+ All Categories
Home > Documents > Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards...

Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards...

Date post: 03-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
92
Competency Seminar Competency Pathways – Control Systems Standard Launch Masonic Centre, Sydney April 2015 August 2015
Transcript
Page 1: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Competency Seminar Competency Pathways – Control Systems Standard Launch Masonic Centre, Sydney

April 2015August 2015

Page 2: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Welcome Jennifer Duxbury Industry Engagement Coordinator

August 2015

Page 3: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

- Transport NSW Asset Standards 00VERNMEl'1T Authority

Emergency evacuation procedure

IF YOU HEAR THE FOLLOWING ALARMS:

ALERT ALARM

Action : All wardens to respond. Staff to check immediate area for signs of darmger and stand by. (Outside normal working hours immediately evacuate on sounding of the Alert Alarm)

EVACUATION ALARM I~ 2ooi>wnoop

Action : All staff evacuate via the nearest exit and proceed to the assembly area.

KNOW YOUR EXITS

FOR YOUR SAFETY MAKE SURE YOU KNOW THE LOCATION OF THE NEAREST EMERGENCY EXIT

ASSEMBLY AREA

LIVERPOOL STREET

1-w w a: t;

GOULBURN STREET

Hyde Park

August 2015

Page 4: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director

April 2015August 2015

Page 5: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

TfNSW update

Page 6: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Freight, Strategy & Planning

Deputy Secretary Freight, Strategy &

Planning

Executive Director Bureau of Statistics &

Analytics

Executive Director Transport Strategy

Executive Director Freight Industry

Executive Director Transport Policy

Executive Director National Policy & Priority Initiatives

Executive Director Transport Networks

Executive Director Asset Standards

Authority

Executive Director Centre for Road

Safety

Executive Director Safety, Environment

& Quality

Page 7: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Our challenges ahead

• Governance across transport modes

• Defining ASA’s technical role across all transport modes

Page 8: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Setting The Scene – The Competency Imperative……. Mark Smith Principal Manager Industry & Technical Development

August 2015

Page 9: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Agenda

• Background • Mark Smith, Principal Manager, Industry & Technical Development • Steve Lemon, Signalling & Control Systems Manager • Fiona Love, Principal Manager, Capability Services, Organisational

Development

• Launch • Omer Saricilar, Principal Engineer, Control Systems • Jocelyn Edwards, Manager Competency Systems

• Demonstration

• Jocelyn Edwards, Manager Competency Systems

• Wrap up

• Mark Smith, Principal Manager Industry & Technical Development

August 2015

Page 10: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Purpose of Seminar

We recognise competency is a popular subject…

Above all else - we want to hear from you regarding competency, our approach and our documentation. Key Objectives

• To focus on the AEO population • To reframe the strategic imperative to broaden the competitive supply

chain for the provision of critical services • To articulate the TfNSW position & intent • To clarify the role of TfNSW and TfNSW engaged entities • To launch the ‘Competency Pathways – Control Systems’ Standard (T

MU CY 04000 ST) & guide • To test elements of the standard in a workshop environment &

feedback accordingly • Start to establish a common language

August 2015

Page 11: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

The Assurance Game - Many pieces to build….

Page 12: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

AEO Capability Profile

Maturity ratings summary 5.0

0.0

1.0

2.0

3.0

4.0

Engineering Management

Competency Management

Configuration Management

Quality Management Systems Engineering

Documented Average Deployed Average Combined Average Highest average

Page 13: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

TfNSW competence, compliance and accreditation framework

(/) :i... Q)

> ·;:::: 0

Q) c urn ·- :l "'O ta "O Q) Eo­o :i... ;:

0 Cl. 0 ~c ~

rn c

'Vi c Q) u ~

National Laws

TfNSW Competency Requirements

(Generic)

NSW Laws

individual to work

August 2015

Page 14: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

TfNSW Collaborative Competency Delivery Model – Who Does What?

TfNSW Asset

Standards Authority

O&M Agencies

(e.g. Sydney Trains)

TfNSW Organisational Development

Sets the Generic competency requirements for specific (critical) functions & publish on behalf of TfNSW for the AEO population

Provides the Product and Domain competency requirements & information

Supports the provision of education, competency and training products and services to enable industry to meet the competency requirements

August 2015

Page 15: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Stephen Lemon Signalling & Control Systems Manager Sydney Trains

August 2015

Page 16: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Collaborative Competency Delivery Model

TfNSW Asset

Standards Authority

O&M Agencies

(e.g. Sydney Trains)

TfNSW Organisational Development

Provides the Product and Domain competency

Supports the provision of Sets the Generic competency education, competency requirements for specific requirements & and training products and (critical) functions & information services to enable publish on behalf of industry to meet the TfNSW for the AEO competency requirements population

Page 17: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

The Operator / Maintainer Perspective

The importance of rigour of assessment. • Sydney Trains need AEOs to be able to demonstrate

they have assured themselves that competent people will deliver the work in control systems

• The network is complex and the consequences are high risk

August 2015

Page 18: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

The Operator / Maintainer Perspective

Road to authorisation

• Sydney Trains are working with ASA & OD to determine the gaps in domain & product knowledge.

