Date post: | 08-Apr-2018 |
Category: |
Documents |
Upload: | rahulgehlot2008 |
View: | 224 times |
Download: | 0 times |
of 48
8/7/2019 Concord_mar09
1/48
January - March 2009 Vol. No. 31 Issue No. 4
8/7/2019 Concord_mar09
2/48
Editor V.S. rnEditorial tEam K. Sn | aex Benjn | V. res K |
aswn Cn | V. Esw | Sb ann
PhotograPhy V.S. NnvedESigN& layout Ss gpcs desn, Cenn.
ContentsVol. No. 31 Issue No. 4
L&T has played a critical role in the development
of technology & capabilities for the Indian nuclear
power sector from its very beginning. ECC, L&Ts
construction Division has the capability to construct
critical and complex structures for nuclear power plants
to international standard specications. Moreover, it has
the distinction of having participated in the construction
of a majority of nuclear power plants and heavy water
plants in the country.
This has opened several avenues for L&T to sign
cooperation agreements / MoUs and forge alliances
with leaders of nuclear technology across the world,
such as: Westinghouse Electric Company (WEC), USA
for Pressurized Water Nuclear Reactors with modular
construction technology; Atomic Energy of Canada
Limited (AECL) for cooperation on Advanced CANDU
Reactor ACR 1000. Recently it signed the MoU with
Atomstroyexport (ASE) of Russia for cooperation
to supply Russian VVER 1000 type reactors for the
Kudankulam nuclear power project.
L&T has been a partner in the development of Indian
Nuclear power programme and it has been playing
an active role in the construction of major nuclear
plants in different parts of the country. As a part of
the operations of L&Ts Infrastructure OC, we take
pleasure in highlighting our contributions to this sector
along with irrigation projects executed by us.
Kaiga Atomic Power Project (Unit 1 & 2)
L&Ts Track Record
in Nuclear Power 4
Endeavours at
Tarapur Nuclear Power Plant 6
Nuclear Reactor
Containment Test Model 12
Kundankulam Nuclear
Power Project 14
PREFRE-3A Project
or BARC Kalpakkam 22L&T signs MoU with World Leaders
in Nuclear Power Sector 23
Indira Sagar
Right Main Canal Project 24
Jindal Dam - L&Ts Maiden Venture
in to Construction o Full-Fledged Dams 28
Veligonda Dam
the Engineering marvel 30
Kaleidoscope 34
8/7/2019 Concord_mar09
3/48
L&T began its journey in to construction o
Nuclear power projects in a modest way, by
undertaking the construction o oce acilities or
the Atomic Energy Establishment and laboratories
or Bhabha Atomic Research Centre at Trombay
during mid 60s. The construction o Main plant
civil works at Kalpakkam or the 220 MWe Madras
Atomic Power Project Unit 1&2 during 70s was
the rst major project in the nuclear segment.Subsequently, the Main plant civil works or the
220 MWe Kaiga Nuclear Power Project (Unit 1&2)
in Karnataka was executed by L&T. Erection o
almost all heavy water plants in India are executed
by L&T.
Realising the vast potential and business
opportunities in this segment the Nuclear Business
Unit was ormed by L&T in the year 1999-2000
when it secured the 540 MWe Tarapur Atomic
Power Project, Unit 3&4. It should be mentioned
that Tarapur Atomic Power Project was one o themajor projects or L&T, where dierent business
units o L&T were actively involved in the execution
o the project - Nuclear, Electrical & Instrumentation
BUs o ECC Division; Heavy Engineering Division;
Nuclear BU o E&C Division to name a ew.
Acevees
Some o the notable achievements in Nuclear
segment include:
Outofthetotalinstalledcapacityof7280MWe
o nuclear power (both commissioned and
ongoing); L&T is involved in almost all Nuclear
power projects in the country extending up to
5280MW.
Successfulcompletionofmainplantcivilworks
o 2x540 MWe Tarapur Nuclear Power project
in a record 60 months rom the rst pour o
concrete is considered as a great achievement
-Oneamongthesixreactorsintheworldto
achieve this eat.
Successful completion of Primary Piping
Package (the heart o the nuclear plant) on
time including other mechanical packages in
the Countrys maiden 2 x 540 MWe Tarapur
Nuclear Power Project. This helped L&T in
understanding the criticality, stringent qualityrequirements, etc and as a sequel, it secured
major mechanical packages in Kudankulam
Nuclear Power Project 1&2.
L&T is involved in the execution o Indias rst
2x1000 MWe Nuclear Power Project at Kudankulam,
which is one o the most prestigious projects
undertaken by Government o India in collaboration
with Russian Government. Initially, L&Ts
participation in civil works involves construction
o inrastructure acilities and auxillary buildingsonly. However, the scenario changed, when L&T
secured our major mechanical packages which
involve technology certications, being done or
the rst time in India, etc.
This apart, auxiliary systems such as Induced Drat
Cooling Towers, HVAC, Service Water Systems,
etc are being constructed on EPC basis.
L&T is also involved in many Reactor back end
projects, that is construction o uel reprocessing
related acilities such as Additional Waste TankFarm, Spent uel Storage Facilities, Power Reactor
Fuel Reprocessing acilities, etc at various locations
in India. Thus, making L&T an all rounder when it
comes to execution o almost the entire spectrum
o activities involved in the construction o nuclear
power projects.
OnthewholeL&Tisplayingacriticalandsignicant
role in the Indias Nuclear Power sector.
Powering The Nation
With Nuclear Energy
ECC Concord|Jan - Mar 203
8/7/2019 Concord_mar09
4/48
Vol. No. 31 Issue No. 4
Nuclear power projects are considered as
one o the sustainable energy projects o the
uture. The Nuclear Power Corporation o India
Limited (NPCIL) presently operates 17 nuclear
power plants in the country at dierent locations.
India has made a strong beginning in the eld o
Nuclear Power. Today it is quite selsucient
rom technology and resources point o view and
NPCIL has ambitious plans o achieving 20,000
MW by 2020, improving rom the current installedcapacity o 4120 MW.
Overthepastvedecades,ECChasconstructed
many nuclear-related structures and played
a major role in this sector. It has the capability
to construct critical and complex structures or
Nuclear Power generation. ECC has the distinction
o making constructive contribution to almost all
the Nuclear power plants in the country. Some o
the important projects are Madras Atomic Power
Project, Kaiga Atomic Power Project, Tarapur
Atomic Power Project, Rajasthan Atomic Power
Project and Kudankulam Nuclear Power Project.
ECC has also been involved in other nuclear
eld related projects such as heavy water plants,
nuclear waste management, rare materials project,
etc alling under the purview o DAE/ BARC. In
act, ECCs association with DAE started in the
early 60s, when it was awarded with design and
construction works or radiological and modular
laboratories at Trombay.
ECCs major involvement in nuclear power projects
started at MAPP in 1970 when it was entrusted with
the construction o the reactor and turbine buildings
or MAPP. The contract or civil construction
included the reactor building with 40m high and
45m dia structure topped by a dome, sub-structure
or service building, cooling water system and
outall structure, demineralisation plant, central
stores, PHT purication buildings, Fast breeder
test reactor building, radio-metallurgical & radio-
chemistry laboratories, active control uel assembly
building, ree stack (100m) and ventilation stacks
(75 m & 65 m tall). The reactor wall and dome were
o prestressed concrete construction requiring
high accuracy. Another salient eature o MAPP
is the double containment wall with outer random
rubble masonry wall to a height o 34 m, which was
done or the rst time in India. ECC has also been
involved in design, installation and commissioning
o 33kV switchyard catering to the entire power
requirement o the Reactor Research Centre at
Kalpakkam. Subsequently electrical installations
or the two research laboratories RCL & MDL
were done by ECC.
NPCIL once again demonstrated its condence in
L&T by awarding the complete civil works or Units
1 & 2 o Kaiga Atomic Power Project. Kaiga was
literally a greeneld project necessitating, in many
cases, even basic inrastructure development. The
site was a natural bowl-shaped terrain surrounded
by hills with deep lush green orest and the site
was accessible in air weather through a orest
road and access to the site was dicult during
monsoon till all the access roads were ready.
ECCs scope o work included construction o
reactor, turbine, service, control, reactor auxiliary,Induced Drat Cooling Towers at 2 x 210 MW Kaiga Atomic Power Plant (Units 3 & 4)
L&Ts Track Record
in Nuclear Power
C Concord|Jan - Mar 2009 4
8/7/2019 Concord_mar09
5/48
Reactor building at Madras Atomic Power Project, Kalpakkam
diesel generator, spent uel buildings, 140m high
ventilation stack, area drainage, excavation, area
grading and miscellaneous structures. During
execution o main civil works, ECC was awarded
additional works such as construction o circulating
water pump houses, saety related pump house,
re water pump house, de-mineralisation, ltration
and chlorination plants, make-up water pre-
treatment acilities, CW Intake structures and
tunnel, domestic water tank, approach channel
to intake structures and outdoor & indoor piping
works.
Some o the advanced construction methods
used at Kaiga site included climbing ormwork
system or prestressed containment walls,
sliporm or ventilation stack and ormwork or
other structures. A special ormwork supporting
structure was designed to support the ormwork
o inner containment dome o the reactor.
Construction o Kaiga nuclear power project was
highly challenging, considering the remoteness o
the site, unriendly weather conditions and other
complexities. Despite the hardships, ECC met the
challenges and successully completed the project
as per the requirements o NPCIL.
L&T is proud o its association with NPCIL, which
has celebrated its Golden Jubilee Year and wishes
to continue its commitment and contribution or
the development o Nuclear Power Generation in
India.
