Concept of E.on Netz for Offshore Grid Connections

Date post: 28-Feb-2018
Category:
Upload: jack
View: 225 times
Download: 0 times
Share this document with a friend

of 33

Transcript
  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    1/33

    1

    Concept of E.ON Netz for

    offshore grid connections

    Our Offshore activities

    NetzOffshore

    David ScharteWaddensea Forum 19. Fan 2008

    Seite 2Waddensea Forum Fanoe November 2008

    Content

    Offshore grid connections background

    How many windfarms have to be connected when and where?

    How shall we do it?

    Projects in 2007 till 2009

    Crossing Norderney

    The first wind park Alpha Ventus

    The first grid connection: NordE.ON 1 for cluster Borkum 2

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    2/33

    2

    Seite 3Waddensea Forum Fanoe November 2008

    Offshore grid connections where we stand now

    In Germany we have ambitious political goals concerning wind power. The

    idea of German politicians is to install round about 1.5 GW until 2011, but

    no German offshore windfarm up to now

    What to do?

    The politicians are seeking acceleration of offshore-process and this

    resulted in a new law based on 17 Abs. 2a EnWG :

    was signed on 17th of December in 2006

    called Infrastrukturplanungsbeschleunigungsgesetz

    Seite 4Waddensea Forum Fanoe November 2008

    TSOs responsible for offshore grid connections and the TSO bears the costof the grid connection

    completion of the connection to the grid must coincide with the end ofconstruction of the wind farm

    the investment & operation cost to be shared between the four GermanTSOs and to be part of price regulation

    the connection must be cost effective and operationally efficient

    the obligation for TSOs applies to all wind farms going into operation

    before end of 2011 (now till 2015 with the new amendment since June

    2008)

    with this amendment the feed in tariff for offshore wind energy into

    German grid will be increased from 13 ct/kWh to 15 ct/kWh

    Offshore grid connections - a new legal task for E.ON Netz

    TSO = Transmission System Operator

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    3/33

    3

    Seite 5Waddensea Forum Fanoe November 2008

    Estimated transmission capacity

    Federal Government: 10.000 MW(until 2020)up to 25.000 MW(until 2030)

    Dena: 20.400 MW (until 2020)

    Requested wind parks (as at November 2008)

    North Sea: >50 (17 approved) EEZ (Exclusive Economic Zone)

    2 12-Mile-Zone

    Baltic Sea: 5 EEZ

    4 12-Mile-Zone

    Seite 6Waddensea Forum Fanoe November 2008

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    4/33

    4

    Seite 7Waddensea Forum Fanoe November 2008

    How many wind farms want to be connected when/where?

    planned installing wind farm capacity is constrained by:- availability of relevant components and facilities- ability to obtain regulatory approvals (planning, permits etc.)

    E.ON Netz must perform a realistic assessment of the installed offshoregeneration capacity over time in order to match transmission capacity to it

    Seite 8Waddensea Forum Fanoe November 2008

    Criteria to validate the date of the operation of a wind

    farm

    BSH- bzw. BImSchG-Approval

    Detailed time schedule of the wind farm build up

    Orders of the components (turbines, grounding structure andtransformer station)

    Assurance of the financing of the wind farm

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    5/33

    5

    Seite 9Waddensea Forum Fanoe November 2008

    How shall we do it? at first every OWP planned his own connection to the grid

    the result: 14 individual cable links with no coordination

    it was neither practical nor efficient

    Seite 10Waddensea Forum Fanoe November 2008

    Implementing the cluster concept: HVDC connections

    Landing point Grid

    Link to the grid

    Property wind park Property E.ON Netz

    Property wind park B

    Wind mills

    AC

    DC

    DC

    AC

    Wind mills

    Property wind park A

    AC SS

    PlatformE.ON Netz

    Converter Converter

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    6/33

    6

    Seite 11Waddensea Forum Fanoe November 2008

    Cluster concept for further distanced connections, a technical

    connection concept developed by E.ON Netz Offshore

    Offshore wind parks (OWP) are combined in clusters and

    connected by one common cable system

    High-capacity North Sea power socket via expandable HVDC

    connections (HVDC= high voltage direct current)

    Economic an environmental advantage: minimizing offshore- and

    onshore routes and use of powerful offshore HVDC cables whichmanage large transmission capacity

