+ All Categories
Home > Documents > Construct Fighter SAPF/SCIF - - The Expeditionary … · Web viewTrenching Itemized Price Schedule...

Construct Fighter SAPF/SCIF - - The Expeditionary … · Web viewTrenching Itemized Price Schedule...

Date post: 07-Apr-2018
Category:
Upload: phungtu
View: 217 times
Download: 3 times
Share this document with a friend
38
STATEMENT OF WORK FOR TRENCHING, DUCTWORK AND MANHOLE CONTRACT IDIQ (INDEFINITE DELIVERY, INDEFINITE QUANTITY) SAMPLE STATEMENT OF WORK 1.0 SUMMARY OF WORK: 1.1 Furnish all plant, equipment, supervision, labor, supplies, services, and materials required to accomplish the work indicated in these specifications, the related drawings and as otherwise set forth in the contract for the purpose of providing trenching and associated communications works thru-out the installation and air force facilities. 1.2 The following intent is provided within this document to assist the contractor with understanding the purpose of this Statement of Work (SOW). The below section is not intended to provide a minimum or maximum amount of work required. Minimum and maximum scopes of work are provided within other sections of the contract and SOW. Contractor’s proposed materials, means and methods can, and are encouraged to exceed the listed minimum requirements. 1.3 Trenching Itemized Price Schedule (ATTACHMENT 1): Nomenclature used below represent the Itemized Line Items for the contract base year. Line Items for subsequent option years will be classified by changing the first digit of the Line Items to match the option year. (i.e. the first CLIN of the first option year shall be: 1001, whereas the second Line Items of the second option year shall be: 2002, and so on.). All task orders will be awarded as a lump sum, but the contractor shall provide a bill of quantity (BOQ), with each proposal, that will include all line items and quantities in accordance with Attachment 1 for the task order. ITEM 0001 MOBILIZATION / DEMOBILIZATION: Work includes all initial actions related to the relocating of equipment, vehicles and material to the vicinity of the work site for use during the life of the project. Modified contract performance periods (extensions), regardless of reason for extension, may not obligate the government to additional mobilization costs. Mobilization line item will apply to the Base Year at the beginning of the IDIQ Contract. ITEM 0002 SITE SURVEY/ DESIGN: Includes all work performed to acquire site specific topographic information necessary to execute the project, to include existing contour lines and spot elevations required for the design of site, grading, and drainage. The survey shall include the location of permanent benchmarks (and temporary benchmarks Page 1 of 38
Transcript

STATEMENT OF WORK FOR

TRENCHING, DUCTWORK AND MANHOLE CONTRACTIDIQ (INDEFINITE DELIVERY, INDEFINITE QUANTITY)

SAMPLE STATEMENT OF WORK1.0 SUMMARY OF WORK:

1.1 Furnish all plant, equipment, supervision, labor, supplies, services, and materials required to accomplish the work indicated in these specifications, the related drawings and as otherwise set forth in the contract for the purpose of providing trenching and associated communications works thru-out the installation and air force facilities.

1.2 The following intent is provided within this document to assist the contractor with understanding the purpose of this Statement of Work (SOW). The below section is not intended to provide a minimum or maximum amount of work required. Minimum and maximum scopes of work are provided within other sections of the contract and SOW. Contractor’s proposed materials, means and methods can, and are encouraged to exceed the listed minimum requirements.

1.3 Trenching Itemized Price Schedule (ATTACHMENT 1):Nomenclature used below represent the Itemized Line Items for the contract base year. Line Items for subsequent option years will be classified by changing the first digit of the Line Items to match the option year. (i.e. the first CLIN of the first option year shall be: 1001, whereas the second Line Items of the second option year shall be: 2002, and so on.). All task orders will be awarded as a lump sum, but the contractor shall provide a bill of quantity (BOQ), with each proposal, that will include all line items and quantities in accordance with Attachment 1 for the task order.

ITEM 0001 MOBILIZATION / DEMOBILIZATION:Work includes all initial actions related to the relocating of equipment, vehicles and material to the vicinity of the work site for use during the life of the project. Modified contract performance periods (extensions), regardless of reason for extension, may not obligate the government to additional mobilization costs. Mobilization line item will apply to the Base Year at the beginning of the IDIQ Contract.