ECC Concord|Jan - Mar 205
8/7/2019 Concord_mar09
6/48
Vol. No. 31 Issue No. 4
Endeavours
at TarapurNuclear Power Plant
B.SundArAmoorthy,Project Manager
ViShVA mohAn ShriVAStAVA,Planning Engineer
C Concord|Jan - Mar 2009 6
8/7/2019 Concord_mar09
7/48
taap Ac Pwe Sa
The Tarapur nuclear power station houses two
200 MW Boiling Water Reactors (BWRs). The new
series o 540 MWe nuclear reactors are developed
indegeneously rom 220 MWe Pressurized Heavy
Water Reactors (PHWR). At present, this power
station has the largest nuclear power reactor in thecountry. It was commissioned seven months ahead
o schedule by the Nuclear Power Corporation o
India.
BArC isallas, taap
The Bhabha Atomic Research Centre (BARC) -
Indias primary nuclear research acility supports
Indias nuclear power and research programme.
BARCs installations at Tarapur support the
operations o Tarapur Atomic Power Station.
L&ts rle
L&T has executed the 2 540 MWe at Tarapur
and was involved in almost all the disciplines o
engineering o a Nuclear Power Project. L&T
was involved in main plant civil works, service
water system, reactor piping, composite chilled
water and HVAC packages, electrical works and
instrumentation works which demonstrated the
capability o L&T in broad spectrum engineering
construction. The heavy engineering division o
L&T had supplied the calandria, steam genertaors
while the Engineering & Construction division
supplied the Primary Steam Piping system. ECC
involved in the mechanical erection o these
structures.
The scope o main civil works package covered
construction o reactor, service, station auxiliary,
reactor auxiliary, control buildings, pipe & cable
bridges, ventilation stack, potable water tank,
roads, site grading, abrication & structural steel
erection, EPs and other miscellaneous structures.
The gestation period or nuclear power projects
today is considerably reduced by commissioning
TAPP 3 & 4 in 60 months. This is an international
benchmark achievement. At TAPP 3&4, the
challenge o completing the total project in 60
months was achieved by deploying innovative
construction methods. Some o them include
pumping o heavy concrete, casting o 7m
high columns in single lit, use o sel climbing
ormwork or inner containment wall, casting o 3.5
mhighwallforOCwall,prefabricationofcalandria
vault liner, use o threaded coupler or reducing
reinorcement congestion and wastage, easy
handling etc.
Design, procurement and construction o service
water system, composite chilled water and
HVAC packages include supply o some critical
equipment such as vertical turbine pumps to work
View o Tarapur Atomic Power Project during construction
ECC Concord|Jan - Mar 207
8/7/2019 Concord_mar09
8/48
Vol. No. 31 Issue No. 4
in sub-marine environment, 3050 TR capacity
centralized chillers and 60 lakh CMH capacity
ventilation system.
The primary piping package executed by ECC(in association with E&C division o L&T) at TAPP
3&4 is meant or nuclear steam supply system
(NSSS) which consists o reactor assembly, the
moderator system and the primary heat transer
system. The reactor assembly system is the
most important part o NSSS and it consists o
calandria, end shields, calandria tubes, coolant
tubes, end ttings, uel bundles and reactivity
control devices. The abrication and erection o
primary piping system is to be carried out in dust
ree environment. Extreme care need to be takenor maintaining clean room conditions not only in
the abrication stage, but also during erection.
The order or electrical and instrumentation works
is probably the single largest order awarded to
any contractor by NPCIL. These packages involve
design, manuacture, supply, erection, testing and
commissioning o various critical electrical and
eld instrumentation items required or a nuclear
power plant.
Aal Wase tak F (AWtF)
ie descpo u toal Qy
Excavation cu.m 15695
Concrete cu.m 17168
Rebar abrication t 2150
Formwork sq.m 24770
Fabrication & erection o inserts and
structural works - Stainless Steel t 123
Fabrication & erection o inserts and
structuralworks-CS t 84
Fabrication & installation o SS 304L liners sq.m 2900
Supply and installation o ventilation system cu.m / hr. 215000
Fabricationandinstal lationof300cu.mSS304Ltanks Nos 08
Fabrication o SS piping ID 13000
Erection o SS piping IM 11000
Unit 3 & 4 o Tarapur Atomic Power Project, ater completion
C Concord|Jan - Mar 2009 8
8/7/2019 Concord_mar09
9/48
8/7/2019 Concord_mar09
10/48
Vol. No. 31 Issue No. 4
shielded vaults (V-1 and V-2) with 4 tanks each
andtwocells(Cell-IandCell-O)accommodating
the in-routing, out-routing and sump tanks. Each
sub-vault has a sump in the vault rat. Necessary
sloping was provided in each sub vault with a
channel. The foors at all sub-vaults and its walls
up to height o 1.5m are lined with 5 mm SS 304L
plates.
In between the two corridors above the vaults,
rooms or sampling blisters and transmitter rooms
are accommodated. The corridors also house
the embedment or the services and utilities like
headers, valves, instrument racks, cables or
taking samples remotely and to open the vault
entry. A monorail (10 t capacity) was provided in
each corridor or liting the plug o the vaults to
enable service inspection.
AWtF Aex Blg
The service building, known as the AWTF Annex
is a two foor building. Vault exhaust an room,
ventilation air supply an room, electrical room and
change room are housed in the rst foor. Second
foor accommodates control room or monitoring
and carrying out the operations o the AWTF, waste
cooling water room, waste o-gas equipment and
blower room.
Spe Fel Sage Facl (SFSF)
SFSF was constructed to receive and store the
spent uel rom nuclear power plants under water
beore sending it or urther processing.
The SFSF project demanded partially underground,
high perormance concrete structures (lined with
stainless steel plates) meant to store the spent
uel discharged rom the Nuclear Power Reactors.
SFSF is lled with de-mineralised water, supported
by water-polishing system and a water-cooling
system.
The scope o work covers constructing and
installing all associated utilities like inltration
gallery, DM water plant, pool water polishing
system, cooling water system including cooling
towers, material handling system including
10 & 75-t EOT cranes, 2-t pool bridge crane,
re protection and alarm system, electrical and
instrumentation and control panels, air conditioning
and ventilation system.
Spe Fel Soage Facly (SFSF)
ie descpo u toal Qy
Excavation cu.m 39365
Concrete cu.m 9475
Rebarfabrication t 1892
Formwork sq.m 27026
Waterproong (Terrace) sq.m 3390
Fabrication and installation o SS 304L liners t 62
Supply and installation o ventilation system cu.m/hr. 235000
Supplyandinstallationof75/5tEOTCrane Nos 01
Supplyandinstallationof10tEOTCrane Nos 01
Supply and installation o 2-t pool bridge crane Nos 01
Supply and installation o DM water plant Nos 01
Supply and installation o pool water polishing unit Nos 01
Fabrication o tanks and vessels Nos 6
EOT crane at Spent Fuel Storage Facility
C Concord|Jan - Mar 2009 10
8/7/2019 Concord_mar09
11/48
SFSF pl blg ses
vehicleairlocks
caskdecontamination/storagearea
EOTcranes,poolbridgeandhoists
undergroundfuelpool
spentfueltransferbayalongwithunderground
duct to nearby reprocessing plant or hydraulic
transer o uel bundles as per the requirement
o BARC
leak detection and collection facility for fuel
pool
poolwaterpolishingunit
domesticwatertank
approachroadfortrailerandtruckmovement
localcontrolpanels
The SFSF pool building extension houses pumps
or water cooling system and polishing; ventilation
system in an exhaust an room; disposal system
or regenerate efuent (underground RCC tank
with pump and piping) and stack or exhaust
vent. The utility building houses air conditioning
and ventilation system; DM water plant; electrical
substation; change room, rooms or monitoring,
aircompressor,controlandlaboratory.Otherareas
A view o Polishing Unit o Spent Fuel Storage Facility
include low level efuent storage and pumping
acility, de-mineralised water storage tanks (atop
uel pool building) and security and access control
system. The administrative oce area has a good
training and conerence room with all gadgets.
Excellent quality ratings are achieved in this project,
which enabled it to bag ECC Quality Trophy.
DM plant at
Spent FuelStorage Facility
ECC Concord|Jan - Mar 2011
8/7/2019 Concord_mar09
12/48
Vol. No. 31 Issue No. 4
The main objective o the test model is to nd out
the behaviour o the Nuclear reactors containment
structure under extreme pressure conditions. The
model is pressurized three times more than the
actual design pressure o the Nuclear Reactor.
The model is also tested to establish and check
the design parameters o the actual containment
structures and to get better understanding o
structural behaviour o the containment structure
or uture.
tes mel a taap
The pre-stressed concrete containment test model
is scaled down to represent the actual Pressurised
Heavy Water Reactor o Tarapur Atomic Power
station 3 & 4 at Tarapur, to a actor o 1:4. This
model is constructed at Tarapur close to the
existing BARC acilities.
Contented by the perormance o L&T in Tarapur
Atomic Power Project 3&4, NPCIL invited L&T to
construct the model on nomination basis.
Ater the construction o the model, the same will
be subjected to a pressure, which is approximately
4.5 to 6 kg/sq.cm or even higher. However, the
actual ailure pressure will be established ater
testing. In any case, it is expected that there will
be nominal leakage at 5 kg/sq.cm.
