of 33
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
1/33
1
Concept of E.ON Netz for
offshore grid connections
Our Offshore activities
NetzOffshore
David ScharteWaddensea Forum 19. Fan 2008
Seite 2Waddensea Forum Fanoe November 2008
Content
Offshore grid connections background
How many windfarms have to be connected when and where?
How shall we do it?
Projects in 2007 till 2009
Crossing Norderney
The first wind park Alpha Ventus
The first grid connection: NordE.ON 1 for cluster Borkum 2
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
2/33
2
Seite 3Waddensea Forum Fanoe November 2008
Offshore grid connections where we stand now
In Germany we have ambitious political goals concerning wind power. The
idea of German politicians is to install round about 1.5 GW until 2011, but
no German offshore windfarm up to now
What to do?
The politicians are seeking acceleration of offshore-process and this
resulted in a new law based on 17 Abs. 2a EnWG :
was signed on 17th of December in 2006
called Infrastrukturplanungsbeschleunigungsgesetz
Seite 4Waddensea Forum Fanoe November 2008
TSOs responsible for offshore grid connections and the TSO bears the costof the grid connection
completion of the connection to the grid must coincide with the end ofconstruction of the wind farm
the investment & operation cost to be shared between the four GermanTSOs and to be part of price regulation
the connection must be cost effective and operationally efficient
the obligation for TSOs applies to all wind farms going into operation
before end of 2011 (now till 2015 with the new amendment since June
2008)
with this amendment the feed in tariff for offshore wind energy into
German grid will be increased from 13 ct/kWh to 15 ct/kWh
Offshore grid connections - a new legal task for E.ON Netz
TSO = Transmission System Operator
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
3/33
3
Seite 5Waddensea Forum Fanoe November 2008
Estimated transmission capacity
Federal Government: 10.000 MW(until 2020)up to 25.000 MW(until 2030)
Dena: 20.400 MW (until 2020)
Requested wind parks (as at November 2008)
North Sea: >50 (17 approved) EEZ (Exclusive Economic Zone)
2 12-Mile-Zone
Baltic Sea: 5 EEZ
4 12-Mile-Zone
Seite 6Waddensea Forum Fanoe November 2008
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
4/33
4
Seite 7Waddensea Forum Fanoe November 2008
How many wind farms want to be connected when/where?
planned installing wind farm capacity is constrained by:- availability of relevant components and facilities- ability to obtain regulatory approvals (planning, permits etc.)
E.ON Netz must perform a realistic assessment of the installed offshoregeneration capacity over time in order to match transmission capacity to it
Seite 8Waddensea Forum Fanoe November 2008
Criteria to validate the date of the operation of a wind
farm
BSH- bzw. BImSchG-Approval
Detailed time schedule of the wind farm build up
Orders of the components (turbines, grounding structure andtransformer station)
Assurance of the financing of the wind farm
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
5/33
5
Seite 9Waddensea Forum Fanoe November 2008
How shall we do it? at first every OWP planned his own connection to the grid
the result: 14 individual cable links with no coordination
it was neither practical nor efficient
Seite 10Waddensea Forum Fanoe November 2008
Implementing the cluster concept: HVDC connections
Landing point Grid
Link to the grid
Property wind park Property E.ON Netz
Property wind park B
Wind mills
AC
DC
DC
AC
Wind mills
Property wind park A
AC SS
PlatformE.ON Netz
Converter Converter
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
6/33
6
Seite 11Waddensea Forum Fanoe November 2008
Cluster concept for further distanced connections, a technical
connection concept developed by E.ON Netz Offshore
Offshore wind parks (OWP) are combined in clusters and
connected by one common cable system
High-capacity North Sea power socket via expandable HVDC
connections (HVDC= high voltage direct current)
Economic an environmental advantage: minimizing offshore- and
onshore routes and use of powerful offshore HVDC cables whichmanage large transmission capacity
How shall we do it? With modular clustered connection
Seite 12Waddensea Forum Fanoe November 2008
How shall we do it?
