+ All Categories
Home > Documents > Concord_mar09

Concord_mar09

Date post: 08-Apr-2018
Category:
Upload: rahulgehlot2008
View: 224 times
Download: 0 times
Share this document with a friend

of 48

Transcript
  • 8/7/2019 Concord_mar09

    1/48

    January - March 2009 Vol. No. 31 Issue No. 4

  • 8/7/2019 Concord_mar09

    2/48

    Editor V.S. rnEditorial tEam K. Sn | aex Benjn | V. res K |

    aswn Cn | V. Esw | Sb ann

    PhotograPhy V.S. NnvedESigN& layout Ss gpcs desn, Cenn.

    ContentsVol. No. 31 Issue No. 4

    L&T has played a critical role in the development

    of technology & capabilities for the Indian nuclear

    power sector from its very beginning. ECC, L&Ts

    construction Division has the capability to construct

    critical and complex structures for nuclear power plants

    to international standard specications. Moreover, it has

    the distinction of having participated in the construction

    of a majority of nuclear power plants and heavy water

    plants in the country.

    This has opened several avenues for L&T to sign

    cooperation agreements / MoUs and forge alliances

    with leaders of nuclear technology across the world,

    such as: Westinghouse Electric Company (WEC), USA

    for Pressurized Water Nuclear Reactors with modular

    construction technology; Atomic Energy of Canada

    Limited (AECL) for cooperation on Advanced CANDU

    Reactor ACR 1000. Recently it signed the MoU with

    Atomstroyexport (ASE) of Russia for cooperation

    to supply Russian VVER 1000 type reactors for the

    Kudankulam nuclear power project.

    L&T has been a partner in the development of Indian

    Nuclear power programme and it has been playing

    an active role in the construction of major nuclear

    plants in different parts of the country. As a part of

    the operations of L&Ts Infrastructure OC, we take

    pleasure in highlighting our contributions to this sector

    along with irrigation projects executed by us.

    Kaiga Atomic Power Project (Unit 1 & 2)

    L&Ts Track Record

    in Nuclear Power 4

    Endeavours at

    Tarapur Nuclear Power Plant 6

    Nuclear Reactor

    Containment Test Model 12

    Kundankulam Nuclear

    Power Project 14

    PREFRE-3A Project

    or BARC Kalpakkam 22L&T signs MoU with World Leaders

    in Nuclear Power Sector 23

    Indira Sagar

    Right Main Canal Project 24

    Jindal Dam - L&Ts Maiden Venture

    in to Construction o Full-Fledged Dams 28

    Veligonda Dam

    the Engineering marvel 30

    Kaleidoscope 34

  • 8/7/2019 Concord_mar09

    3/48

    L&T began its journey in to construction o

    Nuclear power projects in a modest way, by

    undertaking the construction o oce acilities or

    the Atomic Energy Establishment and laboratories

    or Bhabha Atomic Research Centre at Trombay

    during mid 60s. The construction o Main plant

    civil works at Kalpakkam or the 220 MWe Madras

    Atomic Power Project Unit 1&2 during 70s was

    the rst major project in the nuclear segment.Subsequently, the Main plant civil works or the

    220 MWe Kaiga Nuclear Power Project (Unit 1&2)

    in Karnataka was executed by L&T. Erection o

    almost all heavy water plants in India are executed

    by L&T.

    Realising the vast potential and business

    opportunities in this segment the Nuclear Business

    Unit was ormed by L&T in the year 1999-2000

    when it secured the 540 MWe Tarapur Atomic

    Power Project, Unit 3&4. It should be mentioned

    that Tarapur Atomic Power Project was one o themajor projects or L&T, where dierent business

    units o L&T were actively involved in the execution

    o the project - Nuclear, Electrical & Instrumentation

    BUs o ECC Division; Heavy Engineering Division;

    Nuclear BU o E&C Division to name a ew.

    Acevees

    Some o the notable achievements in Nuclear

    segment include:

    Outofthetotalinstalledcapacityof7280MWe

    o nuclear power (both commissioned and

    ongoing); L&T is involved in almost all Nuclear

    power projects in the country extending up to

    5280MW.

    Successfulcompletionofmainplantcivilworks

    o 2x540 MWe Tarapur Nuclear Power project

    in a record 60 months rom the rst pour o

    concrete is considered as a great achievement

    -Oneamongthesixreactorsintheworldto

    achieve this eat.

    Successful completion of Primary Piping

    Package (the heart o the nuclear plant) on

    time including other mechanical packages in

    the Countrys maiden 2 x 540 MWe Tarapur

    Nuclear Power Project. This helped L&T in

    understanding the criticality, stringent qualityrequirements, etc and as a sequel, it secured

    major mechanical packages in Kudankulam

    Nuclear Power Project 1&2.

    L&T is involved in the execution o Indias rst

    2x1000 MWe Nuclear Power Project at Kudankulam,

    which is one o the most prestigious projects

    undertaken by Government o India in collaboration

    with Russian Government. Initially, L&Ts

    participation in civil works involves construction

    o inrastructure acilities and auxillary buildingsonly. However, the scenario changed, when L&T

    secured our major mechanical packages which

    involve technology certications, being done or

    the rst time in India, etc.

    This apart, auxiliary systems such as Induced Drat

    Cooling Towers, HVAC, Service Water Systems,

    etc are being constructed on EPC basis.

    L&T is also involved in many Reactor back end

    projects, that is construction o uel reprocessing

    related acilities such as Additional Waste TankFarm, Spent uel Storage Facilities, Power Reactor

    Fuel Reprocessing acilities, etc at various locations

    in India. Thus, making L&T an all rounder when it

    comes to execution o almost the entire spectrum

    o activities involved in the construction o nuclear

    power projects.

    OnthewholeL&Tisplayingacriticalandsignicant

    role in the Indias Nuclear Power sector.

    Powering The Nation

    With Nuclear Energy

    ECC Concord|Jan - Mar 203

  • 8/7/2019 Concord_mar09

    4/48

    Vol. No. 31 Issue No. 4

    Nuclear power projects are considered as

    one o the sustainable energy projects o the

    uture. The Nuclear Power Corporation o India

    Limited (NPCIL) presently operates 17 nuclear

    power plants in the country at dierent locations.

    India has made a strong beginning in the eld o

    Nuclear Power. Today it is quite selsucient

    rom technology and resources point o view and

    NPCIL has ambitious plans o achieving 20,000

    MW by 2020, improving rom the current installedcapacity o 4120 MW.

    Overthepastvedecades,ECChasconstructed

    many nuclear-related structures and played

    a major role in this sector. It has the capability

    to construct critical and complex structures or

    Nuclear Power generation. ECC has the distinction

    o making constructive contribution to almost all

    the Nuclear power plants in the country. Some o

    the important projects are Madras Atomic Power

    Project, Kaiga Atomic Power Project, Tarapur

    Atomic Power Project, Rajasthan Atomic Power

    Project and Kudankulam Nuclear Power Project.

    ECC has also been involved in other nuclear

    eld related projects such as heavy water plants,

    nuclear waste management, rare materials project,

    etc alling under the purview o DAE/ BARC. In

    act, ECCs association with DAE started in the

    early 60s, when it was awarded with design and

    construction works or radiological and modular

    laboratories at Trombay.

    ECCs major involvement in nuclear power projects

    started at MAPP in 1970 when it was entrusted with

    the construction o the reactor and turbine buildings

    or MAPP. The contract or civil construction

    included the reactor building with 40m high and

    45m dia structure topped by a dome, sub-structure

    or service building, cooling water system and

    outall structure, demineralisation plant, central

    stores, PHT purication buildings, Fast breeder

    test reactor building, radio-metallurgical & radio-

    chemistry laboratories, active control uel assembly

    building, ree stack (100m) and ventilation stacks

    (75 m & 65 m tall). The reactor wall and dome were

    o prestressed concrete construction requiring

    high accuracy. Another salient eature o MAPP

    is the double containment wall with outer random

    rubble masonry wall to a height o 34 m, which was

    done or the rst time in India. ECC has also been

    involved in design, installation and commissioning

    o 33kV switchyard catering to the entire power

    requirement o the Reactor Research Centre at

    Kalpakkam. Subsequently electrical installations

    or the two research laboratories RCL & MDL

    were done by ECC.

    NPCIL once again demonstrated its condence in

    L&T by awarding the complete civil works or Units

    1 & 2 o Kaiga Atomic Power Project. Kaiga was

    literally a greeneld project necessitating, in many

    cases, even basic inrastructure development. The

    site was a natural bowl-shaped terrain surrounded

    by hills with deep lush green orest and the site

    was accessible in air weather through a orest

    road and access to the site was dicult during

    monsoon till all the access roads were ready.

    ECCs scope o work included construction o

    reactor, turbine, service, control, reactor auxiliary,Induced Drat Cooling Towers at 2 x 210 MW Kaiga Atomic Power Plant (Units 3 & 4)

    L&Ts Track Record

    in Nuclear Power

    C Concord|Jan - Mar 2009 4

  • 8/7/2019 Concord_mar09

    5/48

    Reactor building at Madras Atomic Power Project, Kalpakkam

    diesel generator, spent uel buildings, 140m high

    ventilation stack, area drainage, excavation, area

    grading and miscellaneous structures. During

    execution o main civil works, ECC was awarded

    additional works such as construction o circulating

    water pump houses, saety related pump house,

    re water pump house, de-mineralisation, ltration

    and chlorination plants, make-up water pre-

    treatment acilities, CW Intake structures and

    tunnel, domestic water tank, approach channel

    to intake structures and outdoor & indoor piping

    works.

    Some o the advanced construction methods

    used at Kaiga site included climbing ormwork

    system or prestressed containment walls,

    sliporm or ventilation stack and ormwork or

    other structures. A special ormwork supporting

    structure was designed to support the ormwork

    o inner containment dome o the reactor.

    Construction o Kaiga nuclear power project was

    highly challenging, considering the remoteness o

    the site, unriendly weather conditions and other

    complexities. Despite the hardships, ECC met the

    challenges and successully completed the project

    as per the requirements o NPCIL.

    L&T is proud o its association with NPCIL, which

    has celebrated its Golden Jubilee Year and wishes

    to continue its commitment and contribution or

    the development o Nuclear Power Generation in

    India.