Sale eaes
All the components o the actual reactor is scaled
down to 1:4 including pre-stressing, critical
openings etc.
ra
The inner containment wall is supported on a rat
having dimensions o:
Diameter-15.60mand Depthof3m
Stressinggalleryofsize1500mmx1800mm
below the inner containment structure with 4
access shats
ie Cae wall
Thickness-188mm
Heightofthewall-12.475maboveraft
Constructedusing9lifts
TheinnerdiameterofICwallis12.40m
rg Bea
Heightofringbeamis1.2m
Averagethicknessis450mm
ICwall,ringbeamanddomearedesignedas
monolithic structures
nclea reac Cae
tes mel 1:4 Scale Pe-sesseCcee Cae
B.SundArAmoorthy,Project Manager
Completed view o the test model. Right: Sectional view
C Concord|Jan - Mar 2009 12
8/7/2019 Concord_mar09
13/48
ie Cae de (iC de)
The IC dome starts at 13.706 m height and springs
up to the crown 15.750m.
AveragethicknessofICdomeis164mm
Centre line diameter of the IC dome is
19.60 m
Two radial Steam Generator (SG) openings
o diameter 1.35m at the centre line are
provided in the IC dome to simulate the Steam
Generator openings o the prototype
Inner containment dome was cast in single
pour
Sess
To monitor the response during prestressing o
containment and dome, ollowing sensors were
used:
727 sensors were installed in concrete
rom rat to crown o the dome at
pre-determined locations
89sensorswereinstalledonHTstrandsand
stressing was analysed
Dierent type o sensors used in test containment
included:
Embedded type of Vibrating Wire Strain
Gauge(VWSG)
PastableSMER10mm
Spotweldable51mm,Weldable203mmand
Earthpressurecell
Weldable type o sensors were installed on
reinorcement bars whereas embedded type in
concrete.
Pe-sessg
Inner containment wall and dome was subjected
to prestressing using prestressing system 1T15.
This involved:
Totalnumberof 313cables, comprisingof
JO&JI,VerticalandHorizontalcables.
15.2mmdiameterhightensilestrandforpre-
stressing works
HDPEsheathingof25mm-OD/20mm-ID.
Maximum load applied on HT strands was
21.20 t on each cable and
Sheathing was cement grouted with
temperature controlled cement grout
Csc Js-Fk Sse
Construction joints in the dome and the inner
containment wall were sealed using Fuko system
i.e. Re-injectable grouting system with injection o
hydro swelling, water based, low viscous, thermo-
setting resin. This is done ater construction to
make the joint leak tight or air and water.
Calleges
te wk vlve seveal calleges lke:
Placement of reinforcement, HDPE sheaths
and tube units, due to congestion in scaled
down thickness o walls and dome having
stringent tolerances o +/- 3 mm.
Installationandprotection of 727sensorsin
IC wall and dome during preparation o pours
and concreting were tough tasks
Utmost care was taken during installation
and 99% o sensors are unctioning well even
today.
Installationof instruments in wall anddome
due toslender section i.e. 188 mmthickof
wall and 164 mm thick o dome.
Formwork
- Nuts were not allowed through ties and coil
- Slender sections
- Complicated tailor made ormwork system
was used with preabricated C shaped MS
rames
Difculty in mounting large number of
instruments in limited space around openings
o Airlock Barrels.
Eorts required or the construction o the test
model involved same amount o work or more
than that required or the proto-type due to the
limitation in scaled down dimensions.
heal Sae aEve
Regular training and orientation programs or
workmen were conducted to keep them alert at all
times.
Projecthasachievedzeroaccident
Achieved1.4millionsafeman-hours
The project was successully completed in
December 2008 to the fullest satisfaction of the
client.
ECC Concord|Jan - Mar 2013
8/7/2019 Concord_mar09
14/48
Vol. No. 31 Issue No. 4
Indias rst 2 1000 MWe Nuclear power plant
is coming up at Kudankulam. The project is
located on the shores o Gul o Mannar, on the
Southeastern tip o India near Kanyakumari. It is
located at Radhapuram taluk o Tirunelveli district
in Tamilnadu state.
The site experiences a tropical climate with
humidity ranging rom 40% to 90% depending on
the season and is subjected mainly to the winter
monsoonduringthemonthsofOctober,November
and December.
The Kudankulam Nuclear Power Project (KKNPP)
consists o two units o 1000 MWe with two steam
driven turbo generators supplied with turbine
steam rom two pressurized water VVER type
reactors o Russian design. The design o various
equipment, systems and structures are carried out
in accordance with Russian and other International
Standards.
The entire project capacity o 2000 MWe (2 x 1000
MWe) o power will be supplied to three southern
states (Tamil Nadu, Karnataka and Kerala) and the
Union Territory o Pondicherry. NPCIL has divided
the whole project into number o packages and
awarded to dierent contractors. The whole project
cost is about Rs. 13,000 cr.
Packages
L&T has been awarded M2, M4, M5, C5 and E1
packages directly by NPCIL. M3 and I1 have been
awarded to L&T by BHEL & ECIL.
mecacal:
Erection of Nuclear Steam Supply System
(NSSS)and auxiliary systems (equipment,
piping & tubing works) - M2 Package
Seawater system (equipment & piping
erection) - M4 Package
Common service (piping & equipment
erection) - M5 Package
Erectionofturbine-M3Package
Cvl:Radioactive waste processing and storage
buildings - C5 Package
Eleccal: Erection o electrical equipment andsystems - E1 Package
teccal Aspecs
Kudankulam Reactors are Water-cooled Water
moderated Energy Reactor (VVER-1000) o
Pressurized Water Reactor (PWR) technology,
which is worldwide proven concept. VVER-1000
reactors are the most advanced reactors
similar to the PWRs o western design. Nuclear
uel is charged into the reactor where the ssion
takes place and the heat is liberated. The
liberated heat in the reactor is carried away by the
light water rom the reactor to steam generator
by the main coolant pump. De Mineralized
(DM) water acts as reactor coolant. The coolant
water is used in the steam generators to produce
steam. The steam is allowed to pass through
turbine blades with high pressure and velocity.
The turbine then rotates receiving the kinetic
energy o the steam. The generator, which is
mechanically, coupled to the turbine also rotates
and generates power. The back steam o the
turbine is allowed to pass through the surace
type condensers. The condenser will be having
tubes through which sea water is allowed
to fow and over which the steam fows. The
sea water absorbs the heat rom the steam and
condenses the back steam. The condensate is
recycled back to steam generator. The sea water
ater absorbing the heat rom the back steam
is discharged into sea and resh water is drawn
through inlet.
n.P. VArAdhArAJAn & r. BALASuBrAmAniAn, Project Managers
Kudankulam Nuclear
Power ProjectA.u. rAo
Planning Manager
C Concord|Jan - Mar 2009 14
8/7/2019 Concord_mar09
15/48
mecacal wks ias Lages nclea
Pwe Pla
Larsen & Toubro has won all major mechanical
erection and installation. This includes our
mechanical packages and two electrical and
instrumentation packages.
The scope o work in M2 package include handling,
transportation, pre-abrication, welding, erection,
inspection & testing o piping, instrument tubing
and erection o associated equipment along with
accessories or nuclear steam supply systems and
nuclear auxiliary systems or Unit 1 & 2. This main
mechanical package involves heavy erection o
critical nuclear equipment like Reactor Pressure
Vessel, Steam Generators, Reactor Cooling
Pumps, associated piping in reactor and auxiliary
buildings, various saety systems like boron
injection system, passive heat removal system
and containment sprinkler system.
Eec a alge
nSSS Eqpe
In this M2 package, reactor equipment (2 x 316 t
each) was erected in our stages. Being a nuclear
project, high degree tolerances limit (0.01mm) was
maintained. Another challenge during the erection
was the clearance between the inner diameter o
support structure and outer diameter o Reactor
Pressure Vessel (RPV), which is only 10 mm and
large volume o blue matching.
SteamGenerator(8x307teach)waserectedina
conned space with the alignment in the range o
0.4 mm to 0.5 mm.
Pressurizer (2 x 222 t each) was also erected in
conned walls with the tolerance of 8mm w.r.t
containment wall and alignment in the range o
0.4 mm to 0.5 mm.
All the above erections were executed using highly
precision optical tooling survey instruments viz.,
Jig Transit.
MainCoolantPiping(64Jointsof990mmOD)
designed or a pressure o 176 kg/cm2 and
temperature o 320C has our quadrants. It
is connected to reactor pressure vessel (RPV)
assembly, steam generator (SG) and reactor
coolant pump (RCP). The piping is used to re-
circulate the primary coolant thereby removing
heat rom reactor and transer the same to steam
generator.
Pipes are made out o low alloy steel having outside diameter o 990mm and 70mm wall thickness,
cladded inside with austenitic stainless steel. The
total circuit involves 32 weld joints per unit and
the total weight o piping is about 260 t. The pipes
were supplied in pre abricated piping spool. For
the rst time in India, a unique and sophisticated
welding method was adopted or Main Coolant
piping at a nuclear power plant. Controlled and
Induction Heating technique was adopted or the
rst time in India during the welding operation with
Erection o ReactorPressure Vessel in
progress
ECC Concord|Jan - Mar 2015
8/7/2019 Concord_mar09
16/48
Vol. No. 31 Issue No. 4
hot temperature radiography o weld joint at 200
deg centigrade using special xtures and source
protection measures.
te Scpe wk vlve
ReactorEquipment-13,125t
StationaryEquipment-3,036t
RotaryEquipment-652t
Piping(SS/CS)-3,100t
SS/CSValves-1,180t
InstrumentTubing-CS/SS-1,60,920m
TubeWelding-CS/SS-9,000Nos.
tbe Eec
M3 Package work involves handling at site store/
storage yard, transportation to site o work, erection
testing and commissioning o turbine generator,
eed pumps, piping and its auxiliaries.
