Commissioning Of Commissioning Of Mission Critical Facilities Trey King Project Manager E Cube, Inc.
Transcript
Page 1: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Commissioning Of Commissioning Of Mission Critical FacilitiesTrey KingProject ManagerE Cube, Inc.

Page 2: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

AIA Quality Assurance

Learning Objectives

1. Given the commissioning requirement to assist in the pre-certification of a bio-safety laboratory, hospital operating room, or isolation room, the attendee will be able to develop and execute a pre-certification script, helping to assure a smooth certification processhelping to assure a smooth certification process.

2. Given the commissioning requirement to assist in the pre-certification of a bio-safety laboratory, hospital operating room, or isolation room, the attendee will be able to establish a detailed Roles and Responsibilities Matrix that will document the activities and level of involvement of all personnel involved in the certification of the laboratory and its systems.

Page 3: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Cx of Mission Critical Facilities

Page 4: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Cx Of Mission Critical Facilities

Page 5: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Cx Of Mission Critical Facilities

Page 6: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Example Script from a Certifying AgencySystems Failure Testing

Performance acceptance criterion is there are no airflow reversals.

a) Normal operations -> emergency power ❑Pass ❑ Fail ❑ N/Aa) Normal operations emergency power ❑Pass ❑ Fail ❑ N/Ab) Emergency power -> normal operations ❑Pass ❑ Fail ❑ N/Ac) Loss of supply fans (individual, in combination and all) ❑Pass ❑ Fail ❑ N/A

i) Fail AHU-2ii) Fail AHU-3iii) F il AHU 2 & AHU 3iii) Fail AHU-2 & AHU-3iv) Start system

d) Loss of exhaust fans (individual, in combination and all) ❑Pass ❑ Fail ❑ N/Ai) Fail EF-7ii) Fail EF-8)iii) Fail EF-7 & EF-8iv) Start system

e) Verify that upon system failure backdraft/isolation dampers close ❑Pass ❑ Fail ❑ N/A

f) Building automation system maintains operational set points during all failuref) Building automation system maintains operational set points during all failuretesting scenarios and returns to normal operations ❑Pass ❑ Fail ❑ N/Ag) Upon reboot BAS and controllers must retain operational set points

❑Pass ❑ Fail ❑ N/Ah) BAS uninterrupted power supply (UPS) installed ❑Yes ❑ No ❑ N/Ai) R d HVAC/ h t t d if it i t i di ti l i fli) Remove pressure sensor and HVAC/exhaust system and verify it maintains directional airflow

Page 7: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Cx Script from same Project

# ACTION EXPECTED REACTION OK COMMENTS2 Simulation - 2: Generator Test- Fail normal power

Cx Expansion of lines a & b of Certifying Agency’s script

a Fail normal power to building AH-2, 3, 7, and 8 lose powerUpon sensing pressure loss of AH-7 & 8, Pressure set point =__________the supply valves to BSL close.Exhaust valves to BSL remain open.AH 7 & 8 stack velocity dampers closeAH-7 & 8 stack velocity dampers close.

b Emergency power established AH-2, 3, 7 & 8 ramp to static stpts. Time delay toSupply valves remain closed, Emergency Power _______ sec.

BSL-3 rooms remain under negative pressure at all times.

pp y g y _______Exhaust valves modulate to set point.Supply valves modulate open w/time delay. Time delay+ ________ secondsSteady airflow, exhaust & supply, is estab.

Record room Dp's on separate sheet: Sim 2BSL-3 rooms remain under negative pressure t ll ti Record room Dp s on separate sheet: Sim-2

3 Return to normal power AH-2, 3, 7, and 8 continue to oper. @ Stpts.

Lab exhaust valves remain at setpointsLab supply valves remain at setpoint.

Simulation - 3: Generator Test- Return to normal powerat all times.

pp y pRecord room Dp's on separate sheet: Sim-3BSL-3 rooms remain under negative pressure

at all times.

Page 8: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Cx Script from same Project (cont.)Cx Expansion of line c of Certifying Agency’s script

# ACTION EXPECTED REACTION OK COMMENTS4

Disconnect power to AH-7 VFD. BAS alarm shows AH-7 failure Both Local & Remote OWSAH 7 OSA stack velocity dampers closes

Simulation - 4: Fail AH-7

AH-7 OSA stack velocity dampers closesDischarge air damper closesAH-8 continues to operate.

