1 Configuration Management Plan US ATLAS HL-LHC Detector Upgrade Project Brookhaven National Laboratory Upton, New York March 13, 2017 US ATLAS HL-LHC Configuration Management Plan
Transcript
Page 1: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

1

Configuration Management Plan

US ATLAS HL-LHC Detector Upgrade Project

Brookhaven National Laboratory

Upton, New York

March 13, 2017

US ATLAS HL-LHC Configuration Management Plan

Page 2: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

2

Drafted by:

Date: __________

Jonathan Kotcher, US ATLAS HL-LHC Project Manager

Brookhaven National Laboratory

Date: __________

Mike Tuts, US ATLAS HL-LHC NSF Principal Investigator

Columbia University

Page 3: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

3

This page intentionally left blank.

Page 4: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

4

US ATLAS HL-LHC Configuration Management Plan

Change Log

Revision History

Rev. Date Reason

1 12/31/2015 Initial draft

1.1 3/13/2017 Updates for Jonathan Kotcher, Mike Tuts

Page 5: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

5

US ATLAS HL-LHC Configuration Management Plan

Table of Contents

1 INTRODUCTION................................................................................................................... 8 1.1 Purpose ............................................................................................................................... 8 1.2 Plan Overview .................................................................................................................... 8 1.3 Definitions.......................................................................................................................... 9

2 SCOPE AND APPLICABILITY ......................................................................................... 10 2.1 Scope ................................................................................................................................ 10 2.2 Applicability .................................................................................................................... 11

3 ROLES AND RESPONSIBILITIES ................................................................................... 11 3.1 Project Manager ............................................................................................................... 11 3.2 Level 2 Managers ............................................................................................................. 12 3.3 Level 3 Managers ............................................................................................................. 12 3.4 Change Control Board ..................................................................................................... 13 3.5 Document Control Managers ........................................................................................... 13 3.6 ATLAS System Management .......................................................................................... 13

4 TOOLS ................................................................................................................................... 15 4.1 Data Management Systems .............................................................................................. 15 4.2 Configuration Control Database ...................................................................................... 16

5 CHANGE CONTROL PROCESSES ................................................................................. 17 5.1 Configuration Identification............................................................................................. 17

5.1.1 Baseline Definition ...................................................................................................................................... 17 5.1.2 Configuration Items .................................................................................................................................... 17 5.1.3 Configuration Items Data List ................................................................................................................. 18

5.2 Change Control ................................................................................................................ 18 5.2.1 Change Control Process ............................................................................................................................ 18 5.2.2 Change Control Procedures ..................................................................................................................... 19

5.3 Configuration Status Accounting ..................................................................................... 20 5.4 Configuration Verification ............................................................................................... 21