AlignmentoftheturbinewasdoneusingOptical
Aligning instrument and Fronius was adopted or
orbital welding.
Sea Wae Sse
M4 Package work covers handling, transportation,
pre-abrication, welding, erection, inspection,
testing and painting o sea water systems
equipment and piping in Sea Water Pump house
and Chlorination plant. The main work in this
package include works in pump house like EP
abrication and erection, anti corrosive painting,
erection o gates and screens, GRP piping, vertical
pump erection. chlorination building works and
tunnel piping. Again, using or the rst time in
India, Coupon Hycote paints was used or the
internal painting o sea water pipes.
Rotatingequipment 1,432t
Stationaryequipment 1,465t
CSpiping 2,108t
SSpiping 8t
Glassreinforcementpiping 35t
Titaniumpiping 16.5t
Excavationandbacklling 56,000cu.m
Structuralsteel 500t
Coldinsulation 1,183sq.m
Anti-corrosivepainting 55,683sq.m
Coatingandwrapping 4,000sq.m
Gritblastingandpainting 9,000sq.m
C Sevce Sse
The scope o work M5 Package covers handling,
transportation, pre-abrication, welding, erection,
inspection, testing o indoor and outdoor piping
and equipment o common service systems.
This consists o all indoor and outdoors piping,which includes HDPE piping or portable water,
re-ghting system (SGA, SGC, SGE), buried
piping (coating and wrapping included), boiler
associated works, DM plant associated tanks and
piping, and all nuclear ancillary building piping
and equipment.
Rotatingequipment-450t
Stationaryequipment-2,612t
CSpiping-2,452t
SSpiping-405t CIpiping-65t
HDPEpiping-150t
ACpiping-255t
RCCpiping-900t
Excavationandbacklling-238000cu.m
Coatingandwrapping-7,000sq.m
Supply,fabricationanderectionofstructural
steel - 500 t
Piping or Passive Heat Removal System
C Concord|Jan - Mar 2009 16
8/7/2019 Concord_mar09
17/48
The 1000MWe turbine, rst o its kind is a steam
condensing, our cylinder conguration (1 HPC +
3 LPC) with intermediate moisture separation and
steam reheat, with rotational speed o 50 s-1 (3000
rpm), designed to drive directly an alternating
current generator, mounted on a joint oundation
with the turbine. The total length o turbine with
out generator is about 40.65m. The turbine is
provided with throttling steam admission. The
steam rom steam generator is supplied to 4
HP valve blocks each HP valve block consist o
one stop valve and one governing valve through
which the steam enters the HP cylinder.
HP rotor is an integrally orged rotor. LP rotors
are also integrally orged rotors (blade lengthis 1200mm). All rotors are provided with rigid
coupling and supported by two journal bearings.
The thrust bearing, mounted between HP cylinder
and LPC 1 serves as a xed point or the rotor.
The steam from 4th stage of each LPC is
extracted by 3 LP heaters 1.
Thesteam from 3rdstage of LPC2 &3 is
extracted by LP heater 2.
The steam from 2nd stage of LPC 1 is
extracted by LP heater 3.
HPCturbineisofdoubleowcylinderhaving
5 stages in each fow.
The steam is extracted from second, third
and ourth stages o each fow or eed water
heating by HP heater 5,6 and deaerator
respectively.
FromHPCexhauststeamisextractedbyLP
heater 4.
The steam from exhaust of HPC enters
moisture separator reheater.
AfterseparatorreheaterthesteamentersLP
cylinder through LP valve blocks which consist
o 1 stop valve and 1 governing valve.
LPCturbinearedoubleowcylindershaving
5 stages in each fow.
MassofheaviestpartofturbineisLProtor
-80.5t Massofturbine-1800t
Sale Feaes tbe
Qa wk
Turbine 4,028t
Generator 1,297 t
Condenser 2,609 t
Feedpump drive Turbine & Aux 402 t
Feedpumps 169 tCondensate Pumps 257 t
CrossoverPipes 283t
OtherAuxiliaryEquipment 200t
OtherPiping 12t
Two views o Stator (345 t) during erection or 1000 MWe Turbine Generator at Unit #2
ECC Concord|Jan - Mar 2017
8/7/2019 Concord_mar09
18/48
Vol. No. 31 Issue No. 4
Insulation-6,000sq.m
Supplyandxingofhiltybolt-1,000Nos.
Wellerection-824Nos.
Sae
Saety system practiced at the project site is
extremely stringent as it involves several heavy
lits, erection o critical equipment, hot processes
and working in severe conditions like tunnel and
conned space. L&Ts team religiously ollows the
saety norms as per the requirement o the Atomic
Energy Regulatory Board (AERB). L&T has been
awarded the Project Directors rolling trophy or
Best House Keeping by the client.
All the pre-commissioning and commissioning
activities were meticulously planned and
implemented successully. All the erection
sequences and procedures were documented
in 175 volumes. These dierent packages are
progressing well, meeting the quality standards
set by Russian authorities.
Apart rom Mechanical packages Instrument
tubing works in reactor building also in L&Ts
scope which involves 160 km tubing works.
Eleccal Scpe
E1 Package - teccal Aspecs
MainPoweroutputsystem
Auxiliarypowersupplysystem
Classicationofauxiliarypowersupplies GIS
Systemgrounding
ipa eaes e pla
First21000MWepowerplantinIndiaunder
construction with single transormer unit o
capacity 417 MVA
First time in India having 4200m length of
400kV GIBD
Fully inside lined reactor containment, a rst
time eature in India.
SG Pressuriser
erection in progress
Turbine erection
C Concord|Jan - Mar 2009 18
8/7/2019 Concord_mar09
19/48
The tender specications covered electrical
system installation in all the buildings o KKNPP
unit 1 & 2 such as 400kV GIS building, switchyard
control room building, transormer yards, normal
operation power supply building, common station
power supply building, emergency power supply
buildings and other main plant buildings such
as reactor building, turbine building, reactor
auxiliary building, pump house etc. as well as
supply o some electrical equipments, hardware,
accessories required or the installation works.
Sse descp
The electrical system or the two units o
Kudankulam nuclear power plant, each o 1000
MW, mainly consists o power output system and
auxiliary power supply system. The power output
system is designed or evacuation o powergenerated at NPP. The auxiliary power system
provides the power to NPP auxiliaries to carry out
their assigned unctions, in all operating modes o
NPP.
Pwe op Sse
The electrical power generated by the turbine
generators at 24 kV, three phase and 50Hz is
stepped up to 400 kV by the generator transormer
and is evacuated through our 400 kV transmission
lines. For reserve source o power to auxiliaries oNPP, Kudankulam NPP is connected to Tuticorn,
SR Pudur and Kayathar through 230 kV lines.
400 kV and 230 kV lines are connected through
interconnecting transormers. 400 kV and 230 kV
switchgear are o SF6 gas insulated considering
the saline atmosphere at Kudankulam site. 400 kV
is designed as one and hal bus scheme. 230 kV is
designed as two main bus schemes.
Major components o the power output system or
KKNPP include:
24kV1000MWgenerator
24kV31.5KAIsolatedPhaseBusduct(IPDB)
24kV28KAgeneratorcircuitbreaker(GCB)
3X417MVA,24/400kVgeneratortransformer
(GT)
400kV2000Agasinsulatedbusduct(GIDB)
400kVgasinsulatedswitchgear(GIS)
400kVtransmissionlines
315 MVA, 400 kV /230 kV interconnecting
transormer (ICT)
230kVgasinsulatedswitchgear(GIS)
230kVtransmissionlines
1phase26.7MVAshuntreactors(6nos)
Axla Pwe Sppl Sse
The main unction o the auxiliary power system is to
ensure the availability o sucient power supply to
the auxiliary system equipments during all modes
o plant operation i.e. normal plant operation,
shutting down the reactor, maintaining the reactor
in sae shut-down state, containment isolation,
reactor core cooling, preventing signicant release
o radioactive material to the environment and any
other necessary unctions.
For start up as well as or normal shutdown o bothunits o plant, station auxiliary power is drawn rom
the 400kV network through generator transormer
and unit auxiliary transormers with the GCB
open.
During normal plant operation, station auxiliary
power is drawn rom the main generator rom the
tap-o to 24kV bus duct through the UATS.
The reserve power supply is derived rom 230kV
grid through 230/6.3-6.3kV RATS and is used as
backup power during non-availability o powersupply rom UATS.
The common station auxiliary power supply eeding
the common station auxiliary loads is derived rom
230kV grid through 230kV/6.3-6.3kV CSATS and is
backed up by the RATS.
The systemmainly consists of 6kV, 0.38kV and
220 V DC power supply sources to supply to
unit auxiliary loads and common station auxiliary
loads.
Auxiliary power supply system envisaged orKKNPP is categorized as per their unctional
requirements detailed below.
Normal auxiliary power supply for each unit
system including common station auxiliary
supply system or the plant.
Reliable auxiliary power supply of normal
operation or each plant.
Emergency auxiliary power supplies system
or saety systems or each unit.
ECC Concord|Jan - Mar 2019
8/7/2019 Concord_mar09
20/48
Vol. No. 31 Issue No. 4
Eleccal Wks
isalla, esg a pecssg
Description QTY UOM
24KV,2800ASF6GeneratorCircuitBreaker 2 Nos
420/24 KV 417MVAGenerator Transormer 7 Nos
24KV 31500A single phase Isolated Phase Bus Duct 1120 m
315MVA 400/230/33kV interconnecting transormer 2 Nos
63/31.5-31.5MVA, 24/6.3/6.3kV UAT/RAT/CSAT 9 Nos
27MVA 420kV Single phase Shunt reactors 6 Nos
400kV 3150/2000A Single phase SF6 bus duct 4200 m
230kV, 2000A single phase SF6 bus duct 900 m
6kV 6.3MW Diesel Generator Sets 10 sets
6kV 3150A Isolated phase bus duct 2400 m
6kV 3150/1600A Switchgear Panel 522 Nos
6kV/0.4kV 1000KVA/400KVA Dry Type Aux.
