+ All Categories
Home > Documents > CONSENT AUTHORITY: PALMERSTON NORTH CITY COUNCIL …...Advice Note: Any variance from the location,...

CONSENT AUTHORITY: PALMERSTON NORTH CITY COUNCIL …...Advice Note: Any variance from the location,...

Date post: 15-Mar-2020
Category:
Upload: others
View: 9 times
Download: 0 times
Share this document with a friend
39
V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION Page 1 of 15 CONSENT AUTHORITY: PALMERSTON NORTH CITY COUNCIL LAND USE CONSENT LU 3719: CONSTRUCTION OF A BRIDGE IN THE FLOOD PROTECTION ZONE CONSENT HOLDER: PALMERSTON NORTH CITY COUNCIL IN REGARD TO: TO CONSTRUCT A SHARED PEDESTRIAN AND CYCLE BRIDGE IN THE FLOOD PROTECTION ZONE AND ACROSS THE MANAWATŪ RIVER AS PART OF THE WIDER HE ARA KOTAHI PROJECT LOCATION Address of activity: Dittmer Reserve, adjacent to the intersection of Ruha Street and Dittmer Drive Legal descriptions: Section 1701 Town of Palmerston North; road reserve at Dittmer Drive; Manawatū River (Legal River) Map reference: NZMG 2731450.02 E 6089367.99 N LAND USE CONSENT DETAILS Granted: <insert date> Expiry: Unlimited Authorised activity: To erect a pedestrian and cycle bridge, , in a Flood Protection Zone and over the Manawatū River and associated abutments. DEFINITIONS In the following conditions: River Means the Manawatū River, unless stated otherwise Site Means the site of the bridge construction, including both the true left and true right bank of the River Bridge Means the He Ara Kōtahi : Manawatū River Shared Pedestrian And Cycle Bridge, unless stated otherwise
Transcript

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 1 of 15

CONSENT AUTHORITY: PALMERSTON NORTH CITY COUNCIL

LAND USE CONSENT LU 3719: CONSTRUCTION OF A BRIDGE IN THE

FLOOD PROTECTION ZONE

CONSENT HOLDER: PALMERSTON NORTH CITY COUNCIL

IN REGARD TO: TO CONSTRUCT A SHARED

PEDESTRIAN AND CYCLE BRIDGE IN

THE FLOOD PROTECTION ZONE AND

ACROSS THE MANAWATŪ RIVER AS

PART OF THE WIDER HE ARA KOTAHI

PROJECT

LOCATION

Address of activity: Dittmer Reserve, adjacent to the intersection of Ruha Street and

Dittmer Drive

Legal descriptions: Section 1701 Town of Palmerston North; road reserve at Dittmer Drive;

Manawatū River (Legal River)

Map reference: NZMG 2731450.02 E 6089367.99 N

LAND USE CONSENT DETAILS

Granted: <insert date>

Expiry: Unlimited

Authorised activity: To erect a pedestrian and cycle bridge, , in a Flood Protection Zone

and over the Manawatū River and associated abutments.

DEFINITIONS

In the following conditions:

River Means the Manawatū River, unless stated otherwise

Site Means the site of the bridge construction, including both the true

left and true right bank of the River

Bridge Means the He Ara Kōtahi : Manawatū River Shared Pedestrian

And Cycle Bridge, unless stated otherwise

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 2 of 15

Applicant Means the Palmerston North City Council as the Applicant for the

bridge project

City Council Means the Palmerston North City Council as the Consent Authority

Compliance

Monitoring Officer

Means any Compliance Monitoring Officer of the Palmerston North

City Council as the Consent Authority

Roading Manager Means the Roading Manager, Palmerston North City Council

Roading Authority Palmerston North City Council as the roading authority

General Conditions

1. Except as otherwise required by any other condition of this consent, the Activities shall

be carried out in general accordance with the following information provided by the

Applicant (collectively referred to as ‘the Application’):

a. Tonkin & Taylor Ltd (November, 2016) Resource consent application and AEE,

He Ara Kōtahi: Manawatū Pedestrian and Cycle Bridge, including Appendices

A – J; and

b. Tonkin & Taylor Ltd (13 January 2017) He Ara Kōtahi: Manawatū Bridge -

response to request for further information, including Attachments 1 – 8; and

c. Any additional information received prior to, and during the hearing [insert

additional material here].

2. Where there are inconsistencies between the Application and the further information

provided by the Applicant, the most recent information applies. In addition, where there

are inconsistencies between information provided by the applicant and conditions of

the resource consent, the conditions of the resource consent apply.

Advice Note: Any variance from the location, design concepts and parameters,

implementation and / or operation may require a new resource consent or a change of

consent conditions pursuant to section 127 of the Resource Management Act 1991.

3. The Consent Holder shall be responsible for all contracted operations related to the

exercise of this resource consent, and shall ensure contractors are made aware of the

conditions of these resource consents and ensure compliance with those conditions.

4. A copy of these consents shall be kept onsite at all times during the construction phase

of the project and shall be produced without unreasonable delay upon request from a

Compliance Monitoring Officer.

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 3 of 15

5. This consent is subject to the General Conditions in Schedule 1 and the specific

conditions of this land use consent, which must be complied with at all times.

6. In order to provide for health and safety of the community, the Consent Holder shall

notify the Compliance Monitoring Officer before conducting any works in any legal

road.

Construction Noise and Vibration Management

7. The consent holder shall, where practicable, ensure that construction and demolition

activities are managed and controlled in general accordance with the provisions set

out in New Zealand Standard NZS6803:1999 'Acoustics – Construction Noise',

including noise limits for long-term duration construction projects. The construction

noise criteria for the purposes of the Construction Noise and Vibration Management

Plan are:

Time of week Time Period “Long-term” duration construction (dBA)

LAeq LAFmax

Noise criteria at residential buildings

Weekdays 0630-0730 55 75

0730-1800 70 85

1800-2000 65 80

2000-0630 45 75

Saturdays 0630-0730 45 75

0730-1800 70 85

1800-2000 45 75

2000-0630 45 75

Sundays and public

holidays

0630-0730 45 75

0730-1800 55 85

1800-2000 45 75

2000-0630 45 75

8. Construction vibration shall be measured in accordance with DIN 4150-3:1999

“Structural Vibration Part 3: Effects of vibration on structures”. The construction

vibration criteria for the purposes of the Construction Noise and Vibration

Management Plan are:

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 4 of 15

Receiver Details Category A Category B

Occupied dwellings Night-time 2000h –

0730h

0.3mm/s PPV 1 mm/s PPV

Daytime 0730h –

2000h

1 mm/s PPV 5 mm/s PPV

Other occupied

buildings*

Daytime 0730h –

2000h

2 mm/s PPV 5 mm/s PPV

All other buildings Vibration – transient 5 mm/s PPV BS 5228-2:2009

Table B.2

Vibration –

continuous

BS 5228-2:2009,

50% of Table B.2

* ‘Other occupied buildings’ is intended to include daytime workplaces such as offices,

community centres etc., and not industrial buildings. Schools, hospitals, rest homes etc.

would fall under the occupied dwellings category.

9. The Consent Holder shall prepare a schedule that identifies contact details of

individuals that shall be involved in liaison and consultation throughout the Project

construction. These people shall be identified on the following basis:

Tier 1 – Resident and/or owner of

- 125 Dittmer Drive

- 131 Dittmer Drive

- 133 Dittmer Drive

- 20 Ruha Street

- 21 Ruha Street

- 22 Ruha Street

- The operator of the Palmerston North Holiday Park

Tier 2 – Other Resident and/or owner of dwellings within 150 metres of the

construction works area.

Tier 3 – General Public

The level of engagement with each of these persons shall be as described in the

CNVMP.

Construction Noise and Vibration Management Plan

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 5 of 15

10. No less than 40 working days prior to the commencement of any site development

works, the consent holder shall arrange a site visit to which the consent holder, the

construction contractor and a Compliance Monitoring Officer (or nominee) shall attend.

The purpose of the site visit is to discuss the Construction Noise and Vibration

Management Plan (CNVMP) required by Condition 11.