Page 6: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

6

US ATLAS HL-LHC Configuration Management Plan

List of Acronyms

ALD Associate Laboratory Director

AE Acquisition Executive

ATLAS A Toroidal LHC Apparatus

BCP Baseline Change Proposal

BNL Brookhaven National Laboratory

BHSO Brookhaven Site Office

CCB Change Control Board

CERN European Organization for Nuclear Research

CD Critical Decision

CDCM Central Document Control Manager

CDR Conceptual Design Report

CI Configuration Item

CM Configuration Management

CMP Configuration Management Plan

CY Calendar Year

DCM Document Control Manager

DocDB US ATLAS HL-LHC Document Database

DOE Department of Energy

DPM Deputy Project Manager

EAC Estimate at Completion

ES&H Environment, Safety and Health

EVMS Earned Value Management System

FPD Federal Project Director

FTE Full Time Equivalent

FY Fiscal Year

I/C Integration and Commissioning

ISMS Integrated Safety Management System

L2 Level 2

L3 Level 3

LHC Large Hadron Collider

LS2 LHC Long Shutdown 2

LS3 LHC Long Shutdown 3

M&O U.S. ATLAS Maintenance & Operations

NSF National Science Foundation

Page 7: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

7

US ATLAS HL-LHC Configuration Management Plan

OHEP DOE Office of High Energy Physics

OPS U.S. ATLAS Operations Program

PAG Project Advisory Group

PARS Project Assessment and Reporting System

PB Performance Baseline

PEP Project Execution Plan

PM US ATLAS HL-LHC Project Manager

PMG Project Management Group

PMIT Project Management Integration Team

PRR Production Readiness Review

QA Quality Assurance

QC Quality Control

R&D Research and Development

RF Research Foundation

RLS Resource Loaded Schedule

RMB Risk Management Board

SBMS Standards Based Management System

SC Office of Science

SCD Specification Control Document

SHD Specification History Document

TP Testing Procedures

U.S. United States

WBS Work Breakdown Structure

Page 8: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

8

Configuration Management Plan for the

US ATLAS HL-LHC Detector Upgrade Project

1 INTRODUCTION

This Configuration Management Plan (CMP) describes the configuration management (CM)

responsibilities and processes that support the design and implementation of the US ATLAS HL-

LHC Detector Upgrade Project (US ATLAS HL-LHC). The purpose of this CMP is to identify

the organization providing the configuration control, provide a definition of a configuration-

controlled item, describe the change control process, and identify the plan for configuration

status accounting and verification. It is a living document that is developed and maintained by

the US ATLAS HL-LHC Project.

1.1 Purpose

This CMP is designed to ensure that:

Baselines are defined and documented;

Documentation is identified, released and controlled;

A Change Control Board (CCB) is established and functions according to the CMP

guidelines;

Changes to the baseline are evaluated and controlled;

Approved configuration changes are implemented and tracked;

Configuration status accounting is accomplished.

This CMP provides the governing plans for implementation of a system of management and

engineering controls that are necessary for effective execution of the Project.

1.2 Plan Overview

A CMP is employed by US ATLAS HL-LHC to identify and control relationships with respect

to design and construction of the Project deliverables. The Project recognizes the importance of

maintaining clear, concise, and accurate records in order to stay on schedule, remain within cost

constraints, and provide relevant information for future Operations and Maintenance (O&M).

This Plan has been established to ensure that key functional organizations, both BNL and the

collaborating US ATLAS HL-LHC upgrade institutions, are aware of their roles and

responsibilities during the design, prototyping, testing and construction phases of the Project.

Page 9: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

9

The main goal of the CMP is to prevent unauthorized or uncontrolled physical hardware changes

to equipment, changes to controlled documents, and changes to controlled software. The plan

defines and integrates the various CM control systems. It is also meant to focus on the control of

active documents and not on longer-term records management, retention, or archiving. Records

management issues will be addressed according to the requirements listed in DOE Order 200.1,

Information Management Program, and BNL records management policies and procedures.

The key elements of CM are Configuration Identification, Change Control, Configuration Status

Accounting, and Configuration Verification. For convenience, the system is also broken down

into Configuration Items (CIs).

Configuration Identification defines the system through drawings and documents that

specify the system components in terms of functional and physical characteristics, as well

as how they will be manufactured and tested.

The CIs are listed in a Configuration Items Data List (CIDL), which lists each CI and the

data management system in which it is stored.

The Change Control process is the vehicle by which proposed changes are reviewed and

approved. It ensures that the technical, cost and schedule impacts of each major change

are considered before approval is granted.

Configuration Status Accounting is a means to track configuration information and relay

it to key personnel in order to support management decisions and ensure that all work is

performed according to the current design.

The Configuration Verification process ensures that the current hardware and software

configurations match the intended design by verifying the implementation of each

approved change and through periodic configuration audits.

1.3 Definitions

Baseline – The point at which an item's design or requirements are “frozen” and after which all

changes must be tracked and approved.

Change Classification - All proposed changes to Project documentation submitted to the CCB

for consideration are designated as Level 1 through Level 3 changes, corresponding to change

levels and authorities in the PMP. Configuration changes may affect hardware requirements and

the documents, drawings and procedures, which define them.

Change Control Board (CCB) – A board composed of technical and administrative

representatives who recommend approval or rejection of proposed changes to a CI’s current

approved configuration documentation. The CCB, which is composed of the Project

Management Integration Team (PMIT), and is chaired by the US ATLAS HL-LHC Project

Page 10: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

10

Manager (PM). Additional personnel from the U.S. ATLAS Collaboration or BNL staff will be

added, if/as required.