Transormer 107 Nos
0.38kVMCCSingleFrontPanel 444 Nos
0.38kVMCCDoubleFrontPanel 668 Nos
CableTray&Supports 1860 t
Cables 7800 km
HT & LT Termination 129000 Nos
LightFittings 21285 Nos
Sppl, eec, esg a cssg
Line Protection Panels 7 Sets
Lighting /Power Distribution Board 672 Nos
Light Fittings 7331 Nos
GI Conduits 344 km
650/1100VFRLSPVCWire 800 km
Classfca o Axla Pwe Spples
Depending on the degree o reliability or
requirement o saety, the power supplies are
classied into three groups
Gp-1: loads that require uninterruptible power
supply are kept in group-1 class. These can be
interruptible but not more than 20 seconds.
These are supplied from 220 V DC, 380 V and
220 V AC power supplies normally derived rom
group-3 or group-2 power supply sources and
whose back up source o power is rom the battery
banks.
The major components o auxiliary power supply
system are given as below.
63MVA,24/6.3-6.3kVUAT
63MVA,230/6.3-6.3kVRATS
230/6.3-6.3kVCSAT
6.3MW,6kVDG
6kVswitchgear
1000 kVa & 400kVa, 6/0.4kV and 6/0.433kV
auxiliary transormers
0.38kVand0.415kVswitchgear/MCCs
Rectiers
220VDC&110VDCbatteries
Inverters
220VDCdistributionboards
220V/380VACdistributionboards
110VDCdistributionboards
Cabling
Cablepenetrations
Gp-2: AC supply to the loads, which can
tolerate short interruption or a time dened by
the conditions without eecting saety o the
reactor, under all modes o the plant, including the
condition o loss o supply rom all o-site sources,
is called the group-2 loads.
6.6 kV control replay panels
C Concord|Jan - Mar 2009 20
8/7/2019 Concord_mar09
21/48
These are supplied from 6kV, 380V and 220 V
AC, 50Hz supplies normally derived rom group-3
power supply and whose back up source o power
is rom DG sets.
Gp-3: power supply to the plant auxiliary
loads normally required under all modes o plant
but which can tolerate prolonged interruption inthe power supply, without aecting the saety o
the plant, and do not require obligatory availability
o power supply even ater the actuation o the
reactor trip system is called the group-3 power
supply.
Thesearefedfrom6kV,380Vand220VAC,50Hz
supply derived rom UATS, RATS or CSAT.
Pcples Cl, mg a
rela Pec Sse
During operation, a system is understood as a
set o devices o relay protection, control and
monitoring o the electrical equipment, structurally
and unctionally involved. At KudanKulam NPP,
independent system o control, monitoring and
relay protection system are provided or many o
the systems.
Gas islae Sbsa
Here switchgear apparatus or 220kV and 400kV
equipment use the SF6 as dielectric media due tomany o its advantages.
Though SF6 was developed in 1900, it was
used as dielectric medium only ater 1940
Itisapowerfuldielectricmedium
Itsdielectricstrengthis2.35timestothatofair
Itis5timesheavierthanair
Itisnon-toxicinpureform
Its dielectric strength is proportional to the
pressure that it operates
ThisiswellsuitedforHVswitchgearsandGIS.
The gas passing through the isolated bus duct acts
as a powerul insulation media and this compacts
the size o the switchgear.
Gg a Lgg Pec
To achieve the requirements, a grid consisting o
70 sq.mm tinned stranded copper conductor has
been laid by the civil contractors at a depth o not
less than 0.5 m below the oundation, with a mesh
size o 25m 25m in the outdoor area and about
6m 6m mesh size beneath the buildings. GI
earthing conductors run to walls and foors inside
the buildings, which orm the main grounding lines
are connected to the buried copper conductors.
All the metal components inside the building are
connected to the grounding network.
Lightning protection conductors in a mesh
ormation are provided over the building surace,
along outer perimeter walls and on the roo and
are connected to the grounding grid. Lightning
arresters are installed on the stack top.
isea
I1 package involves executing the entire
instrumentation work under the supervision o ECIL.
Scope o work includes calibration and installation
of 18,000 instruments such as Pressure, Flow
and Level transmitters, RTD and Thermo couples,
Pressure and Temperature gauges, Analytical
instruments, Level sensors, Seismic sensors and
Radiation monitors, Installation o 3000 instrument
support stands, abrication and erection o 200 tsteel, 50 km o GI perorated tray or eld routing
and 176 km o cable laying and glanding work
Cvl Wks
C5 package involves 65000 cu.m o concreting
works to construct De-Mineralized Plant (DM Plant),
Boiler House, Solid radioactive waste building,
Chiller units building, Compressor building and
Diesel storage pump House including NPCILs
Main Administration Building.
220 kV gas insulated
substation
ECC Concord|Jan - Mar 2021
8/7/2019 Concord_mar09
22/48
Vol. No. 31 Issue No. 4
PREFRE-3A ProjectF BArC Kalpakka
L&T-ECC is in the verge o completing, the
procurement, construction contract o civil
structure incl. 75 M High RCC stack and electrication
work or PREFRE-3A project (Power Reactor Fuel
Recycling) in the phase II or BARCs premises at
Kalpakkam on the Chennai Puducherry coastal
highway. Valued at Rs.65 Crore, the scope o work
are as ollows :
Excavation - 67500cu.m
Reinforcement - 5400t
Concrete - 27740cu.m
Formwork - 90290sq.m
Brickwork - 3160cu.m
Plastering - 50000sq.m
Painting - 75311sq.m
Site team has received appreciation letter or
achieving 4 million sae man hours. And has got
excellent customer relation ship, TCE Consulting
Engineers are the consultants or this project. Work
commenced in August 2005 and expected to becompleted by May09 in all respect.
These civil structure and electrical works are used
or Nuclear uel recycling received rom designated
Nuclear plants in India.
PREFRE-3A Facility is being developed as an
expansion to the existing KARP-(Kalpakkam Atomic
Recyclingplant)onthesouthside.Oncompletion
the newly constructed structures will be merged
with KARP or enhance the recycling capacity.
The very objective o Recycling programme is to
get to recover materials like Plutonium ,etc in the
process to reuse in non conventional nuclear Power
generation programme like FBR (Fast Breeder
Reactor).
L&TECC Division is engaged in construction works
at Madras Atomic power station (MAPS) Kalpakkam
rom 70s and has the credit o constructing 40m
high and 45m dia dome reactor, turbine buildings,
100m, 75m & 65m RCC stacks or NPCIL.
Scope coss of as ay as 14 sces a e eals ae as follows:
nae of sces deso reaks
High block 60 x 30 x 25 m high 4 storey mainstructures o the plant
Low Block 60 x 26 x 20 m high 4 storey buildingInter mediate Traner acility 24 x 24 x 10 m high 6m substructure and 3 foors
constructed using 19 Ctemp. concrete
75m high RCC stack 75 m high x 3.6 m dia Ventilation stack
Delay tank 24 x 30 x 6 m below RCC tank o sevenchambers below GL.19 C concrete
Substation C 30 x 24 x 10 m high 2 storey structure
ExhaustFanmainplant 50x18x10mhigh 2storeystructure
Exhaust control Room 19 x 17 x 10 m high 2 storey structure
Connecting corridor 25 x 6 x 25 m high 5 storey structure
Fuel Handling Area extn. 21 x 6 x 7 m high
RCCVentilationDuct 60mlong2X2mbox
CompressorHouse 18x12x7m
Bolier House 15 x 16 x 7 m
FOST(Fueloilstoragetank) 13x11m
h.m. BhAdri
Project Manager
Construction in progress at one o the blocks
C Concord|Jan - Mar 2009 22
8/7/2019 Concord_mar09
23/48
to utilize indigenous capabilities or the Turnkey
Construction o nuclear power plants including
supply o reactor equipment and systems,
valves, electrical & instrumentation products and
abrication o structural, piping and equipment
modules or the Westinghouse AP 1000 plants.
Asexp
For Nuclear Power Reactors, L&T and
Atomstroyexport (ASE) o Russia have signed a
MoU or co-operation between the two companies
or Russian design reactors VVER 1000.
The MoU will orm the basis o co-operation
between the companies and address needs
or equipment & other services arising rom the
agreement signed between India & Russia on 5th
December2008,forfouradditionalreactorsKK3-6
at Kudankulam, Tamil Nadu and other Russian
reactors at new sites in India.
L&T is the only Indian company to be accredited by
ASME (American Society o Mechanical Engineers)
to use its N and NPT stamps or critical nuclear
reactor equipment. L&T played an important role
in construction, piping & erection services or the
KK1-2 VVERs at Kudankulam.
According to the signed document L&T and ASE
will develop co-operation in the construction o
Kudankulam new power units, as well as during
construction o plants under the Russian designs
with VVER reactors at new sites in India, and alsoin other countries.
This MoU with ASE represents a major step or L&T
into VVER component & systems manuacturing &
services. It will enable L&T as well as ASE to utilize
indigenous capabilities or nuclear power plants
including supply o equipment and systems,
valves, electrical & instrumentation products and
abrication o structural and piping and construction
or the Russian VVER plants in India and in other
global locations.
