1 – 827.2
The addition of paragraph
822 in DS495 causes
renumbering of
subsequent paragraphs.
148 829.1 –
840.3
These paragraphs should be
renumbered 831.1- 842.3.
Previous change plus new
para 829 in DS495 causes
these to change by 2.
149 832.2 (to
become
It is essential that easy means are
available, preferably in the
Per Feb. 2016 CSM to
reflect updates to
75
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
834.2) identification mark, for
determining under which edition of
the Transport Regulations the
original package design
approval was issued. Beginning with
the 1985 Edition of the Transport
Regulations, this was This will be
achieved by adding the symbol ‘-96-
85’ to the identification
mark. , which was then changed to
‘-96’ when the 1996 Edition of the
Transport Regulations was issued.
The identification mark including ‘-
96’ continued through the 1996
(Revised) and 1996 (As Amended
2003), 2005, 2009, and 2012
Editions of the Transport
Regulations. The 2018 Edition of
the Transport Regulation only
includes the symbol of the year
within the identification mark only
for grandfathered package designs.
Example:
Edition of Transport Regulations
/Package design identification mark
1973 A/132/B(U), or A/132/B(M)
1985 A/132/B(U)-85, or
A/132/B(M)-85
transitioning.
76
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
1996 A/132/B(U)-96, or
A/132/B(M)-96
2018 A/132/B(U), or A/132/B(M)
150 832.3 This technique of adding a symbol
may continue to be used provided
later editions of the Transport
Regulations essentially maintain the
present package identification
marks.
Deleted per Feb. 2016
CSM.
151 832.4 (to
become
834.3)
The continued procedure of adding
the symbol ‘-96’ to the type code
since for the 1996 through the 1996
(Revised) and 1996 (As Amended
2003), 2005, 2009, and 2012
Edition of the Transport Regulations
is was justified because, since that
time, no significant safety
related changes to design or test
requirements for packages, special
form radioactive material
and low dispersible radioactive
material have been were introduced.
Such designs, with the addition
‘-96’, must meet the current
Transport Regulations in full. On
the other hand, all All other designs
with no addition or with the addition
‘-85’ or “-96” are subject to the
provisions of transitional
Per Feb. 2016 CSM to
reflect updates to
transitioning.
77
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
arrangements according to paras
820–823, respectively, and can be
clearly identified as such.
152 840.3 (to
be 842.3)
Proposed revised text:
Recommend this paragraph be
revised as follows:
“For packages which are intended
to be used for shipment after
storage, the competent authority
of the country where storage takes
place and shipment after is
initiated may be different from
the country of origin of package
design. When a package design
approval is withdrawn or not
renewed in the country of origin
of the design, the package may no
longer be authorized to be
transported in the country where
the packages are stored without
package design approval granted
in that country. For this reason,
the competent authority
concerned with storage and
shipment after storage may need
to issue and maintain its own
package design approval which
may be based in part on an
assessment already made by the
Proposed change to
provide clarity in the text.
The text was revised
without using track
changes.
78
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
competent authority of origin of
design, but then completed by an
additional assessment addressing
aspects specific to long-term
storage and shipment after
storage addressing ageing
management, gap analysis,
requirements before shipment,
requirements during post-storage
shipment, and different approval
periods.”
153 References
for Section
VIII
Proposed revised text:
The citation of references listed at
the end of Section VIII needs to be
sorted out. The following references
are listed at the end, they not cited in
the text; but they should be cited:
[3] Chopra, Dierchs, et. al.
[NOTE: Dierchs should be
spelled Diercks]
[4] Saegusa
[5] Wille, Wolfe, et. al.
[6] Nuclear Energy Institute
[10] Pacific Northwest National
Laboratory
[11] Droste, Wille
The citation of the
references listed at the
end of Section VIII
should be properly sorted
out in the text.
79
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
154 References
to
Appendix
III
Proposed revised text for References
to Appendix III:
See recommendation in the column
to the right for References III.5.
Please see earlier
comments regarding the
modal regulatory
documents that are
revised every two years.
It is recommended that
similar wording be used
for this references in this
appendix.
155 Para. IV.2 Proposed revised text:
Recommend changing the text to
replace “tie-down system” with
“retention system”, as follows:
“This appendix provides guidance
on considering the effects of the tie-
down system retention system
loads applied to the package during
routine conditions of transport. It
describes possible methods for
demonstrating compliance with
package design requirements. The
package will include the tie-down
retention system attachment points
but not the remainder of the
retention system tie-down system.
Other components of the retention
system tie-down system, which
are not part of the package, are
addressed by modal and national
This appendix should
consistently use
“retention system” rather
than “tie-down system”
since the title of the
appendix is “retention”
not “tie-down”, Para.
IV.5 uses “retention
system” stating that such
systems may include “tie-
downs”.
80
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
requirements.”
156 Title of
Fig. IV.1.
Proposed revised text:
Recommend changing the title to:
“Fig. IV.1. Retention Tie-down
system components”
This appendix should
consistently use
“retention system” rather
than “tie-down system”.