    How shall we do it? With modular clustered connection

    Seite 12Waddensea Forum Fanoe November 2008

    How shall we do it?

    individual connections

    Landing point

    Windpark

    platform

    Wind mills

    Grid

    Link to the grid

    Property wind park Property E.ON Netz

    Implementation keys for offshore grid connection

    Coastal area: individual connections by 110-kV-AC cable

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    7/33

    7

    Seite 13Waddensea Forum Fanoe November 2008

    An overview: cluster / alpha ventus

    BoardersContinental shelf /exclusive economic zone(200 nautical miles)

    Territorial Waters / 12mile zone

    International Boarder

    Offshore wind parksAuthorizedPlannedCluster connectionAlpha ventus

    Seite 14Waddensea Forum Fanoe November 2008

    Availability of required material

    Just three offshore cable producers in all Europe

    Currently no 300-kV cable available (expected to be available in 2010/11)

    No mass production until 2011

    220-kV-AC offshore cable not yet available

    150/200-kV-DC offshore cable: max. production of 100 km per annum

    Converter Siemens: project pilot TransBay 2009 no further production

    capacity

    Converter ABB: state of the art but long delivery times

    Converter AREVA: merely HVDC classic available, not HVDC light

    Heavy lifting and transportation: capacities for platform mounting are

    booked up in the long term

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    8/33

    8

    Seite 15Waddensea Forum Fanoe November 2008

    Formation in May 2007

    Ca 35 staff members, supported by the staff of E. ON Netz

    Increasment to approx. 70 staff members in the next years

    Who is doing it ? ENEO der E.ON Netz Offshore

    Seite 16Waddensea Forum Fanoe November 2008

    Organisation of ENEO?

    Projectcoordination

    Projcts Technical Approvals Commercial Operation*

    Support/Services from E.ON Netz GmbH

    Geschftsfhrung

    Assistenz TechnischSchulze Wischeler

    KaufmnnischFricke

    *noch auszugestalten

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    9/33

    9

    Crossing Norderney

    Seite 18Waddensea Forum Fanoe November 2008

    Crossing the island Norderney

    HVDC cable laying

    Offshore cable laying

    Onshore cable laying inempty ducts

    HDD-drilling points anddirections

    Levees

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    10/33

    10

    Seite 19Waddensea Forum Fanoe November 2008

    Onshore cable laying via empty duct construction

    Empty duct with 35 conduitsBuilding activities (Norderney spring 2008)

    Seite 20Waddensea Forum Fanoe November 2008

    The cradle of the connection points for the wind farmsin the North Sea

    a parking area on the beach of Norderney

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    11/33

    11

    Individual connection of alpha ventus

    Seite 22Waddensea Forum Fanoe November 2008

    The wind park alpha ventus

    The first German offshore wind park: offshore test field alpha ventus

    Operators = DOTI (Deutsche Offshore Testfeld Infrastrukturgesellschaft),existing with subsidiaries from Vattenfall, EWE and E.ON

    Initial generating capacity: 60 MW (12 x 5 MW) (now in 2009)

    Wind mill producers are Multibrid and REpower

    Grid connection: implementation as individual AC-connection of the 110-kV- transmission line Norddeich-Esens/ Damsum

    New construction of the transformer station Hagermarsch

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    12/33

    12

    Seite 23Waddensea Forum Fanoe November 2008

    Alpha Ventus(E.ON Netz Offshore)

    UW Hagermasch

    Leerrohrbauwerk Norderney

    Alpha Ventus

    Seite 24Waddensea Forum Fanoe November 2008

    The Grid connection for alpha ventus

    cable route offshore:

    54,2 km on the sea

    4,9 km in the tideland between island and mainland

    cable route onshore: 1,5 km on Norderney

    4,5 km up to the transformer station Hagermarsch

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    13/33

    13

    Seite 25Waddensea Forum Fanoe November 2008

    Schedule of building measures regarding alpha ventus

    2007: Four horizontal directional drillings for alpha ventus 1,5 km empty ducts built on Norderney until April 2008

    2008: New construction of the transformer station Hagermarsch Cable bushing through empty ducts at Norderney Laying of the cable route onshore, connection of the transformer station

    Hagermarsch

    Laying of the cable route offshore Connection of the on- and offshore cables including final checking Commissioning of the cable route onshore and of the transformer station

