    10/10/2011 NRLDC: POSOCO 1

    Grant ofGrant of Connectivity,LTAConnectivity,LTA, MTOA, MTOAInIn

    Interstate Transmission systemInterstate Transmission systemRegulation 2009Regulation 2009

    H K CHAWLA, DGMNRLDC, POSOCO

  • 7/28/2019 connectivity,LTA,MTOA

    2/63

    10/10/2011 ERLDC: POSOCO 2

    Contents

    Chapter 1:Chapter 1: DefinitionsDefinitions

    Chapter 2:Chapter 2: General provisionsGeneral provisions

    Chapter 3:Chapter 3: ConnectivityConnectivity

    Chapter 4:Chapter 4: LongLong--term and Mediumterm and Medium--termtermOpenOpen AccesAcces

    Chapter 5:Chapter 5: LongLong--term Accessterm Access

    Chapter 6:Chapter 6: MediumMedium--term Open Accessterm Open Access

    Chapter 7:Chapter 7: Conditions of LTA and MTOAConditions of LTA and MTOA

    Chapter 8:Chapter 8: Information SystemInformation System

    Chapter 9:Chapter 9: Repeals and SavingsRepeals and Savings

  • 7/28/2019 connectivity,LTA,MTOA

    3/63

    Act and Regulatory Provisions

    Generation was de-licensed in the

    Electricity Act 2003 Evacuation of power ensured through

    CERC notification of Long term openaccess in Jan 2004

    Utilization of ISTS for generation projects

    was granted by CTU under the regulatoryframework

  • 7/28/2019 connectivity,LTA,MTOA

    4/63

    CERC approval for implementation

    Regulatory approval was sought for implementation ofthe transmission system

    Based on grant of Open access Generation developers signing the BPTA

    Submission of bank guarantee

    The transmission scheme is under various stages ofimplementation

    Above was developed based on CERC notification, Jan2004

  • 7/28/2019 connectivity,LTA,MTOA

    5/63

    Regulatory frame work - August 2009

    Applicant-Who can apply?

    Connectivity Generating station >= 250MW & CPP of exportable capacity>=250MW

    50MW above for hydro/renewables(vide amendment Dtd.3rd

    Sep,2010)

    Bulk Consumer 100 MW and above for hydro/renewables < 50 MW individually but

    collectively aggregated to >= 50MW through lead generator

    Medium Term Open Access (MTOA) and Long Term

    Access (LTA) a generating station including captive generating plant a consumer an Electricity Trader or a distribution licensee

  • 7/28/2019 connectivity,LTA,MTOA

    6/63

    Chapter I: Definitions Connectivity:

    for a generating station, including a captive generatingplant, a bulk consumer or an inter-State transmission

    licensee means the state of getting connected to the inter-State transmission system

    Long Term Access:

    Right to use the inter-State transmission system for aperiod exceeding 12 years but not exceeding 25 years

    Consumer means any consumer eligible to avail open access as specified bythe State Commission under sub-section (2) of section 42 of theAct;

  • 7/28/2019 connectivity,LTA,MTOA

    7/63

    Definitions.. continued

    Long-term customer: means a person who has been granted long-term

    access and includes a person who has been allocatedcentral sector generation that is electricity supply from agenerating station owned or controlled by the CentralGovernment;

    Medium-term open access: means the right to use the inter-State transmissionsystem for a period exceeding 3 months but notexceeding 3 years;

    Medium-term customer means a person who has been granted medium-term

    open access;

  • 7/28/2019 connectivity,LTA,MTOA

    8/63

    Nodal agency:

    means the Central Transmission Utility referred to inregulation 4 hereof

    Regional entity

    means a person whose metering and energyaccounting are done at the regional level;

    Short-term open access has the meaning ascribed thereto in the CentralElectricity Regulatory Commission (Open Access ininter-State Transmission) Regulations, 2008;

    Definitions.. continued

  • 7/28/2019 connectivity,LTA,MTOA

    9/63

    State network:

    means the intra-State transmission system owned bythe State Transmission Utility, transmission licenseeor the network of any other person who has been

    granted licence by the State Commission to establishor operate distribution lines within the State;

    Stranded transmission capacity:

    means the transmission capacity in the inter-Statetransmission system which is likely to remainunutilized due to relinquishment of access rights by a

    long-term customer in accordance with regulation 16.

    Definitions.. continued

  • 7/28/2019 connectivity,LTA,MTOA

    10/63

    Chapter 2: General Provisions Scope

    Provided that a generating station, including captive generatingplant or a bulk consumer, seeking connectivity to the inter-Statetransmission system cannot apply for long-term access ormedium-term open access without applying for connectivity:

    Provided further that a person may apply for connectivity and

    long-term access or medium-term open access simultaneously.

    Nodal Agency

    The nodal agency for grant of connectivity, long-term access andmedium term open access to the inter-State transmission systemshall be the Central Transmission Utility.

  • 7/28/2019 connectivity,LTA,MTOA

    11/63

    Filing of Application

    Applications for grant of connectivity or long-term access ormedium-term open access shall be made to the nodal agency

    an application for connectivity is not required to be made by anytransmission licensee, since transmission system planning is

    carried out in a coordinated manner by the Central TransmissionUtility and the Central Electricity Authority

    an inter-State transmission licensee other than Central

    Transmission Utility, nevertheless, shall sign a connectionagreement with the Central Transmission Utility, as provided forin Clause (5) of regulation 8 of these Regulations.