11. No less than 20 working days prior to the commencement of any site development

works, the consent holder shall provide a CNVMP prepared by a suitably qualified and

experienced noise and vibration expert/s to the Compliance Monitoring Officer for

written, technical certification. The purpose of the Construction Noise and Vibration

Management Plan is to identify the noise and vibration performance standards that

will, where practicable, be complied with and sets the framework for the development

and implementation of particular noise and vibration management and control

methodologies to minimise adverse effects on the health and safety of nearby

residents.

12. The CNVMP shall include the following information (as a minimum) and describe the

measures that will be adopted to, as far as practicable, meet:

a. The noise criteria set out in Condition 7. Where it is not practicable to achieve

those criteria, alternative strategies must be described to address the effects

of noise and/ or vibration on nearby residents.

b. The Category A vibration criteria set out in Condition 8. Where it is not

practicable to achieve those criteria, alternative strategies must be described

to address the effects of noise and/ or vibration on nearby residents, and a

suitably qualified vibration expert shall be engaged to assess and manage

construction vibration during the activities that exceed the Category A criteria.

If predicted construction vibration levels exceed Category B criteria, then

construction activity should only proceed if approved by the Compliance

Monitoring Officer (in liaison with an independent, suitably qualified noise and

vibration expert/s) and if there is appropriate monitoring of vibration levels and

effects on buildings at risk of exceeding the Category B criteria, in accordance

with a site specific management schedule.

c. In terms of a and b above, where construction work exceeds the limits in

Condition 7 and Condition 8 the alternative strategies shall include, but not be

limited to:

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 6 of 15

i. Liaison with Tier 1 stakeholders to determine the most appropriate time

to undertake the works,

ii. Inform the Tier 1 stakeholders 3 days in advance which days the work

will take place and the planned start and finish times.

iii. Adopting the best practicable option to reduce noise using the quietest

methodology,

iv. Install temporary noise screening as appropriate,

v. Offer temporary relocation if circumstances dictate,

vi. Check for any damage to dwellings caused by vibration and perform

repairs in a workmanlike and timely fashion.

13. The CNVMP shall be prepared in general accordance with the draft CNVMP as

prepared by Opus International Consultants Ltd, 27 January 2017, but need not be

limited to, details describing the following:

a. Description of the works, laydown areas, anticipated equipment/processes and

their scheduled durations;

b. Hours of operation including times and days when construction activities

causing noise and/or vibration would occur;

c. The construction noise and vibration criteria for the project;

d. Identification of affected dwellings and other sensitive activities where noise

and vibration criteria apply;

e. Mitigation options, including alternative strategies where full compliance with

the relevant noise and/ or vibration criteria cannot be achieved;

f. Requirements for management schedules containing site specific information.

Specific management schedules shall include:

i. Construction vehicles delivery speeds and restrictions on routes and

times for deliveries; and

ii. Notification to neighbouring residents and mitigation for pile driving

activities.

g. Methods and frequency for monitoring and reporting on construction noise and

vibration;

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 7 of 15

h. Procedures and methods for maintaining contact with stakeholders, notifying

of proposed construction activities and handling noise and vibration complaints;

i. Construction equipment operator training procedures and expected

construction site behaviours;

j. Contact numbers for key staff, staff responsible for noise and vibration

assessment and Council officers;

k. Undertake a pre-construction building condition survey of buildings at-risk from

construction vibration;

l. Communicate and consult with affected residents regarding construction noise

and vibration effects, including a letter-drop prior to the commencement of

works;

m. Complaints procedures and register; and

n. Monitoring, audit and review programme.

Advice Note: The Compliance Monitoring Officer, subsequent to a review by an

independent, suitably qualified noise and vibration expert/s, will either certify, or

refuse to certify, the CNVMP within 10 working days of receipt. Should the

Compliance Monitoring Officer refuse to certify the CNVMP, then the Compliance

Monitoring Officer will provide a letter outlining why certification is refused based on

the parameters contained in this condition.

14. Should the Compliance Monitoring Officer ( on the advice of an independent, suitably

qualified noise and vibration expert/s) refuse to certify the CNVMP, the Consent Holder

shall submit a revised CNVMP to the appropriate manager for written certification. The

certification process shall follow the same procedure and requirements as outlined in

Condition 11.

15. The Consent Holder shall not initiate works until the CNVMP has been certified in

writing by the Compliance Monitoring Officer.

16. The Consent Holder shall comply with the certified CNVMP at all times.

17. The CNVMP may be amended at any time by the Consent Holder. Any amendments

to the CNVMP shall be submitted by the Consent Holder to the Compliance Monitoring

Officer for written, technical certification following the same process as set out in

Condition 14. If the amended CNVMP is certified, then it becomes the certified plan

for the purposes of condition 11. Any amendments to the CNVMP shall be:

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 8 of 15

a) for the purposes of improving the measures outlined in the CNVMP for achieving

the CNVMP purpose (see condition 11);

b) consistent with the conditions of this resource consent; and

c) be prepared by an appropriately qualified person.

Construction Traffic Management Plan

18. No less than 40 working days prior to the commencement of any site development

works, the consent holder shall arrange a site visit to which the Consent Holder, the

construction contractor, the City Council’s Compliance Monitoring Officer, and the City

Council’s Roading Manager (or nominee) shall attend. The purpose of the site visit is

to discuss the Construction Traffic Management Plan (CTMP) required by Condition

19.

19. No less than 20 working days prior to the commencement of any site development

works, the consent holder shall provide a CTMP to the Compliance Monitoring Officer

(in liaison with the Roading Manager) for written, technical certification. The purpose

of the CTMP is to set out practices and procedures to be undertaken by the Consent

Holder and all contractors during construction of the Bridge, including the

surroundings, in order to avoid, remedy or mitigate any potential adverse effects on

the roading environment and the safety of road users within the City. The CTMP shall

cover the following topics:

a) develop and implement procedures to:

i. manage oversized and heavy vehicles to and from the Site, including any

temporary diversions/ closures and identify the route to and from Park

Road for heavy vehicle movements; either two-way on Ruha Street only

or a one-way loop using Ruha Street, Dittmer Drive and Katene Street;

ii. ensure that trucks can safely and efficiently move through the local street

network.

Advice Note: if Ruha Street is to be used for two-way truck activity (as

per (a)(i) above) this will likely necessitate the restriction of parking to one

side of the street;

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 9 of 15

iii. ensure that truck manoeuvring and loading/ unloading activities do not

obstruct through access or property access for local residents and other

road users;

iv. given that the Dittmer Drive carpark is likely to be part of the construction

site resulting in a temporary reduction in public parking, encourage all

construction vehicles, including staff vehicles, to park within the

construction site; and

v. provide clear guidance with regard to access to the existing riverside

paths both in terms of whether or not access is possible and if so advise

of any route diversions.

vi. manage the drop off and pick up of construction materials, machinery and

waste to and from the Site;

b) hours of operation and duration of works;

c) details of measures to control mud and detritus from the site onto the road;

d) any night time access and parking procedures, including prioritisation of vehicles

utilising parking spaces in closest proximity to the Site between the hours of 7pm

and 6am;

e) training for staff and contractors, including in relation to the safe and quiet use of

the surrounding roads and parking area;

d) staff transport and parking management, including encouraging active, public

and shared transport modes;

e) management of visitors to the Site;

f) procedures to manage the ingress and egress of service vehicles and

pedestrians;

g) complaints procedures and register; and

h) monitoring, audit and review programme.

Advice Note: The Compliance Monitoring Officer (in liaison with the Roading Manager,

or nominee) will either certify, or refuse to certify, the CTMP within 10 working days of

receipt. Should the Compliance Monitoring Officer refuse to certify the CTMP, then the

Compliance Monitoring Officer will provide a letter outlining why certification is refused

based on the parameters contained in this condition.

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 10 of 15

20. Should the Compliance Monitoring Officer refuse to certify the CTMP, the Consent

Holder shall submit a revised CTMP to the Compliance Monitoring Officer for written

certification. The certification process shall follow the same procedure and

requirements as outlined in Condition 19.

21. The Consent Holder shall not initiate works until the CTMP has been certified in writing

by the Compliance Monitoring Officer.