157 Para.IV.5,
last line
Proposed revised text:
Suggest the following change to the
text:
“…shows examples of components
of tie-down retention systems.”
This appendix should
consistently use
“retention system” rather
than “tie-down system”.
158 2nd
paragraph
under
Fig. IV.1
of
Appendix
IV (not
numbered)
.
Proposed revised text:
Suggest the following changes to the
text:
a) Should this be given a new
paragraph number? If so, the
following paragraph numbers
will need to be adjusted
accordingly.
b) In the lead-in text of this
paragraph, make the following
change: ‘For the purposes of the
guidance notes noted in this
appendix, the following
definitions of terms used in
appendix IV apply:’
c) First item in the list “Attachment
point”: in the text change “tie-
Proposed modifications
in text to make text
consistent throughout,
using retention rather
than tie-down where
appropriate, and tyo
correct (in item b listed to
the left) an apparent
typographical error.
81
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
down member” to “retention
member”.
d) Second item in the list “Anchor
point” : in the text change “tie-
down member” to “retention
member”.
e) Penultimate item in the list “Tie-
down member”: change Tie-
down member to read
“Retention member”.
f) Last item in the list “Tie-down
system (or Retention system)”:
Recommend changing as
follows:
“Retention System The
assembly of an attachment
point, an anchor point and a
retention member.”
159 Para. IV.8 Proposed revised text:
Recommend the addition to the text
in the last sentence as follows:
“Operating, and handling, and
maintenance instructions should be
drawn up developed for the use of
any dedicated retention equipment.
Maintenance should be
part of the instructions on
the use of retention
equipment.
160 Para. IV.9 Proposed revised text:
Recommend changing the first part
For consistency of text
within the appendix.
82
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
of the sentence to read:
a) “Training for persons involved
in tie-down the retention of
packages……”.
b) First and second bulleted items,
change “”tie-down operations”
to “retention operations”.
c) 6th
bulleted item, change “tie-
down” to “retention”.
d) 8th
bulleted item, change “tie-
down equipment” to “retention
equipment”; and “tie-down
operations” to “retention
operations”.
161 Para. IV.10 Proposed revised text:
Recommend changing “lifting and
tie-down” to “lifting and retention”.
For consistency of text
within the appendix.
162 Para. VII.2
and
References
listed at
the end of
Appendix
VII.
Proposed revised text:
The only place in this appendix
where references are cited is toward
the end of para. VII.2, and it only
lists References [VII.11, VII.12].
References VII.1 through VII10 are
not cited.
It is recommended that the reference
citation in para. VII.2 be changed as
Utilize all of the
references cited in
Appendix VII.
83
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
follows: “.....should be demonstrated
as being appropriate through the
literature [VII.1 through VII.12
VII.11, VII.12], tests or reasoned
argument. “
163 Paras.
VIII.13
through
VIII.15
Proposed revised text:
Two issues need to be addressed
here.
a) After the three-line paragraph
VIII.13, the next paragraph should
be numbered VIII.4, and what is
now numbered VIII.14 should be
numbered VIII.15.
b) The sub-header “COMPLETION
OF SHIPMENT” is part of the
header dealing with a shipment
involving a country without
regulations. Therefore the sub-
header should not be all caps.
The text of these paragraphs should
be corrected as follows:
“VIII.13. If no regulations for the
safe transport of radioactive material
are implemented in a country, the
Transport Regulation (current
edition of IAEA Safety Standards
Series No. SSR-6) should be applied
for the transport within, from, to or
through that country.
Consistency in text
84
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
VIII.14. If no regulatory body for
the safe transport of radioactive
material is appointed in a country,
the first certificate of approval
(special arrangement), which should
be approved by all countries
relevant to the shipment, may be
issued by the existing national
radiation protection regulator of the
country. The IAEA’s Division on
Radiation, Transport and Waste
Safety can provide guidance on the
application of international
regulations on transport safety.
COMPLETION OF SHIPMENT
Completion of Shipment
VIII.14. VIII.15. In such special
situations, the competent authority
or the concerned safety regulator
should continue tracking the
shipment until its safe completion.
The consignor should inform
the appropriate authority about the
safe completion of such shipments.
164 Various See the attached table. Due to
paragraph renumbering in SSR-6
To correct references to
paragraph numbers that
85
COMMENTS BY REVIEWER
Reviewer: Rick Boyle
Country/Organization: USA/ DOT Date:
RESOLUTION
Comment
No.
Para/Line
No.
Proposed new text Reason Accepted Accepted, but
modified as follows
Rejected Reason for
modification/rejection
and in SSG-26 (as noted in above
comments), cross-references to
paragraphs need to be updated in
many paragraphs. The attached table
lists the updates needed.
changed.