    ECC Concord|Jan - Mar 205

  • 8/7/2019 Concord_mar09

    6/48

    Vol. No. 31 Issue No. 4

    Endeavours

    at TarapurNuclear Power Plant

    B.SundArAmoorthy,Project Manager

    ViShVA mohAn ShriVAStAVA,Planning Engineer

    C Concord|Jan - Mar 2009 6

  • 8/7/2019 Concord_mar09

    7/48

    taap Ac Pwe Sa

    The Tarapur nuclear power station houses two

    200 MW Boiling Water Reactors (BWRs). The new

    series o 540 MWe nuclear reactors are developed

    indegeneously rom 220 MWe Pressurized Heavy

    Water Reactors (PHWR). At present, this power

    station has the largest nuclear power reactor in thecountry. It was commissioned seven months ahead

    o schedule by the Nuclear Power Corporation o

    India.

    BArC isallas, taap

    The Bhabha Atomic Research Centre (BARC) -

    Indias primary nuclear research acility supports

    Indias nuclear power and research programme.

    BARCs installations at Tarapur support the

    operations o Tarapur Atomic Power Station.

    L&ts rle

    L&T has executed the 2 540 MWe at Tarapur

    and was involved in almost all the disciplines o

    engineering o a Nuclear Power Project. L&T

    was involved in main plant civil works, service

    water system, reactor piping, composite chilled

    water and HVAC packages, electrical works and

    instrumentation works which demonstrated the

    capability o L&T in broad spectrum engineering

    construction. The heavy engineering division o

    L&T had supplied the calandria, steam genertaors

    while the Engineering & Construction division

    supplied the Primary Steam Piping system. ECC

    involved in the mechanical erection o these

    structures.

    The scope o main civil works package covered

    construction o reactor, service, station auxiliary,

    reactor auxiliary, control buildings, pipe & cable

    bridges, ventilation stack, potable water tank,

    roads, site grading, abrication & structural steel

    erection, EPs and other miscellaneous structures.

    The gestation period or nuclear power projects

    today is considerably reduced by commissioning

    TAPP 3 & 4 in 60 months. This is an international

    benchmark achievement. At TAPP 3&4, the

    challenge o completing the total project in 60

    months was achieved by deploying innovative

    construction methods. Some o them include

    pumping o heavy concrete, casting o 7m

    high columns in single lit, use o sel climbing

    ormwork or inner containment wall, casting o 3.5

    mhighwallforOCwall,prefabricationofcalandria

    vault liner, use o threaded coupler or reducing

    reinorcement congestion and wastage, easy

    handling etc.

    Design, procurement and construction o service

    water system, composite chilled water and

    HVAC packages include supply o some critical

    equipment such as vertical turbine pumps to work

    View o Tarapur Atomic Power Project during construction

    ECC Concord|Jan - Mar 207

  • 8/7/2019 Concord_mar09

    8/48

    Vol. No. 31 Issue No. 4

    in sub-marine environment, 3050 TR capacity

    centralized chillers and 60 lakh CMH capacity

    ventilation system.

    The primary piping package executed by ECC(in association with E&C division o L&T) at TAPP

    3&4 is meant or nuclear steam supply system

    (NSSS) which consists o reactor assembly, the

    moderator system and the primary heat transer

    system. The reactor assembly system is the

    most important part o NSSS and it consists o

    calandria, end shields, calandria tubes, coolant

    tubes, end ttings, uel bundles and reactivity

    control devices. The abrication and erection o

    primary piping system is to be carried out in dust

    ree environment. Extreme care need to be takenor maintaining clean room conditions not only in

    the abrication stage, but also during erection.

    The order or electrical and instrumentation works

    is probably the single largest order awarded to

    any contractor by NPCIL. These packages involve

    design, manuacture, supply, erection, testing and

    commissioning o various critical electrical and

    eld instrumentation items required or a nuclear

    power plant.

    Aal Wase tak F (AWtF)

    ie descpo u toal Qy

    Excavation cu.m 15695

    Concrete cu.m 17168

    Rebar abrication t 2150

    Formwork sq.m 24770

    Fabrication & erection o inserts and

    structural works - Stainless Steel t 123

    Fabrication & erection o inserts and

    structuralworks-CS t 84

    Fabrication & installation o SS 304L liners sq.m 2900

    Supply and installation o ventilation system cu.m / hr. 215000

    Fabricationandinstal lationof300cu.mSS304Ltanks Nos 08

    Fabrication o SS piping ID 13000

    Erection o SS piping IM 11000

    Unit 3 & 4 o Tarapur Atomic Power Project, ater completion

    C Concord|Jan - Mar 2009 8

  • 8/7/2019 Concord_mar09

    9/48

  • 8/7/2019 Concord_mar09

    10/48

    Vol. No. 31 Issue No. 4

    shielded vaults (V-1 and V-2) with 4 tanks each

    andtwocells(Cell-IandCell-O)accommodating

    the in-routing, out-routing and sump tanks. Each

    sub-vault has a sump in the vault rat. Necessary

    sloping was provided in each sub vault with a

    channel. The foors at all sub-vaults and its walls

    up to height o 1.5m are lined with 5 mm SS 304L

    plates.

    In between the two corridors above the vaults,

    rooms or sampling blisters and transmitter rooms

    are accommodated. The corridors also house

    the embedment or the services and utilities like

    headers, valves, instrument racks, cables or

    taking samples remotely and to open the vault

    entry. A monorail (10 t capacity) was provided in

    each corridor or liting the plug o the vaults to

    enable service inspection.

    AWtF Aex Blg

    The service building, known as the AWTF Annex

    is a two foor building. Vault exhaust an room,

    ventilation air supply an room, electrical room and

    change room are housed in the rst foor. Second

    foor accommodates control room or monitoring

    and carrying out the operations o the AWTF, waste

    cooling water room, waste o-gas equipment and

    blower room.

    Spe Fel Sage Facl (SFSF)

    SFSF was constructed to receive and store the

    spent uel rom nuclear power plants under water

    beore sending it or urther processing.

    The SFSF project demanded partially underground,

    high perormance concrete structures (lined with

    stainless steel plates) meant to store the spent

    uel discharged rom the Nuclear Power Reactors.

    SFSF is lled with de-mineralised water, supported

    by water-polishing system and a water-cooling

    system.

    The scope o work covers constructing and

    installing all associated utilities like inltration

    gallery, DM water plant, pool water polishing

    system, cooling water system including cooling

    towers, material handling system including

    10 & 75-t EOT cranes, 2-t pool bridge crane,

    re protection and alarm system, electrical and

    instrumentation and control panels, air conditioning

    and ventilation system.

    Spe Fel Soage Facly (SFSF)

    ie descpo u toal Qy

    Excavation cu.m 39365

    Concrete cu.m 9475

    Rebarfabrication t 1892

    Formwork sq.m 27026

    Waterproong (Terrace) sq.m 3390

    Fabrication and installation o SS 304L liners t 62

    Supply and installation o ventilation system cu.m/hr. 235000

    Supplyandinstallationof75/5tEOTCrane Nos 01

    Supplyandinstallationof10tEOTCrane Nos 01

    Supply and installation o 2-t pool bridge crane Nos 01

    Supply and installation o DM water plant Nos 01

    Supply and installation o pool water polishing unit Nos 01

    Fabrication o tanks and vessels Nos 6

    EOT crane at Spent Fuel Storage Facility

    C Concord|Jan - Mar 2009 10

  • 8/7/2019 Concord_mar09

    11/48

    SFSF pl blg ses

    vehicleairlocks

    caskdecontamination/storagearea

    EOTcranes,poolbridgeandhoists

    undergroundfuelpool

    spentfueltransferbayalongwithunderground

    duct to nearby reprocessing plant or hydraulic

    transer o uel bundles as per the requirement

    o BARC

    leak detection and collection facility for fuel

    pool

    poolwaterpolishingunit

    domesticwatertank

    approachroadfortrailerandtruckmovement

    localcontrolpanels

    The SFSF pool building extension houses pumps

    or water cooling system and polishing; ventilation

    system in an exhaust an room; disposal system

    or regenerate efuent (underground RCC tank

    with pump and piping) and stack or exhaust

    vent. The utility building houses air conditioning

    and ventilation system; DM water plant; electrical

    substation; change room, rooms or monitoring,

    aircompressor,controlandlaboratory.Otherareas

    A view o Polishing Unit o Spent Fuel Storage Facility

    include low level efuent storage and pumping

    acility, de-mineralised water storage tanks (atop

    uel pool building) and security and access control

    system. The administrative oce area has a good

    training and conerence room with all gadgets.

    Excellent quality ratings are achieved in this project,

    which enabled it to bag ECC Quality Trophy.

    DM plant at

    Spent FuelStorage Facility

    ECC Concord|Jan - Mar 2011

  • 8/7/2019 Concord_mar09

    12/48

    Vol. No. 31 Issue No. 4

    The main objective o the test model is to nd out

    the behaviour o the Nuclear reactors containment

    structure under extreme pressure conditions. The

    model is pressurized three times more than the

    actual design pressure o the Nuclear Reactor.

    The model is also tested to establish and check

    the design parameters o the actual containment

    structures and to get better understanding o

    structural behaviour o the containment structure

    or uture.

    tes mel a taap

    The pre-stressed concrete containment test model

    is scaled down to represent the actual Pressurised

    Heavy Water Reactor o Tarapur Atomic Power

    station 3 & 4 at Tarapur, to a actor o 1:4. This

    model is constructed at Tarapur close to the

    existing BARC acilities.

    Contented by the perormance o L&T in Tarapur

    Atomic Power Project 3&4, NPCIL invited L&T to

    construct the model on nomination basis.

    Ater the construction o the model, the same will

    be subjected to a pressure, which is approximately

    4.5 to 6 kg/sq.cm or even higher. However, the

    actual ailure pressure will be established ater

    testing. In any case, it is expected that there will

    be nominal leakage at 5 kg/sq.cm.