• Authorisation to work on the network follows meeting the Standard and addressing the gaps.

Page 19: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Fiona Love Principal Manager - Capability Services Organisational Development, TfNSW

August 2015

Page 20: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Collaborative Competency Delivery Model

Sets the Generic Provides the Product and competency Domain competency education, competency requirements for specific requirements & and training products and (critical) functions & information services to enable publish on behalf of industry to meet the TfNSW for the AEO competency requirements population

TfNSW Asset

Standards Authority

O&M Agencies

(e.g. Sydney Trains)

TfNSW Organisational Development

Supports the provision of

Page 21: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

& the problem

The Clients and the Problem clients

The problem they h ave: • No well targeted or useable educational pathway • No defined competence standards in some areas • Opaque internal systems that allow contractors to be productive The scale of the problem: • Across all industry sectors.

August 2015

Page 22: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Our challenge is …

Competency & Capability

-

No formal trsiJning cur·1reriH)' exists

August 2015

Page 23: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Create a Capability Framework

August 2015

Rail Control Systems

Competency~;(· 'I Corn~~ B I i C«npe!eocy C

I I I

I

AQF l1Wt:)I 0 Graduate ColtlflcaM In Rall Control Systamt.

Page 24: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Develop a series of e-learning modules

August 2015

Develop a series of elearning modules

Page 25: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Develop an Assessment Framework for Recognition of Current Competence

August 2015

Page 26: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Develop an Authorisation Process

August 2015

AQF aligned

•• •• •• ..... •• ••

Competency Framawork

Step

4

Develop an authorisation process

Page 27: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

The Solution…

August 2015

Generic Rail Control Systems Program

Product-specific Program - ATRICS

Step

4

Evidence Portfolio

Page 28: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Rail Control Systems Capability Framework

Generic (AQF)

Underpinning engineering qualification

Graduate Certificate in Rail Control Systems AQF 8

ASA Competency Pathway – Control Systems.

Underpinning e knowledge Course Underpinning Knowledge

Intro Rail Networks, Infrastructure and Terminology Control Systems Interlocking Telemetry System

Design - Scoping The Project - Designing Control System Data - Designing Infrastructure.

Build Build Infrastructure Load Software

Test - Testing Control Systems - Commissioning Control Systems

(Specific to Sydney Trains)

Products and Systems Training and Accreditation

ATRICS Phoenix VICOSS SIGVIEW

Core Functionality Systems Data Manager Classes of Data Data design /infrastructure design modules Deployment and Commissioning.

Product

Domain (Enterprise)

SX52 – Safely Access Rail Corridor (RISI) Access to live locations. Safety Management System (Sydney Trains SMS) ST Specific Training in Configuration Design, Infrastructure Design & Control and Test.

Authorisation and

commissioning

Page 29: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

What else is happening?

• Sieving exercises to develop domain and product programs • Broader access to Transport Training Centre • Exploring new learning technologies such as e-learning

info/graphics, apps • Ensuring greater use of required capability frameworks such as

Engineers Australia to minimise barriers to recognition of professional standards knowledge

• Advising and collaborating with major AEO’s to design accreditation

• How are systems that are risk base accessible and support efficiency and productivity

• Establishing a glossary of terms for all parties within the transport cluster

August 2015

Page 30: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Sieving exercises to develop domain and product programs

August 2015

Page 31: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Broader Access to Transport Training Centre

August 2015

Page 32: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Exploring new learning technologies such as e-learning info/graphics, apps

• Build 10 e learning modules (Generic)

August 2015

Page 33: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Ensuring greater use of required capability fr ameworks such as Engineers Australia to minimise barriers to recognition of professional standards knowledge

Page 34: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Advising and collaborating with major AEO’s

August 2015

Page 35: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

How are systems that are risk based accessible and support efficiency and productivity

August 2015

Page 36: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Establishing a Glossary of Terms

TtNSW - Glossary or 1 erms

evieUonsl Oe•CriptiODS .,,,,. 'O 20 10

"""9d4atlon

~edCoorse

-eo

\Of

"'9essment (of ::ompetenco)

iluthorisation.

Competence

A mocMI lot lndiclt.ng a combination of on Iha Job. oo.c:lllng and formal teaming lj)l)loacll to development.