22. The Consent Holder shall comply with the certified CTMP at all times.

23. The CTMP may be amended at any time by the Consent Holder. Any amendments to

the CTMP shall be submitted by the Consent Holder to the Roading Manager for

written, technical certification. If the amended CTMP is certified, then it becomes the

certified CTMP for the purposes of Condition 19. Any amendments to the CTMP shall

be:

a) for the purposes of improving the measures outlined in the CTMP for achieving

the CTMP purpose (see Condition 19);

b) consistent with the conditions of this resource consent; and

c) be prepared by an appropriately qualified person.

Landscape and Urban Design Management Plan

24. No less than 20 working days prior to commencing any site development works on the

site, the consent holder shall provide a Landscape and Urban DesignManagement

Plan (LUDMP) for written technical certification by the Compliance Monitoring Officer

(in liaison with the PNCC Landscape Architect). The purpose of the LUDMP is to

demonstrate how the proposed landscaping will be implemented and maintained to

achieve successful establishment.

25. The LUDMP should be prepared in general accordance with the landscape concept

plans contained in the Landscape and Visual Assessment (prepared by Opus

International Consultants Ltd, October 2016), but need not be limited to, details

describing the following:

a) details of vegetation that is to be retained and any protection this vegetation

is to be afforded during construction;

b) details, including species, grade, spacing/location, and anticipated maximum

height of all vegetation to be planted;

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 11 of 15

c) any specific vegetation maintenance procedures to be followed and the

length of time that these will be undertaken;

d) procedures for the inspection of vegetation health and replacement of dead

or dying species (where required);

e) details and specifications for any other landscape works treatments, such as

mulching and tree-staking as appropriate;

f) signage and hard landscaping features

Advice Note: The Compliance Monitoring Officer will either certify, or refuse to certify,

the LUDMP within 10 working days of receipt. Should the Compliance Monitoring

Officer refuse to certify the LUDMP, then the Compliance Monitoring Officer will

provide a letter outlining why certification is refused based on the parameters

contained in this condition.

26. Should the Compliance Monitoring Officer refuse to certify the LUDMP, the Consent

Holder shall submit a revised LUDMP to the Compliance Monitoring Officer for written

certification. The certification process shall follow the same procedure and

requirements as outlined in Condition 24.

27. The Consent Holder shall not initiate works until the LUDMP has been certified in

writing by the Compliance Monitoring Officer.

28. The Consent Holder shall comply with the certified LUDMP at all times.

29. The LUDMP may be amended at any time by the Consent Holder. Any amendments

to the LUDMP shall be submitted by the Consent Holder to the Compliance Monitoring

Officer for written, technical certification. If the amended LUDMP is certified, then it

becomes the certified LUDMP for the purposes of Condition 24. Any amendments to

the LUDMP shall be:

a) for the purposes of improving the measures outlined in the LUDMP for

achieving the LUDMP purpose (see Condition 24);

b) consistent with the conditions of this resource consent; and

c) be prepared by an appropriately qualified person.

30. The works identified in the LUDMP, certified under Condition 24 above, must be

completed by the consent holder within 6 months of completion of construction. The

plantings must be monitored for 18 months from the time of planting in order to allow

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 12 of 15

for plant establishment to the satisfaction of the Council’s Compliance Monitoring

Officer. This includes the removal of weeds within the vicinity of the plantings and the

replacement of plants that die or are removed unlawfully within this period in the same

location, with the same species and sized plants. Any plants that fail must be replaced

at the expense of the consent holder. All plantings must continue to be maintained by

the consent holder thereafter.

Traffic management

31. Following the opening of the bridge for use by the public, the Consent Holder shall

conduct ongoing monitoring of kerbside parking demands on Ruha Street, Henare

Street and Dittmer Drive and public parking in the Dittmer Reserve carpark, on a

weekday and weekend, every two (2) months for twelve (12) months following the

opening of the bridge. The purpose of the monitoring is to assess whether the effects

on parking demand and availability is of a greater scale, character and intensity than

anticipated by the transportation assessment in the AEE as modified by the evidence

provided by the consent holder’s transportation expert to the hearing, being typical

parking demands for 36 to 43 spaces and occasional maximums of 52 vehicles. This

monitoring shall include at least two parking duration surveys throughout the 12 month

period, with the remainder of surveys being occupancy surveys. The cost of this

monitoring is the responsibility of the Consent Holder.

32. The Consent Holder shall monitor traffic activity on Ruha Street, Dittmer Drive, Park

Road Katene Street, and Henare Street (only in relation to Ruha Street) on a weekday

and weekend, every two (2) months for twelve (12) months following the opening of

the bridge. The cost of this monitoring is the responsibility of the Consent Holder. The

purpose of the monitoring is to assess whether the effects on the operation and safety

of the local roading environment are of a greater scale, character and intensity than

anticipated by the transportation assessment in the AEE as modified by the evidence

provided by the consent holder’s transportation expert to the hearing, being a typical

traffic generation of up to 21 to 24 vehicles per hour and occasional maximum of 30

vehicles per hour. This monitoring will include intersection turning counts during the

monitoring period.

33. Within one (1) month of completing the monitoring required by Condition 31 and

Condition 32, the Consent Holder shall report the findings of the monitoring to the

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 13 of 15

Roading Manager. If the Roading Manager produces a written statement stating that

intervention works are required in order to remedy and/ or mitigate any adverse effects

then the Consent Holder shall undertake, at the cost of the Consent Holder, measures

to mitigate these effects. This may include (as appropriate), one or a combination of,

the following actions:

a. work with the Roading Authority to restrict parking to one side of the road on

Ruha Street and Dittmer Drive; and/ or

b. introduce time restrictions, to ensure that a reasonable level of on-street

parking remains available for visitors of local residents; and/or

c. marking of kerbside parking bays to ensure access ways are maintained; and/

or

d. upgrading of public parking and access ways; and/ or

e. any other works that are deemed to be required by the Roading Authority.

f. work with the Roading Authority to alter the intersection of Ruha Street and

Park Road, including the implementation of a right-turn lane and an associated

merge area; and/ or

g. introduce no-stopping lines as appropriate to mitigate impediments to traffic

flow; and/ or

h. any other works that are deemed to be required by the Roading Authority.

34. The Consent Holder shall install traffic management devices to physically restrict

access of unauthorised vehicles and bridge users to the Bridge. The Consent Holder

shall ensure that the traffic management devices installed for this purpose are

removable to allow emergency vehicles and authorised service vehicles to access the

bridge.

35. Marking of on-street parking bays both sides of the entire length of Ruha Street

and on the house frontage side of Dittmer Drive for 100m from the Rhua Street

intersection prior to opening of bridge.

Monitoring Fees

36. The consent holder must pay to the Council the actual and reasonable costs

associated with the monitoring of conditions (or review of consent conditions), or

supervision of the resource consent as set in accordance with section 36 of the Act.

These costs* may include site visits, correspondence and other activities, the actual

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 14 of 15

costs of materials or services, including the costs of consultants or other reports or

investigations which may have to be obtained.

Advice Note: For details of costs please refer to the current schedule of Resource

Management Fees for guidance on the current administration charge and hourly rate

chargeable for Council officers.

Review

37. The Palmerston North City Council may, pursuant to section 128 of the Resource

Management Act 1991, initiate a review of all of the conditions at any time,

commencing at the time of granting of Consent and lasting for the duration of this

Consent. The purpose of the review of the conditions of consent is to deal with any

adverse effect on the environment which have arisen, or may arise from the exercise

of the Consent and which it is appropriate to deal with either immediately and/ or at a

later stage. The review may provide for:

a. Ensuring that any environmental effects arising from the exercise of the

consent are not adversely affecting neighbouring properties; and/or

b. The modification of any monitoring program, including reviewing the frequency

of the monitoring or the developments required; and/or

c. Reviewing the effectiveness of the conditions in avoiding, remedying or

mitigating any adverse effect in the environment but not limited to review of

conditions to mitigate adverse effects attributed to any breach of any condition;

and/or

d. Addressing any significant adverse effects on the environment that may arise

from the exercise of the consent; and/or

e. Ensuring that all Management Plans required by this Consent and by Schedule

1 (General Conditions) are appropriate and are effectively managing all

adverse effects on the environment; and/or

f. To enable consistency with any Regional Plan or any National Environmental

Standards or Regulations; and/or

g. Requiring the consent holder to adopt the best practicable option to remove or

reduce any adverse effect on the environment.