    Sale eaes

    All the components o the actual reactor is scaled

    down to 1:4 including pre-stressing, critical

    openings etc.

    ra

    The inner containment wall is supported on a rat

    having dimensions o:

    Diameter-15.60mand Depthof3m

    Stressinggalleryofsize1500mmx1800mm

    below the inner containment structure with 4

    access shats

    ie Cae wall

    Thickness-188mm

    Heightofthewall-12.475maboveraft

    Constructedusing9lifts

    TheinnerdiameterofICwallis12.40m

    rg Bea

    Heightofringbeamis1.2m

    Averagethicknessis450mm

    ICwall,ringbeamanddomearedesignedas

    monolithic structures

    nclea reac Cae

    tes mel 1:4 Scale Pe-sesseCcee Cae

    B.SundArAmoorthy,Project Manager

    Completed view o the test model. Right: Sectional view

    C Concord|Jan - Mar 2009 12

  • 8/7/2019 Concord_mar09

    13/48

    ie Cae de (iC de)

    The IC dome starts at 13.706 m height and springs

    up to the crown 15.750m.

    AveragethicknessofICdomeis164mm

    Centre line diameter of the IC dome is

    19.60 m

    Two radial Steam Generator (SG) openings

    o diameter 1.35m at the centre line are

    provided in the IC dome to simulate the Steam

    Generator openings o the prototype

    Inner containment dome was cast in single

    pour

    Sess

    To monitor the response during prestressing o

    containment and dome, ollowing sensors were

    used:

    727 sensors were installed in concrete

    rom rat to crown o the dome at

    pre-determined locations

    89sensorswereinstalledonHTstrandsand

    stressing was analysed

    Dierent type o sensors used in test containment

    included:

    Embedded type of Vibrating Wire Strain

    Gauge(VWSG)

    PastableSMER10mm

    Spotweldable51mm,Weldable203mmand

    Earthpressurecell

    Weldable type o sensors were installed on

    reinorcement bars whereas embedded type in

    concrete.

    Pe-sessg

    Inner containment wall and dome was subjected

    to prestressing using prestressing system 1T15.

    This involved:

    Totalnumberof 313cables, comprisingof

    JO&JI,VerticalandHorizontalcables.

    15.2mmdiameterhightensilestrandforpre-

    stressing works

    HDPEsheathingof25mm-OD/20mm-ID.

    Maximum load applied on HT strands was

    21.20 t on each cable and

    Sheathing was cement grouted with

    temperature controlled cement grout

    Csc Js-Fk Sse

    Construction joints in the dome and the inner

    containment wall were sealed using Fuko system

    i.e. Re-injectable grouting system with injection o

    hydro swelling, water based, low viscous, thermo-

    setting resin. This is done ater construction to

    make the joint leak tight or air and water.

    Calleges

    te wk vlve seveal calleges lke:

    Placement of reinforcement, HDPE sheaths

    and tube units, due to congestion in scaled

    down thickness o walls and dome having

    stringent tolerances o +/- 3 mm.

    Installationandprotection of 727sensorsin

    IC wall and dome during preparation o pours

    and concreting were tough tasks

    Utmost care was taken during installation

    and 99% o sensors are unctioning well even

    today.

    Installationof instruments in wall anddome

    due toslender section i.e. 188 mmthickof

    wall and 164 mm thick o dome.

    Formwork

    - Nuts were not allowed through ties and coil

    - Slender sections

    - Complicated tailor made ormwork system

    was used with preabricated C shaped MS

    rames

    Difculty in mounting large number of

    instruments in limited space around openings

    o Airlock Barrels.

    Eorts required or the construction o the test

    model involved same amount o work or more

    than that required or the proto-type due to the

    limitation in scaled down dimensions.

    heal Sae aEve

    Regular training and orientation programs or

    workmen were conducted to keep them alert at all

    times.

    Projecthasachievedzeroaccident

    Achieved1.4millionsafeman-hours

    The project was successully completed in

    December 2008 to the fullest satisfaction of the

    client.

    ECC Concord|Jan - Mar 2013

  • 8/7/2019 Concord_mar09

    14/48

    Vol. No. 31 Issue No. 4

    Indias rst 2 1000 MWe Nuclear power plant

    is coming up at Kudankulam. The project is

    located on the shores o Gul o Mannar, on the

    Southeastern tip o India near Kanyakumari. It is

    located at Radhapuram taluk o Tirunelveli district

    in Tamilnadu state.

    The site experiences a tropical climate with

    humidity ranging rom 40% to 90% depending on

    the season and is subjected mainly to the winter

    monsoonduringthemonthsofOctober,November

    and December.

    The Kudankulam Nuclear Power Project (KKNPP)

    consists o two units o 1000 MWe with two steam

    driven turbo generators supplied with turbine

    steam rom two pressurized water VVER type

    reactors o Russian design. The design o various

    equipment, systems and structures are carried out

    in accordance with Russian and other International

    Standards.

    The entire project capacity o 2000 MWe (2 x 1000

    MWe) o power will be supplied to three southern

    states (Tamil Nadu, Karnataka and Kerala) and the

    Union Territory o Pondicherry. NPCIL has divided

    the whole project into number o packages and

    awarded to dierent contractors. The whole project

    cost is about Rs. 13,000 cr.

    Packages

    L&T has been awarded M2, M4, M5, C5 and E1

    packages directly by NPCIL. M3 and I1 have been

    awarded to L&T by BHEL & ECIL.

    mecacal:

    Erection of Nuclear Steam Supply System

    (NSSS)and auxiliary systems (equipment,

    piping & tubing works) - M2 Package

    Seawater system (equipment & piping

    erection) - M4 Package

    Common service (piping & equipment

    erection) - M5 Package

    Erectionofturbine-M3Package

    Cvl:Radioactive waste processing and storage

    buildings - C5 Package

    Eleccal: Erection o electrical equipment andsystems - E1 Package

    teccal Aspecs

    Kudankulam Reactors are Water-cooled Water

    moderated Energy Reactor (VVER-1000) o

    Pressurized Water Reactor (PWR) technology,

    which is worldwide proven concept. VVER-1000

    reactors are the most advanced reactors

    similar to the PWRs o western design. Nuclear

    uel is charged into the reactor where the ssion

    takes place and the heat is liberated. The

    liberated heat in the reactor is carried away by the

    light water rom the reactor to steam generator

    by the main coolant pump. De Mineralized

    (DM) water acts as reactor coolant. The coolant

    water is used in the steam generators to produce

    steam. The steam is allowed to pass through

    turbine blades with high pressure and velocity.

    The turbine then rotates receiving the kinetic

    energy o the steam. The generator, which is

    mechanically, coupled to the turbine also rotates

    and generates power. The back steam o the

    turbine is allowed to pass through the surace

    type condensers. The condenser will be having

    tubes through which sea water is allowed

    to fow and over which the steam fows. The

    sea water absorbs the heat rom the steam and

    condenses the back steam. The condensate is

    recycled back to steam generator. The sea water

    ater absorbing the heat rom the back steam

    is discharged into sea and resh water is drawn

    through inlet.

    n.P. VArAdhArAJAn & r. BALASuBrAmAniAn, Project Managers

    Kudankulam Nuclear

    Power ProjectA.u. rAo

    Planning Manager

    C Concord|Jan - Mar 2009 14

  • 8/7/2019 Concord_mar09

    15/48

    mecacal wks ias Lages nclea

    Pwe Pla

    Larsen & Toubro has won all major mechanical

    erection and installation. This includes our

    mechanical packages and two electrical and

    instrumentation packages.

    The scope o work in M2 package include handling,

    transportation, pre-abrication, welding, erection,

    inspection & testing o piping, instrument tubing

    and erection o associated equipment along with

    accessories or nuclear steam supply systems and

    nuclear auxiliary systems or Unit 1 & 2. This main

    mechanical package involves heavy erection o

    critical nuclear equipment like Reactor Pressure

    Vessel, Steam Generators, Reactor Cooling

    Pumps, associated piping in reactor and auxiliary

    buildings, various saety systems like boron

    injection system, passive heat removal system

    and containment sprinkler system.

    Eec a alge

    nSSS Eqpe

    In this M2 package, reactor equipment (2 x 316 t

    each) was erected in our stages. Being a nuclear

    project, high degree tolerances limit (0.01mm) was

    maintained. Another challenge during the erection

    was the clearance between the inner diameter o

    support structure and outer diameter o Reactor

    Pressure Vessel (RPV), which is only 10 mm and

    large volume o blue matching.

    SteamGenerator(8x307teach)waserectedina

    conned space with the alignment in the range o

    0.4 mm to 0.5 mm.

    Pressurizer (2 x 222 t each) was also erected in

    conned walls with the tolerance of 8mm w.r.t

    containment wall and alignment in the range o

    0.4 mm to 0.5 mm.

    All the above erections were executed using highly

    precision optical tooling survey instruments viz.,

    Jig Transit.

    MainCoolantPiping(64Jointsof990mmOD)

    designed or a pressure o 176 kg/cm2 and

    temperature o 320C has our quadrants. It

    is connected to reactor pressure vessel (RPV)

    assembly, steam generator (SG) and reactor

    coolant pump (RCP). The piping is used to re-

    circulate the primary coolant thereby removing

    heat rom reactor and transer the same to steam

    generator.

    Pipes are made out o low alloy steel having outside diameter o 990mm and 70mm wall thickness,

    cladded inside with austenitic stainless steel. The

    total circuit involves 32 weld joints per unit and

    the total weight o piping is about 260 t. The pipes

    were supplied in pre abricated piping spool. For

    the rst time in India, a unique and sophisticated

    welding method was adopted or Main Coolant

    piping at a nuclear power plant. Controlled and

    Induction Heating technique was adopted or the

    rst time in India during the welding operation with

    Erection o ReactorPressure Vessel in

    progress

    ECC Concord|Jan - Mar 2015

  • 8/7/2019 Concord_mar09

    16/48

    Vol. No. 31 Issue No. 4

    hot temperature radiography o weld joint at 200

    deg centigrade using special xtures and source

    protection measures.

    te Scpe wk vlve

    ReactorEquipment-13,125t

    StationaryEquipment-3,036t

    RotaryEquipment-652t

    Piping(SS/CS)-3,100t

    SS/CSValves-1,180t

    InstrumentTubing-CS/SS-1,60,920m

    TubeWelding-CS/SS-9,000Nos.

    tbe Eec

    M3 Package work involves handling at site store/

    storage yard, transportation to site o work, erection

    testing and commissioning o turbine generator,

    eed pumps, piping and its auxiliaries.