Accteclllaban Is IN> process In wl1lch cerllficaban of competence. authority. 0< equivalency ls presented that oomplles ...th defined standards_

A prcgram of leaming that oomprises one°'"""" oompononts (e.g. units of competency. modules°' subjecls) lhat has been endorsed by an accredb1g atfhonty.

An lndMdual who hos demonstrelod """"*""'" and been deemed ...-to hold Ille accreditation by an AEO (tnd " required, a RIM)

AtJthorlsed ~Organisation. A IUlll*erol •defined eng1neG1V>g seMce or product that has been assessed and granted AEO status by TINSW

AUSlr.lian Oualificatlons FrameWO<I<.

Assel Standanls Authonty

Austrdan Slub Oua111y Autho<lty The - ~tor fO< Auslrella'• vocabonll oduca1ion and training -

The pn>cess ol oolleclong a range of oY!dence and malting )\Jdgements on whether competence has been - to confirm that an lndMdual can petform to Ille standards expected In Iha """1<placa.

Tile Internal process vmereby a responsible entity deems a produc:t. service °' ondMdual compliant to requifMlenls and regulatory and legislatrve mandates.

The~ slulls and obthlles to perform a - effectively. The venl'lcaban and aUlhentlcatlon of a -· en~1lement to recogn4IOn

The aystemabe proce11 of ensumg thal al equiprl*1t and systems pertorm onteracbvely according to the de$i!jll in1Bnl and the operational andUSe<-ts.

The idenlific:aban and application or know1edge, Skits and behaviours requred to petform laSks 10 the standards "'1'*9d,

''Q·filOv.au

August 2015

Page 37: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Omer Saricilar Principal Engineer, Control Systems Asset Standards Authority

August 2015

Page 38: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Presentation Structure

1. Something Simple

2. Train Control Systems • Design Examples • Components • Competency Examples

3. Customisation

4. Questions

August 2015

Page 39: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

An Analogy…….. Control Systems are normally very complex. We will start with something everybody knows and uses…….

When you buy a car: • You know the reasons behind common functionalities, such why the car

should have a powertrain, what the powertrain does, what are the parameters of powertrain.

• Using the common knowledge, you can understand the common specific functionalities of the powertrain of the specific car and you can make a comparison.

• Without such common knowledge, you may not understand the specific functionalities, such as what is rev, torque, cylinders, kW, hp etc…

• Only common knowledge is transferable between cars – for example knowledge about turbo charge may not transferable, unless it is common to all cars.

August 2015

Page 40: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

An Analogy – cont’d

All vehicles may have the following minimum components: • Powertrain • Transmission capabilities • Steering capabilities • Braking capabilities • Etc…

All cars have the minimum components • All vehicles’ minimum components • Signalling capabilities • Seating capabilities • Night driving capabilities • Protection against weather • Etc…

August 2015

Page 41: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

An Analogy– cont’d There are levels of knowledge: • Generic: applicable for all levels which are specialisations of this knowledge

such as vehicle.

• Domain specific: may not be transferable to other domains, such as bicycle vs car.

• There could be more layers depending upon the system’s complexity and configuration.

It is normally assu med that • Generic knowledge is transferable, re-usable and an enabler for domain

knowledge.

• Domain specific knowledge is not directly transferable, re-usable and an enabler for other domain knowledge. But it enhances and supports the generic knowledge and creates experiences.

August 2015

Page 42: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Venn Diagram - 1880 by John Venn

August 2015

Page 43: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Train Control Systems (TCS)

August 2015

Page 44: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Production Components of TCS • Generic Product – normally software and associated tools

• Infrastructure – environment the product and its configuration reside and perform:

• IT and associated software/firmware • Networking • Interfacing to signalling systems • Electrical • Environment

• Configuration – adapts the generic product and its infrastructure to the specific

application: • Signalling • Operation • Infrastructure

• Testing - needs to cover all three areas.

August 2015

Page 45: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

ATRICS Infrastructure &nr.-lleld

Sl:nltl'lfl!ld &;nal &oc Comra4 R"'°""

~ ......... -· B )

_,,,.. -.c; -·

~

r.,,._ -· Canmmtl11a1il:xl

Backbone

... _ -·

(Homlibusi"t Ccc-Jrct COl!IJe Con:lml ~

!:pplns \'lla'b!Dlkr>

---- ·

-.u -· ---·

--~ --·

·-

August 2015

Page 46: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

PHOENIX Infrastructure

August 2015

Page 47: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Proposed Main West Infrastructure

,-----------------' I I I I I I

......