ITEM 0002 SITE SURVEY/ DESIGN:Includes all work performed to acquire site specific topographic information necessary to execute the project, to include existing contour lines and spot elevations required for the design of site, grading, and drainage. The survey shall include the location of permanent benchmarks (and temporary benchmarks tied to permanent, if any), and shall include the location of surrounding underground utilities, if any. High voltage cable and fiber optic lines shall be identified and hand dug for depth certification. A minimum of three potholes along each identified high voltage and/or fiber optic line shall be completed.

Includes all work performed in preparing engineering documents, drawings and communications with Contracting Officer or project manager. As-built drawings shall be provided as soft copies, in AutoCAD format, and hard copies. As-built drawings shall include the location and layout of all items installed during the life of the project.

Level of design will vary for each individual Task Order executed under this contract. In some cases, contractor will be expected to produce a complete design based on minimal performance based criteria provided by the USG. In other cases the USG may provide all of the design and specifications necessary for the contractor to perform the requested work. The USG will prescribe the level of design effort (conceptual – final) required at the the Task Order Level. Minimum design submittal requirements for each level of design are specified in section 7.0 of this SOW.

Page 1 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

The contractor will be responsible for conducting a design charrette as specified by the government at the Task Order Level. The contractor will coordinate with the government to be sure the proper attendees are invited to and participate in the design charrette. Design Charrettes may include but may not be limited to decision makers from base Security, Communications, Engineering, Contracting and other key agencies. The purpose of the Charrette is to ensure the contractor is designing the project to meet the performance specifications for the individual task order.

ITEM 0003 EXCAVATION / TRENCHING:Work includes the procurement, delivery and all labor, equipment and materials required for the excavating/trenching of soil on site, either by heavy equipment or by hand digging. Trenching shall be deep enough to provide a minimum depth of cover of 30-in [76-cm] for all new conduits. For multiple utilities (i.e. power and comm.) sharing the same trench, the trench shall be wide enough to provide a minimum horizontal (and vertical) separation of 36-in [915-cm] between utility lines.

Excavation shall be performed in accordance with IBC, UFC and USACE EM 385-1-1 requirements and recommendations.

Digging Permit: No excavation work may begin until the Contractor has been issued an Air Force Form 103, Base Civil Engineering Work Clearance Request, commonly called a “Digging Permit.” This permit is only effective for 30 calendar days and will be kept current by the contractor.

ITEM 0004 HAULING:Work includes the removal of excavated material or extra pavement materials not required for project execution to an off-base location and disposed in accordance with U.S. and Host Nations rules and regulations. Disposal location shall be determined by the Contractor.

Specified Haul Route: The Contractor shall follow the specified on-base haul route for the project, unless otherwise directed. Route changes requested by the Contractor may be approved only by the Contracting Officer, if requested in writing and at no additional cost to the Government. The Contractor shall restore the area to its original condition, at the end of the contract period unless specific, written approval has been granted by the Contracting Officer. Normal wear and tear is acceptable with regard to restoration of the area to its original condition. The Contracting Officer shall make the final determination of what is considered acceptable site restoration. All mud, dirt, debris, foreign objects, or spills of any kind from the Contractor's operations (including subcontractors and suppliers) on taxiways, runways, parking aprons, hard surfaces, streets, and parking lots used as access to the work or staging areas, shall be cleaned immediately after use.

ITEM 0005 to 0007 BACKFILL:Work includes the procurement, delivery and all labor, equipment and materials required for the installation of backfill material. Unless otherwise directed in this SOW, all backfill material shall consist of Class A material, as per the 2002 Sample Country Construction Standards, Section 6, Part 4. Class A backfill shall be 2 ½” (63mm) minus engineered crushed limestone. A sieve and chemical analysis shall be submitted for review and approval. All backfill material shall be placed in lifts not to exceed 8 in (203 mm); each lift shall be compacted to 90% of MDD. The organic matter content in the soil shall not exceed 2%. Backfill material shall have a Liquid Limit (LL) not to exceed 35%, and a maximum Plasticity Index (PI) of 10%.

All backfill material under pavement crossings, whether flexible or rigid, and around concrete structures shall be Select Fill. Select Fill is defined as material with aggregate content suitable for use under structural pavements, which shall be 20mm minus engineered crushed limestone, and compliant with gradation requirements for

Page 2 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

Class C material, as per the 2002 Sample Country Construction Standards, Section 6, Part 4. A sieve and chemical analysis shall be submitted for review and approval. All backfill material shall be placed in lifts not to exceed 6 in (152 mm); each lift shall be compacted to 95% of MDD. The organic matter content in the soil shall not exceed 2%. Select Fill shall have a Liquid Limit (LL) not to exceed 25%, and a maximum Plasticity Index (PI) of 6%.