individual connections
Landing point
Windpark
platform
Wind mills
Grid
Link to the grid
Property wind park Property E.ON Netz
Implementation keys for offshore grid connection
Coastal area: individual connections by 110-kV-AC cable
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
7/33
7
Seite 13Waddensea Forum Fanoe November 2008
An overview: cluster / alpha ventus
BoardersContinental shelf /exclusive economic zone(200 nautical miles)
Territorial Waters / 12mile zone
International Boarder
Offshore wind parksAuthorizedPlannedCluster connectionAlpha ventus
Seite 14Waddensea Forum Fanoe November 2008
Availability of required material
Just three offshore cable producers in all Europe
Currently no 300-kV cable available (expected to be available in 2010/11)
No mass production until 2011
220-kV-AC offshore cable not yet available
150/200-kV-DC offshore cable: max. production of 100 km per annum
Converter Siemens: project pilot TransBay 2009 no further production
capacity
Converter ABB: state of the art but long delivery times
Converter AREVA: merely HVDC classic available, not HVDC light
Heavy lifting and transportation: capacities for platform mounting are
booked up in the long term
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
8/33
8
Seite 15Waddensea Forum Fanoe November 2008
Formation in May 2007
Ca 35 staff members, supported by the staff of E. ON Netz
Increasment to approx. 70 staff members in the next years
Who is doing it ? ENEO der E.ON Netz Offshore
Seite 16Waddensea Forum Fanoe November 2008
Organisation of ENEO?
Projectcoordination
Projcts Technical Approvals Commercial Operation*
Support/Services from E.ON Netz GmbH
Geschftsfhrung
Assistenz TechnischSchulze Wischeler
KaufmnnischFricke
*noch auszugestalten
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
9/33
9
Crossing Norderney
Seite 18Waddensea Forum Fanoe November 2008
Crossing the island Norderney
HVDC cable laying
Offshore cable laying
Onshore cable laying inempty ducts
HDD-drilling points anddirections
Levees
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
10/33
10
Seite 19Waddensea Forum Fanoe November 2008
Onshore cable laying via empty duct construction
Empty duct with 35 conduitsBuilding activities (Norderney spring 2008)
Seite 20Waddensea Forum Fanoe November 2008
The cradle of the connection points for the wind farmsin the North Sea
a parking area on the beach of Norderney
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
11/33
11
Individual connection of alpha ventus
Seite 22Waddensea Forum Fanoe November 2008
The wind park alpha ventus
The first German offshore wind park: offshore test field alpha ventus
Operators = DOTI (Deutsche Offshore Testfeld Infrastrukturgesellschaft),existing with subsidiaries from Vattenfall, EWE and E.ON
Initial generating capacity: 60 MW (12 x 5 MW) (now in 2009)
Wind mill producers are Multibrid and REpower
Grid connection: implementation as individual AC-connection of the 110-kV- transmission line Norddeich-Esens/ Damsum
New construction of the transformer station Hagermarsch
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
12/33
12
Seite 23Waddensea Forum Fanoe November 2008
Alpha Ventus(E.ON Netz Offshore)
UW Hagermasch
Leerrohrbauwerk Norderney
Alpha Ventus
Seite 24Waddensea Forum Fanoe November 2008
The Grid connection for alpha ventus
cable route offshore:
54,2 km on the sea
4,9 km in the tideland between island and mainland
cable route onshore: 1,5 km on Norderney
4,5 km up to the transformer station Hagermarsch
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
13/33
13
Seite 25Waddensea Forum Fanoe November 2008
Schedule of building measures regarding alpha ventus
2007: Four horizontal directional drillings for alpha ventus 1,5 km empty ducts built on Norderney until April 2008
2008: New construction of the transformer station Hagermarsch Cable bushing through empty ducts at Norderney Laying of the cable route onshore, connection of the transformer station
Hagermarsch
Laying of the cable route offshore Connection of the on- and offshore cables including final checking Commissioning of the cable route onshore and of the transformer station
Hagermarsch
Seite 26Waddensea Forum Fanoe November 2008
Crossing the island Norderney
HVDC cable laying
Offshore cable laying
Onshore cable laying inempty ducts
HDD-drilling points anddirections
Levees
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
14/33
14
Seite 27Waddensea Forum Fanoe November 2008
Crossing Levees via horizontal directional drilling (HDD)
horizontalbohrung.exe