·---------------------------

-· ·- --! -----~-----------~-----------

August 2015

Page 48: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Infrastructure Components

UNCOMMON COMPONENTS

• Overall design • Types of Servers • Types of Workstations • SOE (Standard Operating

Environment) • Types of Routers/Switches/Firewalls• Network Configurations • Telemetry Interfaces • Electrical Interfaces • Etc…

COMMON COMPONENTS

• Overall design • Servers • Workstations • SOE (Standard Operating

Environment) • Routers/Switches/Firewalls

• Network Configurations • Telemetry Interfaces • Electrical Interfaces • Etc…

August 2015

Page 49: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Common Engineering Knowledge • Understanding business requirements

o Signalling o Operational o Maintenance

• Translating business re quirements to specific control systems’ requirements

• Translating non-functional requirements to specific control systems’ requirements (such as RAM)

• Translating safety requirements to specific control systems’ requirements

• Translating control systems requirements to components’ requirements

• Design or modify the existing design to implement component requirements

• Etc…

August 2015

Page 50: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Common Engineering Knowledge – cont’d

• Information Technology

• Networking Technology

• Electrical Engineering

• Electronic Engineering

• EMI

• RAMS

• Testing

August 2015

Page 51: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

A TCS Example

• Business Requirements: Modification and expansion of the existing train

yard with an additional interlocking – more tracks, points and new operational rules.

• Control Systems Requirements – Element 2: Adding and modifying maps, IO tables, rules, alarms Addition of new interlocking Safety and non-functional performances Etc…

August 2015

Page 52: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

A TCS Example– cont’d

• Infrastructure Requirements – Element 3:

• Handling new interlocking • Handling new workstation – existing workstation can

not handle it due to limited real estate. • Modification of network to handle new workstation • Not affecting the existing RAM requirements due to

new hardware • Not introducing new hazards and affecting existing

hazard • Etc…

August 2015

Page 53: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

A TCS Example– cont’d

Elements

3 E51ablishes

infra51ructure design and

construction

requirements

3.1

Evidence criteria

Identifies and allocates

infrastructure related

requirements from the Project

Scope and Control systems

Funct1onal Specification to:

determine the functionality required by existing or new

1nfrastruaure components

determine what infrastructure

needs to be installed, modified and disposed of to ensure all operation,

maintenance, trainin&. suppon and disposal

requirements have been

addressed

ldentJfy and update RAM requirements

ensure hardware specification

factors are incorporated and

accommodated

establish wflether

components outside the

standard operatirc environment will be required

identify hazards or allocate

hazards or both related to t he

infrastructure

Functions

y y y N N 2, 3, 4,

12, 13,

14

E $

3.2

3.3

3.4

Analyses control systems

f\.nctional specifications, control

systems cil"cuit books and any

other relevant input documents to

Identify and confirm: . staging requirements for the design . impacts on and of other

projects . impacts on testing, training

and s141port systems . other relevant

implementation issues

Identifies and analyses

infrastructu re inte rfaces and the

system integration at a detailed

leve l. Identifies project, system,

and safety hazards and creates or upd.ates sa fety cases accordingly.

Conducts site surveys to: . confirm location and current

state of documented

infrastructure . confirm that existing •As-&JilT" are current . evaluate the capacity and

compatibHity of existlne system to accommodate the

proposed changes . identify site hazards and

potential obstades in meetinc

desi&n requirements . confirm requirements for

meeting desien specifications

'C ~

i >

"" ~ t: 11

c ! 2 ii .. ~ 0

.~ R ~ j !~ y y y N N 2, 3, 4,

U ,13,

14

y y y N N 2,3, 4,

12,13,

14

y y y N N 2, 3, 4,

12,13,

14,15

Elements Evidence criteria

Functions

... .. 1 21

1 ..

N .. -

August 2015

Page 54: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

A TCS Example– cont’d

Infrastructure Design – Element 4: • Workstation only:

• Existing workstation design will be used with brand new hardware – since not available anymore. Check and verify against

• Applicable standards, • Identified interfaces, • Required RAM • Existing or newly identified safety hazards • Addressing existing issues/problems ­

improvements • Proposed testing plan • Create and submit type approval document.

August 2015

Page 55: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

A TCS Example- cont'd

Functions

a: ~ tl i al

c

I g i ·§ ~

!IP ~ ~ ~ R ·c:

~a .t: ~ 9- 8 4.4 Evaluates the feasibility of all y y y N N 4, 12,

Elements Evidence criteria possible design solutions and 13,14

'$ selects the optimum design which

) :i; .. ...,.

i "C ... .. u .i ..... >-

a: ~

tl 11 11 Q :;r

~ 0 5 ~ ;; E

~ ~ ·c } ~ j] ~ ~

meets identified design,

construction, maintenance, and

business constraints.