Sand bedding and cover for all conduits shall be 4.75mm minus engineered crushed limestone. The sand shall be mechanically washed to have salts and other impurities removed in order to meet the specified requirements.

ITEM 0008 to 0009 SAWCUT PAVEMENT, BITUMINOUS:Work includes the procurement, delivery and all labor, equipment and materials required for saw cutting asphalt pavement to a partial depth of up to 7.5 centimeters, or full depth of up to 15 cm, for the purpose of installing road-crossing electrical and/or comm. conduit. Sawcutting shall be performed in straight, neat lines.

The Contractor shall be responsible for sawcutting sections of existing pavement, with a clean, neat edge, to install new conduits. Should any asphalt spalling occur during sawcutting procedures, the Contractor shall sawcut further back to maintain a clean, neat edge line. After installation or conduits, the trench shall be backfilled with Select Fill, as per CLIN 005 to 0007 of this SOW, and new pavement shall be provided, as per applicable CLINs for either asphalt or concrete pavement, respectively. The replacement pavement cross-section shall match existing.

ITEM 0010 PRIME COAT:Work includes the procurement, delivery and all labor, equipment and materials required for the application of cutback asphalt to underlying layer of prepared subgrade, subbase, or asphalt containing base.

All base course surfaces which will come in contact with new asphalt shall be coated with cutback asphalt consisting of a 60/70 penetration grade bitumen and kerosene. A distillation test shall be conducted to 360 degrees Celsius; the residue from the distillation test shall be a minimum of 55% by volume. Prime coat shall conform to AASTO M82, for MC-70 medium curing cutback. The application rate shall be 0.6 Kg/m2 (+/-) 0.15 Kg/m2. The temperature prime coat shall not fall below 60oC, or exceed 85oC during application.

Tack coat shall be allowed to cure a minimum of 24 hours before the subsequent pavement installation activities.

ITEM 0011 TACK COAT:Work includes the procurement, delivery and all labor, equipment and materials required for the application of emulsified asphalt between asphaltic base course and surface course. Emulsified asphalt for tack coating shall conform to ASTM D 977, grade SS-1 or SS-1h.

ITEM 0012 and 0013 BITUMINOUS BASE COURSE, ROADWAY & AIRFIELD:Work includes the procurement, delivery and all labor, equipment and materials required for the placement of a layer of hot mix asphalt base course in the specified thickness. Base course asphalt layers will be installed in lifts of a maximum of 10 cm and compacted to 97% of the maximum mix density. Bituminous base course shall only be placed on compacted sub-grade after applying a suitable prime coat.

ITEM 0014 and 0015 BITUMINOUS SURFACE COURSE, ROADWAY & AIRFIELD:Work includes the procurement, delivery and all labor, equipment and materials required for the placement of an asphalt road mix wearing course or surface course on

Page 3 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

over a suitable tack coat that has been sprayed over an adequate base course. The surface course shall be compacted to 98% of maximum mix density.

ITEM 0016 CONCRETE MANHOLE (MH) CONSTRUCTION: Work includes all labor, equipment and materials required for the construction of a reinforced concrete manhole. Furnish and install manholes to include the following minimum requirements:

General: Inside dimensions shall measure no less than 8’(2438.4 mm)L x 6'(1828.8 mm)W x 8' (2438.4 mm)H, for precast manholes, multidirectional, telecommunications manhole and all items required to prepare the manhole for use. These dimensions shall be relative to the number of conduits traversing the manhole as specified by the design. The manhole shall be equipped with cable racks, cable rack supports, corner rack supports, maintenance manhole frames, extension collars, covers, pull-in irons, ground rod, grounding ribbon, sump, and anything else required to make a complete system with a resistance-to-earth of 10 ohms or less, following MIL-STD-188-124B. The maintenance hole shall be equipped with duct terminators or windows in 4 sides to accommodate the duct banks. The maintenance hole shall be rated as H-20 the manhole lid shall be steel checker plate, H-20 traffic rated with hold down bolts and weld a metallic padlock hasp to structure for future security requirements. Manhole entry way from ground level should be a minimum of 36” in diameter. Communication manholes lids shall have welded markings of the structure ID for each communication space i.e. “US-MH-191736” and “ELECTRIC” for electrical systems. See Fig 1, for manhole type and specifications.