    General provisions.. contd

  • 7/28/2019 connectivity,LTA,MTOA

    12/63

    General provisions contd

    Sl No Quantum of power tobe injected/off takeninto/from ISTS

    Application fees ` lakhs

    for for for

    Connectivity LTA MTOA

    1 Up to 100MW 2 2 1

    2 More than 100MWand up to 500MW

    3 3 2

    3 More than 500MWand upto 1000MW

    6 6 3

    4 More than 1000MW 9 9 4

    Application Fees

  • 7/28/2019 connectivity,LTA,MTOA

    13/63

    Time frame for processing

    General provisions contd

  • 7/28/2019 connectivity,LTA,MTOA

    14/63

    Chapter 3: Connectivity

    Grant of Connectivity

    The application for connectivity shall contain details such as,proposed geographical location of the applicant, quantum of power tobe interchanged, that is the quantum of power to be injected in thecase of a generating station including a captive generating plant andquantum of power to be drawn in the case of a bulk consumer, withthe inter-State transmission system and such other details as may belaid down by the Central Transmission Utility in the detailed procedure

    Provided that where after filing of an application, there has been any

    material change in the location of the applicant or change in thequantum of power to be interchanged with the inter-State transmissionsystem, by more than :

    100 MW in the case of generating station >= 250MW or CPP withexportable capacity of > = 250MW

    40% of the Installed capacity in the case of hydro station from 50to 250MW

    40% of the aggregate Installed capacity in the case of aggregatedgenerators individually < 50MW

  • 7/28/2019 connectivity,LTA,MTOA

    15/63

    Chapter 3: Connectivity Grant of Connectivity

    1. Provided further that the application by the applicant in case ofaggregated capacity >= 50MW but individually < 50MW defined undershall be considered by CTU only if all the generators, whose aggregatecapacity is connected at the single connection point, formalize a writtenagreement among themselves that the lead generator shall act on behalf

    of all the generators to undertake all operational and commercialresponsibilities for all the collective generators connected at that point infollowing the provisions of the Indian Electricity Grid Code and all otherRegulations of the Commission, such as grid security, scheduling anddispatch, collection and payment/ adjustment of Transmission charges,

    UI charges, congestion and other charges, etc., and submit a copy of theagreement to the CTU, with the application of connectivity, along with acopy to the respective RLDC in whose control area it is located.

    Amended vide order Dtd. 3rdSep,2010

    2. On receipt of the application, the nodal agency shall, in consultation and

    through coordination with other agencies involved in inter-Statetransmission system to be used, including State Transmission Utility, ifthe State network is likely to be used, process the application and carryout the necessary interconnection study as specified in the CentralElectricity Authority (Technical Standards for Connectivity to the Grid)

    Regulations, 2007.

  • 7/28/2019 connectivity,LTA,MTOA

    16/63

    Connectivity. contd

    3. While granting connectivity, the nodal agency shall specify the name of the sub-station or pooling station or switchyard where connectivity is to be granted. Incase connectivity is to be granted by looping-in and looping-out of an existing orproposed line, the nodal agency shall specify the point of connection and name ofthe line at which connectivity is to be granted. The nodal agency shall indicate thebroad design features of the dedicated transmission line and the timeframe for

    completion of the dedicated transmission line.

    4. The applicant and all Inter-State Transmission Licensees including the CentralTransmission Utility shall comply with the provisions of Central ElectricityAuthority (Technical Standards for Connectivity to the Grid) Regulations, 2007.

    5. The applicant or inter-State transmission licensee, as the case may be, shall sign aconnection agreement with the Central Transmission Utility or inter-Statetransmission licensee owning the sub-station or pooling station or switchyard orthe transmission line as identified by the nodal agency where connectivity is beinggranted.Provided that in case connectivity of a generating station, including captivegenerating plant or bulk consumer is granted to the inter-State transmissionsystem of an inter-State transmission licensee other than the Central TransmissionUtility, a tripartite agreement as provided in the Central Electricity Authority(Technical Standards for Connectivity to the Grid) Regulations, 2007 shall be

    signed between the applicant, the Central Transmission Utility and such inter-Statetransmission licensee.

  • 7/28/2019 connectivity,LTA,MTOA

    17/63

    Connectivity contd

    6. The grant of connectivity shall not entitle an applicant to interchange

    any power with the grid unless it obtains long-term access, medium-term open access or short-term open access.

    7. A generating station, including captive generating plant which has beengranted connectivity to the grid shall be allowed to undertake testingincluding full load testing by injecting its infirm power into the gridbefore being put into commercial operation, even before availing anytype of open access, after obtaining permission of the concerned RLDC,which shall keep grid security in view while granting such permission.This infirm power from a generating station or a unit thereof, other thanthose based on non-conventional energy sources, the tariff of which isdetermined by the Commission, will be governed by the Central

    Electricity Regulatory Commission (Terms and Conditions of Tariff)Regulations, 2009. The power injected into the grid from othergenerating stations as a result of this testing shall also be charged at UIrates.

    8. A thermal generating station of 500 MW and above and a hydrogenerating station or a generating station using renewable sources ofenergy of capacity of 250 MW and above, other than a captivegenerating plant, shall not be required to construct a dedicatedtransmission line to the point of connection and such station shall betaken into account for coordinated transmission planning by the

    Central Transmission utility and Central Electricity AuthorityAmended vide Order Dtd. 3rdSep,2010

  • 7/28/2019 connectivity,LTA,MTOA

    18/63

    Chapter 4 : LTA & MTOA

    Criteria for Grant: CTU to consider augmentation of ISTS proposed

    under the plans made by the Central Electricity

    Authority. MTOA shall be granted

    if the resultant power flow can be accommodated in theexisting transmission system or the transmission system

    under execution: no augmentation shall be carried out to the transmission

    system for the sole purpose of granting medium-term openaccess:

    Construction of a dedicated transmission line shall not beconstrued as augmentation of the transmission system forthe purpose

  • 7/28/2019 connectivity,LTA,MTOA

    19/63

    LTA & MTOA. contdRelative Priority:

    1.Applications for long-term access or medium-term open access shall beprocessed First-come-first-served basis separately for each of the aforesaid types

    of access: Applications received during a month shall be construed to have arrived

    concurrently.

    While processing applications for medium-term open access receivedduring a month, the application seeking access for a longer term shallhave higher priority.

    In the case of applications for long-term access requiring planning oraugmentation of transmission system, such planning or augmentation,as the case may be, shall be considered on 30th of June and 31st of

    December in each year in order to develop a coordinated transmissionplan, in accordance with the perspective transmission plans

    If an intra-State entity is applying for long-term access or medium-termopen access, concurrence of the State Load Despatch Centre shall beobtained in advance and submitted along with the application to thenodal agency

    2.State Load Despatch Centre shall convey its concurrence to the applicantwithin ten working days

    Where necessary infrastructure required for energy metering and time-blockwise accounting already exists and required transmission capacityin the State network exists

    3. In case SLDC decides not to give concurrence, the same shall becommunicated to the applicant in writing, giving the reason for refusal withinthe above stipulated period.

