Community Bond Oversight Committee Report to the Board of Trustees. Presented by: Ashton Cumberbatch, Bobby Jenkins, and Eliza May March 7, 2011. Bond Projects Status. Major Projects Remaining: Construction of the New Bus Terminal Construction of the soccer fields - PowerPoint PPT Presentation
Popular Tags:
18
Community Bond Oversight Committee Report to the Board of Trustees Presented by: Ashton Cumberbatch, Bobby Jenkins, and Eliza May March 7, 2011
Transcript

Community Bond Oversight CommitteeReport to the Board of Trustees

Presented by: Ashton Cumberbatch, Bobby Jenkins, and Eliza MayMarch 7, 2011

CBOC REPORT

Bond Projects Status

Major Projects Remaining:• Construction of the New Bus Terminal• Construction of the soccer fields• Site selection and construction of New North Central Elementary School

2

2004 Bond Program

Phase Total Projects Completed Projects Total Project Budget

I 91 91 $196,311,445

II 69 67 $70, 847,343

III 63 63 $99,287,503

IV 26 25 $55,931,569

V 13 12 $18,199,959

CBOC REPORT

Bond Projects Status

3

2008 Bond Program

Phase Total Projects Completed Projects Total Project Budget

I 41 28 $184,558,157

II 25 17 $13,802,276

III 13 0 $4,514,360

IV TBD 0 TBD

Major Projects Completed:

• 12 science classroom additions and renovations

• Technology improvements

• Additions and renovations at various schools

Major Projects Remaining:

• Construction of a New Cold Storage Warehouse

• Construction of the New Early Childhood Center

• Site selection for and construction of 2008 Undesignated Elementary School

• Site selection for and construction of the New Performing Arts Center

CBOC REPORT

Program Contingency – 2004 Bond Program

4

CBOC REPORT

Program Contingency – 2008 Bond Program

5

CBOC REPORT

Role of CBOC in Determining Use of Remaining Funds

• When it has been established that there are surplus funds from the 2004 and 2008 bond programs: Toward the end of the bond programs, when there

is clear evidence that all projects can be completed within the project budgets, staff will present a list of recommended projects that would address known facility deficiencies that have been identified through the District’s facility condition assessment, its Facility Master Plan efforts, or during the CBOC oversight process of the bond programs.

CBOC REPORT

Role of CBOC in Determining Use of Remaining Funds

These recommended projects must fall within the intention of the original bond referendum.

Once the CBOC approves the list of recommended projects, it is forwarded to the Board of Trustees for its receipt of public input and subsequent approval in its final form.

CBOC REPORT

Site Acquisition – 2004 Bond Program• Property for 5 of the 6 elementary schools has been acquired and

construction completed (Clayton, Perez, Blazier, Overton and Baldwin); site for North Central Elementary has been identified and discussions with the property owners are ongoing

• Property for both middle schools have been acquired and construction is completed (Garcia and Gorzycki)

• Board approved the purchase of a site for a future Southeast Middle School; closing activities are underway

• Site of Southeast Bus Terminal purchased and design is nearing completion; expected construction completion summer 2012

8

CBOC REPORT

Site Acquisition – 2008 Bond Program• Staff is negotiating purchase of the preferred site for the Performing

Arts Center

• Real-estate consultant is conducting search for site for future South High School and preparing to review results with the Board

• Site of Early Childhood Center purchased and design is nearing completion; expected construction completion summer 2012

• Location of undesignated elementary school will be based on demographic reports and results of Facility Master Plan

9

CBOC REPORT

Prevailing Wage Update• To date, seven wage rate compliance inquiries have been received

Three inquiries determined to be in compliance Four inquiries, including one new inquiry since the last CBOC

report, determined to be out of compliance• To date, 36 random worker surveys performed by AISD project

managers; all appeared to be in compliance• Inquiries are immediately investigated; certified payroll is reviewed• When inquiry is determined to be out of compliance, the District

withholds funds from contractor until issue has been settled

10

CBOC REPORT

HUB Update• Overall 24.57 % of the $434,624,962 in contracts awarded for the 2004/2008 Bond