MH COLLAR EXTENSION 12" Furnish and install 12" (304.8mm) high extension collar(s) to raise the lid on a maintenance hole. The extension collar shall be used to extend a MH cover to ground level. Furnish includes a ring type collar and materials required to install and seal the collar.

ACCESSORIES:

Each manhole shall be equipped with a sump, pull irons, ground rod, bonding ribbon, cable racks and hooks.

SUMP: A sump shall be cast into the floor of the manhole. The floor shall slope toward the sump to provide drainage from all areas into the sump. The sump shall be approximately a 13 in. (330.2 mm) square and 4 in. (101.6 mm) deep equipped with a plugged drain and covered with a removable perforated or punched-steel plate to permit drainage. The cover shall be fastened to the housing by a chain or a hinge.

PULL IRONS: Able pull irons shall be installed on the wall opposite each main conduit entrance location 3 ½ inch (88.9mm) to 9 in (228.6mm) from the floor of the manhole and 6 to12 inches(152.4 to 305 mm) below associated ducts, in line with the center line of the conduit entrance. The pull irons shall be placed and embedded during the construction of the manhole wall.

HARDWARE: A minimum of three cable racks, each containing 47 hook spaces mounted vertically, shall be provided on each long wall. End wall manhole racks shall be provided at the T-end of multi-directional manholes. Corner racks shall be provided at the in-line end of the manhole. Racks shall set out from the wall a minimum of 3 ½ inches (88.9mm). Each cable rack shall be equipped with hooks to support all existing/new cable or if there are no existing/new cables, each rack shall be equipped with two cable hooks (minimum length 7 ½ inch (190.5 mm). All racks and hooks shall be of galvanized metal or non-corrosive materials.

DEPTH OF COVER: A minimum of 24 in. (610 mm) of top cover shall be provided above the top of the concrete lid. Provide riser(s) to allow for manhole cover to be flush with adjacent ground level.

Page 4 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

STUB-OUTS: All concrete manholes shall have 4” PVC conduit stub-outs, extending a minimum of 12 in (305 mm) from the edge of concrete surface, in any of the four directions in which ductbanks are not being installed. The number of conduit stub-outs per manhole face shall be specified in the project scope of work (SOW), and based upon the location in which the manhole is constructed, as this requirement shall facilitate the extension of ductbank systems to support future expansion of the base.

DUCT TERMINATORS: Duct terminators shall be positioned in the manhole consistent with allowing the most efficient path for installation of the cable run passing through the manhole. The number of duct terminators depends on the manhole’s requirement. Duct terminators shall be placed 8.5”(215.9mm) from the inside edge of the manhole wall to the centerline of the near conduit.

Figure 1: Illustration of Typical Comm. Manhole Construction (Illustration for reference purposes only)

Page 5 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

ITEM 0017 CONCRETE HANDHOLE CONSTRUCTION: Work includes all labor, equipment and materials required for the construction of a reinforced concrete pull box. Furnish and install Handhole (HH) to include the following minimum requirements:

General: Furnish and install a 4'(1219mm)L x 4'W(1219mm) x 4'(1219mm)H, precast, multidirectional, handhole capable to support vehicular traffic and all items required to prepare the handhole for use. The handhole shall be equipped with cable racks, cable rack supports, handhole frames, extension collars, covers, pull irons, ground rod, grounding ribbon, and anything else required making a complete system. The handhole cover shall be traffic rated as H-20. The handhole shall be equipped with duct terminators or windows in 4 sides to accommodate the duct banks. The handhole lid shall be steel checker plate; H-20 traffic rated with hold down bolts and a metallic padlock hasp welded to structure for future security requirements. Communication handhole lid shall have welded markings of the structure ID for each communication space i.e. “US-HH-191736” for each communication space and “ELECTRIC” for electrical systems.

ACCESSORIES:

PULL IRONS: Able pull irons shall be installed on the wall opposite each main conduit entrance location 3 ½ inch (88.9mm) to 9 in (228.6mm) from the floor of the handhole and in line with the conduit entrance. The pull irons shall be placed and embedded during the construction of the handhole wall.