38. The review may result in any of the following outcomes:

a. The deletion or amendment of any conditions on the consents; and/or

b. The addition of new conditions; and /or

V3A He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions In Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 15 of 15

c. Achieving an outcome that arises from review of the First Schedule (General

Conditions).

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 1 of 6

SCHEDULE 1: GENERAL CONDITIONS RELATING TO ALL MANAWATŪ-

WANGANUI REGIONAL COUNCIL AND PALMERSTON NORTH CITY COUNICL

CONSENTS

(LAND USE CONSENTS LU3719 AND ATH-2016201174.00 AND ATH-

2016201107.00 AND DISCHARGE PERMIT ATH-2016201172.00 AND WATER

PERMIT ATH-2016201173.00)

CONSENT HOLDER: PALMERSTON NORTH CITY COUNCIL

HE ARA KŌTAHI: MANAWATŪ RIVER SHARED PEDESTRIAN AND CYCLE

BRIDGE

Definitions

In the following conditions:

Activities Means the Activities that are authorised by LAND USE

CONSENTS LU3719 AND ATH-2016201174.00 AND ATH-

2016201107.00 AND DISCHARGE PERMIT ATH-

2016201172.00 AND WATER PERMIT ATH-2016201173.00

River Means the Manawatū River, unless stated otherwise

Bridge Means the He Ara Kōtahi : Manawatū River Shared Pedestrian

And Cycle Bridge, unless stated otherwise

Applicant Means Palmerston North City Council as the Applicant for the

bridge project

Regional Council Means the Manawatū–Wanganui Regional Council

Regulatory Manager Means the Regulatory Manager, Manawatū–Wanganui

Regional Council

City Council Means the Palmerston North City Council as the Consent

Authority

Compliance Monitoring

Officer

Means any Compliance Monitoring Officer of the Palmerston

North City Council as the Consent Authority

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 2 of 6

General

1. Except as otherwise required by any other condition of this consent, the Activities shall

be carried out in general accordance with the following information provided by the

Applicant (collectively referred to as ‘the Application’):

a. Tonkin & Taylor Ltd (November, 2016) Resource consent application and AEE,

He Ara Kōtahi: Manawatū Pedestrian and Cycle Bridge, including Appendices

A – J; and

b. Tonkin & Taylor Ltd (13 January 2017) He Ara Kōtahi: Manawatū Bridge -

response to request for further information, including Attachments 1 – 8; and

c. Any additional information received prior to and during the hearing [insert

additional material here].

2. Where there are inconsistencies between the Application and the further information

provided by the applicant, the most recent information applies. In addition, where there

are inconsistencies between information provided by the applicant and conditions of

the resource consent, the conditions of the resource consent apply.

Advice Note: The plans referred to in the resource consent application and AEE

show a concept design. Through the process of detailed design, modifications and

improvements in design can be made that do not materially change the effects of the

activities authorised by this consent.

3. The Consent Holder shall be responsible for all contracted operations related to the

exercise of this resource consent, and shall ensure contractors are made aware of the

conditions of these resource consents and ensure compliance with those conditions.

4. A copy of these consents shall be kept onsite at all times during the construction phase

of the project, and shall be produced without unreasonable delay upon request from a

servant or agent of the Regional Council and/or City Council.

5. During construction of the Bridge, and until such time that the Bridge is open to the

public, the Consent Holder shall not unnecessarily restrict public access to and along

the River, and its margins, except where required to provide for the health and safety

of the public.

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 3 of 6

6. All construction works, including all off-loading or materials onto the subject site, shall

be restricted to the hours between 7.30am to 6pm Monday to Saturday. Quiet setting

up of site (not including running of plant or machinery) may start at 6:30am. No work

shall occur on a Sunday or Public Holiday. Work may only be commenced outside of

these hours, having notified the Regulatory Manager and Compliance Monitoring

Officer, to prevent an adverse effect on the environment which requires immediate

preventive or remedial works or any sudden event causing loss of life, injury, or serious

damage to property.

Construction Environment Management Plan

7. No less than 40 working days prior to the commencement of any site development

works, the consent holder shall arrange a site visit to which the Consent Holder, the

Construction Contractor, the Regulatory Manager (or nominee) and the Compliance

Monitoring Officer (or nominee) shall attend. The purpose of the site visit is to discuss

the Construction Environmental Management Plan required by Condition 8.

ADVICE NOTE: Condition 7 does not prevent the commencement of works within 40

working days of the submission of the CEMP, if the CEMP is certified in writing within

that timeframe.

8. No less than 20 working days prior to the commencement of any site development

works, the consent holder shall provide a Construction Environmental Management

Plan (CEMP) to both the Regulatory Manager and the Compliance Monitoring Officer

for written, technical certification. The purpose of the CEMP is to set out practices and

procedures to be undertaken by the Consent Holder, and all contractors, during the

construction and commissioning of the activities in order to avoid, remedy or mitigate

any potential adverse effects of construction and to ensure that the bridge construction

is timely, efficient and safe.

9. The CEMP shall cover the following topics:

a) anticipated date of commencement of works

b) a description of the proposed works;

c) a programme of works, including sequencing of works, hours of operation and

anticipated duration of works;

d) contact details for site manager, including their phone number, email address

and address for service;

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 4 of 6

e) a list of key personnel and communications protocols

f) procedures to ensure compliance with the conditions of the relevant consents

and permits;

g) site compound location shown on a plan (including areas for site offices and site

parking);

h) details of any measures to control mud and detritus from the site onto the road,

including any on-site wheel washing and off site road sweeping;

i) swept path analysis of delivery trucks through the access;

g) any local conditions, such as areas that have previously slipped or been earth-

worked, where springs or under-runners may be present, or where seismic

events are likely to affect earth-fills, slopes and liquefiable ground;

h) implementation and operational procedures for the management stormwater;

i) progressive surfacing, top soiling and re-vegetation immediately following

completion of each stage of the works (if required);

j) the monitoring program for effects of the earthworks on and off site (including

transportation of material);

k) Management and mitigation measures for the handling and storage of

hazardous materials including but not limited to:

i. Bulk fuel storage being limited to one location, at least 20m from any

watercourses or external boundary;

ii. Sealed waste bins provided for oil rags, oil filters and other wastes.

These drums will be transported off site to an appropriate receiving

facility;

iii. Confirmation that the storage of hazardous substances during

construction will comply with the requirements of the Hazardous

Substances and New Organisms Act and the requirements of the

Palmerston North District Plan;

iv. A Spill Emergency Response Plan;

v. Covered rubbish and recycling bins are to be provided, regularly

emptied and moved off site to an approved facility;

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 5 of 6

vi. No burning of waste will be permitted;

vii. Portable toilet facilities will be located further than 20m from any

watercourse or external site boundary

l) complaints procedures and register;

m) monitoring, audit and review programme;

n) signage at the site informing of construction works and complaints procedure

Advice Note: The Regulatory Manager and Compliance Monitoring Officer will both

independently either certify, or refuse to certify, the CEMP within 20 working days of

receipt. Should either the Regulatory Manager or Compliance Monitoring Officer

refuse to certify the CEMP, then the Manager and/or Officer will provide a letter

outlining why certification is refused based on the parameters contained in this

condition.

10. Should the Regulatory Manager and/ or Compliance Monitoring Officer refuse to certify

the CEMP, the Consent Holder shall submit a revised CEMP to the appropriate

manager for written certification. The certification process shall follow the same

procedure and requirements as outlined in Condition 8 and 9.

11. The Consent Holder shall not initiate works that are authorised by these Consents until

the CEMP has been certified in writing by both the Compliance Monitoring Officer and

the Regulatory Manager.