    AlignmentoftheturbinewasdoneusingOptical

    Aligning instrument and Fronius was adopted or

    orbital welding.

    Sea Wae Sse

    M4 Package work covers handling, transportation,

    pre-abrication, welding, erection, inspection,

    testing and painting o sea water systems

    equipment and piping in Sea Water Pump house

    and Chlorination plant. The main work in this

    package include works in pump house like EP

    abrication and erection, anti corrosive painting,

    erection o gates and screens, GRP piping, vertical

    pump erection. chlorination building works and

    tunnel piping. Again, using or the rst time in

    India, Coupon Hycote paints was used or the

    internal painting o sea water pipes.

    Rotatingequipment 1,432t

    Stationaryequipment 1,465t

    CSpiping 2,108t

    SSpiping 8t

    Glassreinforcementpiping 35t

    Titaniumpiping 16.5t

    Excavationandbacklling 56,000cu.m

    Structuralsteel 500t

    Coldinsulation 1,183sq.m

    Anti-corrosivepainting 55,683sq.m

    Coatingandwrapping 4,000sq.m

    Gritblastingandpainting 9,000sq.m

    C Sevce Sse

    The scope o work M5 Package covers handling,

    transportation, pre-abrication, welding, erection,

    inspection, testing o indoor and outdoor piping

    and equipment o common service systems.

    This consists o all indoor and outdoors piping,which includes HDPE piping or portable water,

    re-ghting system (SGA, SGC, SGE), buried

    piping (coating and wrapping included), boiler

    associated works, DM plant associated tanks and

    piping, and all nuclear ancillary building piping

    and equipment.

    Rotatingequipment-450t

    Stationaryequipment-2,612t

    CSpiping-2,452t

    SSpiping-405t CIpiping-65t

    HDPEpiping-150t

    ACpiping-255t

    RCCpiping-900t

    Excavationandbacklling-238000cu.m

    Coatingandwrapping-7,000sq.m

    Supply,fabricationanderectionofstructural

    steel - 500 t

    Piping or Passive Heat Removal System

    C Concord|Jan - Mar 2009 16

  • 8/7/2019 Concord_mar09

    17/48

    The 1000MWe turbine, rst o its kind is a steam

    condensing, our cylinder conguration (1 HPC +

    3 LPC) with intermediate moisture separation and

    steam reheat, with rotational speed o 50 s-1 (3000

    rpm), designed to drive directly an alternating

    current generator, mounted on a joint oundation

    with the turbine. The total length o turbine with

    out generator is about 40.65m. The turbine is

    provided with throttling steam admission. The

    steam rom steam generator is supplied to 4

    HP valve blocks each HP valve block consist o

    one stop valve and one governing valve through

    which the steam enters the HP cylinder.

    HP rotor is an integrally orged rotor. LP rotors

    are also integrally orged rotors (blade lengthis 1200mm). All rotors are provided with rigid

    coupling and supported by two journal bearings.

    The thrust bearing, mounted between HP cylinder

    and LPC 1 serves as a xed point or the rotor.

    The steam from 4th stage of each LPC is

    extracted by 3 LP heaters 1.

    Thesteam from 3rdstage of LPC2 &3 is

    extracted by LP heater 2.

    The steam from 2nd stage of LPC 1 is

    extracted by LP heater 3.

    HPCturbineisofdoubleowcylinderhaving

    5 stages in each fow.

    The steam is extracted from second, third

    and ourth stages o each fow or eed water

    heating by HP heater 5,6 and deaerator

    respectively.

    FromHPCexhauststeamisextractedbyLP

    heater 4.

    The steam from exhaust of HPC enters

    moisture separator reheater.

    AfterseparatorreheaterthesteamentersLP

    cylinder through LP valve blocks which consist

    o 1 stop valve and 1 governing valve.

    LPCturbinearedoubleowcylindershaving

    5 stages in each fow.

    MassofheaviestpartofturbineisLProtor

    -80.5t Massofturbine-1800t

    Sale Feaes tbe

    Qa wk

    Turbine 4,028t

    Generator 1,297 t

    Condenser 2,609 t

    Feedpump drive Turbine & Aux 402 t

    Feedpumps 169 tCondensate Pumps 257 t

    CrossoverPipes 283t

    OtherAuxiliaryEquipment 200t

    OtherPiping 12t

    Two views o Stator (345 t) during erection or 1000 MWe Turbine Generator at Unit #2

    ECC Concord|Jan - Mar 2017

  • 8/7/2019 Concord_mar09

    18/48

    Vol. No. 31 Issue No. 4

    Insulation-6,000sq.m

    Supplyandxingofhiltybolt-1,000Nos.

    Wellerection-824Nos.

    Sae

    Saety system practiced at the project site is

    extremely stringent as it involves several heavy

    lits, erection o critical equipment, hot processes

    and working in severe conditions like tunnel and

    conned space. L&Ts team religiously ollows the

    saety norms as per the requirement o the Atomic

    Energy Regulatory Board (AERB). L&T has been

    awarded the Project Directors rolling trophy or

    Best House Keeping by the client.

    All the pre-commissioning and commissioning

    activities were meticulously planned and

    implemented successully. All the erection

    sequences and procedures were documented

    in 175 volumes. These dierent packages are

    progressing well, meeting the quality standards

    set by Russian authorities.

    Apart rom Mechanical packages Instrument

    tubing works in reactor building also in L&Ts

    scope which involves 160 km tubing works.

    Eleccal Scpe

    E1 Package - teccal Aspecs

    MainPoweroutputsystem

    Auxiliarypowersupplysystem

    Classicationofauxiliarypowersupplies GIS

    Systemgrounding

    ipa eaes e pla

    First21000MWepowerplantinIndiaunder

    construction with single transormer unit o

    capacity 417 MVA

    First time in India having 4200m length of

    400kV GIBD

    Fully inside lined reactor containment, a rst

    time eature in India.

    SG Pressuriser

    erection in progress

    Turbine erection

    C Concord|Jan - Mar 2009 18

  • 8/7/2019 Concord_mar09

    19/48

    The tender specications covered electrical

    system installation in all the buildings o KKNPP

    unit 1 & 2 such as 400kV GIS building, switchyard

    control room building, transormer yards, normal

    operation power supply building, common station

    power supply building, emergency power supply

    buildings and other main plant buildings such

    as reactor building, turbine building, reactor

    auxiliary building, pump house etc. as well as

    supply o some electrical equipments, hardware,

    accessories required or the installation works.

    Sse descp

    The electrical system or the two units o

    Kudankulam nuclear power plant, each o 1000

    MW, mainly consists o power output system and

    auxiliary power supply system. The power output

    system is designed or evacuation o powergenerated at NPP. The auxiliary power system

    provides the power to NPP auxiliaries to carry out

    their assigned unctions, in all operating modes o

    NPP.

    Pwe op Sse

    The electrical power generated by the turbine

    generators at 24 kV, three phase and 50Hz is

    stepped up to 400 kV by the generator transormer

    and is evacuated through our 400 kV transmission

    lines. For reserve source o power to auxiliaries oNPP, Kudankulam NPP is connected to Tuticorn,

    SR Pudur and Kayathar through 230 kV lines.

    400 kV and 230 kV lines are connected through

    interconnecting transormers. 400 kV and 230 kV

    switchgear are o SF6 gas insulated considering

    the saline atmosphere at Kudankulam site. 400 kV

    is designed as one and hal bus scheme. 230 kV is

    designed as two main bus schemes.

    Major components o the power output system or

    KKNPP include:

    24kV1000MWgenerator

    24kV31.5KAIsolatedPhaseBusduct(IPDB)

    24kV28KAgeneratorcircuitbreaker(GCB)

    3X417MVA,24/400kVgeneratortransformer

    (GT)

    400kV2000Agasinsulatedbusduct(GIDB)

    400kVgasinsulatedswitchgear(GIS)

    400kVtransmissionlines

    315 MVA, 400 kV /230 kV interconnecting

    transormer (ICT)

    230kVgasinsulatedswitchgear(GIS)

    230kVtransmissionlines

    1phase26.7MVAshuntreactors(6nos)

    Axla Pwe Sppl Sse

    The main unction o the auxiliary power system is to

    ensure the availability o sucient power supply to

    the auxiliary system equipments during all modes

    o plant operation i.e. normal plant operation,

    shutting down the reactor, maintaining the reactor

    in sae shut-down state, containment isolation,

    reactor core cooling, preventing signicant release

    o radioactive material to the environment and any

    other necessary unctions.

    For start up as well as or normal shutdown o bothunits o plant, station auxiliary power is drawn rom

    the 400kV network through generator transormer

    and unit auxiliary transormers with the GCB

    open.

    During normal plant operation, station auxiliary

    power is drawn rom the main generator rom the

    tap-o to 24kV bus duct through the UATS.

    The reserve power supply is derived rom 230kV

    grid through 230/6.3-6.3kV RATS and is used as

    backup power during non-availability o powersupply rom UATS.

    The common station auxiliary power supply eeding

    the common station auxiliary loads is derived rom

    230kV grid through 230kV/6.3-6.3kV CSATS and is

    backed up by the RATS.

    The systemmainly consists of 6kV, 0.38kV and

    220 V DC power supply sources to supply to

    unit auxiliary loads and common station auxiliary

    loads.

    Auxiliary power supply system envisaged orKKNPP is categorized as per their unctional

    requirements detailed below.

    Normal auxiliary power supply for each unit

    system including common station auxiliary

    supply system or the plant.

    Reliable auxiliary power supply of normal

    operation or each plant.

    Emergency auxiliary power supplies system

    or saety systems or each unit.