HARDWARE: A minimum of two cable racks, each containing 47 hook spaces mounted vertically, shall be provided on each long wall. End wall manhole racks shall be provided at the T-end of multi-directional handholes. Corner racks shall be provided at the in-line end of the manhole. Racks shall set out from the wall a minimum of 3 inch. Each cable rack shall be equipped with hooks to support all existing/new cable or if there are no existing/new cables, each rack shall be equipped with two cable hooks (minimum length 7.5” inch / 190.5mm). All racks and hooks shall be of galvanized metal or non-corrosive materials..

DEPTH OF COVER: A minimum of 24 inch of top cover shall be provided above the top of the concrete lid. Provide riser(s) to allow for handhole cover to be flush with adjacent ground level.

STUB-OUTS: All concrete handholes shall have 4”(101.6 mm) PVC conduit stub-outs, extending a minimum of 12”(304.8 mm) from the edge of concrete surface, in any of the four directions in which ductbanks are not being installed. The number of conduit stub-outs per handhole face shall be specified in the project scope of work (SOW), and based upon the location in which the handhole is constructed, as this requirement shall facilitate the extension of ductbank systems to support future expansion of the base. The minimum number of conduit stub-outs per handhole face shall be four in a typical handhole and placed even with the bottom of an active window.

ITEM 0018 to 0029 DUCTBANK CONSTRUCTION: General: Work includes all labor, equipment and materials required for the construction of ductbanks to include multiple PVC conduits. There shall be a minimum horizontal and vertical separation of 2-in [5.1-cm] between PVC conduits sharing the same ductbank by using conduit spacers or a suitable substitute as authorized by Contracting Officer. The width of the trench for the ductbank shall be a minimum of 12-in (30.5-cm) [6-in (15.2-cm) to each side] wider than the total width of the ductbank. See Fig 2 for additional information regarding conduit installation and ductbank constructions.

Page 6 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

NON-CONCRETE ENCASED DUCTBANK AND TRENCH CONSTRUCTION:

Work includes all labor, equipment and materials required for the construction of a ductbank for one or multiple PVC conduits. The dimensions of the ductbank shall vary according to the number of conduits required, Place 152.4 mm (6 in) of sand for electrical conduits and 152.4mm of sand for communication conduits placed at the bottom of trench. Install conduit centered on sand bed. The Contractor shall not backfill the trench until it has been inspected and deemed satisfactory by the U.S. Government. Put 152.4 mm (6 inch) of sand on electrical ductbank and 152.4mm (6 inch) of sand on communication ductbanks cable or conduit. The next 254 mm (10 inch) of the trench shall be filled with sieved backfill and compacted to 95% via vibratory compaction. The Contractor shall not continue backfill work until an additional inspection has been inspected and deemed satisfactory by the project manager. The remaining empty trench shall be filled with coarse backfill, with “ELECTRICAL” or “COMMUNICATION” warning tape placed at 305 mm (12 inch) below the finished grade. The top grade shall match the surrounding natural grade. The filled trench shall then be vibratory-compacted to 95%.

CONCRETE-ENCASED CONDUIT DUCTBANK CONSTRUCTION:

Work includes all labor, equipment and materials required for the construction of a ductbank to concrete encase one or multiple PVC conduits. The dimensions of the concrete ductbank shall vary according to the number of conduits required for either electrical or communication systems. In addition to requirements mentioned in the above section for Non-Concrete Encased Ductbank and Trench Construction, in areas where the trench must cross an existing road, concrete-encased duct with multiple sleeves to house up to twelve 4-inch conduits, shall be placed in the trench extending 1524mm (60 inches) beyond the edges of the road,. “ELECTRICAL” or “COMMUNICATION” warning tape shall be placed at 305 mm (12 inch) below the finished grade. The trench will then be properly backfilled and paved to restore the road to its original condition. Provide a minimum 3-in [7.6-cm] concrete cover in all directions to the outermost conduit(s) to be encased. Concrete design mix shall have a minimum compressive strength 4,000-psi (27.6-MPa). Sidewalks shall be squarely saw-cut and professionally replaced or repaired as needed. Arrows with the denotation “ELECTRICAL” or “COMMUNICATIONS” will be stamped on affected sidewalks.

