+ All Categories
Home > Documents > Commonwealth Sewer System Improvements News Release04!28!09

Commonwealth Sewer System Improvements News Release04!28!09

Date post: 30-May-2018
Category:
Upload: carlylenewzguy
View: 221 times
Download: 0 times
Share this document with a friend
3
 ALEXANDRIA SANITATION AUTHORITY  1500 Eisenhower Ave Alexandria, VA 22314 PO Box 1987 Alexandria, VA 22313  tel 703-549-3382 fax 703-519-9023 www.alexsan.com FOR IMMEDIATE RELEASE – Media Contact: Joelle Jordan 202-288-3241 April 28, 2009 Construction Continues on Commonwealth Avenue Sewer System Improvements ALEXANDRIA, VA – Alexandria residents and businesses will continue to have safe and reliable sewer operations as the Alexandria Sanitation Authority (ASA) furthers the modernization of approximately 3,000 feet of the Commonwealth Avenue Sewer this month. Improvements include rehabilitating existing sewer lines and manholes; replacing existing sewer manhole covers and frames; installing a new sewer liner; and repaving and re-striping portions of the roadway surface affected by the construction activities. The project will resume in May and is expected to be complete by the end of June. During construct ion, there will be traffic delays and lane closures in the project area. Motorists, bicyclis ts and pedestrians are encouraged to use alternate routes. However, mass transit providers, including the DASH bus line, Metrobus, Metrorail, Amtrak, Alexandria trolley and the Virginia Railway Express (VRE), as well as school buses, will maintain normal operations. Most work will be done within the roadway and on public property. Phase 3 of the Commonwealth Avenue Sewer System Improvements Project includes work on Daingerfield Road from King Street to Duke Street and will include the following lane closures and movement restrictions:  Daingerfield Road – Southbound through traffic will be reduced to one lane from King Street to Dechantal Street.  Prince Street will be closed from Reinekers Lane to Daingerfield Road and Reinekers Road will be limited to one lane reversible cont rolled by flaggers. This closure will be limited to one weeke nd.  There will be temporary lane closures on Duke Street just east of Daingerfield Road. During these temporary closures, eastbound and westbound traffic will be reduced to single lanes.  There will be temporar y no parking zones on the east side of Daingerfield Road and along Diagonal Road near the Reinekers Lane intersection. Sidewalks will remain open.  Sidewalk ramps will be installed over the by-pass piping on Duke Street. Citizens can expect traffic delays and lane closures in the area beginning on Monday, May 11, 2009 until Friday, June 19, 2009. After more than 50 years of service, the Commonwealth Avenue Sewer is in need of rehabilitation to reduce the possible likelihood of a sewer service interruption. In 1997, ASA began the initial design of the modernization project which is being implemented in five phases and involves sewer improvements from Caton Avenue to the Hooff’s Run Junction Chamber. Currently, the project is in its fourth phase, focusing on improvements from Oak Street to Duke Street. The fifth and final phase will involve improveme nts from Duke Street to Hooff’s Run. The estimated construc tion cost for this phase of the Commonwealth Avenue Sewer System Improvements Project is $1.4 million. Throughout the project, ASA will be working closely with its contractor, AM-Liner East, Inc., to minimize the construction’s impact on the community; provide updates on projected work; and respond to concerns and questions from the public.
Transcript
Page 1: Commonwealth Sewer System Improvements News Release04!28!09

8/14/2019 Commonwealth Sewer System Improvements News Release04!28!09

http://slidepdf.com/reader/full/commonwealth-sewer-system-improvements-news-release042809 1/2

 

ALEXANDRIA SANITATION AUTHORITY  

1500 Eisenhower Ave • Alexandria, VA 22314 •PO Box 1987 •Alexandria, VA 22313

 tel 703-549-3382 • fax 703-519-9023 • www.alexsan.com

FOR IMMEDIATE RELEASE –

Media Contact: Joelle Jordan202-288-3241

April 28, 2009

Construction Continues on Commonwealth Avenue Sewer System Improvements

ALEXANDRIA, VA – Alexandria residents and businesses will continue to have safe and reliable sewer operations as theAlexandria Sanitation Authority (ASA) furthers the modernization of approximately 3,000 feet of the CommonwealthAvenue Sewer this month. Improvements include rehabilitating existing sewer lines and manholes; replacing existing sewer manhole covers and frames; installing a new sewer liner; and repaving and re-striping portions of the roadwaysurface affected by the construction activities. The project will resume in May and is expected to be complete by the endof June.

During construction, there will be traffic delays and lane closures in the project area. Motorists, bicyclists andpedestrians are encouraged to use alternate routes. However, mass transit providers, including the DASH bus line,Metrobus, Metrorail, Amtrak, Alexandria trolley and the Virginia Railway Express (VRE), as well as school buses, willmaintain normal operations. Most work will be done within the roadway and on public property.

Phase 3 of the Commonwealth Avenue Sewer System Improvements Project includes work on Daingerfield Road fromKing Street to Duke Street and will include the following lane closures and movement restrictions:

•  Daingerfield Road – Southbound through traffic will be reduced to one lane from King Street to Dechantal Street.

•  Prince Street will be closed from Reinekers Lane to Daingerfield Road and Reinekers Road will be limited to one lanereversible controlled by flaggers. This closure will be limited to one weekend.

•  There will be temporary lane closures on Duke Street just east of Daingerfield Road. During these temporaryclosures, eastbound and westbound traffic will be reduced to single lanes.

•  There will be temporary no parking zones on the east side of Daingerfield Road and along Diagonal Road near theReinekers Lane intersection. Sidewalks will remain open.

•  Sidewalk ramps will be installed over the by-pass piping on Duke Street.

Citizens can expect traffic delays and lane closures in the area beginning on Monday, May 11, 2009 until Friday, June19, 2009.

After more than 50 years of service, the Commonwealth Avenue Sewer is in need of rehabilitation to reduce the possiblelikelihood of a sewer service interruption. In 1997, ASA began the initial design of the modernization project which is

being implemented in five phases and involves sewer improvements from Caton Avenue to the Hooff’s Run JunctionChamber. Currently, the project is in its fourth phase, focusing on improvements from Oak Street to Duke Street. The fifthand final phase will involve improvements from Duke Street to Hooff’s Run. The estimated construction cost for thisphase of the Commonwealth Avenue Sewer System Improvements Project is $1.4 million.

Throughout the project, ASA will be working closely with its contractor, AM-Liner East, Inc., to minimize the construction’simpact on the community; provide updates on projected work; and respond to concerns and questions from the public.

Page 2: Commonwealth Sewer System Improvements News Release04!28!09

8/14/2019 Commonwealth Sewer System Improvements News Release04!28!09

http://slidepdf.com/reader/full/commonwealth-sewer-system-improvements-news-release042809 2/2

ALEXANDRIA SANITATION AUTHORITY  

1500 Eisenhower Ave • Alexandria, VA 22314 •PO Box 1987 •Alexandria, VA 22313

 tel 703-549-3382•

fax 703-519-9023•

www.alexsan.com

"This is a critical infrastructure investment for the community and will allow us to continue to protect the public’s healthand safety, as well as the environment," said Karen Pallansch, Alexandria Sanitation Authority General Manager.

For more detailed information on the entire project, please visit: www.alexsan.com/commonwealthsewer or call theproject construction hotline at (703) 549-3383.

###

PRIMARY CONTACTS: Media Contact: Joelle Jordan, (202) 288-3241Cheryl St. Amant, Director of Technical Services, ASA, (703) 549-3382ext. 2250

Gavin Dawson, Construction Manager, ARCADIS, (443) 418-1615


Recommended