12. The Consent Holder must comply with the certified CEMP at all times.

13. The certified CEMP may be amended at any time by the Consent Holder. Any

amendments to the certified CEMP shall be submitted by the Consent Holder to both

the Regulatory Manager and Compliance Monitoring Officer for certification. If the

amended CEMP is certified, then it becomes the certified CEMP for the purposes of

Conditions 8 and 9. Any amendments to the CEMP shall be:

a) for the purposes of improving the measures outlined in the CEMP for achieving

the CEMP purpose (see Conditions 8 and 9);

b) consistent with the conditions of this resource consent; and

c) be prepared by an appropriately qualified person.

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Page 6 of 6

Discovery protocol

14. Prior to the commencement of works, the Consent Holder shall develop and have in

place a procedure that is to be followed in the event that any urupā, taonga (significant

artefacts), kōiwi (human remains) or archaeological sites (whether recorded or

unrecorded) are disturbed and/ or discovered during site works, including:

a. works in the location of any accidental discovery immediately cease; and

b. the area is to be secured in a way that ensures any remains or artefacts are

untouched;

c. inform Tanenuiarangi Manawatū Incorporated (TMI), the Regulatory Manager,

the Compliance Monitoring Officer and New Zealand Police (only if koiwi are

discovered) and Heritage New Zealand.

Cultural commitments

15. During construction of the Bridge, the Consent Holder shall allow Rangitāne o

Manawatū (or nominee) to conduct cultural monitoring where there is likely to be

culturally sensitive sites which may be disturbed by works. The Consent Holder may

restrict unsupervised access, to areas identified by the Consent Holder, only for

health and safety reasons.

16. Prior to the commencement of works, the Consent Holder shall contact Rangitāne o

Manawatū (or nominee) to arrange an appropriate time in construction to place a mauri

stone within a pile casing (at the deepest point possible) to connect the Bridge to the

River.

17. Prior to the completion of works, the Consent Holder shall contact the Rangitāne o

Manawatū kaumātua to arrange a karakia ceremony, according to Rangitāne o

Manawatū tikanga, prior to the opening of the bridge to the general public.

V3B He Ara Kotahi Bridge Project – MWRC, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – CLEAN VERSION

Appendix A MANAWATU-WANGANUI REGIONAL COUNCIL

DEFINITIONS

In the following conditions:

Activity/Activities Means the Activities authorised by Land Use

Consents ATH-2016201107.00, ATH-

2016201107.00, Discharge Permit ATH-

2016201172.00 and Water Permit ATH-

2016201173.00

River Means the Manawatu River, unless stated

otherwise

Site Means the site of the bridge construction,

including both the true left and true right bank

of the River

Bridge Means the He Ara Kotahi : Manawatu River

Shared Pedestrian And Cycle Bridge, unless

stated otherwise

Council Means the Manawatu-Wanganui Regional

Council

Regulatory Manager Means the Regulatory Manager of the

Manawatu-Wanganui Regional Council or

nominee

E&SCP Means an Erosion and Sediment Control Plan

General Conditions

1. The consent holder must undertake the activity in general accordance with the consent

application including all accompanying plans and documents first lodged with the Council on

9 November 2016 and;

a. further information received on 13 January 2017 via email being a description of fish

species, riparian vegetation, herpetofauna and bird species near the site, an updated

draft Erosion and Sediment Control Plan (ESCP), hydraulic model files and result files

and an agreed memorandum of understanding from Tanenuiarangi Manawatu

Incorporated (TMI); and

b. further information received on 24 January 2017 via email being draft Sketches of

the River Diversions proposed.

Where there may be inconsistencies between information provided by the applicant and

conditions of the resource consent, the conditions of the resource consent will prevail.

Advice Note: Any variation of an activity greater in scope than that requested in the

resource consent application, may require a new resource consent or a change of consent

conditions in accordance with section 127 of the Resource Management Act 1991.

2. The activities authorised by these consents/permits shall be restricted to:

a. construction of a bridge over the River;

b. the construction of retaining structures;

c. movement and disturbance of an existing stopbank;

d. land disturbance and vegetation clearance;

e. the associated temporary diversions in the River; and

f. the associated discharge of sediment into the River.

3. The consent holder shall be responsible for all contracted operations related to the exercise

of these consents/permits and shall ensure contractors are made aware of the conditions of

these resource consents and ensure compliance with those conditions.

4. This consent is subject to the General Conditions in Schedule 1 and the specific conditions of

these consents/permits, which must be complied with at all times.

Erosion and Sediment Control Plan

5. The consent holder shall inform the Regulatory Manager and Area Engineer Central in

writing at least ten (10) working days prior to the commencement of the construction works

authorised by these consents of the start date, and within ten (10) working days following

the completion of the construction works.

Advice Note: The Regulatory Manager can be contacted on 0508 800 800 or by email

[email protected].

Advice Note: The Area Engineer, Central, can be contacted on 0508 800 800.

6. The consent holder shall provide the Council with a finalised E&SCP, at least 20 working days

prior to the commencement of activities authorised by these resource consents. The

objective of the E&SCP shall be to minimise sediment discharge from the site to the extent

practicable.

7. The E&SCP required by Condition 6 shall as a minimum be based upon and incorporate those

specific principles and practices which are appropriate for the activity authorised by this

consent and contained within the Council document titled “Erosion and Sediment Control –

Guidelines for the Wellington Region, dated September 2002 ”, and shall include at least the

following:

Page 3 of 12

i. Details of all principles, procedures and practices that will be implemented to

undertake erosion and sediment control to minimise the potential for sediment

discharge from the site;

ii. The design criteria and dimensions of all key erosion and sediment control

structures;

iii. A Flocculation Management Plan, if requested under Condition 17 of this consent;

iv. A River Diversion Management Plan, as required by Condition 23 of this consent;

v. Details of the proposed works during 1 May to 30 September, in accordance with

Conditions 14-16 of this consent;

vi. A site contour plan of a suitable scale to identify;

a. The extent of soil disturbance and vegetation removal;

b. Any “no go” and/or buffer areas to be maintained undisturbed adjacent to

watercourses;

c. Areas of cut and fill;

d. details of fill specifications, including sediment yield as determined by a

Universal Soil Loss Equation (USLE);

e. Locations of topsoil stockpiles;

f. All key erosion and sediment control structures;

g. The boundaries and area of catchments contributing to all stormwater

impoundment structures;

h. The locations of all specific points of discharge to the River;

vii. Construction timetable for the erosion and sediment control works and the bulk

earthworks proposed;

viii. Timetable and nature of progressive site rehabilitation and re-vegetation proposed;

ix. Maintenance, monitoring and reporting procedures,

x. Complaint procedures, in accordance with Conditions 46 and 47 of this consent;

xi. Rainfall response and contingency measures including procedures to minimise

adverse effects in the event of rainfall events that are likely to impair the function or

performance of the controls and/or result in the failure of any key erosion and

sediment control structures, in accordance with Condition 48 of this consent;

xii. Procedures and timing for review and/or amendment to the E&SCP;

xiii. Identification and contact details of personnel responsible for the operation and

maintenance of all key erosion and sediment control structures; and

xiv. Any other relevant documents.

8. The E&SCP required by Condition 6 shall be certified in writing by the Council acting in a

technical certification capacity prior to any activities authorised by these resource consents

commencing and the consent holder shall undertake all earthworks authorised by this

consent in accordance with the certified E&SCP.

Advice Note: The certification (or withholding of certification) shall be based on the Councils

assessment of whether the matters being considered achieve the objective of minimising

sediment discharges from the site to the extent practicable.

9. Any changes proposed to the E&SCP required by Condition 6 shall be confirmed in writing by

the consent holder and certified in writing by the Council acting in a technical certification

capacity, prior to the implementation of any changes proposed.

10. The consent holder shall ensure that a copy of the certified E&SCP, including any certified

amendments, is kept onsite and this copy is updated within 5 working days of any

amendments being certified.

11. Any activities authorised by these consents must not commence until the E&SCP has been

certified in writing by the Manawatu-Wanganui Regional Council acting in a technical

certification capacity and the consent holder shall, at all times, comply with the approved

E&SCP required under Conditions 6-10.