SEPARATION OF CONDUIT SYSTEMS WITHIN DUCTBANKS:

Electrical (low voltage (LV) & medium voltage (MV)) and communications ductbank systems shall be completely separated from each other by a minimum of 3 feet (915 mm) in both horizontal and vertical directions. They may share the same trench if separation distances can be achieved. Furthermore, electrical (LV & MV) and communications ductbank systems shall not share trenching and ductbanks with any other underground utility ductbanks or trenching.

Page 7 of 26

Figure 2: Communication and Electrical Ductbank Installation Details Minimum Requirements

Page 8 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

ITEM 0030 STRUCTURAL CONCRETE: Work includes the procurement, delivery and all labor, equipment and materials required for placement of structural concrete used for the repair of existing underground structures to include, but not be limited to manholes, handholes, concrete covers and concrete-encased ductbanks. All structural concrete shall have a minimum compressive strength of 34.5 MPa (5,000 psi).

Concrete samples shall be taken at the average rate of one sample every 30 cubic meters of concrete, with a minimum of one sample taken of each mix every day the mix is used. A sample consists of four cubes, one to be tested at 7 days, two at 28 days, and one to be held in reserve. Additional cubes may be prepared as directed by the U.S. Government. Cube forms shall be metal or non-porous wood (marine board) only. Samples shall be covered with damp burlap and removed to a laboratory for climate controlled curing the same day as the sample was taken. Cube samples shall not be cured on site.

All concrete work shall be placed, compacted, and cured to meet applicable ACI Standards. All surfaces shall have a smooth finish.

ITEM 0031 and 0032 PORTLAND CEMENT CONCRETE ROADWAY PAVEMENT, PLAIN:

Work includes the procurement, delivery and all labor, equipment and materials required for placement of a plain concrete slab, of a thickness as specified in project documents. Formwork and surface smooth finish shall be included.

ITEM 0033 and 0034 PORTLAND CEMENT CONCRETE PAVEMENT, REINFORCED:Work includes the procurement, delivery and all labor, equipment and materials required for placement of a reinforced concrete slab of a thickness as specified in project documents. Formwork and surface smooth finish shall be included.

Reinforcing steel shall meet the requirements of ASTM A615. Reinforcing Steel to be welded shall meet the requirements of ASTM A706. All bends, hooks, lap splices, and other requirements shall meet the requirements of ACI 318.

ITEM 0035 to 00062 BUILDING INTERIOR ELECTRICAL WIRING REQUIREMENTS: General: All electrical wiring within the buildings shall be installed in electrical metallic tubing (EMT) or rigid galvanized steel (RGS) conduits. No exception shall be approved and no exposed wiring shall be allowed.

ITEM 0063 to 0065 ELECTRICAL UNDERGROUND CONDUIT REQUIREMENTS:General: Work Includes all labor, equipment and materials required for provision and installation of electrical LV and MV underground conduit systems. For additional information refer to section 0013-Duct Bank Construction.

LV(less than 600V) cables according to following: Install all underground LV (600V and less) power cables in PVC schedule 40, NEMA TC-2 rated conduits with no exception approved. Minimum depth from the top of conduit to finished grade shall be 30 inch (762 mm).

MV (above 600V) cables according to following: Install all underground MV (above 600V) power cables in PVC schedule 40, NEMA TC-2 rated conduits with no exception approved. Minimum depth from the top of conduit to finished grade shall be 42 inch (1,067 mm).

MV (above 600V), LV (600V and less) and communications cables shall be installed in separate trenches and dedicated to their voltage and systems and shall not share same trenches or manholes. They shall not also share trenches or ductbanks with any

Page 9 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

other systems unless separation distances of 3 feet (914mm) can be maintained in all directions between their ductbanks.

Provide cable and/or conduit spacers to maintain minimum of 2 feet between cables and 7.5 inch between conduits (center-to-center).

MV (above 600V), LV (600V and less) and communications cables shall be installed in separate trenches and dedicated to their voltage and systems and shall not share same trenches or manholes. They shall not also share trenches or duct-banks with any other systems.

Electrical conduits shall be provided and sized in accordance with NEC (NFPA 70). Minimum size of conduits shall be ¾ in. (19.5 mm).

Provide 25% spare capacity with minimum of (1) each size of conduit.

Plugs: All ducts, sub-duct and/or inner duct, whether main or subsidiary runs, not scheduled for immediate use shall be plugged using duct plugs or sealing compound. The area between conduits and penetrated floors and walls shall be sealed to be water-proof or fire-stopped as appropriate.