Phase 1:Pilot drilling
Phase 2:
Broaching
Phase 3:Cable bushing
Seite 28Waddensea Forum Fanoe November 2008
Horizontal directional drilling for alpha ventus (2007)
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
15/33
15
Seite 29Waddensea Forum Fanoe November 2008
Transformer station Hilgenriedersiel (June / August 2008)
Seite 30Waddensea Forum Fanoe November 2008
Offshore-cable/ AC 110 kV (exemplary)
Three-phase XLPE (cross-linked
polyethylene) cable with fiber optics for
steering and monitoring the windmills
of the offshore transforming station
Relevant data:
110 kV, 3 x 240mm Cu
Weight: approx. 53 kg/m
External diameter: approx. 18 cm
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
16/33
16
Seite 31Waddensea Forum Fanoe November 2008
Offshore cable at the producer Prysmian in Naples (July 2008)
Approximately 60kilometer cable forthe offshore cablelaying
Seite 32Waddensea Forum Fanoe November 2008
Giulio Verne & operational platform (July 2008)
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
17/33
17
Seite 33Waddensea Forum Fanoe November 2008
Rewinding of the offshore cable from Giulio Verne to the
operational platform (end of July 2008)
Offshore cable fortideland laying
Seite 34Waddensea Forum Fanoe November 2008
Vessels for laying and operational platform
Team Oman86 x 24 m
CLB Ocean Team Installer65 x 22 m
Combifloat48 x 42 m
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
18/33
18
Seite 35Waddensea Forum Fanoe November 2008
Ocean Trencher 01 milling cutter on the operational
platform
Milling cutter forthe cable layingin the mud flats
Seite 36Waddensea Forum Fanoe November 2008picture: H.W. Linders, ecoplan, Leer
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
19/33
19
Seite 37Waddensea Forum Fanoe November 2008
picture: H.W. Linders, ecoplan, Leer
Seite 38Waddensea Forum Fanoe November 2008
picture: H.W. Linders, ecoplan, Leer
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
20/33
20
Seite 39Waddensea Forum Fanoe November 2008
picture: H.W. Linders, ecoplan, Leer
Seite 40Waddensea Forum Fanoe November 2008
Rewinding of 3,5 km offshore cable: from Team Oman to
Ocean Team Installer
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
21/33
21
Seite 41Waddensea Forum Fanoe November 2008
Sword to flush in the cable into the grounds in shallow
water areas (north of Norderney on Ocean Team Installer)
Seite 42Waddensea Forum Fanoe November 2008
Oceanjet 200 for the offshore cable laying deeper as 10
meter (on the vessel Team Oman)
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
22/33
22
Seite 43Waddensea Forum Fanoe November 2008
Offshore Cable laying: Team Oman / cable flushing carriage
Seite 44Waddensea Forum Fanoe November 2008
Offshore cable laying
Cables are laid directly on the ocean bed
Threat of damage, if cables are not protected
Main jeopardy are trawls
Therefore, cables have to be flushed into the ground. Different demandfor different techniques: Cables are being milled in the tideland and
flushed in the sea using a flushing sword or a carriage slide
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
23/33
23
Seite 45Waddensea Forum Fanoe November 2008
Monitoring concept
supervision of the construction by a nature conservation expert
Monitoring of the development after the construcction and during
operation
Monitoring of compensation measures
Seite 46Waddensea Forum Fanoe November 2008
Design of infauna monitoring
Arial surveys
picture: H.W. Linders, ecoplan, Leer
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
24/33
24
Seite 47Waddensea Forum Fanoe November 2008
Temperature Monitoring during operation
Quellen: BfN, Ifa
Seite 48Waddensea Forum Fanoe November 2008
Compensations- und Coherence measuresDeconstruction of an old harbour on Spiekeroog
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
25/33
25
Seite 49Waddensea Forum Fanoe November 2008Concept byHW Linders, ecoplan, Leer, Germany
Cluster connection Borkum 2
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
26/33
26
Seite 51Waddensea Forum Fanoe November 2008
UW Diele
Leerrohrbauwerk Norderney
NordE.ON1 for
Cluster Borkum 2(E.ON Netz Offshore)
Windpark-ClusterBorkum 2
Seite 52Waddensea Forum Fanoe November 2008
First wind park expected to be ready for operation in September 2009
First HVDC system linking an offshore-Windpark and the extra high
voltage grid
Platform
Approx. 120 km cable offshore
Approx. 75 km cable onshore
Grid connection: transformer station Diele
Turn key contract with ABB (signed September 2007)
Value: > 300 Mill.