    Hagermarsch

    Seite 26Waddensea Forum Fanoe November 2008

    Crossing the island Norderney

    HVDC cable laying

    Offshore cable laying

    Onshore cable laying inempty ducts

    HDD-drilling points anddirections

    Levees

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    14/33

    14

    Seite 27Waddensea Forum Fanoe November 2008

    Crossing Levees via horizontal directional drilling (HDD)

    horizontalbohrung.exe

    Phase 1:Pilot drilling

    Phase 2:

    Broaching

    Phase 3:Cable bushing

    Seite 28Waddensea Forum Fanoe November 2008

    Horizontal directional drilling for alpha ventus (2007)

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    15/33

    15

    Seite 29Waddensea Forum Fanoe November 2008

    Transformer station Hilgenriedersiel (June / August 2008)

    Seite 30Waddensea Forum Fanoe November 2008

    Offshore-cable/ AC 110 kV (exemplary)

    Three-phase XLPE (cross-linked

    polyethylene) cable with fiber optics for

    steering and monitoring the windmills

    of the offshore transforming station

    Relevant data:

    110 kV, 3 x 240mm Cu

    Weight: approx. 53 kg/m

    External diameter: approx. 18 cm

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    16/33

    16

    Seite 31Waddensea Forum Fanoe November 2008

    Offshore cable at the producer Prysmian in Naples (July 2008)

    Approximately 60kilometer cable forthe offshore cablelaying

    Seite 32Waddensea Forum Fanoe November 2008

    Giulio Verne & operational platform (July 2008)

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    17/33

    17

    Seite 33Waddensea Forum Fanoe November 2008

    Rewinding of the offshore cable from Giulio Verne to the

    operational platform (end of July 2008)

    Offshore cable fortideland laying

    Seite 34Waddensea Forum Fanoe November 2008

    Vessels for laying and operational platform

    Team Oman86 x 24 m

    CLB Ocean Team Installer65 x 22 m

    Combifloat48 x 42 m

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    18/33

    18

    Seite 35Waddensea Forum Fanoe November 2008

    Ocean Trencher 01 milling cutter on the operational

    platform

    Milling cutter forthe cable layingin the mud flats

    Seite 36Waddensea Forum Fanoe November 2008picture: H.W. Linders, ecoplan, Leer

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    19/33

    19

    Seite 37Waddensea Forum Fanoe November 2008

    picture: H.W. Linders, ecoplan, Leer

    Seite 38Waddensea Forum Fanoe November 2008

    picture: H.W. Linders, ecoplan, Leer

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    20/33

    20

    Seite 39Waddensea Forum Fanoe November 2008

    picture: H.W. Linders, ecoplan, Leer

    Seite 40Waddensea Forum Fanoe November 2008

    Rewinding of 3,5 km offshore cable: from Team Oman to

    Ocean Team Installer

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    21/33

    21

    Seite 41Waddensea Forum Fanoe November 2008

    Sword to flush in the cable into the grounds in shallow

    water areas (north of Norderney on Ocean Team Installer)

    Seite 42Waddensea Forum Fanoe November 2008

    Oceanjet 200 for the offshore cable laying deeper as 10

    meter (on the vessel Team Oman)

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    22/33

    22

    Seite 43Waddensea Forum Fanoe November 2008

    Offshore Cable laying: Team Oman / cable flushing carriage

    Seite 44Waddensea Forum Fanoe November 2008

    Offshore cable laying

    Cables are laid directly on the ocean bed

    Threat of damage, if cables are not protected

    Main jeopardy are trawls

    Therefore, cables have to be flushed into the ground. Different demandfor different techniques: Cables are being milled in the tideland and

    flushed in the sea using a flushing sword or a carriage slide

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    23/33

    23

    Seite 45Waddensea Forum Fanoe November 2008

    Monitoring concept

    supervision of the construction by a nature conservation expert

    Monitoring of the development after the construcction and during

    operation

    Monitoring of compensation measures

    Seite 46Waddensea Forum Fanoe November 2008

    Design of infauna monitoring

    Arial surveys

    picture: H.W. Linders, ecoplan, Leer

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    24/33

    24

    Seite 47Waddensea Forum Fanoe November 2008

    Temperature Monitoring during operation

    Quellen: BfN, Ifa

    Seite 48Waddensea Forum Fanoe November 2008

    Compensations- und Coherence measuresDeconstruction of an old harbour on Spiekeroog