  • 7/28/2019 connectivity,LTA,MTOA

    20/63

    LTA & MTOA contd

    Interface Meters1. Interface meters shall be installed by the Central Transmission Utility for and at the cost of

    the regional entities;

    by the State Transmission Utility for and at the cost ofthe State entities.

    2. Interface meters for the regional entities shall be open forinspection by

    any person authorized by the Central Transmission Utilityand the Regional Load Despatch Centre.

    3. Interface meters for the intra-State entities shall be openfor inspection

    by any person authorized by the State TransmissionUtility or the State Load Despatch Centre.

  • 7/28/2019 connectivity,LTA,MTOA

    21/63

    Chapter 5 : Long Term Access

    Application

    Name of the entity/ies

    Quantum of power to be transacted

    Name of the target region where electricity is proposed to beinterchanged in case augmentation required but exactsource/destination not firmed up

    Exact source of source of supply/destination of offtake to befirmed up at least three years prior to availing intended date ofLTA

    Any other information sought by Nodal agency

    BG of Rs.10000/- per MW of power

    In favor of Nodal agency

    Validity till execution of LTA in case of augmentation Till operationalization of LTA when no augmentation reqd

    Encashment in case of withdrawal or relinquishment ofLTA rights prior to operationalization for no augmentation

    Discharged on submission of new BG for construction phin case of augmentation

  • 7/28/2019 connectivity,LTA,MTOA

    22/63

    Long Term Access.. contd

    1. Nodal agency to carry out the necessary system studiesthrough coordination with agencies including StateTransmission Utility, if the State network is likely to beused

    2. Based on the system studies, the nodal agency shallspecify the inter- State transmission system that wouldbe required to give long-term access. In case

    augmentation to the existing inter-State transmissionsystem is required, the same will be intimated to theapplicant.

    3. The Empowered Committee established in accordance

    with the Tariff based Competitive-bidding Guidelines forTransmission Service issued by the CentralGovernment, may identify one or more elements neededfor augmentation of inter-State transmission system tobe developed through tariff based competitive bidding

    System Studies

  • 7/28/2019 connectivity,LTA,MTOA

    23/63

    Communication of Estimate of Transmission Charges, etc.

    the date from which long-term access shall be granted an estimate of the transmission charges likely to be payable based on

    the prevailing costs, prices and methodology of sharing of transmissioncharges specified by the Commission.

    Execution of Long-term Access AgreementThe applicant shall:

    sign an agreement for long-term access with the CTU. shall sign a tripartite long-term access agreement with the Central

    Transmission Utility and the inter-State transmission licensee in case of

    seeking LTA from ISTS licensee other than CTU The longterm access agreement shall contain

    the date of commencement of long-term access the point of injection of power into the grid point of drawal from the grid the details of dedicated transmission lines, if any In case augmentation of transmission system is required, the long-

    term access agreement shall specify: the time line for construction of the facilities

    the bank guarantee required other details in accordance with the procedure.

    Long Term Access.. contd

  • 7/28/2019 connectivity,LTA,MTOA

    24/63

    Long Term Access..contd

    Information to RLDC and SLDC

    Immediately after grant of long-term access, thenodal agency shall inform the RLDCs and the SLDCsconcerned so that they can consider the same whileprocessing requests for grant of short-term openaccess

    Renewal of Term for Long-term access

    On expiry the LTA shall stand extended on a written requestprovided by the long-term customer

    LTA customer to mention the period for extension that isrequired

    The written request shall be submitted by the customer tothe Central Transmission Utility at least six months prior tothe date of expiry

    In case no written request, access shall stand withdrawn.

  • 7/28/2019 connectivity,LTA,MTOA

    25/63

    Long-term Access contd

    Relinquishment of access rights1. A long-term customer may relinquish the long-term access rights fully or

    partly before the expiry of the full term of long-term access, by makingpayment of compensation for stranded capacity as follows:-

    (a)Long-term customer who has availed access rights for at least 12 years

    (i) Notice of one (1) year application to the CTU at least 1 (one) year prior to the date from whichsuch customer desires to relinquish the access rights, there shall be nocharges.

    (ii) Notice of less than one (1) year application to the CTU at any time lesser than a period of 1 (one) year

    customer shall pay an amount equal to 66% of the estimatedtransmission charges (net present value) for the stranded transmissioncapacity for the period falling short of a notice period of one (1) year.

    L A d

  • 7/28/2019 connectivity,LTA,MTOA

    26/63

    Long-term Access contd

    Relinquishment of access rights..ctd

    (b) Long-term customer who has not availed access rights for at least12 (twelve) years

    such customer shall pay an amount equal to 66% of theestimated transmission charges (net present value) for thestranded transmission capacity for the period falling short of12 (twelve) years of access rights:

    shall submit an application to CTU at least 1 (one) year prior tothe date

    in case a customer submits an application for relinquishmentof long term access rights at any time at a notice period of lessthan one year, then such customer shall pay an amount equalto 66% of the estimated transmission charges (net presentvalue) for the period falling short of a notice period of one (1)

    year, in addition to 66% of the estimated transmission charges(net present value) for the stranded transmission capacity forthe period falling short of 12(twelve) years of access rights.

  • 7/28/2019 connectivity,LTA,MTOA

    27/63

    Long-term Access .. contd

    The discount rate that shall be applicable for computingthe net present value as referred to in sub-clause (a) and(b) of clause (1) above shall be the discount rate to beused for bid evaluation in the Commissions Notification

    issued from time to time in accordance with theGuidelines for Determination of Tariff by Bidding Processfor Procurement of Power by Distribution Licenseesissued by the Ministry of Power.

    The compensation paid by the long-term customer forthe stranded transmission capacity shall be used forreducing transmission charges payable by other long-

    term customers and medium-term customers in the yearin which such compensation payment is due in the ratioof transmission charges payable for that year by suchlong term customers and medium-term customers.