12. The consent holder must submit to the Council an as-built statement signed by an

appropriately qualified and experienced professional certifying that all erosion and sediment

control structures have been constructed in accordance with the E&SCP required by

Condition 6. The certification and as-built statement shall be supplied to Council within 5

working days of the completion of the construction of the structures concerned. Information

contained in the certification statement shall include at least the following;

i. Confirmation of contributing catchment areas;

ii. The location, capacity and design of each structure;

iii. Position of inlets and outlets;

iv. Stability of the structures;

v. Measures to control erosion; and

vi. Any other relevant matter.

Advice Note: Bulk earthworks includes cut and fill operations associated with the

construction of bridge.

13. The consent holder shall ensure that sediment losses to natural water arising from the

exercise of these resource consents are minimised during the duration of the works and

during the term of this consent. In this regard, erosion and sediment control measures shall

be established and maintained in accordance with the document titled “Erosion and

Sediment Control – Guidelines for the Wellington Region, dated September 2002, and the

certified E&SCP.

Page 5 of 12

Winter Works

14. The consent holder shall ensure that the site is appropriately stabilised by 30 April of each

year unless otherwise certified in writing by the Council. Stabilisation shall be undertaken by

providing adequate measures (vegetative and/or structural and including, pavement,

metalling, hydro-seeding, re-vegetation and mulching) that will minimise erosion of exposed

soil to the extent practical, in accordance with Erosion and Sediment Control – Guidelines for

the Wellington Region and the E&SCP certified under Condition 8.

15. Earthworks shall not be conducted during the period 1 May to 30 September inclusive

during any year that these resource consents is current, apart from necessary maintenance

works to maintain the operational effectiveness and efficiency of all erosion and sediment

control measures specifically required by the certified E&SCP referred to in Condition 6,

unless certified in writing by Council.

16. Requests to undertake earthworks during the period 1 May to 30 September inclusive, for

any year that these resource consents are current, the consent holder must provide Council

with a Winter Works Plan, for certification from the Regulatory Manager by 1 April and shall

be in the form of amendments to the certified E&SCP. In considering a request for the

continuation of winter earthworks, the Council will consider a number of factors including:

a. The nature of the site and the winter soil disturbance works proposed;

b. The quality of the existing/proposed erosion and sediment controls;

c. The compliance history of the site/operator;

d. Seasonal/local soil and weather conditions;

e. Sensitivity of the receiving environment; and

f. Any other relevant factor.

Flocculation Management Plan

17. The consent holder must provide a Flocculation Management Plan within 10 working days of

the commissioning of any flocculation treatment system. The Flocculation Management Plan

shall include as a minimum:

i. Specific design details of the flocculation system;

ii. Monitoring, maintenance (including post-storm) and including a record system;

iii. Details of optimum dosage (including assumptions);

iv. Results of any initial flocculation trial;

v. A spill contingency plan;

vi. Contact details of the person responsible for the operation and maintenance of the

flocculation treatment system and the organisational structure to which this person

shall report.

18. The Flocculation Management Plan required by Condition 17 shall be certified in writing by

the Council acting in a technical certification capacity prior to the commissioning of any

flocculation treatment system.

19. Any changes proposed to the Flocculation Management Plan required by Condition 17 shall

be confirmed in writing by the consent holder and certified in writing by the Council acting in

a technical certification capacity, prior to the implementation of any changes proposed.

20. The consent holder shall ensure that a copy of the certified Flocculation Management Plan,

including any certified amendments, is kept onsite and this copy is updated within 5 working

days of any amendments being certified.

21. Unless site specific analysis provides evidence to the contrary, as detailed in the Flocculation

Management Plan required by Condition 17 of this resource consent, the consent holder

shall ensure that the soluble aluminium concentration of any discharge to the River shall not

exceed 0.2 grams per cubic metre.

22. Unless site specific analysis provides evidence to the contrary, as detailed in the Flocculation

Management Plan required by Condition 17 of these resource consents, the consent holder

shall ensure that the pH of any discharge to the River shall not be less than 5.5 or greater

than 8.5 pH units.

River Diversion Management Plan

23. 20 days prior to any works within the bed of the River including any river diversions

authorised under resource consent ATH-2016201173.00, the consent holder must provide a

finalised River Diversion Management Plan to Council for certification. The River Diversion

Management Plan must include the following:

i. Timing and duration of in-river works;

ii. Locations of access to the in-river works sites;

iii. Specific sizing of diversion channel and associated bunds to suit expected flows;

iv. Hydrological analysis of the effect on the diversion channel on the Manawatu-

Regional Council’s upstream flow monitoring station (at Teacher’s Collage);

v. A drawing outlining the proposed diversion required to access the piling site on the

true right side of the River;

vi. Measures to maintain the current level of flood protection;

vii. Proposed remediation works to reinstate the River; and

viii. A description of any procedures in place to minimise impacts on fish during the

proposed instream works, including methodologies undertaken to minimise fish

mortality and to rescue any stranded fish.

Page 7 of 12

Construction Conditions

24. The consent holder must provide a finalised design plan of the bridge to the Council for

certification within 10 working days of completion of construction works certifying that the

structure have been constructed in accordance certified design.

25. The activities approved under these consents shall remain the responsibility of the consent

holder and shall be maintained over the life of the bridge structure to ensure that:

a. any erosion, scour or instability of the river bed or banks that is attributable to the

works carried out as part of this consent is remedied by the consent holder within 10

working days;

b. the works shall not adversely affect the ability of the River to convey flood flows or

floating or flood borne debris and shall remain substantially free of debris. Debris

greater than 10 cm in standard diameter or greater than 2 metres in length shall be

removed as soon as possible after any flood; and

c. the structural integrity of the structures remains sound, for the life of the structure.

26. The consent holder shall ensure that any disturbance, damage or slumping caused by the

works to the river banks that will result in erosion or sediment discharges are rectified or

repaired as soon as is practicable and no longer than 10 days after the disturbance, damage

or slumping has occurred.

27. The structure must be constructed and maintained to avoid any aggradation or scouring of

the bed that may inhibit the passage of fish both upstream and downstream at all flows.

Flood Contingency Plan

28. No less than 20 working days prior to the commencement of works, the consent holder

shall prepare and submit a flood contingency plan to the Council’s Regulatory Manager for

technical certification.

This plan shall include, but not be limited incorporating procedures which will be carried out

to ensure that adjacent property and infrastructure are not put at risk during a flood and

while the construction phase of the works is still in progress.

Advice Note: The Regulatory Manager can be contacted on 0508 800 800 or by email at

[email protected].

29. The consent holder shall ensure there is sufficient machinery on site to raise any low

sections of the stopbank if a large flood is predicted in accordance with the certified Flood

Contingency Plan certified under Condition 28.

Dotterels

30. Prior to any works being carried out in the bed of the River during the period 1 August to 31

December, the consent holder shall ensure that:

a. A suitably qualified and experienced ecologist inspects the proposed area of works

no earlier than eight working days prior to any works being carried out, and locates

any banded dotterel breeding or nesting sites; and

b. If banded dotterel breeding or nesting sites are found within a 50 metre radius of

any construction area, construction activities within that 50 metre radius shall be

postponed until such time as all nests are abandoned or the chicks have fledged.

Moreporks / Ruru

31. Any clearance of the pine trees within the works area on the true left bank must be

undertaken between April and September inclusive, to minimise effects on morepork/ruru

fledging.

Lizards

32. Prior to vegetation works commencing, the consent holder must ensure a suitably qualified

and experienced ecologist/herpetologist acceptable to Council, shall be onsite to supervise

all areas requiring vegetation removal in order to search for, and rescue, any native lizards

found and relocate them to a suitable alternative location on or near the site. If an

investigation over an 8 hour period does not identify any lizards, then the search and rescue

requirement of this condition will be considered as fulfilled.

33. The woody vegetation within the proposed works area on the true right bank shall be

removed and stockpiled immediately adjacent to similar riparian vegetation outside of the

works area to assist in the search and rescue operation required by Condition 32.

34. One month prior to construction works on the true left bank, the Consent Holder shall mulch

and keep short the rank grass vegetation to reduce habitat suitability for native skinks.