    ECC Concord|Jan - Mar 2019

  • 8/7/2019 Concord_mar09

    20/48

    Vol. No. 31 Issue No. 4

    Eleccal Wks

    isalla, esg a pecssg

    Description QTY UOM

    24KV,2800ASF6GeneratorCircuitBreaker 2 Nos

    420/24 KV 417MVAGenerator Transormer 7 Nos

    24KV 31500A single phase Isolated Phase Bus Duct 1120 m

    315MVA 400/230/33kV interconnecting transormer 2 Nos

    63/31.5-31.5MVA, 24/6.3/6.3kV UAT/RAT/CSAT 9 Nos

    27MVA 420kV Single phase Shunt reactors 6 Nos

    400kV 3150/2000A Single phase SF6 bus duct 4200 m

    230kV, 2000A single phase SF6 bus duct 900 m

    6kV 6.3MW Diesel Generator Sets 10 sets

    6kV 3150A Isolated phase bus duct 2400 m

    6kV 3150/1600A Switchgear Panel 522 Nos

    6kV/0.4kV 1000KVA/400KVA Dry Type Aux.

    Transormer 107 Nos

    0.38kVMCCSingleFrontPanel 444 Nos

    0.38kVMCCDoubleFrontPanel 668 Nos

    CableTray&Supports 1860 t

    Cables 7800 km

    HT & LT Termination 129000 Nos

    LightFittings 21285 Nos

    Sppl, eec, esg a cssg

    Line Protection Panels 7 Sets

    Lighting /Power Distribution Board 672 Nos

    Light Fittings 7331 Nos

    GI Conduits 344 km

    650/1100VFRLSPVCWire 800 km

    Classfca o Axla Pwe Spples

    Depending on the degree o reliability or

    requirement o saety, the power supplies are

    classied into three groups

    Gp-1: loads that require uninterruptible power

    supply are kept in group-1 class. These can be

    interruptible but not more than 20 seconds.

    These are supplied from 220 V DC, 380 V and

    220 V AC power supplies normally derived rom

    group-3 or group-2 power supply sources and

    whose back up source o power is rom the battery

    banks.

    The major components o auxiliary power supply

    system are given as below.

    63MVA,24/6.3-6.3kVUAT

    63MVA,230/6.3-6.3kVRATS

    230/6.3-6.3kVCSAT

    6.3MW,6kVDG

    6kVswitchgear

    1000 kVa & 400kVa, 6/0.4kV and 6/0.433kV

    auxiliary transormers

    0.38kVand0.415kVswitchgear/MCCs

    Rectiers

    220VDC&110VDCbatteries

    Inverters

    220VDCdistributionboards

    220V/380VACdistributionboards

    110VDCdistributionboards

    Cabling

    Cablepenetrations

    Gp-2: AC supply to the loads, which can

    tolerate short interruption or a time dened by

    the conditions without eecting saety o the

    reactor, under all modes o the plant, including the

    condition o loss o supply rom all o-site sources,

    is called the group-2 loads.

    6.6 kV control replay panels

    C Concord|Jan - Mar 2009 20

  • 8/7/2019 Concord_mar09

    21/48

    These are supplied from 6kV, 380V and 220 V

    AC, 50Hz supplies normally derived rom group-3

    power supply and whose back up source o power

    is rom DG sets.

    Gp-3: power supply to the plant auxiliary

    loads normally required under all modes o plant

    but which can tolerate prolonged interruption inthe power supply, without aecting the saety o

    the plant, and do not require obligatory availability

    o power supply even ater the actuation o the

    reactor trip system is called the group-3 power

    supply.

    Thesearefedfrom6kV,380Vand220VAC,50Hz

    supply derived rom UATS, RATS or CSAT.

    Pcples Cl, mg a

    rela Pec Sse

    During operation, a system is understood as a

    set o devices o relay protection, control and

    monitoring o the electrical equipment, structurally

    and unctionally involved. At KudanKulam NPP,

    independent system o control, monitoring and

    relay protection system are provided or many o

    the systems.

    Gas islae Sbsa

    Here switchgear apparatus or 220kV and 400kV

    equipment use the SF6 as dielectric media due tomany o its advantages.

    Though SF6 was developed in 1900, it was

    used as dielectric medium only ater 1940

    Itisapowerfuldielectricmedium

    Itsdielectricstrengthis2.35timestothatofair

    Itis5timesheavierthanair

    Itisnon-toxicinpureform

    Its dielectric strength is proportional to the

    pressure that it operates

    ThisiswellsuitedforHVswitchgearsandGIS.

    The gas passing through the isolated bus duct acts

    as a powerul insulation media and this compacts

    the size o the switchgear.

    Gg a Lgg Pec

    To achieve the requirements, a grid consisting o

    70 sq.mm tinned stranded copper conductor has

    been laid by the civil contractors at a depth o not

    less than 0.5 m below the oundation, with a mesh

    size o 25m 25m in the outdoor area and about

    6m 6m mesh size beneath the buildings. GI

    earthing conductors run to walls and foors inside

    the buildings, which orm the main grounding lines

    are connected to the buried copper conductors.

    All the metal components inside the building are

    connected to the grounding network.

    Lightning protection conductors in a mesh

    ormation are provided over the building surace,

    along outer perimeter walls and on the roo and

    are connected to the grounding grid. Lightning

    arresters are installed on the stack top.

    isea

    I1 package involves executing the entire

    instrumentation work under the supervision o ECIL.

    Scope o work includes calibration and installation

    of 18,000 instruments such as Pressure, Flow

    and Level transmitters, RTD and Thermo couples,

    Pressure and Temperature gauges, Analytical

    instruments, Level sensors, Seismic sensors and

    Radiation monitors, Installation o 3000 instrument

    support stands, abrication and erection o 200 tsteel, 50 km o GI perorated tray or eld routing

    and 176 km o cable laying and glanding work

    Cvl Wks

    C5 package involves 65000 cu.m o concreting

    works to construct De-Mineralized Plant (DM Plant),

    Boiler House, Solid radioactive waste building,

    Chiller units building, Compressor building and

    Diesel storage pump House including NPCILs

    Main Administration Building.

    220 kV gas insulated

    substation

    ECC Concord|Jan - Mar 2021

  • 8/7/2019 Concord_mar09

    22/48

    Vol. No. 31 Issue No. 4

    PREFRE-3A ProjectF BArC Kalpakka

    L&T-ECC is in the verge o completing, the

    procurement, construction contract o civil

    structure incl. 75 M High RCC stack and electrication

    work or PREFRE-3A project (Power Reactor Fuel

    Recycling) in the phase II or BARCs premises at

    Kalpakkam on the Chennai Puducherry coastal

    highway. Valued at Rs.65 Crore, the scope o work

    are as ollows :

    Excavation - 67500cu.m

    Reinforcement - 5400t

    Concrete - 27740cu.m

    Formwork - 90290sq.m

    Brickwork - 3160cu.m

    Plastering - 50000sq.m

    Painting - 75311sq.m

    Site team has received appreciation letter or

    achieving 4 million sae man hours. And has got

    excellent customer relation ship, TCE Consulting

    Engineers are the consultants or this project. Work

    commenced in August 2005 and expected to becompleted by May09 in all respect.

    These civil structure and electrical works are used

    or Nuclear uel recycling received rom designated

    Nuclear plants in India.

    PREFRE-3A Facility is being developed as an

    expansion to the existing KARP-(Kalpakkam Atomic

    Recyclingplant)onthesouthside.Oncompletion

    the newly constructed structures will be merged

    with KARP or enhance the recycling capacity.

    The very objective o Recycling programme is to

    get to recover materials like Plutonium ,etc in the

    process to reuse in non conventional nuclear Power

    generation programme like FBR (Fast Breeder

    Reactor).

    L&TECC Division is engaged in construction works

    at Madras Atomic power station (MAPS) Kalpakkam

    rom 70s and has the credit o constructing 40m

    high and 45m dia dome reactor, turbine buildings,

    100m, 75m & 65m RCC stacks or NPCIL.

    Scope coss of as ay as 14 sces a e eals ae as follows:

    nae of sces deso reaks

    High block 60 x 30 x 25 m high 4 storey mainstructures o the plant

    Low Block 60 x 26 x 20 m high 4 storey buildingInter mediate Traner acility 24 x 24 x 10 m high 6m substructure and 3 foors

    constructed using 19 Ctemp. concrete

    75m high RCC stack 75 m high x 3.6 m dia Ventilation stack

    Delay tank 24 x 30 x 6 m below RCC tank o sevenchambers below GL.19 C concrete

    Substation C 30 x 24 x 10 m high 2 storey structure

    ExhaustFanmainplant 50x18x10mhigh 2storeystructure

    Exhaust control Room 19 x 17 x 10 m high 2 storey structure

    Connecting corridor 25 x 6 x 25 m high 5 storey structure

    Fuel Handling Area extn. 21 x 6 x 7 m high

    RCCVentilationDuct 60mlong2X2mbox

    CompressorHouse 18x12x7m

    Bolier House 15 x 16 x 7 m

    FOST(Fueloilstoragetank) 13x11m

    h.m. BhAdri

    Project Manager

    Construction in progress at one o the blocks

    C Concord|Jan - Mar 2009 22

  • 8/7/2019 Concord_mar09

    23/48

    to utilize indigenous capabilities or the Turnkey

    Construction o nuclear power plants including

    supply o reactor equipment and systems,

    valves, electrical & instrumentation products and

    abrication o structural, piping and equipment

    modules or the Westinghouse AP 1000 plants.

    Asexp

    For Nuclear Power Reactors, L&T and

    Atomstroyexport (ASE) o Russia have signed a

    MoU or co-operation between the two companies

    or Russian design reactors VVER 1000.

    The MoU will orm the basis o co-operation

    between the companies and address needs

    or equipment & other services arising rom the

    agreement signed between India & Russia on 5th

    December2008,forfouradditionalreactorsKK3-6

    at Kudankulam, Tamil Nadu and other Russian

    reactors at new sites in India.

    L&T is the only Indian company to be accredited by

    ASME (American Society o Mechanical Engineers)

    to use its N and NPT stamps or critical nuclear

    reactor equipment. L&T played an important role

    in construction, piping & erection services or the

    KK1-2 VVERs at Kudankulam.

    According to the signed document L&T and ASE

    will develop co-operation in the construction o

    Kudankulam new power units, as well as during

    construction o plants under the Russian designs

    with VVER reactors at new sites in India, and alsoin other countries.

    This MoU with ASE represents a major step or L&T

    into VVER component & systems manuacturing &

    services. It will enable L&T as well as ASE to utilize

    indigenous capabilities or nuclear power plants

    including supply o equipment and systems,

    valves, electrical & instrumentation products and

    abrication o structural and piping and construction

    or the Russian VVER plants in India and in other

    global locations.