  • 7/28/2019 connectivity,LTA,MTOA

    28/63

    Chapter 6: MTOA

    Application for Medium-term Open Access The application for grant of medium-term open accessshall contain the point of injection into the grid, point of drawal from the grid

    and the quantum of power for which medium-term openaccess has been applied for.

    The start date of the medium-term open access shallnot be earlier than 5 months and

    not later than 1 year from the last day of the month in whichapplication has been made.

    System Studies by the Nodal Agency On receipt of the application, the nodal agency shall, in

    consultation and through coordination with other agenciesinvolved in inter-State transmission system to be used, includingState Transmission Utility, if the State network is likely to be used,process the application and carry out the necessary systemstudies as expeditiously as possible so as to ensure that thedecision to grant or refuse medium-term open access is madewithin the timeframe

  • 7/28/2019 connectivity,LTA,MTOA

    29/63

    MTOA contd

    Grant of MTOA

    The applicant shall: sign an agreement for MTOA with the CTU. shall sign a tripartite agreement with the Central Transmission

    Utility and the inter-State transmission licensee in case ofMTOA from ISTS licensee other than CTU

    The MTOA shall contain

    the date of commencement of long-term access the point of injection of power into the grid point of drawal from the grid the details of dedicated transmission lines, if any Immediately after grant of MTOA, the nodal agency shall

    inform the RLDCs and the SLDCs concerned so that theycan consider the same while processing requests for grantof short-term open access

    MTOA contd

  • 7/28/2019 connectivity,LTA,MTOA

    30/63

    MTOA .. contd

    Execution of Dedicated Transmission LineMedium-term customer may arrange for execution of thededicated transmission line at its own risk and cost before thestart date of the mediumterm open access.

    No overriding preferenceOn the expiry of period of the medium-term open access, themedium-term customer shall not be entitled to any overridingpreference for renewal of the term.

    Exit option for medium-term customersA medium-term customer may relinquish rights, fully or partly, bygiving at east 30 days prior notice to the nodal agency: Provided

    that the medium-term customer relinquishing its rights shall payapplicable transmission charges for the period of relinquishmentor 30 days which ever is lesser.

    Ch 7 C di i f LTA & MTOA

  • 7/28/2019 connectivity,LTA,MTOA

    31/63

    Chapter 7: Conditions of LTA & MTOA

    Curtailment1. Transmission constraints or in the interest of grid

    security - transactions already scheduled may becurtailed by the Regional Load Despatch Centre.

    2. Subject to provisions of the Grid Code and any otherregulation specified by the Commission,

    the short-term customer shall be curtailed firstfollowed by the

    medium-term customers, which shall be followedby

    the long term customers and amongst the customers of a particular category,

    curtailment shall be carried out on pro ratabasis.

    C diti f LTA & MTOA

  • 7/28/2019 connectivity,LTA,MTOA

    32/63

    Conditions of LTA & MTOA

    Transmission Charges

    The transmission charges for use of the inter-State transmissionsystem shall be recovered from the long-term customers and themedium-term customers in accordance with terms and conditionsof tariff specified by the Commission from time to time

    Provided that if the State network is also being used in the accessas a part of inter-State transmission system for the conveyance ofelectricity across the territory of an intervening State as well asconveyance within the State which is incidental to such inter-

    State transmission of electricity, recovery of charges for suchState network and terms and conditions thereof shall be inaccordance with the regulation as may be specified by theCommission under 25 section 36 of the Act for interveningtransmission facilities, if such charges and terms and conditionscannot be mutually agreed upon by the licensees;

    Provided that any disagreement on transmission charges forsuch State network as specified above, shall not be the solereason for denying access and either party may approach theCommission for determination of transmission charges for such

    State network.

    C di i f LTA & MTOA

  • 7/28/2019 connectivity,LTA,MTOA

    33/63

    Detailed Procedure1.Subject to the provisions of these regulations,

    the Central Transmission Utility shall submit the detailedprocedure to the Commission for approval within 60 days ofnotification of these regulations in the Official Gazette:

    Provided that prior to submitting the detailed procedure tothe Commission for approval, the Central TransmissionUtility shall make the same available to the public and invitecomments by putting the draft detailed procedure on itswebsite and giving a period of one month to submitcomments;

    Provided further that while submitting the detailed procedureto the Commission, the Central Transmission Utility shallsubmit a statement indicating as to which of the commentsof stakeholders have not been accepted by it along with

    reasons thereof.

    Conditions of LTA & MTOA

    Conditions of LTA & MTOA

  • 7/28/2019 connectivity,LTA,MTOA

    34/63

    2.The detailed procedure submitted by the CTU shall, inparticular, include(a) The proforma for the connection agreement(b) The proforma for the long-term access agreement(c) The time line for phasing of construction/modification of the transmission

    elements by the Central Transmission Utility/transmission licensee, as thecase may be, and the coming up of generation facilities or facilities of bulkconsumer, as the case may be, so as to match the completion times of thetwo;

    (d) Aspects such as payment security mechanism and bank guarantee duringthe period of construction operation. Provided that the bank guarantee

    during construction phase shall not exceed Rs. 5 lakh per MW of the totalpower to be transmitted by that applicant through inter-State transmissionsystem.

    (d) The proforma for the medium-term open access: agreement, referred to inthe second proviso to clause (1) of regulation 21 above.

    (e) Provisions for collection of the transmission charges for inter- Statetransmission system from the long-term customers or medium-termcustomers, as the case may be, by the transmission licensee or the CentralTransmission Utility as and when so designated in accordance with the firstproviso to clause (1) of regulation 29 hereof and disbursement to theCentral Transmission Utility and/or the transmission licensees as the casemay be.

    Conditions of LTA & MTOA

    Conditions of LTA & MTOA

  • 7/28/2019 connectivity,LTA,MTOA

    35/63

    Fees and charges for the Regional Load Despatch Centreand the State Load Despatch Centre

    1.The fees and charges for the Regional LoadDespatch Centre including charges for theUnified Load Despatch and CommunicationScheme shall be payable by the long-termcustomer and medium-term customer as maybe specified by the Commission.