Configuration Item (CI) – An aggregation of hardware or software that satisfies an end use

function.

Configuration Items Data List (CIDL) – An US ATLAS HL-LHC Project-controlled listing

that identifies all CIs and the data management system which stores and controls release of the

documents. The principal associated tool is the Document Database (DocDB).

Configuration Management (CM) – The systematic control and evaluation of all changes to

documentation that has reached the baseline point.

Documentation – The controlled paper and software versions of data that define Configuration

Items and controlled changes.

Pending Changes – Pending changes are those for which conceptual design has been approved,

changes that have been approved for implementation, or approved unincorporated changes that

have been implemented in the field but for which the document revision has not been completed.

A Baseline Change Proposal (BCP) form will be submitted to the CCB for all proposed CM

changes.

Project Baseline Approval – The point at which the Project's performance baseline has been

approved and final design can occur.

Final Design Report – Defines the technical specifications, physical characteristics, and

functional operating parameters of the US ATLAS HL-LHC deliverables.

2 SCOPE AND APPLICABILITY

The US ATLAS HL-LHC Project encompasses the design, prototyping and construction and

final acceptance testing at CERN of the U.S. components for the ATLAS HL-LHC Upgrade.

This CMP is applicable to all hardware and documentation associated with the US ATLAS HL-

LHC Project.

2.1 Scope

This CMP is applicable to all work performed as part of the US ATLAS HL-LHC Project, which

includes the design, prototyping, testing, construction, shipment and acceptance testing at CERN

of the U.S. deliverables. It provides guidelines for all personnel on CM activities in support of

the Project, including all subsystem teams, collaborators, and subcontractors. CM is applied to

items selected by the Project Manager and includes hardware components along with the related

design documents, specifications, drawings, procedures and other support documents in both

paper and electronic media. The scope of this CMP encompasses the lifecycle of the Project, the

Page 11: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

11

end of which is defined by limited acceptance testing on the surface at CERN prior to in situ

installation and commissioning in the ATLAS detector below ground. Installation and

commissioning will be supported by the U.S. ATLAS Operations Program, and are outside the

scope of this Project.

2.2 Applicability

In general, the CMP governs control of the following items, relevant to the US ATLAS HL-LHC

deliverables:

Mechanical and electrical computer-aided design models, design drawings and text

documents showing the specifications for the equipment and subcomponents;

Conceptual and Technical Design Reports;

Management documents, such as the Project Management Plan, Risk Management

Plans, Quality Assurance Plans, Baseline Schedule, PMP, MoUs, Work Authorization

Documents, etc.;

Technical Specification Sheet, which define the design parameters for each

deliverable;

Quality assurance and acceptance testing sheets, defined for each deliverable;

Hardware and Firmware.

3 ROLES AND RESPONSIBILITIES

The section below identifies the roles and responsibilities of US ATLAS HL-LHC personnel in

the implementation, management and maintenance of configuration for the Project.

3.1 Project Manager

The following describes the responsibilities in CM of the US ATLAS HL-LHC PM, or his/her

designee:

Chair of the CCB/PMIT;

Oversee and coordinate Project configuration control activities;

Notify the CCB of any need to change documentation or a system as soon as that

need is identified and determined to be valid;

Ensuring that all Project CIs are identified and controlled;

Page 12: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

12

Ensuring any changes to controlled documents are appropriately recorded, tracked,

and incorporated into existing design models, drawings and/or documents in a timely

manner;

Ensuring any additional testing or certification required as a result of changes are

explicitly identified and included in the appropriate places;

Maintaining a list that identifies controlled documents, as well as the owners and

locations of those documents, for the Project;

Periodically auditing the CMP to determine the effectiveness of the plan. This may

include reviewing controlled copies of documents to ensure their accuracy and their

consistency with the master copies, the electronic master, or design models.