    AECL ACr 1000 reacs

    L&T and Canadian based Atomic Energy o Canada

    Limited (AECL) have signed a Memorandum o

    Understanding or co-operation on Advanced

    CANDU Reactor ACR1000. This agreement is

    subject to nal approval by the governments

    o India and Canada, o a bilateral Nuclear Co-

    operation Agreement between the two countries.

    Pressurized Water Nuclear Reactors (PHWR) designis one o the most highly competitive nuclear

    technologies in the world with regard to capital

    cost, saety & eciency. The unique design allows

    reueling online which eliminates the periodic

    reueling outage required by other designs.

    The ACR1000 is AECLs generation III+ reactor

    design that utilizes the proven concepts o the

    PHWR. L&T and AECL have joined hands to

    develop a competitive cost model or the ACR

    1000. Upon completion o the indicative cost/scope

    model AECL and L&T agree to begin discussions

    to develop Nuclear Power Plants in India on EPC

    basis and utilize the collective expertise o the

    Parties in global markets.

    Wesgse mla nclea Pwe

    reacs

    L&T and US-based Westinghouse Electric Company

    (WEC) have signed a MoU or co-operation to

    eectively address the projected need in India or

    Pressurized Water Nuclear Reactors with Modularconstruction technology. Westinghouse technology

    is in use in over orty per cent o the operating

    nuclear power plants in the world.

    Whereas L&T has been playing a lead role

    in equipment manuacture, construction and

    project management or Pressurized Heavy

    Water Reactors in Indias domestic program, this

    MoU with Westinghouse represents a major step

    orward or L&T in Pressurized Water Reactors o

    modular design. It will enable L&T as well as WEC

    L&t sgs mu w

    World Leaders in

    Nuclear Power Sector

    ECC Concord|Jan - Mar 2023

  • 8/7/2019 Concord_mar09

    24/48

    Vol. No. 31 Issue No. 4

    Indira Sagar

    Right Main CanalProject

    SAJid FArooQ mohAmmEdProject Manager

    C Concord|Jan - Mar 2009 24

  • 8/7/2019 Concord_mar09

    25/48

    The Indira Sagar (Polavaram) project is located

    in Andhra Pradesh on the river Godavari

    near Polavaram Village above 34km upstream o

    Kovvur, Rajahmundry. The Polavaram project is

    contemplated as multipurpose project envisaging

    irrigation benets or the upland areas o East

    Godavari under Let Main Canal and West Godavari

    and Krishna District under Right Main Canal.

    rg ma Caal

    The Indira Sagar (Polavaram) Right Main Canal

    project is taking o rom the Godavari River on

    the upstream o Indira Sagar Project (Polavaram),

    Rajahmundry and runs or a length o 174.000 km

    in West Godavari and Krishna Districts o Andhra

    Pradesh. The Right main Canal at 174.000 km gets

    linked up with Krishna River through the existing

    Budameru Diversion Channel. This Right MainCanal is contemplated to irrigate an ayacut area o

    129259 hectares (Ha) in the upland area o West

    Godavari and Krishna District. This canal provides

    for diversion of80TMC ofGodavari water tothe

    Krishna River to meet the irrigation requirements

    o Krishna Delta.

    Cac

    As a part o the ambitious and most prestigious

    Jalayagnam Projects, the Irrigation & Command

    Area Development (I&CAD) Department,Government o Andhra Pradesh divided the

    174.000 km length Right Main Canal into 7

    Packages and awarded the 7th Package to ECC,

    L&Ts Construction Division on EPC turnkey basis

    foravalueofRs.181crores.

    Lca

    Chainage 156.500 km - 174.00 km o package 7

    begins at Nunna village, 25 km rom Vijayawada.

    The main canal traverses through thick mango

    elds, reserve orest, hills, deep cut quarries,ponds, lakes and small villages. The project is

    ully surrounded by long stretches o green elds.

    The 17.5 km long canal passes through 9 small

    villages and terminates on the upstream side o

    Budameru regulator at Velagaleru village.

    Scpe Wk

    Construction o this 17.5 km Right Main Canal

    involves detailed investigation, survey, preparation

    o land plan schedules, design and engineering,

    earthwork excavation, ormation o embankments,

    lining o main canal, construction o CM & CD

    structures and plantation on both sides o main

    canal.

    Csc

    The construction o main canal involves theollowing important stages.

    deale ivesga a Sve

    The entire stretch o the 17.5Km was studied in

    detail by conducting various other alternative

    alignment surveys. To the extent possible, the

    alignment was done in FSL Contour to avoid

    embankments. For nalizing the alignment and to

    mark the route in thick reserve orest, bushes and

    mango elds, GPS Navigators and Total Stations

    were used.

    La Pla Scele a La acqs

    The village-wise Land Plan Schedules were

    prepared or acquiring about 1000 acres o land

    involving Private Lands, Revenue Govt. Lands and

    Forest Area. About 3.25 km o main canal passes

    throughthereserveforestofareaof120.68acres

    and the balance part o the alignment traverses

    through mango elds and cultivated lands. Digital

    Cadastral drawings showing the boundaries o

    each Village, extent o land and area to be acquired

    were some o the important issues involved in

    preparation o Land Plan Schedule and in Land

    acquisition.

    desg a Egeeg

    The design and engineering or the entire

    package was done by ECCs Engineering Design

    & Research Centre (EDRC) at HQ, Chennai. The

    design scope involved preparation o Bore log

    sheet, preparation o Hydraulic particulars o maincanal, km-wise LS & plan o main canal, design

    & drawings o cross masonry and cross drainage

    structures.

    The part o the alignment rom km 163.150 to km

    163.700 has been designed as Flumed Section

    with a bed width o 65.50 m considering the deep

    cut excavation and alignment passing between

    the hills. Standard Penetration Test and Plate

    Load Tests were conducted at each structure to

    ascertain the bearing capacity o soil.

    ECC Concord|Jan - Mar 2025

  • 8/7/2019 Concord_mar09

    26/48

    Vol. No. 31 Issue No. 4

    halc Paclas ma Caal

    Length o main canal : 17.50 km

    Bed width o main canal : 73.25 m

    Topwidthofmaincanal : 88.85m

    Full supply depth : 4.2 m

    Freeboard : 1.0 mSide slopes : 1.5H : 1V

    Bed all : 1 in 20,000

    Designeddischarge : 318.48Cumecs

    No. o structures as per HPs : 24

    Eawk Excava

    The 73.25m bed width canal involves about

    85 lakh cu.m of earthwork excavation and

    10 lakh cu.m o embankment. The soils met with

    on the course o the alignment were generally red

    earth and hard gravel.

    The depth o earthwork excavation in normal

    section ranges rom 5-7 m depending upon the

    ground level. A 40 m deep cut hard rock excavationat fumed section is one o the most critical and

    adventurous one.

    Lg ma Caal

    Prole Walls shall be laid at8.75m and 17.5 m

    intervals in curve portion and straight portion

    respectively or ormation o Subgrade beore

    laying the Lining Concrete. More than 600 workmen

    C Concord|Jan - Mar 2009 26

  • 8/7/2019 Concord_mar09

    27/48

    were deployed or Subgrade preparation. In

    addition, Graders and Rollers were also deployed

    or ormation o Subgrade.

    The lining or the main canal was done with M10

    grade o concrete with 40mm maximum size o

    aggregates. 100mm thick lining concrete was laid

    or the entire bed width o 73.25m with slopes on

    both sides up to a height o 4.95m rom the canal.

    Onthewholetheworkinvolved1.8lakhcu.mof

    lining concrete.

    Contraction Joints at 5m intervals were provided

    in both transverse and longitudinal direction.

    This apart, suitable construction joints, concrete

    sleepers, transverse drains, longitudinal drains,

    porous plugs were also provided in lining

    Concrete.

    Css mas &

    Css daage Sces

    A number o streams and small village roads cut

    across the main canal at dierent locations. Toprovide access to the villagers as well as to allow

    the streams to pass across the main canal or

    irrigation acilities etc., dierent types o structures

    were proposed in the alignment o the main canal.

    Thus, 24 dierent structures were constructed

    in the canal alignment or meeting various

    requirements.

    Panoramic view o the canal

    ECC Concord|Jan - Mar 2027

  • 8/7/2019 Concord_mar09

    28/48

    Vol. No. 31 Issue No. 4

    Jindal Dam - L&Tsmaiden venture in to

    construction o ull-fedged dams

    G. BhASKArA rAoPlanning Manager

    C Concord|Jan - Mar 2009 28

  • 8/7/2019 Concord_mar09

    29/48

    Jindal Power Limited, a leading power generation

    company, and a subsidiary o Jindal Steel has

    set up a 1,000 MW super thermal power plant at

    Tamnar in Raigarh district, o Chhattisgarh. For the

    consumptive water use in the power plant, a dam

    has been built across river Kurket, near village

    Rabo, which is about 33 km rom the power plant.

    This200mlong18.5mhighdamsuppliesabout

    40 cu.m per minute o water to the power plant

    and meet the consumptive and circulating

    requirements o the power plant.

    Apart rom being the ull fedged dam project

    undertaken by ECC, this unique and landmark

    project was raught with several social and

    environmental problems.

    Braving all the odds, L&T successully completed

    the project and the food gates were ormallyopened and inaugurated by Mr. Sara, President

    Jindal Power Limited on July 13, 2007.