    2.The fees and charges for the State Load

    Despatch Centre shall be payable asapplicable.

    Conditions of LTA & MTOA

    Conditions of LTA & MTOA

  • 7/28/2019 connectivity,LTA,MTOA

    36/63

    Payment of transmission charges and Fees and Charges for the Regional LoadDespatch Centre1. The transmission charges in respect of the LTA and MTOA

    customer payable directly to the transmission licensee: CTU may be designated by the Commission as agency for the

    purpose of collecting and disbursing the transmission chargesfor ISTS CTU shall enter into agreements with the long-term customers

    and medium-term customers for collection of transmissioncharges and with the transmission licensees whose inter-Statetransmission system is being used

    disbursement of transmission charges: pro rata to thetransmission charges payable to the transmission licenseesand to the Central Transmission Utility

    Provided also that the CTU shall be entitled to reimbursementof reasonable costs incurred by it in collecting the

    transmission charges

    3. The fees and charges for RLDCs (including the charges for UnifiedLoad Despatch Scheme) and SLDCs shall be payable by the long-term customer and medium-term customer directly to the RLDCsor the SLDCs concerned.

    Conditions of LTA & MTOA

    Conditions of LTA & MTOA

  • 7/28/2019 connectivity,LTA,MTOA

    37/63

    Unscheduled Inter-change (UI) Charges1. Scheduling of all transactions pursuant to grant of long-

    term access and medium-term open access shall becarried out on day-ahead basis in accordance with theGrid Code.

    2. Based on net metering on the periphery of each regionalentity, composite accounts for Unscheduled Interchangesshall be issued for each regional entity on a weekly cycle:

    Provided that Unscheduled Inter-changes accounting forintra-State entities shall not be carried out at the regionallevel.

    3. The State utility designated for the purpose of collection or

    disbursement of the Unscheduled Interchanges chargesfrom or to the intra- State entities shall be responsible fortimely payment of the States composite dues to theregional Unscheduled Interchanges Pool Account Fund.

    Conditions of LTA & MTOA

    Conditions of LTA & MTOA

  • 7/28/2019 connectivity,LTA,MTOA

    38/63

    4. Any mismatch between the scheduled and the actual drawal at drawalpoints and scheduled and the actual injection at injection points for theintra- State entities shall be determined by the concerned State LoadDespatch Centre and covered in the intra-State UnscheduledInterchanges accounting scheme.

    5. Unless specified otherwise by the State Commission concerned, theUnscheduled Interchanges rate for intra-State entity shall be 105% (foroverdrawals or under generation) and 95% (for under-drawals or overgeneration) of the Unscheduled Interchanges rate at the periphery of

    regional entity.

    Transmission LossesThe buyers of electricity shall bear apportioned losses in thetransmission system as estimated by the Regional Power Committee.

    Redressal MechanismAll disputes arising out of or under these regulations shall be decidedby the Commission on an application made in this behalf by the

    person aggrieved.

    Conditions of LTA & MTOA

  • 7/28/2019 connectivity,LTA,MTOA

    39/63

    Chapter 8: Information System The nodal agency shall post the following documents / information on itswebsite in a separate web-page titled Long-term access and Medium-term open access information:

    a) These regulations;

    b) Detailed procedure;c) List of applications, separately, for LTA and MTOA received by the nodal agency

    along with necessary details.d) Separate lists for LTA and MTOA granted, indicating-

    (i) Name of customers;

    (ii) Period of the access granted (start date and end date);(iii) Point or points of injection;(iv) Point or points of drawal;(v) Transmission systems used (in terms of regions and States);(vi) Capacity (MW) for which access has been granted.

    e) List of applications where approval for connectivity or LTA or MTOA, as the casemay be, has not been granted along with reasons thereof.

    nodal agency to take steps in accordance with the requirements hereinto provide as much information suo motu to the public at regularintervals through various means of communications, including internet,

    so that information is disseminated widely and in such form and mannerwhich is easily accessible to the public.

  • 7/28/2019 connectivity,LTA,MTOA

    40/63

    Chapter 9: Repeal and Savings

    (1) On commencement of these regulations, Regulation No.s4(1)(a), 4(ii), 5(i), 6(i), 7, 8(i), 9, 10, 11, 12, 16(i), 18, as faras it applies to long-term customers, and 31(i) of theCentral Electricity Regulatory Commission (OpenAccess ininter-State Transmission) Regulations, 2004, shall stand

    repealed.(2) Notwithstanding anything contained in clause (1), long-

    term access granted in accordance with the Central

    Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004 shall continue to bevalid till the expiry of the term of long-term access.

  • 7/28/2019 connectivity,LTA,MTOA

    41/63

    Issues Ensuring commitment of either parties (Jan 2004 regulation)

    BPTA was signed and BG was submitted

    In the new regulation (Aug 2009) :Readiness of the generation is more critically monitored for aspects like land

    under possession, water , coal , environmentalDevelopers should realistically bring out the factual position so that an

    adequate transmission proposal can be evolved and taken further afterexamination from various aspects.

    Any under-provision or over-provision of transmission network leads to Gridoperational problems like congestion, over-voltage situation Ultimatelycausing constraints in generation or ensuring power availability to

    consumer.As per IEGC ; Generation developers have apply for signing of connectionagreement also ensureapproval under Sec 68 of Act from Govt of India isobtained

  • 7/28/2019 connectivity,LTA,MTOA

    42/63

    PROCEDURES FORCONNECTIVITY/LTA/MTOA

    CONNECTIVITY PROCEDURES

  • 7/28/2019 connectivity,LTA,MTOA

    43/63

    CONNECTIVITY PROCEDURES

    Eligibility

    Nodal agency

    No additional connectivity for same capacity

    Connection agreement / tripartite agreement

    Information to be submitted alongwith connectivity application:

    Site identification and land acquisition

    Environmental clearance

    Forest clearance(if applicable)

    Fuel arrangements

    Water linkage

    Affadavit alongwith these docs as per format CON-1

    Application as per Format CON-2

    Application during a month treated as received concurrently

  • 7/28/2019 connectivity,LTA,MTOA

    44/63

    PROCESSING TIMEFRAMES

    CONNECTIVITY PROCEDURES

  • 7/28/2019 connectivity,LTA,MTOA

    45/63

    change in connectivity requirement Eligibility

    fresh application for change in requirement by > 100Mw/40% of IC, aggregate IC asper format CON-2