3.2 Level 2 Managers

The US ATLAS HL-LHC Level 2 Project Managers and Deputy Project Managers will:

Serve on the CCB/PMIT;

Maintain CM control over their areas of responsibility and subcontractors;

Notify the PM of any need to change documentation or a system as soon as that need

is identified and determined to be valid;

Ensure the PM is informed of as-built changes and revisions to controlled documents;

Assess impacts of proposed changes on cost, schedule, resources, risk, technical

performance, and scientific objectives;

Submit requests for changes (via BCPs) and implement approved changes to the

Project requirements, cost and schedule baselines.

3.3 Level 3 Managers

The US ATLAS HL-LHC Level 3 Managers will:

Keep track of progress on work activities under their control, including work by

subcontractors and collaborations;

Notify the Level 2 Managers of any need to change documentation or a system as

soon as that need is identified and determined to be valid;

Ensure that people under their authority use the latest versions of documentation

available;

Transmit changes made as a result of fieldwork up the chain of command in an

orderly and timely manner.

Page 13: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

13

3.4 Change Control Board

The composition of the CCB is outlined in Section 1.3 of this document. The CCB will make

recommendations to the PM on changes that affect the Project baseline cost, schedule, and

technical specifications at Change Control threshold Levels 3 and 4 in accordance with the

change control process. The CCB will be chaired by the PM unless he/she designates another

member as the Chair. The CCB will meet at regular intervals, unless there are no pending

actions; it is anticipated that initial meetings will be held on a quarterly basis. Notices of

approval or denial of all proposed changes will be distributed to the relevant managers by the

Project Office.

3.5 Document Control Managers

The PM, or his/her designee, evaluates and establishes satellite sites at the collaborating

institutions for the individual US ATLAS HL-LHC CIs. The principal at each US ATLAS HL-

LHC institution will serve as the Document Control Manager (DCM) whose responsibilities

include transmission of the site's documentation to his/her Level 2 Manager, and to the US

ATLAS HL-LHC Central Documentation database, which is overseen by the project office

The DCMs are responsible to ensure that only the latest versions of documentation are

disseminated and available for use and outdated documentation is replaced throughout the

system. Outdated documentation will be properly archived. If outdated documentation is

requested for any reason, it shall be labeled as outdated or obsolete in a clear and well-described

manner. DCMs are responsible for the data management system in their organization.

3.6 ATLAS System Management

Project management and tracking for each system in International ATLAS (TDAQ, LAr, Tile,

Muon, ITK, etc.) is the responsibility of the system’s Project Leader (PL) and associated

Management Committee that is comprised of the PL, the managers for each component of the

system and ATLAS management (see Figure 1). The Project Leaders report directly to both the

overall Upgrade Steering Committee (USC, chaired by the ATLAS Upgrade Coordinator) on

upgrade issues and to the ATLAS Executive Board (EB, chaired by the ATLAS Spokesperson,

and the Technical Coordinator (TC)) on wider system issues. These are the highest executive

management committees of the experiment. All inter-system configuration, integration issues as

well as overall scheduling are managed and tracked directly by the technical and upgrade

coordinators and their teams who work together with each system.

Page 14: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

14

Figure 1. ATLAS Organization Chart

The ATLAS Resources Coordinator is responsible for coordinating resources across the

experiment. For upgrade funding, he chairs the Upgrade Advisory Board (UAB) that addresses

resources issues between the participating countries and the experiment. The UAB comprises the

National Contact Physicists from each ATLAS member state, ATLAS management, and the

system PLs.

The system PL and management committee deal with all aspects of project planning,

management, scheduling and tracking. Management committees typically meet bi-weekly. Wider

issues are brought to the USC and TC and ultimately the EB if necessary and appropriate. US

personnel are well integrated, and have direct representation in the management structures of

systems in which they are participating. This facilitates good direct coordination between US

ATLAS Upgrade construction and International ATLAS system management.

Each international ATLAS system develops and maintains a complete WBS with associated

Page 15: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

15

schedule and milestones. The US Construction Project deliverables are included in this WBS.

Three levels of milestones are typically defined:

Project Milestones (which will include some or all of the US construction project

milestones). These are at the lower or project level, and are tracked by the PLs and

Management Committee.

EB milestones (middle level), tracked for each system by the ATLAS EB.

LHCC Milestones (high level) tracked by the CERN LHC Experiments’ Committee.

