May 19, 2009S. Mashio, T. Shimizu, K. Kumagawa, M. Doi
Completion of220 kV XLPE cable project in Qatar
JTD23-X2410
7/27/2019 Completionof220kVProjectinQatar(JPS).pdf
http://slidepdf.com/reader/full/completionof220kvprojectinqatarjpspdf 2/8
Outline of Project
• Power Utility(KAHRAMAA) developed
7th and 8th power line projectswith 220kV and 400kV XLPE cables
in the vicinity Doha City.
• Two circuit 220kV line constructionstarted in 2007.
• J-Power Systems (JPS) supplied one circuit 220kV Lineand it was recently commissioned in April 2009.
• 400kV line is under construction by JPS andplaned to be commissioned in May 2010.
Umm Al Amad
Super
Al Wajbah
Super
Al Waab Super
400kV XLPE
2 cct x 22km(JPS supply 1cct)
LDS 2
220kV XLPE
2 cct x 12km
(JPS supply 1 cct)
7/27/2019 Completionof220kVProjectinQatar(JPS).pdf
http://slidepdf.com/reader/full/completionof220kvprojectinqatarjpspdf 3/8
Features
Heavy Duty and High Transmission Capacity Design
Transmission Capacity : 515MVA (1352 A/cable,100% load)
Cable Type : 2500mm2(4934KCM) Lead Sheathed Cable
( against saline contamination in soil )
Route Length: 7.5miles (12km)
Premold Joints: 66 (w/ copper sleeve in FRP box)
Section length :1600ft (500m) (32 tons/reel)
Installed in Trench (Major section is direct burial)
Special concern about soil dry out:
DTS monitoring system provided for entire route.
FEM thermal analysis for optimum duct bank design.
7/27/2019 Completionof220kVProjectinQatar(JPS).pdf
http://slidepdf.com/reader/full/completionof220kvprojectinqatarjpspdf 4/8
FEM analysis in plural soil condition
Bedrock (0.7Km/W)
Normal soil in over layer was assumed dry out ( 2.7K.m/W) whilst
Bedrock was 0.7Km/W. Due to difficulty of cutting trench and
procurement of backfill, trench width was optimized by FEM analysis
7/27/2019 Completionof220kVProjectinQatar(JPS).pdf
http://slidepdf.com/reader/full/completionof220kvprojectinqatarjpspdf 5/8
JPS has supplied more than 1500pcs of 220kV premolded joints.
Though premolded joint can be tested in factory, previous
experiences showed vital importance of jointing work.
Jointing Work
[ System approach by JPS ]
Qualification & training for joint team
Keeping clean & low humidity circumstances
Process control of jointing work by engineer
[ Final verification in commissioning test]
AC high voltage test for entire length PD measurement at each Joint with PD sensor
7/27/2019 Completionof220kVProjectinQatar(JPS).pdf
http://slidepdf.com/reader/full/completionof220kvprojectinqatarjpspdf 6/8
AC High Voltage Test (IEC 62067) Test Voltage AC 180kV (1.4Uo)
for 1 hour
Route Length : 7.5 Miles (12km) Resonant Frequency : 25 Hz
AC High Voltage Test
Frequency Resonant AC Transformer
7/27/2019 Completionof220kVProjectinQatar(JPS).pdf
http://slidepdf.com/reader/full/completionof220kvprojectinqatarjpspdf 7/8Capacitive PD sensor Terminal Box in
Termination
Insulating Jointwith Coffin Box
220kV XLPECable
Coaxial Cable
Portable PDmeasurement
device
Test Voltage : Uo
Nos. of Joint : 66 (22JB)
Test voltage was raised to 1.4Uofor 10sec, then gradually
decreased to Uo considering
PD inception voltage ratio.
PD Measurement