    Intimation to applicant for grant of connectivity within 60days of last day ofmonth on which app. Received as per CON3

    Additional information as per CON-4 at least > 2 years prior to physicalconnectivity

    Further processing by CTU & intimation of connectivity details as per CON-5 Connection agreement as per CON-6 & tripartite agreement in case of any

    other ISTS licensee

    Nodal agency to provide copy of connectivity agreement to concerned

    SLDC/RLDC

    CONNECTIVITY PROCEDURES

  • 7/28/2019 connectivity,LTA,MTOA

    46/63

    No interchange of power except LTA/MTOA/STOA

    A generating station, including captive generating plant which has beengranted connectivity to the grid shall be allowed to undertake testing

    including full load testing by injecting its infirm power into the grid beforebeing put into commercial operation, even before availing any type of openaccess, after obtaining permission of the concerned Regional Load DespatchCentre, which shall keep grid security in view while granting such

    permission. This infirm power from a generating station or a unit thereof,other than those based on non-conventional energy sources, the tariff ofwhich is determined by the Commission, will be governed by the Central

    Electricity Regulatory Commission (Terms and Conditions of Tariff)Regulations, 2009. The power injected into the grid from other generatingstations as a result of this testing shall also be charged at UI rates.

    In the procedures

    drawal of power for commissioning activities mentioned as allowable

    without OA

    Station shall submit likely date of synchronization, likely quantum andperiod of injection of infirm power before being put into commercialoperation to the SLDC and RLDC concerned at least one month in

    advance.

    CONNECTIVITY PROCEDURES

  • 7/28/2019 connectivity,LTA,MTOA

    47/63

    Conditions for construction of dedicated transmission system by CTU

    BG as per con-7 2.5L/mw FOR < 20kM & 5L/MW for > 20MW or only forconnectivity work in case line constructed by applicant

    Agreement with CTU as per CON-8

    For Connectivity/LTA concurrently max 5L/MW

    Time frame for commissioning from dt. of signing of BPTA/TSA Sharing of dedicated line

    MTOA PROCEDURES

  • 7/28/2019 connectivity,LTA,MTOA

    48/63

    Nodal agency : CTU

    earlier than 5 months and later than 1 year from the last day of the month inwhich application has been made

    MTOA > 3 mo & < 3yrs with exception cl. For delay in CTU construction

    MTOANo augmentation of transmission system is envisaged &

    Construction of dedicated transmission line shall not be construed asaugmentation of the transmission system.

    A power transaction involving combination of both multiple injections andone drawl point in case the MTOA is sought by a single bulk consumer shallnot require filing of separate applications.

    Eligibility for MTOAgenerating station/captive generating plant/consumer/Electricity Trader/distribution licensee/State Government owningsome quantum of power (like free power given to the State Government in

    which the hydro station is located, equity power given to a State for allowing

    a power station to be set up in the State), who desires to utilize ISTS for Interstate transfer of power, provided the power station from which the power isbeing sourced or the load, as the case may be, is already connected to thegrid, whether the State grid or the inter-State grid, or is likely to getconnected to the grid before the intended start date of MTOA

    Documentary evidences

  • 7/28/2019 connectivity,LTA,MTOA

    49/63

    MTOA PROCEDURES

    No application for medium-term open access without applying for connectivity(ifnot connected)

    Whether connectivity reqd. in case embedded in a control area?

    Correctness of Application info to affirmed vide affidavit MTOA-I Application MTOA-II with SLDC clearances

    SLDC clearances MTOA-III within 10days or reasons for refusal

    Application fees:

    MTOA PROCEDURES

  • 7/28/2019 connectivity,LTA,MTOA

    50/63

    MTOA timelines:

    All apps. In a month construed to have come together on last day ofmonth(M0)

    Approval on FCFS basis

    CTU studies & circulation to SLDC/RLDCs 15th of M1

    Calculation methodology for TTC , RM

    Comments on studies upto 25th

    of M1 Provisional decision to grant MTOA 10th of M3

    Within a month, priority more for those seeking MTOA for longer duration

    CTU shall notify the following on 31st day of March of each year:

    Total Transfer Capability (TTC) for 4 (four) years. This may be revised by CTU due

    to change in anticipated network topology or change of anticipated generation orload at any of the nodes, giving reasons for such change. TransmissionReliability Margin considered along with basis.

    Available Transfer Capability (ATC) for MTOA will be worked out after allowing thealready approved applications for Long-term access, Medium Term Open Accessand Transmission reliability margin.

    The grant of MTOA shall be subject to ATC as per MTOA-IV

    Sharing of transmission charges agreement MTOA-V-30days

    BG for 2 months transmission charges 30days bi-annual review

    Informtion to RLDC/SLDCs

    Tripartite agreement for other ISTS licensee No over-riding preference for previous holder

    MTOA SCHEDULING

  • 7/28/2019 connectivity,LTA,MTOA

    51/63

    Priority

    Underutilization of corridor If request for scheduling is consistently (for more than 5 days) lower than the

    capacity granted by the Nodal Agency (i.e.; CTU), RLDC may issue a notice to

    such MTOA customer asking the reasons for such under-utilization. TheMTOA customer shall furnish the reasons for such under-utilization and will

    provide such details like the reduced requirement, likely period, etc. by thefollowing day. The un-utilized transfer capability will then be released forscheduling of Short-term open access transaction.