4.5 Identifies designs and develops y y y N N 4, 12,

preliminary tests in order to 13,14 4 Develops a 4.1 Identifies, interprets and analyses y y y N N 2, 3, 4,

desien and the relevant desi:n, industry and 12

construction reeulatory standards and design

mitigate previously identified risks~

safety and interface issues.

solution that th• infrastructuro solutions to 4.6 Assesses whether or not • type y N N N N 4, 12,

m•ots proj•ct comply. approval" is required for any a.ssets 13,14

r•quirem• nts 4.2 Analyses previously produc•d y y y N N 2, 3, 4, and initiate type approval

project documents to determine: 12,13, 4.7 Initiates "ASA concession• process y N N N N 4, 12, . th• compl•xities and risks of 14 if the design does not comply with 13,14

th• intorfacos and standards.

intord•pond•ncies with existing control systems

infrastructure and rail

4.8 Identifies analyses a nd documents y y y N 4, 12,

all new or modified confi~ration N 13,14

operations data applicable to the new or

. dosign options and solutions modified systems for the

infrastructure. . applicable RAMS

requireme nts desien 4.9 Documents the design, using y N N N N 1, 4,

constraints and construction appropriate software tools to 12,

limitations produce detailed diagrams and 13,14 . appropriate precedent desiens drawings.

that could be replicated for 4.10 Validates design quality and y y y N N 4, 12, the rurrent pro,,ect completeness, ensuring that: 13,14 . protection and isolation of the

safetY critical systems . it meets the requirements of

the Control Systems . potontial businoss continuity Functional Speafication problems and mitigation . it complies with all relevant

4.3 Applies knowled&e of enginee ring y y y N N 4,12, standard.s desoen concepts, principles, 13,14

theones and techniques to explore 4.11 Pre5ent5 the design solution, y N N N N 4, 12,

possibilities, solve design problems ensuring all stakeholders 13,14

and develop credible solutions understand the merits of the

which proporty address the critical design, and how it meets the

design issues and assumptions. project requirements.

--------------------------------------------

·~ ..... >

August 2015

Functions

Eleme nts Evidence criteria

'$ ~ l5 .. ...,.

i s ·c: g_ ..

Page 56: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

What is a Standard?

• Common and repeated use of rules, conditions, guidelines or characteristics for products or related processes and production methods, and related management systems practices.

• The definition of terms; classification of components; delineation of procedures; specification of dimensions, materials, performance, designs, or operations; measurement of quality and quantity in describing materials, processes, products, systems, services, or practices; test methods and sampling procedures; or descriptions of fit and measurements of size or strength. http://www.nist.gov/standardsgov/definestandards.cfm

Is it voluntary to adopt:

• Some cases it is, e.g. “adoption of IEC standards by any country, whether it is a member of the Commission or not, is entirely voluntary.” http://www.iec.ch/standardsdev/publications/is.htm

• TfNSW cases it is mandatory.

August 2015

Page 57: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

ASA Charter Functions

August 2015

• Technical Capability

• AEO Obligations

• Transport Agency Obligations

Page 58: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

The Asset Life Cycle

t nterprise Life C ycle Stages .__R_ .. _,._;,_,.,_,._,._n_ .. _v_,._1n_P'_'_""_" _' _,, __ P_r_o1_· e_.<_.t _D_~_. _•n_lt_io_n __

: ·~~ Dcvclopmcn~: · .. :... Producticn """ Ltilis~tion ""' R.cti1c•m_'f1t • • Syste m Life Cycle Stages ,_ __ E_,._P_lo_ro_to~ry.;....•_· __ ....... ___ c_o_n~cc-'_P_t ·- ·--

1

c..,,..bili!>· Fea•lbllty I s,. ,. m P hases

•• 1s 0-1 s2aa. S tages

Stak&holder& UWY• NwY:.lli

- - -

R~~i:::~ Stmli>'Js -<~.l~~~~~;~h-' P~~1:":.~.~r¥ g~~"-9~~ = ~:~,~~~~~ ';~~::.~~~:~~ 10~"';~!.t' '' & <.;v,",",'~~,.,. O J _·r ~1hon,.. & r11~,111 .c11..t r1L:W D~~::~~~~r

~\_.. ___ P_I ___ -&-'--~~,---o~ .. =,....,..=~•"""'Jc,,=:~•P'S=-~\ : 0 S t y ...O·d 1· ,...._,... ati & D• '; ~ ~,nng \\ & M etres Optinn~ ~ •. - ,:_ • - .. :..J'~ ~ .. ~ !~ ' ' ' ...,.......· ore :\ Uutr:,;;~it:-:lt \~ ~'\nql~~&Trqri""°ll. , - -- ·=- . • : ~ • - • ~ .. - i;h~~:~~~~~1~ ~1:1~~~:~ /:

r e H ibility G=udy • - .~tatn u_,, , • • '-------------H------' f : : :..t=riqirir..--ririq ' V' rr1tHt r-I r .f ...,.( \ ff'm "' I fr• c .. ( d t" k :