VFD @ _____Hz.Duct static pressure. ______VFDs @ _____Hz. _____HzDuct static pressure. ______

AH-8 VFD increases output to maintain static setpoint.AH-2 and AH-3 continue to operate & maintain duct static pressure setpoint. BSL 3 i d ti

Record room Dp's on separate sheet: Sim-45

Disconnect power to AH-8 VFD. BAS alarm shows AH-7 & AH-8 failure Both Local & Remote OWSAH-8 OSA stack velocity dampers closesExhaust Air valves remain open.

Pressure set point =__________S l V l t L b lUpon loss of exhaust duct static pressure

Simulation - 5: Failure of AH-7 and AH-8 (AH-7 has not been restarted)

BSL-3 rooms remain under negative pressure at all times.

Supply Valves to Labs close. BAS stops AH-2 & AH-3, controls operating.

Exhaust valves remain openRecord room Dp's on separate sheet: Sim-5

6Restore power to AH-7 and 8

Simulation - 6: Restore power to AH-7 and AH-8

BSL-3 rooms remain under negative pressure at all times.

AH-7 & 8 stack velocity dampers remain

BAS confirms 7 & 8 start, starts AH-2 & 3.Lab supply valves remain closed.

Time delay= ________ seconds

BSL-3 rooms remain under negative pressure at all times.

closed.

Exhaust valves stage open with 15 second time delays per stpt.

Record room Dp's on separate sheet: Sim-6AF-7 & 8 return to normal operating set points

Lab supply valves stage open at 15 second intervals after a 30 second delay.

Labs return to operating pressure setpoints.

Page 9: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Importance of Scripting

Why is scripting important?Why is scripting important?

S t C l it• System Complexity • Contractor Buy-in• Documentation• Save Time and Money

Page 10: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Importance of Scripting

• System complexity○A systematic approach to verify proper

system integrationsystem integration○Multiple players with multiple responsibilities○Advance notice to participants○Establish criteria and identify conflicts early

• Contractor Buy-in○A sense of ownership from the beginning○Leverage their knowledge base

Page 11: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Importance of Scripting

• Documentation○Contractor’s pre-functional and start-up○Contractor s pre-functional and start-up

documents○Owner’s O&M staff○Future RCx○Facility Baseline

• Save Time and Money○Solve problems prior to actual testing

L D O '○Less Do-Over's

Page 12: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Scripting for Smoke Evacuation Systems

Page 13: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Scripting for Black-Out Tests

Page 14: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Failure Mode Testing of Labs

Page 15: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Data Center Integrated Systems Tests

Page 16: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Script Development

Divide the Script into 3 major sectionsDivide the Script into 3 major sections

Contractor Roles and Responsibilities (Pre Testing)Contractor Roles and Responsibilities (Pre-Testing)Failure Mode SimulationsDocumentation

Page 17: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Script Development

C t t R l & R ibiliti• Contractor Roles & Responsibilities○ Clear delineation of tasks○ Each participant knows and understands their expected level of

involvement○ Established as a part of the overall Script, and as a supplement to

the Cx Plan.- More detail than the Cx Plan- Broken down by specific contractors

» Mechanical and Sheet Metal» Electrical and Lighting» Controls» TAB» CM/GC» CxA

○ Detail installation and pre-testing requirements to be p g qcompleted prior to Cx

Page 18: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Contractor Roles & Responsibilities

Atrium Smoke Exhaust Pre-Testing Requirements

# Description Type Resp Party Due Done Status

1 Verify that all 8 sets of blow open doors are fully operational Cx Func

CM/GC, Door

Installer08/10/07

Verify that all 8 sets of blow open doors can be opened at same time with one command Cx Func

CM/GC, Door

Installer08/10/07

Installer

2 Verify door end switches confirm open status for each blow open door Cx Func Controls 08/10/07

3 Verify three Relief Air dampers open 100%, and make end switches Cx Func Controls 08/10/07

4 Verify RF-1, RF-2, RF-3 start and ramp up to C F Electrician, 08/10/074 Verify RF 1, RF 2, RF 3 start and ramp up to 100% Cx Func Electrician,