    No refund of transmission charges shall be made due to above curtailment

    Transmission cherges as per Terms & conditions of Tariff-9-14 Billing/collection & disbursement by CTU & adminstrative charge payable

    STU charges as per SERC norms

    Irrevocable revolving LC for 105% of average monthly charges 15 daysbefore MTOA commencement

    BG of 2mo also to be concurrently < 3mo prior to scheduled commencementdate and > 1mo after expiry of MTOA period

    RLDC/ULDC fees & charges payable to RLDC

    BG encashed in case of default & to be recouped

    Downsizing of application BG adjusted after expiry of MTOA period

    MTOA EXIT/DOWNSIZING

  • 7/28/2019 connectivity,LTA,MTOA

    52/63

    At least 30 days notice

    Exit charges minimum of [30 days of period of relinquishment] Exit charges used for reducing transmission charges payable by other long-

    term customers and medium-term customers in the year in which such

    compensation payment is due in the ratio of transmission charges payablefor that year by such long term customers and medium-term

    For upward revision fresh application

    LTA PROCEDURES

  • 7/28/2019 connectivity,LTA,MTOA

    53/63

    Eligibility conditions same as MTOA

    For LTA applicant:(i) already be connected to grid, whether the State grid or the inter-State grid,(ii) have already been granted permission for connectivity to the grid

    (iii) have already applied for connectivity to the grid

    (iv) be making application for connectivity to the grid simultaneously withthis application in line with the Regulations

    Documents with application

    LTA 12 -25 Yrs period

    May require Transmission augmentation

    Provision of target regions in case PPAs(purchasing entities) not firmed up

    applicant shall have to firm up exact source of supply or destination, as thecase may be, at least 3 years prior to the intended date of availing long term

    access at least for a capacity equivalent to 50% of the quantum of power forwhich LTA has been sought for through signing of PPA with such gridconnected entity(ies)/ State Utilities.

    LTA PROCEDURES

  • 7/28/2019 connectivity,LTA,MTOA

    54/63

    The augmentation of the transmission system as identified for grant of LTAshall be undertaken only after fulfillment of above condition. In case acommon system augmentation/strengthening has been identified for morethan one generator, then the above condition of signing of PPA for at least

    50% of LTA sought for, with the grid connected entity(ies)/ State Utilities,shall have to be met by all the generators.

    In the event of failure of any generator meeting above condition of 3 yearsprior to the intended date of availing long term access, the implementation ofaugmentation/strengthening of system shall be undertaken in dueconsideration of the same and if necessary with the approval of CERC for the

    same.(Grant of regulatory approval for execution of ISTS schemes to CTU)

    For the balance capacity (not exceeding 50% of LTA sought for) for whichexact source of supply or destination could not be firmed up on long-term

    basis, the augmentation/system strengthening further from the target regionshall be taken up only after identification of exact source/destination. CTUshall be allowed up to 3 years time for such augmentation/systemstrengthening from the target region to the exact source/destination. During

    such period the applicant shall be liable to pay the transmission charges up

    to the target region.

    LTA PROCEDURESP t f h t i i h f th b l it f hi h

  • 7/28/2019 connectivity,LTA,MTOA

    55/63

    Payment of such transmission charges for the balance capacity for whichexact source on long term basis is not known, shall not entitle the applicantany right over the transmission system up to the target region and CTU mayrelease this balance transmission capacity up to target region for short-term

    open access or the medium term open access till the applicant firms upsource/destination on long-term basis and its operationalisation.

    However, applicant may seek short-term open access or the medium termopen access separately till such time it gets long-term access for the balancecapacity as any other short-term open access customer or the medium termopen access customer.

    As it takes about 9 months for pre-investment activities and in additionconstruction time for the transmission project as given in the CERC (Termsand Conditions of Tariff)Regulations, 2009, applicant should expedite the

    finalization the beneficiaries and intimate to CTU. The date of commencementof LTA shall be applicable from atleast 3 years and 9 months (9 months timerequired for project preparation and investment approval) from firming upbeneficiaries and signing of BPTA/TSA with them.

    Application for change in quantum/location as per MTOA procedures

    Nodal agency CTU

    LTA PROCEDURESA li ti i F t LTA 2 ith ffid it LTA 1

  • 7/28/2019 connectivity,LTA,MTOA

    56/63

    Application in Format LTA-2 with affidavit as per LTA-1

    Period for 12 to 25 yrs Not earlier than 3 yrs from last date of month of receipt of application

    Multiple injection to single pt or single injection to multiple point allowable

    Connectivity information to be furnished

    Embedded utilities

    concurrance as per LTA-3 BG of Rs.10,000/MW as per LTA-4

    BG will stand discharged with operationalization of long-term open access,when augmentation of transmission system is not required or thesubmission of appropriate bank guarantee required to be given by the

    applicant to the CTU during construction phase when augmentation oftransmission system is required

    The bank guarantee may be encashed by the nodal agency,

    (i) if the application is withdrawn by the applicant or(ii) the long-term access rights are relinquished prior to theoperationalisation of such long-term access when augmentation oftransmission system is not required.

    LTA PROCEDURES(iii) If the applicant fails to sign the Long Term Access Agreement with CTU

  • 7/28/2019 connectivity,LTA,MTOA

    57/63

    (iii) If the applicant fails to sign the Long Term Access Agreement with CTUor a tripartite agreement with CTU and transmission licensee, as the casemay be, and fails to furnish appropriate BG for construction phase, withinstipulated time as indicated in the intimation letter.

    (iv) If the applicant fails to revalidate the earlier furnished BG at least 30 daysprior to its expiry.

    (v) If the applicant fails to firm up beneficiaries,3 years prior to intended dateof Long Term Access. Genuine requests for extension of time shall besuitably accommodated on merit upon furnishing of documentaryevidence(s).

    Empowered Committee established in accordance with the Tariff based

    Competitive-bidding Guidelines for Transmission Service issued by theCentral Government, may identify one or more elements needed foraugmentation of inter-State transmission system to be developed throughtariff based competitive bidding:

    Provided that the agency identified to construct one or more elementsneeded for augmentation of the inter-State transmission system for long-termaccess shall be eligible for grant of transmission licence in accordance withthe regulations specified by the Commission from time to time and the

    guidelines for competitive bidding for transmission issued by the Central

    Government.

    LTA - APPLICATION PROCESSING The applications shall be processed on first come first served basis The

  • 7/28/2019 connectivity,LTA,MTOA

    58/63

    The applications shall be processed on first-come-first-served basis. Theapplications received during a month and upto the last day of the month shallbe construed to have arrived concurrently.

