+ All Categories
Home > Documents > CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage...

CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage...

Date post: 27-Aug-2018
Category:
Upload: lydat
View: 214 times
Download: 0 times
Share this document with a friend
31
Footer Text Date CONSISTENCY IN CONTRACT DEFAULT PROCESS Joe S. Graff, P.E., Director Construction Section, CST 10/10/17
Transcript
Page 1: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

CONSISTENCY IN CONTRACT DEFAULT PROCESS

Joe S. Graff, P.E., Director

Construction Section, CST

10/10/17

Page 2: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Presentation Outline

2

Defaults – A Necessary evil.

Default Considerations

Default Process

Proposed Default Process

Notice to Cure and Default Letters

Takeover Agreements

Termination for Convenience

1

2

3

4

5

6

7

8

Page 3: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

See Something? Say Something!

Page 4: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date 4

Page 5: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

STORY: DEFAULTSThey are not beautiful!!!!!!!

Page 6: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

DEFAULTS – A VERY SERIOUS STEP!!Do not take them lightly!

Page 7: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date 7

Page 8: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Disclaimer!

The proposed changes are not

approved and included in TxDOT policy

at this time! Formal policy changes

will be sent out to the Districts as

changes are approved by the

appropriate parties!

8

Page 9: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Item 8.7.1. Declaration of Default

Declaration of Default. The Engineer may declare the Contractor to be in default of the Contract if the Contractor:

1. fails to begin the work within the number of days specified;

2. fails to prosecute the work to assure completion within the number of days specified;

3. is uncooperative, disruptive or threatening;

4. fails to perform the work in accordance with the Contract requirements;

5. neglects or refuses to remove and replace rejected materials or unacceptable work;

6. discontinues the prosecution of the work without the Engineer’s approval;

7. makes an unauthorized assignment;

8. fails to resume work that has been discontinued within a reasonable number of days after notice to do so;

9. fails to conduct the work in an acceptable manner; or

10. commits fraud or other unfixable conduct as determined by the Department.

9

Page 10: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Default Categories

10

1. fails to begin the

work within the

number of days

specified;

2. fails to prosecute

the work to assure

completion within

the number of days

specified;

6. discontinues the

prosecution of the

work without the

Engineer’s approval;

8. fails to resume work

that has been

discontinued within

a reasonable

number of days after

notice to do so;

4. fails to perform the

work in accordance

with the Contract

requirements;

5. neglects or refuses

to remove and

replace rejected

materials or

unacceptable work;

10. commits fraud or

other unfixable

conduct as

determined by the

Department.

Timeliness Quality Criminal Other

3. is uncooperative,

disruptive or

threatening;

7. makes an

unauthorized

assignment;

9. fails to conduct

the work in an

acceptable

manner;

Page 11: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Default Considerations

1.Default frequently has disastrous

financial consequences

2.Often result in Claims and

potential litigation

3.Explore other possibilities before

exercising your default rights.

4.Remove emotions out of the

process!

–Use every step in the escalation

ladder!

–Give adequate opportunities for

success.

5.Meet with the Contractor.

6.Follow the standard process to

the letter!

–Notice of Intent to Default –

Notice to Cure

• Copy Surety.

• Provide clear, reasonable criteria.

7.Act in a timely fashion

–Default at the end of the period

indicated in the notice!

–Failure to act, indicates

acceptance of performance!

11

Page 12: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date 12

Page 13: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Existing Default Process –

Exhaust all options to continue the project before moving to

default.

1. Escalate issues!

2. Send a Notice of Intent to Default. Copy Surety.

3. Analyze performance. Was there a concerted effort by the

contractor?

4. If the answer to 3. is no, send default letter.

5. If the answer is yes, meet with contractor to establish the

expectations going forward.

6. A new notice should be sent for future issues.

13

Page 14: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Default Process – Proposed.

Exhaust all options to continue

the project before moving to

default.

1. Escalate issues to the

highest person on escalation

ladder!

2. Send Warnings. Use a

formal letter to notify the

contractor that:

• They are behind schedule.

• Their material or

performance quality is not

acceptable

• You have safety concerns

• Their equipment is

unacceptable

• Project management is

poor.

• Their workforce are not

skilled.

• Etc.

14

Page 15: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Default Process – Proposed. (Continued)

3. Last Chance Meeting –

Meet with the contractor.

Establish Expectations.

Communicate next step -

Notice of Intent to Default.

Include Division staff as

desired.

4. Send a Notice to Cure.

Copy Surety. Use an

appropriate time period.

15

Page 16: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Default Process – Proposed. (Continued)

5. Follow up in a timely

manner

6. Analyze performance

during the cure period.

7. If the answer to 6. is no,

prepare and send default

letter. Default letter

should come from no lower

than the Director of

Construction or Director of

Maintenance.

8. Consider forming a District

Default Review Committee.

If the answer is yes, establish

the expectations going

forward.

Send a new notice for future

issues.

16

Page 17: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Questions and Answers

When can you default a contractor?

– As soon as the contractor fails to meet the requirements of Item

8.7.!

– Too early – Give the contractor an opportunity to perform.

– Too late – We have put up with poor production and they are now

120-200% of the adjusted time used. However they have

performed 80-90% of the work.

17

Page 18: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date 18

2%5%

9%

14%14%

20%

27%

35%

44%

54%

65%

77%

90%

100%

0%

20%

40%

60%

80%

100%

120%

0% 20% 40% 60% 80% 100% 120% 140%

Pe

rce

nt

Co

mp

lete

Percent of Time Used

Performance Curve

Page 19: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date 19

1% 2%5%

10%

15%

20%

25%

30%

35%

40%40%

50%

60%

70%

80%

90%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0% 20% 40% 60% 80% 100% 120% 140% 160%

Pe

rce

nt

Co

mp

lete

Percent of Time Used

Performance Curve

Page 20: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date 20

Page 21: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Questions and Answers (Continued)

What other problems have occurred.