International ATLAS Project documentation (design and technical specifications, interfaces etc.)

is centrally stored in the experiment’s Engineering & Equipment Data Management Service

(EDMS) database. Once approved, such documents may be changed or updated following

appropriate review and signoff procedures both at the system and TC levels. Major changes to

deliverables are subject to an engineering change request process requiring documentation

concerning the change (reason; details; cost, schedule, technical or other impacts; etc.) as well as

approval by the appropriate system’s Management Committee, the TC and, ultimately, the EB.

Additional documentation specifically concerning: manufacturing, production and testing

history; cabling; electronics rack assignments and configuration; and system specific hardware

details is stored and controlled in dedicated integrated databases developed for the purpose.

Each system has its associated Institute Board (IB) comprised of the system’s management and

representatives from each institute in the system, where issues relating to the institutes’

participation in the system’s work can be addressed. The PL regularly reports to the IB on

project progress. All US Institutes are represented directly in IBs of systems where they

participate.

4 TOOLS

Elements of US ATLAS HL-LHC CM include many hardware and firmware tools. For the

Project to maintain proper CM it is important that Project personnel are trained in these tools and

disciplined in their use.

4.1 Data Management Systems

The items included in the CMP, listed in Section 2.2 above, do not naturally lend themselves to a

single data management solution. In addition, different tools are used at different sites to

manage their CIs for the Project.

Page 16: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

16

Management documents, reports, and technical design documents that are under CM control will

be managed using the US ATLAS HL-LHC Document Database (DocDB), found at this link

https://atlas-hllhc.docdb.bnl.gov/cgi-bin/private/DocumentDatabase. The US ATLAS HL-LHC

Central Documentation allows each satellite site to gain access to the controlled documentation

inside this central repository.

CM for all US ATLAS HL-LHC hardware and structures is achieved through the life of the

Project through use of fundamental engineering documentation practices, such as:

Requirements change control;

CAD model (where applicable), drawing and specification change control, and

revision control;

Manufacture records;

Quality Assurance inspection and qualification testing documentation;

Manufacture and construction change control;

As-built configuration documentation.

The CM of detector firmware will be managed according to the process outlined in this plan. A

version control system that can record and control the history of source files, as well as

documents will be implemented, where deemed necessary by the PM.

The US ATLAS HL-LHC Project Schedule (resources, schedule, and cost) is documented in the

PRIMAVERA scheduling and COBRA cost processing software tools. Prior to baselining, the

Schedule is “unlocked” (not under Configuration Management) to allow Project planning to

smoothly evolve. At baseline, the Master Schedule is “locked” to a baseline configuration,

thereby placing it under CM, to allow for its use as the tool for the Earned Value Management

System (EVMS). Thereafter, any change to the Schedule requires the approval of the PM and

the CCB, as discussed in the PEP and Section 5 of this CMP. Changes to the Project baseline

will require a re-baselining of the Schedule.

Risk management is outlined in the US ATLAS HL-LHC Risk Management Plan (RMP). Risk

will be documented and managed via a Risk Management Board and Risk Registries, as outlined

in the US ATLAS HL-LHC RMP and the PMP. Write access to the Risk Registry is restricted to

selected individuals in the Project Office and managed by the PM.

4.2 Configuration Control Database

To track and manage changes to the baseline during the life of the Project, a Change Control Log

will be developed. This will be utilized for submitting changes, tracking change approvals, and

reporting change status. Completed BCP forms, on which these changes are documented and

submitted to the CCB, are maintained in the DocDB.

Page 17: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

17

5 CHANGE CONTROL PROCESSES

The Change Control process consists of four ongoing stages: (1) configuration identification, (2)

change control, (3) configuration status accounting, and (4) configuration verification.

5.1 Configuration Identification

Configuration Identification is the ongoing process of identifying and documenting the

functional and physical characteristics of all components, from initial requirements selection

through design, development, fabrication, test, shipping, and final on-site acceptance testing.

Configuration Identification provides a unique identification for each deliverable, as well as for

the configuration documentation.