    System studies to be carried out by CTU methodology for TTC, RMcalculations similar to MTOA

    In case system augmentation not reqd CTU proposal to be discussed in

    RPCs & planning forum & grant to be given within 120days Transmission system augmentation planning shall be considered on 30th of

    June and 31st of December in each year in order to develop a coordinatedtransmission plan. The applications received during 1st half of the calendaryear shall be considered together by 30th June and finalized by 31st Dec of

    the same calendar year. Similarly application received during the 2nd half ofthe calendar year shall be considered together by 31st December andfinalized by 30th June of the next calendar year. The intimation for grant ofLTA as per the provisions of Regulations shall be communicated to the

    applicant and RLDC/NLDC with copy to all the constituent States of theregion(s) involved, transmission licensee (if any), concerned RPC(s) and CEA

    While granting long-term access in ISTS, the nodal agency shallcommunicate to the applicant, the date from which long-term access is

    granted and an estimate of the transmission charges likely to be payable

    LTA - APPLICATION PROCESSING Confirmation of LTA where system strengthening not required:

  • 7/28/2019 connectivity,LTA,MTOA

    59/63

    Confirmation of LTA where system strengthening not required:

    Grant of LTA within 120days as per LTA-5

    Applicant to enter into BPTA/TSA within 30days

    LTA agreement/tripartite agreement within 30days

    Confirmation of LTA where system strengthening required:

    Same with system strengthening elements identified

    Nodal agency may further optimize without disadvantage to applicant

    Cosntruction Ph BG to be restricted to Rs.5L/MW in case of concurrentapplication of connectivity/LTA & construction of dedicated line not required

    UI accounting: Unless specified otherwise by the State Commission concerned, the

    Unscheduled Interchanges rate for intra-State entity shall be 105% (foroverdrawals or under generation) and 95% (for under-drawals or overgeneration) of the Unscheduled Interchanges rate at the periphery of regional

    entity

    LTA - APPLICATION PROCESSING In case of applicants who have already firmed up the entity or entities to

  • 7/28/2019 connectivity,LTA,MTOA

    60/63

    In case of applicants who have already firmed up the entity or entities towhom electricity is proposed to be supplied or from whom electricity isproposed to be procured for the entire quantum of power for which LTA hasbeen sought through signing of PPA or, in the case of Inter-State Generating

    Stations owned by the Central Government or Ultra Mega Power Projectscoming up through the initiative of the Central Government, allocation of

    power to various beneficiaries as notified by it, then the applicant shall notbe required to submit Bank Guarantee(BG) with the application form or theConstruction Stage BG. In such cases, however, the augmentation of thetransmission system as identified for grant of LTA shall be undertaken onlyafter agreement of the beneficiaries in Standing Committee on Power System

    Planning/Regional Power Committee for bearing its transmission charges.The applicant shall submit a copy of PPA or notification made by Govt. of

    India, whichever is applicable. The long-term access agreement, may, in suchcases be directly signed by the beneficiaries with the CTU or tripartiteagreement with the CTU and ISTS, as the case may be

    System strengthening work to be taken up by CTU/Licensee/empoweredcommittee or on basis of competitive bidding

    Applicant 90days ahead w.r.t COD/commercialization

    Nodal 60days ahead intimation w.r.t payment security mech & intimation to

    RLDCs/SLDCs

    LTA - APPLICATION PROCESSING Priority

  • 7/28/2019 connectivity,LTA,MTOA

    61/63

    Priority

    Transmission constraints

    Curtailment nor refunds LTA may be extended as per the desired extension period on request by LTA

    holder at least 6months in advance

    Surrender of LTA rights

    Compensation for stranded transmission capacity for LTA customers havingavailed access rights for 12yrs min

    Notice period of 1yrs no charges

    66% of transmission charge(NPV) corr. to period which fell short of thenotice period of 1 year

    Compensation for stranded transmission capacity for LTA holders who haveavailed access rights for less than 12yrs

    With a notice period of 1 yr transmission charges(NPV) corr. to 66% oftransmission charges for the period falling short of 12yrs

    For notice < 1yr, 66% of transmission charges(NPV) for the period short of notice

    period of 1 year

    discount rate for NPV the discount rate to be used for bid evaluation in theCommissions Notification issued from time to time in accordance with theGuidelines for Determination of Tariff by Bidding Process for Procurement of

    Power by Distribution Licensees issued by the Ministry of Power

    LTA - APPLICATION PROCESSING Compensation reducing transmission charges payable by other long-term

  • 7/28/2019 connectivity,LTA,MTOA

    62/63

    Compensation reducing transmission charges payable by other long termcustomers and medium-term customers in the year in which suchcompensation payment is due in the ratio of transmission charges payablefor that year by such long-term customers and medium-term customers

    However, some of the dedicated transmission system indicated at Annexure-3 i.e. from the generation switchyard up to various pooling

    points/substations shall be built, owned and operated by POWERGRID. Thetransmission charges for these dedicated transmission system shall be paidby the concerned generation developers.

    The charges for the transmission system (other than the dedicated system)indicated at Annexure-3 would be borne by the generation developers in

    proportion to capacity for which long term open access has been sought.The transmission charges will be corresponding to phased development oftransmission system and in each time frame, charges should be shared by all

    the generation developer whose generation projects are scheduled to comeup in that time frame or earlier.

    The long term Open Access Applicants would also have to share theapplicable Regional transmission charges in proportion to the Long termcapacity sought by them as per CERC norm.

    LTA - APPLICATION PROCESSING As the transmission system has been evolved considering target

  • 7/28/2019 connectivity,LTA,MTOA

    63/63

    As the transmission system has been evolved considering targetbeneficiaries and tentative allocation indicated by the developer(s) in theirapplication, some transmission strengthening may be required in thereceiving end/region once the beneficiaries/quantum of allocation is finalized.

    The cost/tariff of such system strengthening would also have to be borne bythe developer(s) as and when identified.

    In the event of default by any developer under Clause 5 and 6 of thisAgreement, the transmission charges for the system mentioned at Annexure-3 would be shared by balance developers. However, the damages collected(if any) from the defaulting developer(s) under clause 5 & 6 of this agreementshall be adjusted for the purpose of claiming transmission charges from the

    balance (remaining) developers.