– Sent Cure Notice(s) Letters to wrong Zip Code.

• Recommend correspondence be mailed using certified mail

and emailed. Maintain accurate records of all

correspondence.

– Did not monitor mail return receipts.

• Keep a log of correspondence and monitor return receipts.

– Pressure by third parties to default. For example, 3rd party

financing entities.

• Manage Contract in a timely manner.

21

Page 22: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Notice to Cure and Default Letters

Recommendations for Notice of Intent to

Default (Notice to Cure)

– Escalate the issues through the

escalation ladder!

– The intent should be to salvage the

project! If you have already decided to

default, you have waited too late!

– Make sure that the stipulated

requirements are clear and more

importantly, reasonably achievable.

– Must use one of the ten “thou shalt nots”

– Be specific enough to provide notice of

the reason for the default: Is there

enough information for the contractor to

be able to successfully dispute it?

– Set a time and place for a final meeting to

see if default can be avoided.

– Let CST or MNT review the draft before

sending!

– Do not reference issues that are not true!

For example:

• fails to prosecute the work to assure

completion within the number of days

specified. - project is already at 150%

of time used.

• discontinues the prosecution of the

work - Contractor worked every week.

– Copy the Bonding Company!

– Do not ask the contractor to accelerate

their schedule.

22

Page 23: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Notice to Cure and Default Letters

Recommendations for Default Letters

– Set a time and place for a final meeting to see if default can be avoided.

– Have contractor explain why they should not be defaulted.

– If they have not satisfied Notice to Cure, prepare default letter.

– Let CST review the draft before sending

– Contractor’s may declare themselves to be in self default (must be in writing). The 10 day cure notice is not required under this circumstance.

– Know when to pull the trigger! Default them if they have not

performed in the time given! Failure to default can be considered acceptance of performance!

– Copy the Bonding Company!

– Stop all work!

– Make project safe to the traveling public!

– Work with CST, to have estimates stopped immediately.

– Work with CST and FIN to prepare takeover agreement with Surety.

– Continue time charges.

– Document, document, document!!!

23

Page 24: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Takeover Agreement

Work with CST to prepare

takeover agreement.

Frequently takes 2-6 months.

– Surety hires consultant.

– Consultant may have to hire

surveyors or other consultants

to review existing situations.

– Consultant bids work out to

selected contractors.

– Takeover Contractor will have

to mobilize.

Surety is now the prime

contractor.

– Takeover contract is a sub-

contractor to the Surety and

we may deny subcontractor.

– Once a takeover agreement is

executed, SiteManager will be

changed to reflect the Surety’s

name as the contractor.

• Payment can be released.

24

Page 25: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date 25

Page 26: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Item 8.8. Termination of Contract

The Department may terminate the Contract in

whole or in part whenever the Contractor is

prevented from proceeding with the work by

reason of :

An executive order of the President of the

United States or the Governor of the State,

A national emergency, freezing or diversion

of materials, equipment or labor as the

result of an order or a proclamation of the

President of the United States,

An order by any federal authority,

A preliminary, special, or permanent

restraining court order where the issuance

of the restraining order is primarily caused

by acts or omissions of persons or agencies

other than the Contractor, or

The Department determines that

termination of the Contract is in the best

interest of the State or the public.

– Discovery of significant hazardous

material problems,

– Right of way acquisition problems,

– Utility conflicts that would cause

substantial delays

– etc.

26

Page 27: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Item 8.8. Termination of Contract

Consider Termination for Convenience if

there are issues on TxDOT side. - A

termination for convenience clause allows

you to terminate without cause, and without

having to justify the termination decision.

– CST should Terminate Contracts in

accordance with the CCAM.

– TxDOT required to pay contractor for their

costs to terminate – Mobilization,

restocking materials, bonds, insurance,

etc. Will not pay for anticipated profit.

27

Page 28: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Item 8.7.2 Wrongful Default

What is a wrongful default?

– If TxDOT did not follow all

procedures to the letter, it

could be considered a

“Wrongful Default”.

• Failure to give adequate

notice.

• Failure to provide

warnings.

• Defaulting a contractor for

poor performance when

TxDOT is the cause of the

delays

• Failure to act in a timely

manner.

• Expecting more than the

specifications require.

28

Page 29: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Use a Progressive Process when Defaulting!

Progressive discipline is a

process for dealing with job-

related behavior that does not

meet expected and

communicated performance

standards. The primary

purpose of progressive

discipline is to assist the

contractor to understand that

a performance problem or

opportunity for improvement

exists.

The process features a series

of increasingly formal efforts to

provide feedback to the

contractor so that they can

correct the problem.

The process of progressive

discipline is not intended as a

punishment, but to assist the

contractor to overcome

performance problems and

satisfy job expectations.

29

Page 30: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date

Summary

1. Explore other possibilities before exercising your default rights.

2. Have a Last Chance Meeting.

3. Make sure documentation and all procedures have been followed!

4. Get CST or MNT involved.

5. Provide clear, reasonable criteria.

6. Act in a timely fashion – Know when to pull the trigger!

7. Send formal Warning letters.

8. Do not ask the contractor to accelerate their schedule.

9. Have contractor explain why they should not be defaulted.

10. Use Termination of contract when appropriate.

11. Use a Progressive Process

30

Page 31: CONSISTENCY IN CONTRACT DEFAULT PROCESS · escalation ladder! –The intent should be to salvage the project! If you have already decided to default, you have waited too late!

Footer Text Date 31

Questions/[email protected]


Recommended