5.1.1 Baseline Definition

The configuration baseline of the Project is defined by the design output documents, which

include procurement and construction specifications, drawings, test procedures, and operating

and maintenance information, where relevant. Configuration identification is developed,

baselined, and maintained via a peer review process that includes input from the U.S. ATLAS

and ATLAS Collaborations, and a series of formal internal US ATLAS HL-LHC technical and

management reviews. The peer review process will be overseen internally by the US ATLAS

HL-LHC Project, which can solicit outside reviewers for independent assessments. In addition,

technical reviews and site visits are organized by the Project using subject matter experts from

within and outside the Project at various stages of configuration development. Formal reviews

are conducted by the BNL Associate Laboratory Director for Nuclear and Particle Physics, the

Department of Energy, and the National Science Foundation.

5.1.2 Configuration Items

In order to facilitate CM, the Project systems and components will be broken down into

manageable units, called CIs. CIs are identified through a top-down analysis that divides the

total system into logically related and subordinate aggregates of components. The main criterion

is to select those items whose performance parameters and physical characteristics can be

separately defined, tested, and managed. In general, these correspond to US ATLAS HL-LHC

deliverables.

Page 18: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

18

5.1.3 Configuration Items Data List

All CIs will be listed in a Technical Specifications Control Document (TCSD), containing

relevant technical information and design specifications related to each CI. The TCSD is under

change control. Quality assurance and testing criteria will be maintained in separate sheets for

each deliverable, and will also be under change control. Where the design incorporates

commercial off-the-shelf (COTS) hardware or software, the design data and documentation is

owned by the vendor and is not subject to and therefore not included in the US ATLAS HL-LHC

CMP.

5.2 Change Control

Configuration management refers to the techniques used to identify the components of the

Project in order to track the configuration at all times throughout the Project life-cycle. The US

ATLAS HL-LHC Project uses several tools to achieve this objective, including a document

control system that supports versioning and document signoff for version approval.

Change Management, as described below, is the process by which scope, cost and schedule

changes are managed by the Project. The CCB will provide the necessary oversight of changes

to the Project scope. Project Controls tools and Earned Value Management practices, as

described with this document, will identify and elevate threshold variances to the Project’s cost

and schedule constraints.

5.2.1 Change Control Process

Change management includes the actions necessary to ensure adequate control of Project

baselines, including the Performance Measurement Baseline. The change control reporting

thresholds for the US ATLAS HL-LHC Project will be developed and documented as the project

moves towards baselining. L2 and L3 managers are responsible for ensuring that changes falling

below the defined threshold levels are appropriately verified, and documented. Change

management is the responsibility of the PM. A Change Control Board (CCB) will advise the PM

and DPM on all proposed changes above WBS Level 3.

Once the Project is baselined, all changes in technical scope or performance, cost, or schedule

must be documented by a written BCP. Change requests must originate in the Project Office or

below. The change request should include a description of the proposed change and its basis,

with appropriate backup documentation, either attached or referenced; an evaluation of the

impact of the proposed change; and the newly proposed course of action for integrating this

change into the baseline scope.

The change request must initially be submitted for action at the lowest applicable level. If

approval is denied at that level, a copy of the request, together with the reasons for denial, is

Page 19: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

19

posted in the DocDB, and the requestor is notified of the decision and location of the filed

information. If the change is approved at that level, a copy of the request with the approval

indicated, together with any qualifications or further analysis or documentation generated in

considering the request, is also uploaded to the DocDB, and the requestor is notified of the

approval and location of the set of documentation.

If final approval is within the authority of the person at this level, the process is considered

complete, except that the person at the next higher control level may review the change to ensure

proper application of the procedure and consistency of the change with Project goals. If

consideration at the next higher control level is required, then the aforementioned process is

repeated at that level.

The change control system may be audited by the Project Manager at his/her discretion.

5.2.2 Change Control Procedures

Formal change control procedures will be used to track technical, schedule, and cost changes in

the Project. Each such change requires the preparation of a BCP and submittal to the CCB,

nominally by the Level 2 Project Manager. The Project Manager will review each BCP. The

CCB/PMIT will advise the PM on a course of action who will maintain current records of all

Change Requests and their disposition through the DocDB.