AECL ACr 1000 reacs
L&T and Canadian based Atomic Energy o Canada
Limited (AECL) have signed a Memorandum o
Understanding or co-operation on Advanced
CANDU Reactor ACR1000. This agreement is
subject to nal approval by the governments
o India and Canada, o a bilateral Nuclear Co-
operation Agreement between the two countries.
Pressurized Water Nuclear Reactors (PHWR) designis one o the most highly competitive nuclear
technologies in the world with regard to capital
cost, saety & eciency. The unique design allows
reueling online which eliminates the periodic
reueling outage required by other designs.
The ACR1000 is AECLs generation III+ reactor
design that utilizes the proven concepts o the
PHWR. L&T and AECL have joined hands to
develop a competitive cost model or the ACR
1000. Upon completion o the indicative cost/scope
model AECL and L&T agree to begin discussions
to develop Nuclear Power Plants in India on EPC
basis and utilize the collective expertise o the
Parties in global markets.
Wesgse mla nclea Pwe
reacs
L&T and US-based Westinghouse Electric Company
(WEC) have signed a MoU or co-operation to
eectively address the projected need in India or
Pressurized Water Nuclear Reactors with Modularconstruction technology. Westinghouse technology
is in use in over orty per cent o the operating
nuclear power plants in the world.
Whereas L&T has been playing a lead role
in equipment manuacture, construction and
project management or Pressurized Heavy
Water Reactors in Indias domestic program, this
MoU with Westinghouse represents a major step
orward or L&T in Pressurized Water Reactors o
modular design. It will enable L&T as well as WEC
L&t sgs mu w
World Leaders in
Nuclear Power Sector
ECC Concord|Jan - Mar 2023
8/7/2019 Concord_mar09
24/48
Vol. No. 31 Issue No. 4
Indira Sagar
Right Main CanalProject
SAJid FArooQ mohAmmEdProject Manager
C Concord|Jan - Mar 2009 24
8/7/2019 Concord_mar09
25/48
The Indira Sagar (Polavaram) project is located
in Andhra Pradesh on the river Godavari
near Polavaram Village above 34km upstream o
Kovvur, Rajahmundry. The Polavaram project is
contemplated as multipurpose project envisaging
irrigation benets or the upland areas o East
Godavari under Let Main Canal and West Godavari
and Krishna District under Right Main Canal.
rg ma Caal
The Indira Sagar (Polavaram) Right Main Canal
project is taking o rom the Godavari River on
the upstream o Indira Sagar Project (Polavaram),
Rajahmundry and runs or a length o 174.000 km
in West Godavari and Krishna Districts o Andhra
Pradesh. The Right main Canal at 174.000 km gets
linked up with Krishna River through the existing
Budameru Diversion Channel. This Right MainCanal is contemplated to irrigate an ayacut area o
129259 hectares (Ha) in the upland area o West
Godavari and Krishna District. This canal provides
for diversion of80TMC ofGodavari water tothe
Krishna River to meet the irrigation requirements
o Krishna Delta.
Cac
As a part o the ambitious and most prestigious
Jalayagnam Projects, the Irrigation & Command
Area Development (I&CAD) Department,Government o Andhra Pradesh divided the
174.000 km length Right Main Canal into 7
Packages and awarded the 7th Package to ECC,
L&Ts Construction Division on EPC turnkey basis
foravalueofRs.181crores.
Lca
Chainage 156.500 km - 174.00 km o package 7
begins at Nunna village, 25 km rom Vijayawada.
The main canal traverses through thick mango
elds, reserve orest, hills, deep cut quarries,ponds, lakes and small villages. The project is
ully surrounded by long stretches o green elds.
The 17.5 km long canal passes through 9 small
villages and terminates on the upstream side o
Budameru regulator at Velagaleru village.
Scpe Wk
Construction o this 17.5 km Right Main Canal
involves detailed investigation, survey, preparation
o land plan schedules, design and engineering,
earthwork excavation, ormation o embankments,
lining o main canal, construction o CM & CD
structures and plantation on both sides o main
canal.
Csc
The construction o main canal involves theollowing important stages.
deale ivesga a Sve
The entire stretch o the 17.5Km was studied in
detail by conducting various other alternative
alignment surveys. To the extent possible, the
alignment was done in FSL Contour to avoid
embankments. For nalizing the alignment and to
mark the route in thick reserve orest, bushes and
mango elds, GPS Navigators and Total Stations
were used.
La Pla Scele a La acqs
The village-wise Land Plan Schedules were
prepared or acquiring about 1000 acres o land
involving Private Lands, Revenue Govt. Lands and
Forest Area. About 3.25 km o main canal passes
throughthereserveforestofareaof120.68acres
and the balance part o the alignment traverses
through mango elds and cultivated lands. Digital
Cadastral drawings showing the boundaries o
each Village, extent o land and area to be acquired
were some o the important issues involved in
preparation o Land Plan Schedule and in Land
acquisition.
desg a Egeeg
The design and engineering or the entire
package was done by ECCs Engineering Design
& Research Centre (EDRC) at HQ, Chennai. The
design scope involved preparation o Bore log
sheet, preparation o Hydraulic particulars o maincanal, km-wise LS & plan o main canal, design
& drawings o cross masonry and cross drainage
structures.
The part o the alignment rom km 163.150 to km
163.700 has been designed as Flumed Section
with a bed width o 65.50 m considering the deep
cut excavation and alignment passing between
the hills. Standard Penetration Test and Plate
Load Tests were conducted at each structure to
ascertain the bearing capacity o soil.
ECC Concord|Jan - Mar 2025
8/7/2019 Concord_mar09
26/48
Vol. No. 31 Issue No. 4
halc Paclas ma Caal
Length o main canal : 17.50 km
Bed width o main canal : 73.25 m
Topwidthofmaincanal : 88.85m
Full supply depth : 4.2 m
Freeboard : 1.0 mSide slopes : 1.5H : 1V
Bed all : 1 in 20,000
Designeddischarge : 318.48Cumecs
No. o structures as per HPs : 24
Eawk Excava
The 73.25m bed width canal involves about
85 lakh cu.m of earthwork excavation and
10 lakh cu.m o embankment. The soils met with
on the course o the alignment were generally red
earth and hard gravel.
The depth o earthwork excavation in normal
section ranges rom 5-7 m depending upon the
ground level. A 40 m deep cut hard rock excavationat fumed section is one o the most critical and
adventurous one.
Lg ma Caal
Prole Walls shall be laid at8.75m and 17.5 m
intervals in curve portion and straight portion
respectively or ormation o Subgrade beore
laying the Lining Concrete. More than 600 workmen
C Concord|Jan - Mar 2009 26
8/7/2019 Concord_mar09
27/48
were deployed or Subgrade preparation. In
addition, Graders and Rollers were also deployed
or ormation o Subgrade.
The lining or the main canal was done with M10
grade o concrete with 40mm maximum size o
aggregates. 100mm thick lining concrete was laid
or the entire bed width o 73.25m with slopes on
both sides up to a height o 4.95m rom the canal.
Onthewholetheworkinvolved1.8lakhcu.mof
lining concrete.
Contraction Joints at 5m intervals were provided
in both transverse and longitudinal direction.
This apart, suitable construction joints, concrete
sleepers, transverse drains, longitudinal drains,
porous plugs were also provided in lining
Concrete.
Css mas &
Css daage Sces
A number o streams and small village roads cut
across the main canal at dierent locations. Toprovide access to the villagers as well as to allow
the streams to pass across the main canal or
irrigation acilities etc., dierent types o structures
were proposed in the alignment o the main canal.
Thus, 24 dierent structures were constructed
in the canal alignment or meeting various
requirements.
Panoramic view o the canal
ECC Concord|Jan - Mar 2027
8/7/2019 Concord_mar09
28/48
Vol. No. 31 Issue No. 4
Jindal Dam - L&Tsmaiden venture in to
construction o ull-fedged dams
G. BhASKArA rAoPlanning Manager
C Concord|Jan - Mar 2009 28
8/7/2019 Concord_mar09
29/48
Jindal Power Limited, a leading power generation
company, and a subsidiary o Jindal Steel has
set up a 1,000 MW super thermal power plant at
Tamnar in Raigarh district, o Chhattisgarh. For the
consumptive water use in the power plant, a dam
has been built across river Kurket, near village
Rabo, which is about 33 km rom the power plant.
This200mlong18.5mhighdamsuppliesabout
40 cu.m per minute o water to the power plant
and meet the consumptive and circulating
requirements o the power plant.
Apart rom being the ull fedged dam project
undertaken by ECC, this unique and landmark
project was raught with several social and
environmental problems.
Braving all the odds, L&T successully completed
the project and the food gates were ormallyopened and inaugurated by Mr. Sara, President
Jindal Power Limited on July 13, 2007.