Controls 08/10/07

5 Verify if any RF, (RF-1, RF-2, RF-3) fail, an alarm is sent to the OWS Cx Func Controls 08/10/07

6 Verify the OSA dampers on AH-1 are 100% open and the MA dampers are 100% closed Cx Func Controls 08/10/07

7 Verify that SF-1 and SF-2 are commanded on to 90% on the VFD Cx Func Electrician,

Controls 08/10/07

Page 19: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Script Development

• Failure Modes sectionFailure Modes section○Most important part of the Script to “get right”○Divide the modes into Simulations and return the

Baseline Simulation when practical - Some modes may have several different simulations

○List the “Action” and “Expected Reaction” of every○List the Action and Expected Reaction of every device involved in a failure mode

○Record actual results in this section also

Page 20: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Failure Modes Section# ACTION EXPECTED REACTION OK COMMENTS4

Disconnect power to AH-7 VFD. BAS alarm shows AH-7 failure Both Local & Remote OWSAH 7 OSA stack velocity dampers closes

Simulation - 4: Fail AH-7

AH-7 OSA stack velocity dampers closesDischarge air damper closesAH-8 continues to operate.

VFD @ _____Hz.Duct static pressure. ______VFDs @ Hz Hz

AH-8 VFD increases output to maintain static setpoint.AH 2 and AH 3 contin e to operate & VFDs @ _____Hz. _____Hz

Duct static pressure. ______

Record room Dp's on separate sheet: Sim-45

Disconnect power to AH 8 VFD BAS alarm shows AH 7 & AH 8 failure Both Local & Remote OWSSimulation - 5: Failure of AH-7 and AH-8 (AH-7 has not been restarted)

AH-2 and AH-3 continue to operate & maintain duct static pressure setpoint. BSL-3 rooms remain under negative pressure at all times.

Disconnect power to AH-8 VFD. BAS alarm shows AH-7 & AH-8 failure Both Local & Remote OWSAH-8 OSA stack velocity dampers closesExhaust Air valves remain open.

Pressure set point =__________Supply Valves to Labs close.BAS stops AH 2 & AH 3 controls operating

Upon loss of exhaust duct static pressure

BAS stops AH-2 & AH-3, controls operating.Exhaust valves remain open

Record room Dp's on separate sheet: Sim-5BSL-3 rooms remain under negative pressure at all times.

Page 21: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Script Development

• Documentation○ Especially important to document the Baseline p y p○ NO SAMPELING○ Don’t assume that because a room controls in one Failure Mode, it

will control in similar modes○ Changes to the Sequence of Operation (SoO) in one space may○ Changes to the Sequence of Operation (SoO) in one space may

disrupt the SoO control in adjacent spaces○ The Certifying Authority will measure and record every space

pressure relationship in every failure mode and include this in their reportreport

○ Remember to document System control info:- Pressures and Differentials- Frequencies, Hertz, Amps- Program setpoints and actual control points- Program setpoints and actual control points - Reaction times- Alarm points

Page 22: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Script Documentation

Room No, BaselineSim-1 Sim-2 Sim-3 Sim-4 Sim-5 Sim-6 Sim-7 Sim-8 Sim-9a Sim-9b Sim-10a Sim-10b Sim-11a Sim-11b Sim-12a Sim-12b

300K to 300S

300S to

ROOM PRESSURES DURING SIMULATIONS

300S to 300M

300R to 318A

318A to318

300R to 300 to318B

Room #300 M Main BSL-3 Corridor300S N th Ai l k

Room Name

300S North Airlock300N South Airlock300K North Exterior Corridor300R West Exterior Corridor318 Vestibule

318A North Shower Out318A North Shower Out318B Gown-In318C South Shower Out319 Support Lab320 Procedure Room321 Animal Holding Roomg322 Animal Holding Room323 Animal Holding Room

Page 23: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Script Development

Most important lesson from today’s lecture

START EARLYS

Page 24: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

AIA Quality Assurance

Portland Energy Conservation, Inc is a registered provider with The American Institute of Architects Continuing Education Systems. Credit

d l i f hi ill b d CES R dearned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-AIA members are available on request.

Thi i i t d ith th AIA/CES f ti iThis program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling,

i di t ib ti d li i t i l d t Q tiusing, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

Page 25: Commissioning of Mission Critical Facilities€¦ · Cx Script from same Project # ACTION EXPECTED REACTION OK COMMENTS 2 Simulation - 2: Generator Test- Fail normal power Cx Expansion

Thank-you Trey King

Project ManagerE Cube, Inc.