    Sale eaes

    Main earthen dam in the Riverbed - 200m

    long,18.5mmaximumheight

    Rightbankdykeof1150mlongand2to15m

    height

    Leftbankdykeof201mlongand2to6m

    height

    Spillway dam and energy dissipation

    arrangement 145m long with 10 vertical

    gatesofsize12mx8.5mand2stoplogswith

    operating system

    Intake and pump house with stop log and

    trash rack o 4m x 11m

    Riverdiversionworks

    Completehydro-mechanicalequipment

    Approach roads to the project with

    illumination

    maj Scpe Wk

    Excavationinordinarysoil-5,80,246cu.m

    Excavationinrock(alltypes)-3,42,500cu.m

    Concrete(allgrades)-57,772cu.m

    Reinforcement-1534t

    HMworks(GatesandHoist)-800t

    Groutingmaterial(cement)-3,243bags

    Bentonitefordiaphragmwall-27t

    Excavationofcutofftrench-55,500cu.m

    Fillingofcutofftrench-55,500cu.m

    Earthworkllinginembankment-

    48,2407cu.m

    Rip-rapworks-30,917cu.m

    Metalledroadatthetopofdamfacilities-

    2.60 km

    Electricalttingsandillumination

    ree Lca

    As the site was located at 35 km rom Raigarh,

    a 11km approach road to site was strengthened

    beore commencement o the work. In addition,

    L&T had to establish V-sat connection as there

    were no communication networks available in the

    vicinity.

    dapag wall

    Initially, the diaphragm wall or the main dam was

    an RCC structure. Ater the work was awarded,

    the consultant changed the structure rom a rigid

    D-wall to a fexible D-wall using plastic concrete

    and doing away with the reinorcement. The

    Foundation Engineering Competency Cell o ECC

    took this challenge and developed a new design

    mix or this type o plastic concrete. The ormula

    worked perectly and the work was executed

    successully.

    Acevees

    Major portion o project excavation or spillway,

    concrete or spillway, abrication, erection &

    commissioning o spillway gates and earthen dam

    in the river portion including rip-rap works, were

    completed in the stipulated time o 25 months

    and handed over to clients. This project received

    Prashansha Patra rom National Saety Council

    o India (Saety Awards 2007) or achieving 4

    million sae man-hours without any lost time due

    to injury. Site also received Annual Quality trophy.

    View o the dam and

    hydro-mechanicalstructures (gates)

    in position

    ECC Concord|Jan - Mar 2029

  • 8/7/2019 Concord_mar09

    30/48

    Vol. No. 31 Issue No. 4

    Veligonda Dam

    The engineeringmarvel

    A. r. nErurKArProject Manager

    PAnKAJ KEShAV GurSALEPlanning Manager

    C Concord|Jan - Mar 2009 30

  • 8/7/2019 Concord_mar09

    31/48

    Arid landscapes, barren elds and dusty track

    lands dene the upland areas o Prakasam,

    Nellore and Kadapa Districts in the State o Andhra

    Pradesh, which all under the severe drought

    prone zone. With the completion o our ongoing

    irrigation projects Veligonda, Gundlakamma,

    Ramatheertham and Palair, the scenario is

    changing. These our projects increased the

    irrigation potential o this region rom the present

    7.45 lakh acres (3.01 lakh hectares) to 13.45 lakh

    acres (5.44 lakh hectares) in a couple o years.

    Thisquantumjumpof80percentwillbeachieved

    ater the completion o Rs.4000 crore projects

    under the Jalayagnam programme.

    A huge reservoir, called the Nallamala Sagar,

    is being ormed and three dams are being

    constructed at Gottipadia, Sunkesula and Kakarla.

    Water is drawn rom Kollamvagu oreshore on

    rightbankofSrisailamreservoirthrough18.80km

    long tunnel by gravity and thereater diverted to

    Nallamala sagar through a 23.36km eeder canal.

    The canals are proposed rom Sunkesula gap,

    Gottipadia gap and Kakarla gap and envisages to

    draw 43.50 TMC o food water rom river Krishna

    upstreamofSrisailamreservoirtoirrigate4.38lakh

    acres (1.7 lakh hectares) in 29 mandals, mostly in

    Prakasam district and marginally in Nellore and

    Kadapa districts.

    L&T is entrusted with the construction o one o

    these dream irrigation projects The Veligonda

    Dam. The project will provide irrigation benets

    to upland areas o the district besides providing

    sae drinking water to 15 lakh people, who have

    been consuming groundwater with excess fuoride

    content or decades. L&Ts scope o works

    comprise construction o dam at Gothipadia

    and excavation o Gottipadia Canal including

    construction o cross masonry and cross drainage

    works, distributory system or 9500 acres. L&Tsecured this contract in 2005 rom Irrigation &

    Command Area Development Department o

    Andhra Pradesh against sti competition.

    Valued at Rs. 395 crore, this is the rst major

    concrete dam project executed by L&T on an EPC

    (Engineering, Procurement and Construction)

    basis. The scheme comprises construction o

    dam rom EL 162 to EL 230 having a base width o

    57.96m and top width o 12m, canal length 11.40

    km and distributory system or 9500 acres.

    Sale Feaes

    Heightofthedamfromthedeepest

    level-87m

    Totallengthofthedamatthetop-600m

    Slopeofthedownstreamface-1:0.662

    Slopeoftheupstreamface-1:0.045

    ECCs major scope o work includes 10,00,000

    cu.mof excavation,9,21,181cu.mand 1,00,000

    cu.m o concreting in two stages, 1600 t o

    reinforcement,2,30,000sq.mofformwork,58,000

    Rmt drilling or grouting, 51,000 cement bags or

    grouting.

    Cceg

    Totalconcretingis10,21,181cu.mintwo

    stages

    Totaldurationofconcretepouring

    24 months

    Averagerateofconcretepouringachieved

    1500 cu.m perday

    Peakrateofconcretepouringachieved

    2903 cu.m per day

    The project had a huge requirement o concrete,

    which was to be poured at a temperature o 15

    degree celsius. The herculean task o achieving

    and maintaining the standard o concreting was

    managed with meticulous planning. As the height

    o dam started increasing, earthen ramps up to

    30m height was created or the movement o

    concrete. Later, conveyor was used or shiting

    concrete rom the batching plant to the top. As

    the project required steel ormwork, the entire

    shuttering was designed and schemed in-houseat site. Hydra cranes were used or handling the

    orms. To reduce the cycle time, the shutters

    were combined (4.8 m combined width) with

    structural steel channels. The whole sequence

    o operations, rom aggregate production to

    concreting was mechanized thereby ensuring

    accuracy and maximum output. The client

    awarded commendation certicates or the highest

    concreting (46000 cu.m) in the month o February

    2006.

    ECC Concord|Jan - Mar 2031

  • 8/7/2019 Concord_mar09

    32/48

    Vol. No. 31 Issue No. 4

    Egeeg Calleges

    Veligonda dam project is the rst dam project

    designed by the Engineering Design and Research

    Centre (EDRC). EDRC looked at the opportunity

    as a challenge and successully completed the

    design o concrete dam. The internal arrangements

    within the dam body like gallery, adit, shat, and lit

    were designed with precision. The dam consists o

    around 2 km o gallery within it or inspection and

    grouting. Planning and aligning this multi level

    gallery and the interconnection o the galleries

    with access adits were really brain racking. Like in

    any other dam, A holes and B holes or grouting

    were designed to improve the impermeability o

    dam base. The dam base was grouted with a

    total drill length o around 22 km. Dierent types

    o instruments were embedded in dam body to

    monitor the dam in terms o settlement, plumb

    and thermal. The monitoring was reviewed with a

    computerized data acquisition system.

    resces

    Remoteness o the project posed the biggest

    challenge as management o materials was

    a critical task. Except or the aggregates, the

    minimum distance or sourcing o other materials

    was around 200 km away rom project site.

    Interacting with the vendors and convincing them

    to deliver as per the schedule was one o the most

    critical activity or the smooth progress o the

    project.

    Sourcing o aggregates was another major issue.

    Markapur is amous or slate rock ormation

    which cannot be used as aggregates because

    o its hard and sot rock combination. The site

    has established a rapport with a local quarry or

    uninterrupted supply o aggregates.

    Identiying and sourcing the total requirement o

    boulders (22 lakh mtp), was a major issue during

    the initial phase as the local terrain had anity

    C Concord|Jan - Mar 2009 32

  • 8/7/2019 Concord_mar09

    33/48

    to slate rock. Two crushers with a combined

    capacity o 450 tph are installed to cater to the

    aggregate production. Sand impactors are used

    to enhance the quality o the aggregate output.

    This mechanized system o aggregate operations

    was instrumental to achieve the planned output.

    Sourcing o river sand also was a challenging taskas the nearest supplier was around 220 km away

    rom project site.

    Pla & mace

    The initial review o similar dam sites was

    instrumental in planning the machinery

    requirement or the project. The methodology

    involved in concreting was through dump trucks,

    transit mixers and tower cranes. Two 125 tpd

    chilling plants, 250t o rerigeration, two ice plants

    were installed or getting the required concrete

    pour. During summer, the temperature crossed 50

    degree celsius and maintaining concrete pour at

    15 degree celsius was the most critical challenge

    through out the execution.

    Specialized major P&M deployed include

    120 cu.m/hr concrete batching plants with

    aggregate individual weighing system or the best

    accuracy.

    Qal a Sae

    TheprojectsitefollowedthenormsofISO9000

    and has been reviewed by various audit systems

    at regular intervals. Sae methodology was

    incorporated in all activities o the project. Daily

    pep talks and regular orientation programmes

    ensured the communication o saety issues

    and awareness is created down the line across

    various departments. A system o automated

    house keeping was implemented, where beore

    commencement o work, the workmen ensure

    appropriate environment is maintained.

    Some o the sae methods employed at sites

    included three lockwork permit systems or

    rotating parts, cordless communication system or

    tower cranes, and sensor alarm in hydra cranes.

    ivas

    Innovations and in-house alternatives are the

    hallmarks to the speedy execution o this project.

    Buckets o 3 cu.m capacity or concreting andvibrator needles were locally abricated which

    resulted in considerable saving o time. Gantry

    or handling o Formwork was designed by

    Construction Methods and Planning Cell (CMPC).

    CSr

    As part o the corporate social responsibility, two

    additional class rooms or the local government

    school was built by L&T. An environment riendly

    zone is being nurtured at the project site. About

    892saplingswereplantedduringHHLCentenary

    Celebrations. Three more class rooms were

    constructed or the Government school at

    Kaolabhimanipadu village.

    The project team maintained cordial relationships

    with the locale population, which was instrumental

    in the smooth fow o work. Veligonda Project

    contributed to reconstruct a temple which had to

    be relocated due to the dam construction.