Water Quality

35. The Consent Holder shall ensure that any discharge of sediment into the River directly

caused by each stage of the instream works associated with the project work, must not,

after reasonable mixing, cause any increase in turbidity (NTU) by more than 30%, for more

than 24 hours in total across 5 consecutive days. The Consent Holder shall also ensure

deposited sediment does not increase by more than 25% compared to the upstream

monitoring site. The Consent Holder must take turbidity samples and measure deposited

sediment at the upstream site at map reference NZTopo50 BM34:216-276 and

Page 9 of 12

approximately 200m downstream of the furthest discharge point. Turbidity samples must be

taken twice per day during in-stream works, on the same side of the river as the works.

Deposited sediment assessment must be undertaken prior to and at the completion of each

of the three separate phases of in river works (i.e., pier 1, pier 2, and final channel

reinstatement), on the same side of the river as the works.

Advice Note: Reasonable mixing is defined as 200m downstream of the discharge.

Advice Note: For clarification, the 5 working days applies to each stage of the works within

the wetted channel i.e. the construction of the true left and right bunds and any remedial

works.

Advice Note: An appropriate methodology for assessing deposited sediment would be the

Sediment Assessment Method 2 (SAM-2) of Clappcott et al. (2011) [see

http://www.cawthron.org.nz/media_new/publications/pdf/2014_01/SAM_FINAL_LOW.pdf].

Advice Note: The exact downstream site for deposited sediment monitoring will be

dependent on being able to wade into the channel on the same side as the works are

occurring, hence may be further downstream than the 200m mixing zone limit.

36. The consent holder shall ensure monitoring required under Conditions 35 and 38, is

undertaken by an appropriately qualified and experienced person and ensure calibrated field

metres are used to collect turbidity measurements.

37. The consent holder shall take all measures to ensure that no uncured cement or cement

based products enter or come in contact with the River during the exercise of works. Any

uncured concrete placed in or near the watercourse shall be undertaken in such a manner

that no concrete or cement leaches out and enters the watercourse. New concrete or

mortar shall not be exposed to the flow of water before the concrete or mortar has

hardened to a strength of at least 10 megapascal (MPa), or for at least forty-eight (48) hours

from completion of pouring.

38. The consent holder shall monitor pH at the times when concrete/cement work is being

undertaken to ensure the pH of the Manawatu River does not change by more than 0.5 units

between the same upstream and downstream monitoring sites described in Condition 35.

Advice Note: A pH field meter will be suitable for this but note handheld pH meters require

very regular calibration.

39. The consent holder must ensure an electronic record is kept of the results for measuring

turbidity (NTU) and pH, required under Conditions 35 and 38, are provided to the Regulatory

Manager via email to [email protected] on a weekly basis.

40. The consent holder shall ensure that:

a. machinery or vehicles entering the River should have had a stand down of at least

forty-eight (48) hours since being in contact with another water body other than the

Manawatu River; and

b. machinery or vehicles used at the proposed site should be stood down for forty-

eight (48) hours prior to use in any catchment upstream of the site;

c. standard check, clean and dry procedures should be adopted for any vehicles,

equipment, clothing or footwear that has been in contact with a water body other

than the upstream of the River within the past 48 hours; and

d. all standard check, clean and dry procedures carried out for vehicles and equipment

used onsite are recorded in a Log book and are available upon request to the

Manawatu Wanganui Regional Council’s Regulatory Manager.

41. Any discharge of sediment into water directly caused by activities authorised under resource

consent, excluding in-stream works, must not cause a change in visual clarity by more than

20%, for more than 24 hours in total across 5 consecutive days.

Advice note: For clarification, in-stream works applies to the construction of pier 1, pier 2,

and final channel reinstatement works.

42. The consent holder shall comply with all notices and guidelines issued by Biosecurity New

Zealand (refer to www.biosecurity.govt.nz/didymo) in relation to avoiding the spread of the

pest organism Didymosphenia geminata (known as ‘Didymo’).

Fuel Storage, Machinery and Equipment

43. The consent holder shall ensure that:

a. Any onsite storage areas for fuel and lubricants shall be bunded or contained to such

an extent that any spill (whether it be accidental or deliberate) does not result in any

discharge of contaminants directly into water or onto or into land where it may

enter water.

b. All machinery and equipment is regularly maintained in such a manner so as to

minimise the potential for leakage of fuels, lubricants and similar contaminants.

c. All machinery and equipment is operated in a manner, which ensures spillages of

fuel, oil and similar contaminants are prevented, particularly during refuelling and

machinery servicing and maintenance.

d. Refuelling and lubrication activities shall be carried out away from any water body,

such that any spillage can be contained so that it does not enter surface water.

e. All machinery not being used is stored away from any water body or out of the

active river bed.

Page 11 of 12

f. .Refuelling and lubrication activities shall be carried out away from any water body,

such that any spillage can be contained so that it does not enter surface water.

g. All machinery not being used is stored away from any water body or out of the

active river bed.

Operational Restrictions

44. In-stream works authorised under resource consent ATH-2016201173.00 shall be restricted

to:

a. 7:00 am - 6:30 pm on weekdays; and

b. 7:30 am - 1:00 pm on Saturdays; and

c. No works authorised on any Sunday or Public Holiday.

45. The consent holder shall undertake the works authorised by these consents in such a

manner that ensures there is no objectionable dust from the works area beyond the

property boundary.

Advice Note: Manawatu Wanganui Regional Council staff will assess complaints about

objectionable dust beyond the property boundaries in terms of whether or not the dust is

objectionable to a reasonable ordinary person. When considering whether the dust is

objectionable, Council staff with take into consideration the FIDOL factors: frequency,

intensity, duration, offensiveness and location.

46. If any complaints are received by the consent holder regarding the activities authorised by

this resource consent, the consent holder shall notify the Manawatu-Wanganui Regional

Council of those complaints as soon as practicable and no longer than one working day after

receiving the complaint.

Advice Note: Notification of a compliant can be submitted to the Regulatory Manager via

email [email protected] –OR- by phone on 0508 800 800.

47. If complaints are received, the consent holder shall record the following details in a

Complaints Log:

i. Time and type of complaint, including details of the incident, e.g. duration, any effects

noted;

ii. Name, address and contact phone number of the complainant (if provided);

iii. The response made by the consent holder including any corrective action undertaken by

the consent holder in response to the complaint.

48. The consent holder shall ensure that all erosion and sediment control structures are

inspected on a weekly basis and within 24 hours of each rainstorm event that is likely to

impair the function or performance of the controls. Records of the erosion and sediment

control structure inspections shall be provided to Manawatu-Wanganui Regional Councils

Regulatory Manager upon request.

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – TRACKED VERSION

Page 1 of 6

SCHEDULE 1: GENERAL CONDITIONS RELATING TO ALL MANAWATŪ-

WANGANUI REGIONAL COUNCIL AND PALMERSTON NORTH CITY COUNICL

CONSENTS

(LAND USE CONSENTS LU3719 AND ATH-2016201174.00 AND ATH-

2016201107.00 AND DISCHARGE PERMIT ATH-2016201172.00 AND WATER

PERMIT ATH-2016201173.00)

CONSENT HOLDER: PALMERSTON NORTH CITY COUNCIL

HE ARA KŌTAHI: MANAWATŪ RIVER SHARED PEDESTRIAN AND CYCLE

BRIDGE

Definitions

In the following conditions:

Activities Means the Activities that are authorised by LAND USE

CONSENTS LU3719 AND ATH-2016201174.00 AND ATH-

2016201107.00 AND DISCHARGE PERMIT ATH-

2016201172.00 AND WATER PERMIT ATH-2016201173.00

River Means the Manawatū River, unless stated otherwise

Bridge Means the He Ara Kōtahi : Manawatū River Shared Pedestrian

And Cycle Bridge, unless stated otherwise

Applicant Means Palmerston North City Council as the Applicant for the

bridge project

Regional Council Means the Manawatū–Wanganui Regional Council

Regulatory Manager Means the Regulatory Manager, Manawatū–Wanganui

Regional Council

City Council Means the Palmerston North City Council as the Consent

Authority

Compliance Monitoring

Officer

Means any Compliance Monitoring Officer of the Palmerston

North City Council as the Consent Authority

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – TRACKED VERSION

Page 2 of 6

General

1. Except as otherwise required by any other condition of this consent, the Activities shall

be carried out in general accordance with the following information provided by the

Applicant (collectively referred to as ‘the Application’):

a. Tonkin & Taylor Ltd (November, 2016) Resource consent application and AEE,

He Ara Kōtahi: Manawatū Pedestrian and Cycle Bridge, including Appendices

A – J; and

b. Tonkin & Taylor Ltd (13 January 2017) He Ara Kōtahi: Manawatū Bridge -

response to request for further information, including Attachments 1 – 8; and

c. Any additional information received prior to and during the hearing [insert

additional material here].