American Standards for 4 inch PVC, Sch. 40 conduit is as follows and includes the metric conversion: Outside Diameter (inches / mm) = 4.500 / 114.30 Nominal Inside Diameter (inches / mm) = 4.026 / 102.26 Minimum Wall Thickness (inches / mm) = 0.237 / 6.02

ITEM 0066 to 0068 COMMUNICATION UNDERGROUND CONDUIT REQUIREMENTS:General: Work Includes all labor, equipment and materials required for provision and installation of communication underground conduit systems. For additional information refer to section 0013-Duct Bank Construction. Refer to Fig.2.

Conduits shall be PVC schedule 80, NEMA-TC-2 rated. Conduit bends or stub ups shall be installed using factory manufactured wide sweep elbows with minimum bending radius of 12 times the conduit radius. Minimum depth from the top of communication conduits to finished grade shall be 24 inch (610 mm).

Provide minimum of (12) 4 in. (101.6 mm) conduits within each ductbank from ITN or main communication building communication/server room to first manhole outside ITN, from each manhole to next manhole within main communication backbone ductbank system.

Provide minimum of (1) communication handhole within 10 feet (3 m) of each facility requiring communication systems. Unless otherwise noted, each handhole may be used for two adjacent facilities as long as straight runs without bends exist between the handhole and communication room where conduits will be stubbed up. Maximum distance between the handhole and second facility communication room/closet shall not exceed 300 feet (91.4 m).

Unless otherwise noted for a specific facility, provide as a minimum, (2) 4 in. (101.6 mm) conduits from each facility’s communication room or closet to the handhole outside the facility.

Unless otherwise noted on the drawings or within this document, provide a minimum of four (4) 4 in. (101.6 mm) conduits between the communication manholes to communication handholes adjacent to the facility requiring communication system.

Plugs: All ducts, sub-duct and/or inner duct, whether main or subsidiary runs, not scheduled for immediate use shall be plugged using duct plugs or sealing compound. The area between conduits and penetrated floors and walls shall be sealed to be water-proof or fire-stopped as appropriate.

Page 10 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

American Standards for 4 inch PVC, Sch. 80 conduit is as follows and includes the metric conversion: Outside Diameter (inches / mm) = 4.500 / 114.30 Nominal Inside Diameter (inches / mm): 3.826 / 97.18 Minimum Wall Thickness (inches / mm): 0.337 / 8.56

ITEM 0069 INSPECTIONS:All work is subject to the satisfactory inspection of the project manager at a minimum twice during the rough-in stage and twice after a satisfactory rough-in inspection. A final satisfactory inspection will be required before occupancy and project acceptance. Reports of inspection shall be kept on project files.

ITEM 0070 PLYWOOD COMMUNICATION BOARD:Work includes the procurement, delivery and all labor, equipment and materials required for the installation of a 4-ft x 8-ft x ¾-in (122-cm x 244-cm x 19-mm), ACX, or equivalent, plywood comm. board (ACX plywood is American Grade “A” plywood made of Pine and Fir with a smooth face). The plywood shall be painted on 6 sides with two coats of white fire retardant paint and installed with the smooth side facing out. The comm. board will be mounted to the back wall of the utility or TC/CER, at a minimum of 3-ft [90.5-cm] away from electrical and any other utilities for the facility. Unless otherwise noted, all cabling will be handled by the US Air Force.

ITEM 0071 GROUNDING BAR:Work includes the procurement, delivery and all labor, equipment and materials required for the installation of a grounding bar (TGB/TMGB) at the bottom center of the comm. board (ITEM 0071) that is connected to the facilities ground. The grounding shall be performed in accordance with EIA/TIA 607 “Commercial Building Grounding and Bonding Requirements for Telecommunications”. All bonding and ground conductors shall be #6 AWG or greater.

ITEM 0072 PULL STRING / ROPE:Work includes the procurement, delivery and all labor, equipment and materials required for the installation of a pull string/rope at the end of each conduit or inner duct. The pull string/rope shall be at a minimum high tensile strength, low stretch, 1/2" x 5,000' Spool, 1,250 lbs. Tensile Strength printed sequential footage markings for accurate measurements easily blown through conduit or ducts.