: : ' --, · ~ : / 0"V'!rf'lt1r.Fa Requirements ..._ :... ;;_;r;"':~, \ . :_ . _ . ~l~c~o~ ~~te~1 .. ...L ·• ':::. ... ~l S)"Bt&rn

Va lidation Arcrillietu re : : : : • Acce pt• nce

Oc~lsn ~ · • ~ ~ l ! . T-~·P • y:: enficat10n •• :: \. \ t'iy~~·•• \ : Veriftjation (Sys1Efm lnterfacej3) 7'/ ~~:~ /:

--:;.._ Ph . I w- . - ··- - - . ·- . - - - . I ""' . I : . r \ .o.«hr:,. \. ~ l ~ < &T~::0 / ~

n e:H;ign : : : : : • : v.-.r iric{'tii:u'l ' : Subt)'••m v ::irlficatlon (SLbsystem) LI: S dii)fa;tem 1.'h :

: · -+ I r.vr.1 .: - • - • :- • - • ' I Lo~~ ;//. : • • \ c..;gn \\' ' ' ' I ntegrotion I/I. ' ; '-' ' ;, 1, ¥, & Teatg ///_ ;,

Design

vr: rlfication l\. . ~ I Jnll I'"'' '\~\>. Vcrificatioi1 (Un it) I : .nff I ••• 1 /~ l ;: ~\ Daiign ~ " - ·:- • -r Toala /// , :

r . ':"~" i / tf :: l Bui I~ ""'ij"'i:::== = = = !..:. : ,,_ :

Varificatio::' , _ \ P""Oci..,..,..e,._t. r•~ca~.: =.t?7i ~:::, M a111.n:ictu111tg /@ C on 1truction/ ln t<i; l::tlli:.·i...n /.~

Life Cycle

Baseline Ex lorato Coneeot Build Vel1dation Retirement Stage Gateways P ry P1chm1nary Pes t Build Op'"'"'"!!

August 2015

Page 59: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

AEO Guide to Engineering Management

I ··-·-

S T AKEHOLDER & USER

REQUIR EMENTS TRAOEASIUTY

Eleplora'!cty ba&EChe galeway -----------

V ertncatton of De&gn stage Ou-.put

I - ~ ,_ i ~ . 12 I!!:!

. TR.".O~IUTY_

- . - . - . --·111!11.lll!l!!•i~!!ll;lll;r=ll!t;"\lll!ll'!!l!'llllfll!ll ... _.,A. blulod . -~-.Fo-r-~-SEl-i:u_n_:U_OCI_"~ IDaSE!lne

1:::--E

D~te<a ( conngpratlon ) garewa'.)' Gm.'emance Cor.:rol Gat e

FABRICATION,. "As Bullt"

I(') ~ !! a: I Ill: I ::;; !!;! .·u

CONSTRUCTION & INSTALL.A TION

D05'1-0una ._ ___ a_a&e1_,._1_ne ___ _. tt.a&efln.e

I I ..,

·I

ll'SSPECT. TEST & COMMISSION

g.ateway

va1Jda-.Jon °' lrr:egra-IE<I sy.s~em

I I m

I

I

1- . J

I

CONF IG U RATION MANAGEM ENT

R E CORDS

August 2015

Page 60: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Elements

vs A

sset Lifecycle Rail Industry Control Systems Functions

I I I rain ConLrol Systems Ocsagn

Systcrn Arch1tc:cturc Design

I ram Conl rol Systems Constructilblltt-y Review

System Architecture Design

System Architecture

Chcck/Rcvi~ / Verification/ Approve

O<Jta Configll'ation Design

Dota Config .. ation Check I Review

Data Configll'atioo Design Verification

Data Configll'ation Design Approve

Systems Software Design

Systems Software Design Check/ Review

Systems Software Design Verification

Systems Software Design Approve

Infrastructure Ocsign

Infrastructure Ocsign Check / Rcvic.w

lnfrastruct.urc Ocsign Verification

Infrastructure Ocsign Approve

Verification and Validation Design

Verification and Validation

Check/Review/Verification/Approve

Concept Draft

System Architecture Design

System Architecture

Check/Revl.,.,/Verlflcatlon/Approve

Conflg.,.atlon Design

Conflg .. atlon Checker / Review

Conflg.,.atlon Design Vcrlflcotlon

Conflg.,.otlon Design Approve

Systems Software Design

Systems Software Design Ched< / Review

Systems Software Design Verification

SystcmsSoftwore Design Approve

lnrrasl rucLUrc Design

lnrrasl ruclurc Design Check / Rcvic.w

lnfrasl ructurc Design Vcrif1cauon

Infrastructure Design Approve

Verification and Validation Design

Verificct:ion and Validation

Check/Revlcw/Verlflcatlon/Approv"

Design Ornft

ConfigLration lnstalla.ion

Softw are Installation

lnfrasl ruclurc Installation

Control System Integration

§' it

l

i

Control System Integration f I Control System Valida:ion ..