2. Where there are inconsistencies between the Application and the further information

provided by the applicant, the most recent information applies. In addition, where there

are inconsistencies between information provided by the applicant and conditions of

the resource consent, the conditions of the resource consent apply.

Advice Note: The plans referred to in the resource consent application and AEE show a

concept design. Through the process of detailed design, modifications and improvements in

design can be made that do not materially change the effects of the activities authorised by

this consent.

3. The Consent Holder shall be responsible for all contracted operations related to the

exercise of this resource consent, and shall ensure contractors are made aware of the

conditions of these resource consents and ensure compliance with those conditions.

4. A copy of these consents shall be kept onsite at all times during the construction phase

of the project, and shall be produced without unreasonable delay upon request from a

servant or agent of the Regional Council and/or City Council.

5. During construction of the Bridge, and until such time that the Bridge is open to the

public, the Consent Holder shall not unnecessarily restrict public access to and along

the River, and its margins, except where required to provide for the health and safety

of the public.

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – TRACKED VERSION

Page 3 of 6

6. All construction works, including all off-loading or materials onto the subject site, shall

be restricted to the hours between 7.30am to 6pm Monday to Saturday. Quiet setting

up of site (not including running of plant or machinery) may start at 6:30am. No work

shall occur on a Sunday or Public Holiday. Work may only be commenced outside of

these hours, having notified the Regulatory Manager and Compliance Monitoring

Officer, to prevent an adverse effect on the environment which requires immediate

preventive or remedial works or any sudden event causing loss of life, injury, or serious

damage to property.

Construction Environment Management Plan

7. No less than 40 working days prior to the commencement of any site development

works, the consent holder shall arrange a site visit to which the Consent Holder, the

Construction Contractor, the Regulatory Manager (or nominee) and the Compliance

Monitoring Officer (or nominee) shall attend. The purpose of the site visit is to discuss

the Construction Environmental Management Plan required by Condition 8.

ADVICE NOTE: Condition 7 does not prevent the commencement of works within 40

working days of the submission of the CEMP, if the CEMP is certified in writing within

that timeframe.

8. No less than 20 working days prior to the commencement of any site development

works, the consent holder shall provide a Construction Environmental Management

Plan (CEMP) to both the Regulatory Manager and the Compliance Monitoring Officer

for written, technical certification. The purpose of the CEMP is to set out practices and

procedures to be undertaken by the Consent Holder, and all contractors, during the

construction and commissioning of the activities in order to avoid, remedy or mitigate

any potential adverse effects of construction and to ensure that the bridge construction

is timely, efficient and safe.

9. The CEMP shall cover the following topics:

a) anticipated date of commencement of works

b) a description of the proposed works;

c) a programme of works, including sequencing of works, hours of operation and

anticipated duration of works;

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – TRACKED VERSION

Page 4 of 6

d) contact details for site manager, including their phone number, email address

and address for service;

e) a list of key personnel and communications protocols

f) procedures to ensure compliance with the conditions of the relevant consents

and permits;

g) site compound location shown on a plan (including areas for site offices and site

parking);

h) details of any measures to control mud and detritus from the site onto the road,

including any on-site wheel washing and off site road sweeping;

i) swept path analysis of delivery trucks through the access;

g) any local conditions, such as areas that have previously slipped or been earth-

worked, where springs or under-runners may be present, or where seismic

events are likely to affect earth-fills, slopes and liquefiable ground;

h) implementation and operational procedures for the management stormwater;

i) progressive surfacing, top soiling and re-vegetation immediately following

completion of each stage of the works (if required);

j) the monitoring program for effects of the earthworks on and off site (including

transportation of material);

k) Management and mitigation measures for the handling and storage of

hazardous materials including but not limited to:

i. Bulk fuel storage being limited to one location, at least 20m from any

watercourses or external boundary;

ii. Sealed waste bins provided for oil rags, oil filters and other wastes.

These drums will be transported off site to an appropriate receiving

facility;

iii. Confirmation that the storage of hazardous substances during

construction will comply with the requirements of the Hazardous

Substances and New Organisms Act and the requirements of the

Palmerston North District Plan;

iv. A Spill Emergency Response Plan;

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – TRACKED VERSION

Page 5 of 6

v. Covered rubbish and recycling bins are to be provided, regularly

emptied and moved off site to an approved facility;

vi. No burning of waste will be permitted;

vii. Portable toilet facilities will be located further than 20m from any

watercourse or external site boundary

l) complaints procedures and register;

m) monitoring, audit and review programme;

n) signage at the site informing of construction works and complaints procedure

Advice Note: The Regulatory Manager and Compliance Monitoring Officer will both

independently either certify, or refuse to certify, the CEMP within 20 working days of

receipt. Should either the Regulatory Manager or Compliance Monitoring Officer

refuse to certify the CEMP, then the Manager and/or Officer will provide a letter

outlining why certification is refused based on the parameters contained in this

condition.

10. Should the Regulatory Manager and/ or Compliance Monitoring Officer refuse to certify

the CEMP, the Consent Holder shall submit a revised CEMP to the appropriate

manager for written certification. The certification process shall follow the same

procedure and requirements as outlined in Condition 8 and 9.

11. The Consent Holder shall not initiate works that are authorised by these Consents until

the CEMP has been certified in writing by both the Compliance Monitoring Officer and

the Regulatory Manager.

12. The Consent Holder must comply with the certified CEMP at all times.

13. The certified CEMP may be amended at any time by the Consent Holder. Any

amendments to the certified CEMP shall be submitted by the Consent Holder to both

the Regulatory Manager and Compliance Monitoring Officer for certification. If the

amended CEMP is certified, then it becomes the certified CEMP for the purposes of

Conditions 8 and 9. Any amendments to the CEMP shall be:

a) for the purposes of improving the measures outlined in the CEMP for achieving

the CEMP purpose (see Conditions 8 and 9);

b) consistent with the conditions of this resource consent; and

3VC -He Ara Kotahi Bridge Project – PNCC Regulator Section 42A Officer, Amended Conditions in Response to Matters Raised at Hearing at 8-03-17 – TRACKED VERSION

Page 6 of 6

c) be prepared by an appropriately qualified person.

Discovery protocol

14. Prior to the commencement of works, the Consent Holder shall develop and have in

place a procedure that is to be followed in the event that any urupā, taonga (significant

artefacts), kōiwi (human remains) or archaeological sites (whether recorded or

unrecorded) are disturbed and/ or discovered during site works, including:

a. works in the location of any accidental discovery immediately cease; and

b. the area is to be secured in a way that ensures any remains or artefacts are

untouched;

c. inform Tanenuiarangi Manawatū Incorporated (TMI), the Regulatory Manager,

the Compliance Monitoring Officer and New Zealand Police (only if koiwi are

discovered) and Heritage New Zealand.

Cultural commitments

15. During construction of the Bridge, the Consent Holder shall allow Rangitāne o

Manawatū (or nominee) to conduct cultural monitoring where there is likely to be

culturally sensitive sites which may be disturbed by works. The Consent Holder may

restrict unsupervised access, to areas identified by the Consent Holder, only for

health and safety reasons.

16. Prior to the commencement of works, the Consent Holder shall contact Rangitāne o

Manawatū (or nominee) to arrange an appropriate time in construction to place a mauri

stone within a pile casing (at the deepest point possible) to connect the Bridge to the

River.

17. Prior to the completion of works, the Consent Holder shall contact the Rangitāne o

Manawatū kaumātua to arrange a karakia ceremony, according to Rangitāne o

Manawatū tikanga, prior to the opening of the bridge to the general public.


Recommended