Sale eaes
Main earthen dam in the Riverbed - 200m
long,18.5mmaximumheight
Rightbankdykeof1150mlongand2to15m
height
Leftbankdykeof201mlongand2to6m
height
Spillway dam and energy dissipation
arrangement 145m long with 10 vertical
gatesofsize12mx8.5mand2stoplogswith
operating system
Intake and pump house with stop log and
trash rack o 4m x 11m
Riverdiversionworks
Completehydro-mechanicalequipment
Approach roads to the project with
illumination
maj Scpe Wk
Excavationinordinarysoil-5,80,246cu.m
Excavationinrock(alltypes)-3,42,500cu.m
Concrete(allgrades)-57,772cu.m
Reinforcement-1534t
HMworks(GatesandHoist)-800t
Groutingmaterial(cement)-3,243bags
Bentonitefordiaphragmwall-27t
Excavationofcutofftrench-55,500cu.m
Fillingofcutofftrench-55,500cu.m
Earthworkllinginembankment-
48,2407cu.m
Rip-rapworks-30,917cu.m
Metalledroadatthetopofdamfacilities-
2.60 km
Electricalttingsandillumination
ree Lca
As the site was located at 35 km rom Raigarh,
a 11km approach road to site was strengthened
beore commencement o the work. In addition,
L&T had to establish V-sat connection as there
were no communication networks available in the
vicinity.
dapag wall
Initially, the diaphragm wall or the main dam was
an RCC structure. Ater the work was awarded,
the consultant changed the structure rom a rigid
D-wall to a fexible D-wall using plastic concrete
and doing away with the reinorcement. The
Foundation Engineering Competency Cell o ECC
took this challenge and developed a new design
mix or this type o plastic concrete. The ormula
worked perectly and the work was executed
successully.
Acevees
Major portion o project excavation or spillway,
concrete or spillway, abrication, erection &
commissioning o spillway gates and earthen dam
in the river portion including rip-rap works, were
completed in the stipulated time o 25 months
and handed over to clients. This project received
Prashansha Patra rom National Saety Council
o India (Saety Awards 2007) or achieving 4
million sae man-hours without any lost time due
to injury. Site also received Annual Quality trophy.
View o the dam and
hydro-mechanicalstructures (gates)
in position
ECC Concord|Jan - Mar 2029
8/7/2019 Concord_mar09
30/48
Vol. No. 31 Issue No. 4
Veligonda Dam
The engineeringmarvel
A. r. nErurKArProject Manager
PAnKAJ KEShAV GurSALEPlanning Manager
C Concord|Jan - Mar 2009 30
8/7/2019 Concord_mar09
31/48
Arid landscapes, barren elds and dusty track
lands dene the upland areas o Prakasam,
Nellore and Kadapa Districts in the State o Andhra
Pradesh, which all under the severe drought
prone zone. With the completion o our ongoing
irrigation projects Veligonda, Gundlakamma,
Ramatheertham and Palair, the scenario is
changing. These our projects increased the
irrigation potential o this region rom the present
7.45 lakh acres (3.01 lakh hectares) to 13.45 lakh
acres (5.44 lakh hectares) in a couple o years.
Thisquantumjumpof80percentwillbeachieved
ater the completion o Rs.4000 crore projects
under the Jalayagnam programme.
A huge reservoir, called the Nallamala Sagar,
is being ormed and three dams are being
constructed at Gottipadia, Sunkesula and Kakarla.
Water is drawn rom Kollamvagu oreshore on
rightbankofSrisailamreservoirthrough18.80km
long tunnel by gravity and thereater diverted to
Nallamala sagar through a 23.36km eeder canal.
The canals are proposed rom Sunkesula gap,
Gottipadia gap and Kakarla gap and envisages to
draw 43.50 TMC o food water rom river Krishna
upstreamofSrisailamreservoirtoirrigate4.38lakh
acres (1.7 lakh hectares) in 29 mandals, mostly in
Prakasam district and marginally in Nellore and
Kadapa districts.
L&T is entrusted with the construction o one o
these dream irrigation projects The Veligonda
Dam. The project will provide irrigation benets
to upland areas o the district besides providing
sae drinking water to 15 lakh people, who have
been consuming groundwater with excess fuoride
content or decades. L&Ts scope o works
comprise construction o dam at Gothipadia
and excavation o Gottipadia Canal including
construction o cross masonry and cross drainage
works, distributory system or 9500 acres. L&Tsecured this contract in 2005 rom Irrigation &
Command Area Development Department o
Andhra Pradesh against sti competition.
Valued at Rs. 395 crore, this is the rst major
concrete dam project executed by L&T on an EPC
(Engineering, Procurement and Construction)
basis. The scheme comprises construction o
dam rom EL 162 to EL 230 having a base width o
57.96m and top width o 12m, canal length 11.40
km and distributory system or 9500 acres.
Sale Feaes
Heightofthedamfromthedeepest
level-87m
Totallengthofthedamatthetop-600m
Slopeofthedownstreamface-1:0.662
Slopeoftheupstreamface-1:0.045
ECCs major scope o work includes 10,00,000
cu.mof excavation,9,21,181cu.mand 1,00,000
cu.m o concreting in two stages, 1600 t o
reinforcement,2,30,000sq.mofformwork,58,000
Rmt drilling or grouting, 51,000 cement bags or
grouting.
Cceg
Totalconcretingis10,21,181cu.mintwo
stages
Totaldurationofconcretepouring
24 months
Averagerateofconcretepouringachieved
1500 cu.m perday
Peakrateofconcretepouringachieved
2903 cu.m per day
The project had a huge requirement o concrete,
which was to be poured at a temperature o 15
degree celsius. The herculean task o achieving
and maintaining the standard o concreting was
managed with meticulous planning. As the height
o dam started increasing, earthen ramps up to
30m height was created or the movement o
concrete. Later, conveyor was used or shiting
concrete rom the batching plant to the top. As
the project required steel ormwork, the entire
shuttering was designed and schemed in-houseat site. Hydra cranes were used or handling the
orms. To reduce the cycle time, the shutters
were combined (4.8 m combined width) with
structural steel channels. The whole sequence
o operations, rom aggregate production to
concreting was mechanized thereby ensuring
accuracy and maximum output. The client
awarded commendation certicates or the highest
concreting (46000 cu.m) in the month o February
2006.
ECC Concord|Jan - Mar 2031
8/7/2019 Concord_mar09
32/48
Vol. No. 31 Issue No. 4
Egeeg Calleges
Veligonda dam project is the rst dam project
designed by the Engineering Design and Research
Centre (EDRC). EDRC looked at the opportunity
as a challenge and successully completed the
design o concrete dam. The internal arrangements
within the dam body like gallery, adit, shat, and lit
were designed with precision. The dam consists o
around 2 km o gallery within it or inspection and
grouting. Planning and aligning this multi level
gallery and the interconnection o the galleries
with access adits were really brain racking. Like in
any other dam, A holes and B holes or grouting
were designed to improve the impermeability o
dam base. The dam base was grouted with a
total drill length o around 22 km. Dierent types
o instruments were embedded in dam body to
monitor the dam in terms o settlement, plumb
and thermal. The monitoring was reviewed with a
computerized data acquisition system.
resces
Remoteness o the project posed the biggest
challenge as management o materials was
a critical task. Except or the aggregates, the
minimum distance or sourcing o other materials
was around 200 km away rom project site.
Interacting with the vendors and convincing them
to deliver as per the schedule was one o the most
critical activity or the smooth progress o the
project.
Sourcing o aggregates was another major issue.
Markapur is amous or slate rock ormation
which cannot be used as aggregates because
o its hard and sot rock combination. The site
has established a rapport with a local quarry or
uninterrupted supply o aggregates.
Identiying and sourcing the total requirement o
boulders (22 lakh mtp), was a major issue during
the initial phase as the local terrain had anity
C Concord|Jan - Mar 2009 32
8/7/2019 Concord_mar09
33/48
to slate rock. Two crushers with a combined
capacity o 450 tph are installed to cater to the
aggregate production. Sand impactors are used
to enhance the quality o the aggregate output.
This mechanized system o aggregate operations
was instrumental to achieve the planned output.
Sourcing o river sand also was a challenging taskas the nearest supplier was around 220 km away
rom project site.
Pla & mace
The initial review o similar dam sites was
instrumental in planning the machinery
requirement or the project. The methodology
involved in concreting was through dump trucks,
transit mixers and tower cranes. Two 125 tpd
chilling plants, 250t o rerigeration, two ice plants
were installed or getting the required concrete
pour. During summer, the temperature crossed 50
degree celsius and maintaining concrete pour at
15 degree celsius was the most critical challenge
through out the execution.
Specialized major P&M deployed include
120 cu.m/hr concrete batching plants with
aggregate individual weighing system or the best
accuracy.
Qal a Sae
TheprojectsitefollowedthenormsofISO9000
and has been reviewed by various audit systems
at regular intervals. Sae methodology was
incorporated in all activities o the project. Daily
pep talks and regular orientation programmes
ensured the communication o saety issues
and awareness is created down the line across
various departments. A system o automated
house keeping was implemented, where beore
commencement o work, the workmen ensure
appropriate environment is maintained.
Some o the sae methods employed at sites
included three lockwork permit systems or
rotating parts, cordless communication system or
tower cranes, and sensor alarm in hydra cranes.
ivas
Innovations and in-house alternatives are the
hallmarks to the speedy execution o this project.
Buckets o 3 cu.m capacity or concreting andvibrator needles were locally abricated which
resulted in considerable saving o time. Gantry
or handling o Formwork was designed by
Construction Methods and Planning Cell (CMPC).
CSr
As part o the corporate social responsibility, two
additional class rooms or the local government
school was built by L&T. An environment riendly
zone is being nurtured at the project site. About
892saplingswereplantedduringHHLCentenary
Celebrations. Three more class rooms were
constructed or the Government school at
Kaolabhimanipadu village.
The project team maintained cordial relationships
with the locale population, which was instrumental
in the smooth fow o work. Veligonda Project
contributed to reconstruct a temple which had to
be relocated due to the dam construction.