First project NordE.ON 1 for the connection of the ClusterBorkum 2
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
27/33
27
Seite 53Waddensea Forum Fanoe November 2008
2007: 1,5 km empty ducts built on Norderney until April 2008 Conduits used for several projects
2008:
eight HDDs on Norderney and Hilgenriedersiel for NordE.ON 1
Fall: Cable bushing for NordE.ON 1 through the empty ducts at Norderney
37,5 km onshore cable laying for NordE.ON 1 incl. crossing the river Ems
2009: Enlargement of the transformer station Diele Remaining cable laying onshore (37,5 km) Cable laying offshore (120 km) Connection at the transformer station Diele
Schedule of building measures regarding Borkum 2
Seite 54Waddensea Forum Fanoe November 2008
380-kV-Umspannwerk Diele
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
28/33
28
Seite 55Waddensea Forum Fanoe November 2008
UW Diele- Konvertergebude
Baustart Fundamente Konverter und Trafo: August 2008
Stahlrahmenkonstruktion mit PaneelbekleidungAbmessungen 74 x 38 x 14m
Seite 56Waddensea Forum Fanoe November 2008
Onshore route Hilgenriedersiel Diele
Length 75 km
2008
Cable laying in the administrative district Aurich (37,5 km)
and crossing of the river Ems
2009
Cable laying in the administrative district Leer (37,5 km)
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
29/33
29
Seite 57Waddensea Forum Fanoe November 2008
Trassenquerschnitt EC Trasse Nord und Querverbindung
Seite 58Waddensea Forum Fanoe November 2008
Onshore Kabel HG Light
Spannung +-150 kV
Leistung 400 MW
Leitermaterial Aluminium
Leiterdurchmesser 55,8 mm
Leiterquerschnitt 2300 mm Kabeldurchmesser 98,4 mm
Gewicht 11,5 kg/m
Lieferlnge 750 m
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
30/33
30
Seite 59Waddensea Forum Fanoe November 2008
Cable laying onshore / Georgsheil June 2008
Construction work in the
administrative district Aurich
Seite 60Waddensea Forum Fanoe November 2008
HDD in the tideland - alpha ventus and NordE.ON1
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
31/33
31
Seite 61Waddensea Forum Fanoe November 2008
Offshore-cable / HVDC light
HVDC = High voltage direct current
Modal performance:
150 kV, 1200 mm Cu
400 MW
weight approx. 30 kg/m
approx. 10 cm
Offshore laying in 2009
Seite 62Waddensea Forum Fanoe November 2008
400 MW offshore converter station
Measures: 54x35x25 m
Weight of top side: approx. 3000 t
Weight of jacket: approx. 2000 t
Water depth: 40 m
Height of the jacket: 60 m
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
32/33
32
Seite 63Waddensea Forum Fanoe November 2008
The HVDC platform an offshore transformer station
Foundation mounted in the North Sea
Top site is piled up with so called heavy lifting equipment
Seite 64Waddensea Forum Fanoe November 2008
Crane for anchoring the platform (heavy lifting)
7/25/2019 Concept of E.on Netz for Offshore Grid Connections
33/33
Thank you very much for yourattention !!!
NetzOffshore
Waddensea Forum 19. Fan 2008