    Night view o the Veligonda dam, during construction

    ECC Concord|Jan - Mar 2033

  • 8/7/2019 Concord_mar09

    34/48

    K A L E i d o S C o P En E W o r d E r S

    rs. 605 C. oes Wae &Seel Secs

    Larsen & Toubro (L&T) has bagged resh orders

    worth Rs.605 Crores rom the Water and Steel

    Sectors in the last quarter o FY 09. L&T secured

    three orders aggregating Rs.416 Crores rom the

    WaterSectorandanotherorderofRs.189Crores

    rom the Steel Sector. The Metallurgical, Material

    Handling& WaterOperating Company ofL&Ts

    Construction Division will be executing these

    orders.

    Wae Sec: The company bagged a Rs.165

    Crores order rom the Rural Water Supply &

    Sanitation Department, Government o Andhra

    Pradesh, or supply o potable water to 152

    inhabitations in the Ananthapur district o the

    state. The project is to be completed in 15 months.

    At present, L&T is already executing water supply

    projects worth Rs.319 Crores in Ananthapur

    district.

    L&T has also won a Rs.133 Crores EPC contractrom Delhi Jal Board or design & laying o MS

    pipeline rom the Dwaraka Water Treatment Plant

    to various areas o Dwaraka, Nazagarh, Daulatpur,

    Ujwa and IGI airport (Package 3). The project is

    to be completed in 21 months. At present, L&T

    is executing the Dwaraka water supply scheme

    (package1A)inDelhiforRs.248Crores.

    ThecompanyhasalsosecuredaRs.118Crores

    order rom Utkal Alumina International Limited or

    design & construction o raw water intake structure,

    raw water transmission pipeline & reservoir works

    attheirAluminaPlantatRayagadaDistrict,Orissa,

    to be completed in 17 months. L&T is already

    executing Civil & Structural Works or this Alumina

    Plant or Rs.455 Cr.

    Seel Sec: In the steel sector, the company has

    wonanorderof Rs.189Crores fromSAIL-IISCO

    SteelPlantforCivilWorksforRollingMill,BOF,CCP

    LDCP Complex, Lime Dolomite Plant at Burnpur,

    West Bengal, to be completed in 12 months. L&T is

    already executing the Sinter Plant & Raw MaterialHandling plant on EPC basis. Securing this new

    order reinorces the condence placed on L&T by

    SAIL, one o its major customers.

    rs.1,143 C. es tAtA

    Seel

    L&T has bagged two orders totaling Rs. 1143 Cr.

    rom TATA Steel.

    ThiscomprisesaRs.689croreorderforturnkey

    construction o Dry Crushing & Material PreparationPlant (DCMP) at Joda Mines and Engine-on-Load

    (EOL)Scheme atNoamundiMinesand another

    Rs.454croreorderforIronOre&PelletHandling

    System at Jamshedpur. The Metallurgical, Material

    Handling&WaterOperatingCompany(MMH&W)

    o L&Ts Construction Division will execute these

    orders.

    L&Ts scope o work or the projects include basic

    & detail engineering; complete civil & structural

    works; supply and erection o mechanical,

    electrical & instrumentation works including testing

    & commissioning.

    These turnkey projects are to be executed in

    a schedule o 30 months or DCMP Project, 24

    monthsforEOLschemeand23monthsforIron

    Ore&PelletHandlingSystem.

    L&T is already implementing Blast Furnace &

    Pellet Plant packages or 3 MTPA expansion

    project o TATA Steel at Jamshedpur which is

    progressing at a ast pace. With these orders,

    L&T has emerged as the major partner o TATA

    Steel in the implementation o 3 MTPA expansion

    project. Moreover, this covers the complete chain

    rom material preparation at mines to receipt &

    handling o iron ore & pellet and delivery to the

    blast urnace.

    rs. 1,100 C. Eleccal oes

    L&T has bagged a slew o large-value orders

    aggregating Rs.1,100 crores in the electrical

    constructionsectorinthefourthquarterof2008-09.

    C Concord|Oct-Dec08 34

  • 8/7/2019 Concord_mar09

    35/48

    The orders have come rom leading public sector

    organizations the Power Grid Corporation o

    India Limited and the Rail Vikas Nigam Limited

    and involves setting up high end transmission

    lines and substations as well as a project or the

    Indian Railways

    Mr K. V. Rangaswami, President (Construction)and Member of the Board said: The 800 kV

    HVDC Transmission Line project and the 765

    kV substation orders represent technological

    breakthroughs and they auger well or our growth

    potential in these critical segments.

    The order secured rom the Power Grid Corporation

    o India (PGCIL) involves construction o a part o

    thecountrys rst 800 kVHVDC transmission

    system or transmitting power rom the north east to

    the northern and western parts o India. Extending

    across 190 km, this HVDC bi-pole transmission

    line, valued at Rs.169 crores will be executed or

    the section between Nidhaura Village to Agra in

    Uttar Pradesh on the main line between Biswanath

    toChariyali.Thisistherst800kVtransmission

    line system o its kind in India and signies a

    major step orward in high end electrical project

    execution.OtherorderssecuredincludeaRs.190

    crores order rom Power Transmission Corporation

    o Uttarakhand Limited or 400 kV double circuit

    Transmission Line between Loharinagpala to

    Koteshwar, a Rs.175 crores order rom Rail Vikas

    Nigam Limited or the Bharuch-Dahej Railway

    Construction Project., and a Rs. 83crore order

    rom PGCIL or the construction o 765 kV single

    circuit transmission line rom Agra to Jatikalan.

    Meanwhile, in a major oray into the high end 765

    kV segment o substations, L&T secured three

    majorordersfromPGCILvaluedatRs.480crores

    or the construction o 765 kV Substations at

    Balia, Lucknow and Satna along with associated

    transormer packages.The entire project will be

    executed within a tight schedule o 27months. It

    involves detailed engineering and construction

    o 51 bays o 765kV system including supply

    and installation o 35 numbers o 500MVA Auto

    Transormers.

    The 765 kV orders were secured against sti

    international competition, through a consortium

    with Areva SA (France) and Hyosung (Korea) or

    765kV switchgear and transormers respectively.

    These projects will be executed by the Electrical

    & Gulf Projects Operating Company of L&Ts

    Construction Division.

    rs. 1,438 C. Gl oes t&d sec

    L&ThasbaggedthreenewordersworthRs1438

    crores. Two orders worth Rs 1130 crores werebooked in the Gul Region and a third, worth Rs.

    308crore,wasbaggedfromtheWestBengalState

    Electricity Distribution Company.

    L&ThasbaggedanEPCordervaluedatRs.800

    crores (USD 164 million/ AED 600 million) rom

    the Al Ain Distribution Company (AADC) or the

    construction o 7 electrical substations, associated

    MV cabling and overhead transmission line in the

    Al Ain city o Abu Dhabi.

    This is one o the single largest value orders

    received by L&T in the UAE, or Power Transmission

    & Distribution Sector.

    According to the terms o the contract, L&T

    will Design and Build these 33/11kV primary

    substations to the specications o the international

    consultant PB Power & will be completed within 24

    months.

    Each substation consists o 33 kV gas insulated

    switchgear, 11 kV air insulated switchgear,

    15/20 MVA 33/11 kV transormers, Substation

    Control and Monitoring System, Protection andtelecommunication system, DC system and

    auxiliaries. The contract encompasses design and

    construction o civil buildings with complete set

    o utilities such as air conditioning, re protection

    and lighting systems.

    L&T has also received another EPC order or

    Augmentation & Expansion o 33 kV Power

    Transmission Network with a value o Rs 330 crores

    (USD 67 million / AED 247 million) rom Abudhabi

    Distribution Company (ADDC). The scope covers

    design, supply & construction o 300 km o 33 kV

    Transmission line network in the western region

    o Abudhabi, with the contract completion o 22

    months.

    These orders were secured against sti

    international competition and will be executed

    by the Power Transmission & Distribution Sector

    o L&T Abu Dhabi. At present L&T is already

    executing 20 substations o various capacities in

    Al Ain, Abu Dhabi and Dubai areas o UAE.

    ECC Concord|Oct-Dec35

  • 8/7/2019 Concord_mar09

    36/48

    In another development Larsen & Toubro has

    baggedaRs.308croresorderfromWestBengal

    State Electricity Distribution Company Limited

    (WBSEDCL) or Rural Electrication Works in

    Jalpaiguri and North 24 Parganas districts o

    West Bengal State. As part o the contract, L&T will

    carry the 11 kV distribution lines to electriy 2274

    villages in these districts, to benet the citizens

    o Below Poverty Line ( BPL).The project will be

    completedwithin18months.

    rs.1,245 C. hpwe

    Pjec e

    The Infrastructure Opreating Company of

    Construction Division has bagged a contract o

    Rs.1245 crores or the construction o the Dam

    Package, a part o the 1200 MW Punatsangchhu-I

    Hydroelectric Project in Bhutan.

    The project is being set up by the Punatsangchhu-I

    Hydroelectric Project Authority which has been

    constituted through an agreement between the

    Government o India and the Royal Government o

    Bhutan. It is located across Punatsangchhu River,

    about80kmfromThimpu,thecapitalofBhutan.

    To be executed in 66 months, the scope o work

    involves construction o the diversion tunnel, dam,

    intake and desilting arrangement including hydro-

    mechanical works. L&T won the order through acompetitive bidding process. WAPCOS Limited

    is the engineering and design consultant o the

    Project.

    This is the rst o a series o 10 hydropower

    projects jointly identied by the governments o

    India & Bhutan and to be implemented or a total

    installed capacity o 11,576 MW by 2020.

    For L&T, this is the second hydroelectric power

    project in Bhutan - the rst one was the 1020 MW

    Tala Hydroelectric Project, which was completedahead o schedule.

    rs.1,162 C. oe Blgs & Faces oC

    L&TsBuildings&FactoriesOperatingCompany

    part o its Construction division has bagged new

    orders aggregating around Rs.1162 crores in the

    fourth quarter of2008-09for the construction of

    actories and residential projects.

    L&T has bagged a major design & build order

    valued at Rs. 605 crores rom the Andhra Pradesh

    Rajiv Swagruha Corporation Limited or the

    construction o an integrated thematic township

    comprising o 3517 fats (27 blocks) and consisting

    o Classic/ Intrinsic/ Basic & Civil type fats

    at Bachupally, Hyderabad. This project is to be