Night view o the Veligonda dam, during construction
ECC Concord|Jan - Mar 2033
8/7/2019 Concord_mar09
34/48
K A L E i d o S C o P En E W o r d E r S
rs. 605 C. oes Wae &Seel Secs
Larsen & Toubro (L&T) has bagged resh orders
worth Rs.605 Crores rom the Water and Steel
Sectors in the last quarter o FY 09. L&T secured
three orders aggregating Rs.416 Crores rom the
WaterSectorandanotherorderofRs.189Crores
rom the Steel Sector. The Metallurgical, Material
Handling& WaterOperating Company ofL&Ts
Construction Division will be executing these
orders.
Wae Sec: The company bagged a Rs.165
Crores order rom the Rural Water Supply &
Sanitation Department, Government o Andhra
Pradesh, or supply o potable water to 152
inhabitations in the Ananthapur district o the
state. The project is to be completed in 15 months.
At present, L&T is already executing water supply
projects worth Rs.319 Crores in Ananthapur
district.
L&T has also won a Rs.133 Crores EPC contractrom Delhi Jal Board or design & laying o MS
pipeline rom the Dwaraka Water Treatment Plant
to various areas o Dwaraka, Nazagarh, Daulatpur,
Ujwa and IGI airport (Package 3). The project is
to be completed in 21 months. At present, L&T
is executing the Dwaraka water supply scheme
(package1A)inDelhiforRs.248Crores.
ThecompanyhasalsosecuredaRs.118Crores
order rom Utkal Alumina International Limited or
design & construction o raw water intake structure,
raw water transmission pipeline & reservoir works
attheirAluminaPlantatRayagadaDistrict,Orissa,
to be completed in 17 months. L&T is already
executing Civil & Structural Works or this Alumina
Plant or Rs.455 Cr.
Seel Sec: In the steel sector, the company has
wonanorderof Rs.189Crores fromSAIL-IISCO
SteelPlantforCivilWorksforRollingMill,BOF,CCP
LDCP Complex, Lime Dolomite Plant at Burnpur,
West Bengal, to be completed in 12 months. L&T is
already executing the Sinter Plant & Raw MaterialHandling plant on EPC basis. Securing this new
order reinorces the condence placed on L&T by
SAIL, one o its major customers.
rs.1,143 C. es tAtA
Seel
L&T has bagged two orders totaling Rs. 1143 Cr.
rom TATA Steel.
ThiscomprisesaRs.689croreorderforturnkey
construction o Dry Crushing & Material PreparationPlant (DCMP) at Joda Mines and Engine-on-Load
(EOL)Scheme atNoamundiMinesand another
Rs.454croreorderforIronOre&PelletHandling
System at Jamshedpur. The Metallurgical, Material
Handling&WaterOperatingCompany(MMH&W)
o L&Ts Construction Division will execute these
orders.
L&Ts scope o work or the projects include basic
& detail engineering; complete civil & structural
works; supply and erection o mechanical,
electrical & instrumentation works including testing
& commissioning.
These turnkey projects are to be executed in
a schedule o 30 months or DCMP Project, 24
monthsforEOLschemeand23monthsforIron
Ore&PelletHandlingSystem.
L&T is already implementing Blast Furnace &
Pellet Plant packages or 3 MTPA expansion
project o TATA Steel at Jamshedpur which is
progressing at a ast pace. With these orders,
L&T has emerged as the major partner o TATA
Steel in the implementation o 3 MTPA expansion
project. Moreover, this covers the complete chain
rom material preparation at mines to receipt &
handling o iron ore & pellet and delivery to the
blast urnace.
rs. 1,100 C. Eleccal oes
L&T has bagged a slew o large-value orders
aggregating Rs.1,100 crores in the electrical
constructionsectorinthefourthquarterof2008-09.
C Concord|Oct-Dec08 34
8/7/2019 Concord_mar09
35/48
The orders have come rom leading public sector
organizations the Power Grid Corporation o
India Limited and the Rail Vikas Nigam Limited
and involves setting up high end transmission
lines and substations as well as a project or the
Indian Railways
Mr K. V. Rangaswami, President (Construction)and Member of the Board said: The 800 kV
HVDC Transmission Line project and the 765
kV substation orders represent technological
breakthroughs and they auger well or our growth
potential in these critical segments.
The order secured rom the Power Grid Corporation
o India (PGCIL) involves construction o a part o
thecountrys rst 800 kVHVDC transmission
system or transmitting power rom the north east to
the northern and western parts o India. Extending
across 190 km, this HVDC bi-pole transmission
line, valued at Rs.169 crores will be executed or
the section between Nidhaura Village to Agra in
Uttar Pradesh on the main line between Biswanath
toChariyali.Thisistherst800kVtransmission
line system o its kind in India and signies a
major step orward in high end electrical project
execution.OtherorderssecuredincludeaRs.190
crores order rom Power Transmission Corporation
o Uttarakhand Limited or 400 kV double circuit
Transmission Line between Loharinagpala to
Koteshwar, a Rs.175 crores order rom Rail Vikas
Nigam Limited or the Bharuch-Dahej Railway
Construction Project., and a Rs. 83crore order
rom PGCIL or the construction o 765 kV single
circuit transmission line rom Agra to Jatikalan.
Meanwhile, in a major oray into the high end 765
kV segment o substations, L&T secured three
majorordersfromPGCILvaluedatRs.480crores
or the construction o 765 kV Substations at
Balia, Lucknow and Satna along with associated
transormer packages.The entire project will be
executed within a tight schedule o 27months. It
involves detailed engineering and construction
o 51 bays o 765kV system including supply
and installation o 35 numbers o 500MVA Auto
Transormers.
The 765 kV orders were secured against sti
international competition, through a consortium
with Areva SA (France) and Hyosung (Korea) or
765kV switchgear and transormers respectively.
These projects will be executed by the Electrical
& Gulf Projects Operating Company of L&Ts
Construction Division.
rs. 1,438 C. Gl oes t&d sec
L&ThasbaggedthreenewordersworthRs1438
crores. Two orders worth Rs 1130 crores werebooked in the Gul Region and a third, worth Rs.
308crore,wasbaggedfromtheWestBengalState
Electricity Distribution Company.
L&ThasbaggedanEPCordervaluedatRs.800
crores (USD 164 million/ AED 600 million) rom
the Al Ain Distribution Company (AADC) or the
construction o 7 electrical substations, associated
MV cabling and overhead transmission line in the
Al Ain city o Abu Dhabi.
This is one o the single largest value orders
received by L&T in the UAE, or Power Transmission
& Distribution Sector.
According to the terms o the contract, L&T
will Design and Build these 33/11kV primary
substations to the specications o the international
consultant PB Power & will be completed within 24
months.
Each substation consists o 33 kV gas insulated
switchgear, 11 kV air insulated switchgear,
15/20 MVA 33/11 kV transormers, Substation
Control and Monitoring System, Protection andtelecommunication system, DC system and
auxiliaries. The contract encompasses design and
construction o civil buildings with complete set
o utilities such as air conditioning, re protection
and lighting systems.
L&T has also received another EPC order or
Augmentation & Expansion o 33 kV Power
Transmission Network with a value o Rs 330 crores
(USD 67 million / AED 247 million) rom Abudhabi
Distribution Company (ADDC). The scope covers
design, supply & construction o 300 km o 33 kV
Transmission line network in the western region
o Abudhabi, with the contract completion o 22
months.
These orders were secured against sti
international competition and will be executed
by the Power Transmission & Distribution Sector
o L&T Abu Dhabi. At present L&T is already
executing 20 substations o various capacities in
Al Ain, Abu Dhabi and Dubai areas o UAE.
ECC Concord|Oct-Dec35
8/7/2019 Concord_mar09
36/48
In another development Larsen & Toubro has
baggedaRs.308croresorderfromWestBengal
State Electricity Distribution Company Limited
(WBSEDCL) or Rural Electrication Works in
Jalpaiguri and North 24 Parganas districts o
West Bengal State. As part o the contract, L&T will
carry the 11 kV distribution lines to electriy 2274
villages in these districts, to benet the citizens
o Below Poverty Line ( BPL).The project will be
completedwithin18months.
rs.1,245 C. hpwe
Pjec e
The Infrastructure Opreating Company of
Construction Division has bagged a contract o
Rs.1245 crores or the construction o the Dam
Package, a part o the 1200 MW Punatsangchhu-I
Hydroelectric Project in Bhutan.
The project is being set up by the Punatsangchhu-I
Hydroelectric Project Authority which has been
constituted through an agreement between the
Government o India and the Royal Government o
Bhutan. It is located across Punatsangchhu River,
about80kmfromThimpu,thecapitalofBhutan.
To be executed in 66 months, the scope o work
involves construction o the diversion tunnel, dam,
intake and desilting arrangement including hydro-
mechanical works. L&T won the order through acompetitive bidding process. WAPCOS Limited
is the engineering and design consultant o the
Project.
This is the rst o a series o 10 hydropower
projects jointly identied by the governments o
India & Bhutan and to be implemented or a total
installed capacity o 11,576 MW by 2020.
For L&T, this is the second hydroelectric power
project in Bhutan - the rst one was the 1020 MW
Tala Hydroelectric Project, which was completedahead o schedule.
rs.1,162 C. oe Blgs & Faces oC
L&TsBuildings&FactoriesOperatingCompany
part o its Construction division has bagged new
orders aggregating around Rs.1162 crores in the
fourth quarter of2008-09for the construction of
actories and residential projects.
L&T has bagged a major design & build order
valued at Rs. 605 crores rom the Andhra Pradesh
Rajiv Swagruha Corporation Limited or the
construction o an integrated thematic township
comprising o 3517 fats (27 blocks) and consisting
o Classic/ Intrinsic/ Basic & Civil type fats
at Bachupally, Hyderabad. This project is to be