86
Paragraph Cross-Reference Corrections
Found in Para # (old #)
New Para # for text Containing Reference
Currently Referenced Para #/ Updated or Corrected Para # that Should be Referenced
218.1 same 526/527, 525/526, 566(c)/568(c), 567/569, 568/570, 569/571, 541/543, 542/544
222.11 223.11 222/223
228.3 229.3 TS-R-1/SSR-6
239.2 same 603.1-603.4/602.1-602.4, 604.1/603.1, 604.2/603.2
240.5 Same 226/227
244.2 Same 218.3/218.2
302.1(e) Same 562.1-562.14/564.1-564.14
309.3 Same 526-529/527-530, 566/568, 573/575
310.4 Same 830.1/832.1
405.3 Same 409.10-409.14/409.9-409.13
409.1 Same 226.3/227.3
409.10 Same 409.14/409.13
413.5 Same 409.16/409.15
417.1 Same 570/572 (twice)
417.5 Same 570(c)/572(c)
417.6 Same 570(d)/572(d)
417.7 Same 570(e)/572(e)
417.8 Same 606.7/605.7
418.2 Same 606/605
420.8 Same 419(b)/419(c)
501.1 Same 547/549
501.6 Same 659.21-659.24/659.20-659.23
502.1 Same 547/549
503.1 Same 547/549
503.5 Same 838/840
513.5 Same 233.1-233.6/221.1-221.7
516.2 Same 562.12-562.14/564.12-564.14
520.9 Same 613/612
521.2 Same 226.1/227.1
87
Found in Para # (old #)
New Para # for text Containing Reference
Currently Referenced Para #/ Updated or Corrected Para # that Should be Referenced
526.1 527.1 527/528, 528/529
527.1 528.1 526.1/527.1
528.1 529.1 526.1/527.1
528.2 529.2 573/575, 233.2/221.2
530.1 531.1 530/531
531.2 532.2 533.2-533.6/534.2-534.6
532.4 533.4 533.2-533.6/534.2-534.6
533.5 534.5 533.2-533.4/534.2-534.4
534.3 535.3 533.2-533.6/534.2-534.6
535.1 536.1 832(c)/834(c)
535.3 536.3 533.2-533.6/534.2-534.4
538.2 540.2 536/537
541.1 543.1 568/570, 569/571
541.2 543.2 538/540
542.1 544.1 541.1-541.3/543.1-543.3
543.1 545.1 571/573
546.1 548.1 546/548, 532.1/533.1
546.3 548.3 546(k)/548(l) (L, not K)
546.6 548.6 546(f)/548(g) (G, not F)
546.7 548.7 540.3/542.3
562.13 564.13 562/564
565.1 567.1 554/556
567.1 569.1 526.1/527.1, 825/826
570.1 572.1 570/572
571.1 573.1 543.1/545.1, 544.1/546.1
572.1 573.1 544.1/546.1
573.1 575.1 221.1-221.6/222.1-222.6
573.4 575.4 564.1-564.3/566.1-566.3
573.6 575.6 573(a)(iii)/575(a)(iii)
575.1 577.1 573/575
575.2 577.2 574/576
88
Found in Para # (old #)
New Para # for text Containing Reference
Currently Referenced Para #/ Updated or Corrected Para # that Should be Referenced
576.1 578.1 566/568
578.1 579.1 578/580
583.1 585.1 562.1-562.14/564.1-564.14, 568.1/570.1
584.1 586.1 584-588/586-590
603.3 602.3 603/602
606.4 605.4 606(b)/605(b)
606.5 605.5 606/605
606.6 605.6 606/605
606.7 605.7 606/605
607.1 606.1 613/612
607.2 606.2 564.1/566.1, 564.2/566.2
610.3 609.3 610/609
611.2 610.2 610.2-610.4/609.2-609.4
621.2 same 578.1/579.1, 229.1-229.3/230.1-230.4
627.5 same 624.8/624.5
629.5 same 624.8/624.5
648.6 same 624.8/624.5
659.14 same 527/528, 528/529, 526/527
659.19 Same DELETE this paragraph as it references 624.8 which has been deleted (and then renumber paragraphs 659.20-.26 as 659.19-.25)
663.1 same 229.3/229.4
666.3 same 229.3/229.4
665.1 same 605/604
671.2 same 659.24/659.24
674.2 same 566(c)/568(b)
674.10 same 606/605 (3 times)
677.2 same 503.4/503.5
683.2 same 683.2(a)/683(a)
701.25 same 716.7/716.11
704.2 same 603/602
704.3 same 603.3/602.3, 603.4/602.4
89
Found in Para # (old #)
New Para # for text Containing Reference
Currently Referenced Para #/ Updated or Corrected Para # that Should be Referenced
705.1 Same 603.1/602.1
712.2 same 605/604, 605(b)/604(b)
712.4 same 605.5/604.5, 605.7-605.9/604.7-604.9
716.13 same 659.19/659.18
728.17 same 659.24/659.23
803.2 Same 602-604/601-603
804.1 same 832.1-832.5/834.1-834.4
807.1 same 832/834
832.4 834.4 823/824
840.2 842.2 833(b)/835(b)
App.III, III.1(i) Same 562/564
III.1(iii) Same 562(d)/564(d)
III.2 Same 562.11/564.11
III.3 Same 562/564
III.4 same 562/564
III.27 same 562(c)/564(c)
App. IV, IV.1 Same 607/606, 612/611, 613/612
App. VI, VI.25(a) Same 222/223