Control Systems Commissioni~ !

Control System Malntalncnance

Control System Commissioning

i i

f

I

D D "" ~

h .... .. .... :;.

.. :i: ~ ~ ~

0 "' Q.

ii ,. i'i

Q. i5'

" " ~ "' Q.

g "

Q Q. s-Q "' "' :;.

,. "

2' :; " 8. 2' 0

" " :l "' i5' a

I \ ...

August 2015

Page 61: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Elements vs Asset Lifecycle - cont

• Elements 01: Establishes design assurance requirements • Elements 02: Establishes control systems documentation • Elements 03: Establishes infrastructure design and construction requirements • Elements 04: Develops a design and construction solution that meets project

requirements • Elements 05: Develops the installation work packages and test plans • Elements 06: Undertakes peer or independent review or both • Elements 07: Procures and tests infrastructure components • Elements 08: Approves • Elements 09: Establishes and prepares installation requirements • Elements 10: Maintains quality control during installation works • Elements 11: Installs and configures infrastructure components and parts • Elements 12: Decommissions and removes existing infrastructure • Elements 13: Completes post installation activities • Elements 14: Verifies installed infrastructure • Elements 15: Audits installed infrastructure

August 2015

Page 62: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Is this a Straitjacket ? Each AEO and Transport Agency (may not be AEO) may have different: • Authorisation scope • Engineering framework • Processes and procedures • Competency framework • Products • Services • Culture

An example: • Based on ASA asset lifecycle guideline, procurement happens before the

design. Design is based on the procured or existing product

• An AEO may do design first and procure the product to meet design parameters.

August 2015

Page 63: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Customisation & Flexibility Normally all requirements within the standard must be complied • If an AEO can not comply the requirement, must seek “concession” from

ASA before the design phase, which may be accepted or rejected or standard may be updated.

• If an AEO’s implementation does not fulfil the standard’s requirements, it is called “non-conformant” & treated accordingly.

But this particular case, ASA is giving power to tailor the standard as detailed in T MU CY 01000 GU TfNSW Competency Standards Guidelines and Glossary v1.0 as long as: • Customisation to the standards must be justified and will be auditable by

ASA

• Unacceptable to customise the evidence criteria against elements.

August 2015

Page 64: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Competency Jocelyn Edwards, Manager Competency Systems

August 2015

Page 65: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

How does it all fit together?

Competency Guidelines and Glossary

Competency Pathways Standards

August 2015

Page 66: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Ongoing Work Plans

• The Standard and Guidelines - collaborative development

• Structure of the standards, definitions and how the

variables work. • Further work is underway in Control Systems,

Signalling and Electrical.

August 2015

Page 67: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

TfNSW Competency Pathways – Control Systems

• Version 1 - Published July 2015

• Effective October 2015

• A Standard which sets the minimum generic requirements

• Developed as a collaboration project between ASA, Sydney Trains and TfNSW OD.

August 2015

Page 68: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

The Standard

• Establishes pathways and generic competency requirements to perform functions within the control systems discipline.

• Provides additional information to an AEO for the

development of its auditable competency management system (CMS).

• Provides guidance to enable assessment of

personnel who are required to demonstrate competency.

August 2015

Page 69: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Pathways

New entrants

• This pathway will identify the pre-requisite qualifications and training requirements for those personnel with little to no experience

Skilled and Experienced

• Personnel wit h current or previous experience working on the TfNSW rail network • Demonstrate

domain or product knowledge

Transferable Skills

• Personnel who are able to demonstrate they have some of the skills and knowledge to carry functions • Includes personnel

with National or/or International experience

August 2015

Page 70: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Roles Vs Functions

• The competency standards describe the generic competencies that are relevant to functions or tasks.

• ASA has elected to specify functions that exist over the Asset life Cycle as opposed to Roles.

Design

Design Engineer

Check

Approve Verify

August 2015

Page 71: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

August 2015

Standards - ASA business activities

Alignment to

international and professional

standards

• Overseas Frameworks (e.g. IRSE) • Washington Accord Agreement • Professional Bodies &

Institutes

Alignment to AQF (where possible)

• Developing National Competencies & UOC’s • Vocational Education & Higher

Education alignment • Accreditation

Page 72: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

TfNSW Competency Standards, Guidelines and Glossary

August 2015

Page 73: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Where can I find the standards and guide?