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    25/33

    25

    Seite 49Waddensea Forum Fanoe November 2008Concept byHW Linders, ecoplan, Leer, Germany

    Cluster connection Borkum 2

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    26/33

    26

    Seite 51Waddensea Forum Fanoe November 2008

    UW Diele

    Leerrohrbauwerk Norderney

    NordE.ON1 for

    Cluster Borkum 2(E.ON Netz Offshore)

    Windpark-ClusterBorkum 2

    Seite 52Waddensea Forum Fanoe November 2008

    First wind park expected to be ready for operation in September 2009

    First HVDC system linking an offshore-Windpark and the extra high

    voltage grid

    Platform

    Approx. 120 km cable offshore

    Approx. 75 km cable onshore

    Grid connection: transformer station Diele

    Turn key contract with ABB (signed September 2007)

    Value: > 300 Mill.

    First project NordE.ON 1 for the connection of the ClusterBorkum 2

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    27/33

    27

    Seite 53Waddensea Forum Fanoe November 2008

    2007: 1,5 km empty ducts built on Norderney until April 2008 Conduits used for several projects

    2008:

    eight HDDs on Norderney and Hilgenriedersiel for NordE.ON 1

    Fall: Cable bushing for NordE.ON 1 through the empty ducts at Norderney

    37,5 km onshore cable laying for NordE.ON 1 incl. crossing the river Ems

    2009: Enlargement of the transformer station Diele Remaining cable laying onshore (37,5 km) Cable laying offshore (120 km) Connection at the transformer station Diele

    Schedule of building measures regarding Borkum 2

    Seite 54Waddensea Forum Fanoe November 2008

    380-kV-Umspannwerk Diele

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    28/33

    28

    Seite 55Waddensea Forum Fanoe November 2008

    UW Diele- Konvertergebude

    Baustart Fundamente Konverter und Trafo: August 2008

    Stahlrahmenkonstruktion mit PaneelbekleidungAbmessungen 74 x 38 x 14m

    Seite 56Waddensea Forum Fanoe November 2008

    Onshore route Hilgenriedersiel Diele

    Length 75 km

    2008

    Cable laying in the administrative district Aurich (37,5 km)

    and crossing of the river Ems

    2009

    Cable laying in the administrative district Leer (37,5 km)

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    29/33

    29

    Seite 57Waddensea Forum Fanoe November 2008

    Trassenquerschnitt EC Trasse Nord und Querverbindung

    Seite 58Waddensea Forum Fanoe November 2008

    Onshore Kabel HG Light

    Spannung +-150 kV

    Leistung 400 MW

    Leitermaterial Aluminium

    Leiterdurchmesser 55,8 mm

    Leiterquerschnitt 2300 mm Kabeldurchmesser 98,4 mm

    Gewicht 11,5 kg/m

    Lieferlnge 750 m

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    30/33

    30

    Seite 59Waddensea Forum Fanoe November 2008

    Cable laying onshore / Georgsheil June 2008

    Construction work in the

    administrative district Aurich

    Seite 60Waddensea Forum Fanoe November 2008

    HDD in the tideland - alpha ventus and NordE.ON1

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    31/33

    31

    Seite 61Waddensea Forum Fanoe November 2008

    Offshore-cable / HVDC light

    HVDC = High voltage direct current

    Modal performance:

    150 kV, 1200 mm Cu

    400 MW

    weight approx. 30 kg/m

    approx. 10 cm

    Offshore laying in 2009

    Seite 62Waddensea Forum Fanoe November 2008

    400 MW offshore converter station

    Measures: 54x35x25 m

    Weight of top side: approx. 3000 t

    Weight of jacket: approx. 2000 t

    Water depth: 40 m

    Height of the jacket: 60 m

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    32/33

    32

    Seite 63Waddensea Forum Fanoe November 2008

    The HVDC platform an offshore transformer station

    Foundation mounted in the North Sea

    Top site is piled up with so called heavy lifting equipment

    Seite 64Waddensea Forum Fanoe November 2008

    Crane for anchoring the platform (heavy lifting)

  • 7/25/2019 Concept of E.on Netz for Offshore Grid Connections

    33/33

    Thank you very much for yourattention !!!