Programs has been awarded to HUBs

• Professional Services Participation is 34.84% --$56,559,233

• Construction Services Participation is 23.03% --$378,065,729

• Small Firm Participation is 59.72% --$434,624,962

• Local Firm Participation is 84.77% -- $ 434,624,962

• Phase I of the Mentor-Protégé Program was successfully completed; During the program:

mentors were awarded a total of $88,926,883; and

protégés were awarded $1,573,055

• Phase II of the Mentor-Protégé Program has begun

• HUB Subcommittee has been formed

11

CBOC REPORT

Communications Update• Eblasts – topics included general updates, site acquisition process

and update, Baldwin dedication, Facility Master Plan, technology projects, annual report and CBOC reports to the Board

• Annual Report – covers 2004 and 2008 Bond Programs; will be distributed in Austin American Statesman and ¡Ahora Sí! in late spring 2011

• Dedication – for Baldwin ES was held November 14, 2010

• Surveys – 24 facilities were surveyed; 1,259 total responses received

12

CBOC REPORT

Safety Update• From July 2010 to December 2010, three accidents were reported:

‒ Three Contractor Injuries:

• Broken arm

• Strained back

• Debris in eyes

• 2008 Bureau of Labor Statistics “Nonresidential Building Construction,” nationwide, contractors in 2009 had 4.4 accidents per 100 employees; bond issue contractors had only 3.19 accidents per 100 employees

13

Reported Injuries Sept. 2004 - December 2010

Contractor injuries reported 10

Student injuries reported 3

Teacher injuries reported 0

Staff injuries reported 0

Visitor injuries reported 0

CBOC REPORT

Sustainability Update• Total of $1,134,059 in rebates from Austin Energy; $28,321 more in rebates

in process• New construction and renovations continue to achieve goal of 2-star or

greater rating from AEGBP:

• Summer energy conservation program expanded this fall to all campuses• District-wide Single-Stream Recycling Program • Elementary School Educational Food Waste Composting Program• Food/Ag Waste Pilot Program at Lanier High School

14

Rating New Schools/Facilities Additions

2-Star 3 Awarded2 Pending/Expected

4 Awarded5 Pending/Expected

3-Star 3 Awarded1 Pending

2 Awarded3 Pending/Expected

4-Star 2 Awarded2 Pending/Expected

CBOC REPORT

Technology Update• Computers on Wheels (COW) Refresh – Phase 1 of this program provided

7,490 netbooks to campuses for use with mobile labs; Phase 2 will provide a similar number to campuses

• Mobile Carts – Phase 1 deployed 500 carts in conjunction with the COW program mobile labs; Phase 2 will provide a similar number of carts

• Classroom Computers Refresh – 7,000 desktops deployed to campuses; next phase will distribute 6,500 desktops

• Campus Printer Refresh – complete; 1,320 printers distributed

• Document Management – This program now includes paperless workflow; vendor has been selected and the contract is pending approval

• Technology for Special Education – 90 color laser printers were deployed in November; 5 LCD interactive touch screens (TAPit boards) were deployed in January

15

CBOC REPORT

Recognitions• The tri-chairs would like to take this opportunity to recognize the

dedication of our fellow members.

• Our committee is a group of dedicated individuals who take their charge very seriously.

• Our members are consistently involved, and three have taken on the extra responsibility of serving on the Facility Master Plan Task Force.

16

CBOC REPORT

Challenges• For 2004 Bond Program, increased costs for site acquisitions in

current market

• Lack of maintenance funding has an adverse impact on new and expensive capital improvements provided by bond programs

• Possibility of increasing sustainability requirements in future projects

• REQUEST: Final date when the Board will make a decision on a site for the New North Central Elementary School

17

Community Bond Oversight CommitteeReport to the Board of Trustees

Presented by: Ashton Cumberbatch, Bobby Jenkins, and Eliza MayMarch 7, 2011


Recommended