Here’s where you find them… http://www.asa.transport.nsw.gov.au/

August 2015

Published July 2015 Effective October 2015

Page 74: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Morning Tea

Page 75: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Competency: detailed overview Jocelyn Edwards, Manager Competency Systems

August 2015

Page 76: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Structure of the competency standards

Functions: A specialty area of a role usually comprised of a collection of tasks

Elements: Describes the activities or tasks for which a function might be needed to be competent

Evidence Criteria: Assigned under Elements and expresses an expectation of what a competent person would do in terms of observable results and behaviours.

Standard Title: The discipline area covered by the Standard.

Variables: References the variables, located in the following section of the Standard, and relevant to the Evidence Criteria. The variables contained within each list guides the user to the relevant domain/ product knowledge or further specific items to be selected and used for assessment.

August 2015

Page 77: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Variable Examples

Page 78: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Flexibility o f the standards

Can be tailored to fit AEO organisation

Language can be revised but careful not to lose the essence

Elements can be discounted

However…

Must be justified and will be auditable by ASA

No customisation of evidence criteria against elements

August 2015

Applicable: Since Element 10 is applicable, then 10.1 and 10.2 are applicable.

Not Applicable because: (a) The AEO is not authorised for de-commissioning (b) Site is new and there is no existing infrastructure to be decommissioned therefore this Element might be deemed not applicable.

Page 79: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Additional Notes • The specific competency attributes that underpin expected

performance are embedded within the Elements and Evidence Criteria.

• These are expected behavioural and ‘soft skill’ attributes. They are

common core competencies such as: • the ability to communicate effectively, • the capacity to problem-solve, • risk adversity • accept responsibility and accountability.

• This allows the Competency Standards to serve as a measure of

expected performance against which actual performance can be assessed and evidenced by an AEO.

August 2015

Page 80: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Proficiency levels

AEOs shall define the proficiency levels. The following proficiency levels have been provided as guidance: • Level 1

– can perform the identified competency independently and without supervision in complex activities. Can produce quality outcomes based on the relevant standards and AEO’s process and procedures.

• Level 2

– can perform the identified competency for less complex activities without supervision or can perform the identified competency in complex activities under supervision or both. Can produce quality outcomes based on the relevant standards and AEO’s process and procedures.

August 2015

Page 81: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Customisation of the standards

August 2015

Page 82: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Practical Exercise

We will carry out an exercise to demonstrate the use of the Standard and look at how it can be integrated into the AEO’s competency management system.

August 2015

Page 83: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Assessment

“The process of collecting evidence and making judgment's on the nature and

extent of progress towards the performance requirements set out in a standard or a learning outcome, and, at

the appropriate point, making the judgment as to whether the competency

has been achieved." VEETAC 1993

August 2015

Page 84: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Evidence – Getting the Balance Right

Summative Making a judgment based on all evidences, where learning has ended and cumulative evidences allow the assessor to determine competency sufficient to award a competency outcome.

August 2015

Page 85: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Types of Evidence It is important that the evidence is: Current Authentic Relevant Sufficient

Direct evidence • e.g. observation from previous work, references from employers or clients

Indirect • e.g. written or oral questions evidence

Supplementary • E.g. reports, logbook, project plans evidence

August 2015

Page 86: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Example

Comments Elements Evidence criteria Appropriate evidence examples

Develops a quality design and construction solution that meets project requirements

Identifies, interprets and analyses the relevant design, industry and regulatory standards and design the infrastructure solutions to comply

• design reports or plans

• interviews

• log books

• references

Undertakes peer review or independent review or both

Provides constructive feedback to the designer, questioning and challenging decisions made

• meeting minutes

• design review comments registers

• reports of corrective actions

• reassessment engineer reports

• Existing for employees?

• Ease of access in HR/HRIS

• Currency

• Sufficiency

August 2015

Page 87: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Workshop Example

• Work in groups according to your seating

• Elect spokesperson

• Use sample assessment tool to determine appropriate evidence types against the Elements of Competency – Consider relevancy and sufficiency of evidence – Consider proficiency levels

• Please record evidence types on the provided flip charts.

August 2015

Page 88: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Sample Assessment Tool

August 2015

Page 89: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Customisation of the standards

August 2015

Page 90: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Activity Feedback & Discussion

• What were the challenges? Sufficiency of information Quality of information Currency of information

• Type of evidences

• Assessors Finding suitable assessors Checking quality of assessment

August 2015

Page 91: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Contact details 02 9422 7187 [email protected]

August 2015

Page 92: Competency Pathways - Control Systems Standard …...2015/08/15  · August 2015 Asset Standards Authority Progressing across all modes Jim Modrouvanos, Executive Director August 2015

Thank you!

August 2015


Recommended