The BCP is also used to process technical changes at the deliverable level and to notify the

Project team that an approved change has been implemented.

5.2.2.1 Technical Change Control

The following describes the change control procedures for technical changes at the deliverable

level:

Design Specifications: Design specifications for each deliverable are listed in a Technical

Specification Control Document (TSCD). The TSCD contains the relevant technical information

about each deliverable, such as WBS item number, title, owner and responsible organization,

technical specifications, change documentation, approvals and concurrences. The TSCD will

also include appropriate ATLAS agreement to ensure that ATLAS is aware and approves of the

changes and that these changes are consistent with the ATLAS Experiment.

The Project Engineer (PE), as PM’s designee, is responsible for ensuring that any changes to the

specifications of the deliverables are recorded, tracked and incorporated into the TSCD. This

document and its version are controlled through the US ATLAS HL-LHC Document Database

(DocDB) that is described in Section 4.1 Data Management Systems.

Page 20: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

20

To make changes to these specifications, a BCP must be completed and submitted to the PE.

The change request shall include a description and justification of the proposed change, with

appropriate backup documentation included, either attached or referenced, an evaluation of the

impact of the proposed change, and the newly proposed course of action for integrating this

change into the baseline scope. The PE is responsible for updating and integrating all changes

into the TSCD and maintaining the document. Design specifications that are no longer applicable

will be considered “obsolete” and archived in the DocDB for historical purposes.

Drawings and Schematics: Drawings and schematics, as applicable, will be uploaded and

maintained in the DocDB as versions become available. These drawings are owned by the

associated L3 manager, and reviewed and approved by the L2 manager. The L2 manager must

approve changes to these documents.

QA & Testing Procedures: Quality assurance and testing procedures will be documented for

each deliverable in a QA & Testing Procedures (TP) Document and maintained in the DocDB,

including the means by which the calibration and control of testing equipment will be achieved.

These procedures are owned by the L3 manager, and reviewed and approved by the L2 manager.

The L2 manager must approve changes to these procedures.

Approval/Concurrence and Interface Control: Updates to the specifications in the TSCD are

made by the PE prior to release of funds for the submission of every prototype cycle and/or any

significant design change for each deliverable. These updates consist of changes to the design

that are being integrated, ensuring the inclusion of relevant changes and interfaces originating

from both U.S. ATLAS and International ATLAS. The PE, in consultation with the PM, has

final concurrence and ownership of these parameters for U.S. ATLAS as he/she integrates the

changes into the TSCD. If ATLAS agreement is required for a given specification change, the L2

and L3 managers are responsible for ensuring that ATLAS collaborators and/or Project Leaders

are aware of the change, and that they are consistent with the ATLAS design prior to seeking

ATLAS approval. They are also responsible for ensuring that changes proposed on the

international ATLAS side that in any way affect US ATLAS deliverables are suitable discussed

within the US project, and their approval or opposition by the US project conveyed to the

appropriate international ATLAS responsible or body.

5.3 Configuration Status Accounting

Changes to CIs will be tracked via information uploaded into the DocDB by each of the

institutional principals, and the process managed by the Level 2 Managers, Deputies, and Level 3

Managers/CAMs. The individual data management systems at each of the sites, and on

International ATLAS at CERN, will in general be used to produce documentation for the Project.

Page 21: Configuration Management Plan US ATLAS HL-LHC Detector ... ATLAS HL-LHC CMP.pdfUS ATLAS HL-LHC Detector Upgrade Project 1 INTRODUCTION This Configuration Management Plan (CMP) describes

21

5.4 Configuration Verification

The Level 2 Project Managers are responsible for implementing and closing the CCB-approved

changes to CIs that are under their control. The signoff serves as notice that a document change

has been implemented and verified. The verification of hardware changes is reported by

reporting at following CCB meetings on the implementation status; where requested by the PM,

the Level 2 Manager will sign the bottom of the BCP to acknowledge his responsibilities in

implementation, and will archive this copy in the DocDB. In this manner, all changes can be

tracked to completion and easily audited. CIs will be periodically audited prior to delivery for

integration into the higher-level system to ensure that the as-built configuration conforms to the

configuration documentation.