ITEM 0073 UNDERGROUND WARNING TAPES:Work includes the procurement, delivery and all labor, equipment and materials required for the installation of underground warning tapes. Warning tapes shall be underground warning tape to help to reduce the amount of time spent locating buried lines. Underground warning tape shall be buried 12 inch (305 mm) below the finished grade to mark the underground utility locations of electrical or communication lines. Underground warning tape shall meet OSHA regulation 1926.956(c) (1) for covering the location of underground utility lines, and shall be easily identified with sharply printed legend on APWA color-coded background. The warning tape shall be made of tough B-721 metal detectable polyester material with subsurface graphics to seal the legend from acids, alkalis and other soil substances. Foil shall be 5 mils and standard roll size is 2" W x 1,000 ft.

Workalso includes the procurement, delivery and all labor and equipment required for the installation of detectable underground warning tape. Warning tape shall be 3 in. (75 mm) wide and shall conform to APWA color schemes. Warning tape shall be polyethylene with metallic core, and be buried at a depth not to exceed 12 in. (305 mm) below ground level

Page 11 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

ITEM 0074 DUCT PLUG:Work includes the procurement, delivery and all labor, equipment and materials required for the installation of plugs for all ducts, sub-ducts and/or inner ducts, whether main or subsidiary runs, not scheduled for immediate use. Duct plug shall be as a minimum: Solid round duct plugs with rope ties for sealing vacant conduits and innerducts

entering enclosures of any type. Corrosion proof. No metallic parts Water, air, and gas tight seal. Easy installation Attachment secures pull rope in conduit. No hazardous toxic compounds or messy foams used. Injection molded chemical resistant gasket. Sealing capacity tested to minimum 22 psi (50' head of hydrostatic pressure). Reduces long-term maintenance costs. Removable and reusable

ITEM 0075 4” CONCRETE STRUCTURE CORING:Work includes all labor, equipment and materials required for core 4 in (101.6-mm) diameter openings into walls of existing concrete manholes/handholes, up to 6 in. (152 mm), to insert new underground utility conduits. Concrete structure penetrations shall be adequately grouted or sealed to avoid potential leaks.

ITEM 0076 VAPOR BARRIERVapor Barrier shall be polyethylene sheet with a minimum thickness of 6 mil (0.15mm). Vapor Barrier shall be placed between all concrete surfaces exposed to soil. Where two section of vapor barrier abut, a minimum overlap of 6 in (150mm) in both directions shall be provided, for a minimum total overlap of 300mm.

ITEM 0077 HORIZONTAL EARTH BORING (TRENCHLESS):Work includes the procurement, delivery and all labor, equipment and materials required for the implementation of horizontal earth boring to install utilities conduit(s). Horizontal earth boring shall be executed by Directional Drilling method.

2.0 PROJECT REQUIREMENTS:2.1 Location of Project: The project is located in Sample city, Sample Country, Sample AB.

2.2 Location Plan: Attachment 1.

2.3 Site Plan: Attachment 2.

2.4 Codes and Regulations: the Contractor will be responsible for all design and layout required to properly fabricate and fit the various systems required and described herein. The Contractor shall ensure that all work, and all installations are accomplished by following the MOST RECENT:

Air Force Instructions (AFI); Unified Facilities Criteria (UFC); American Concrete Institute (ACI) Construction Specification Institute (CSI); International Building Code (IBC); International Fire Code (IFC); International Electrical Code (IEC); National Electric Code (NEC); National Fire Protection Association (NFPA); Energy Information Administration (EIA); Telecommunications Industry ASSOCIATION (TIA);

Page 12 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

Power Company Regulations Sample Country Ministry Of Electricity And Water (MEOW); Sample Country Construction Specifications (SCS); Occupational Safety And Health Administration (OSHA);

The most stringent code shall apply in all cases. Deviations from the codes can only be approved by the contracting officer in writing. In addition, all work shall be performed in a professional manner by journeyman craftsmen certified in the trade in which they are employed.

3.0 GENERAL REQUIREMENTS:3.1 General Drawings: General Drawings shall be provided by the Contractor. The cover sheet

shall contain the owner’s name and project number. A general map of the area with the site identified. The prime contractor name, subcontractor names, ALUA contract number and their project numbers shall be included. A general notes page shall be included in the general drawings. Index of Sheets shall be provided. Survey Drawings shall include survey points. At a minimum, two benchmarks shall be identified in all three dimensions. Temporary or project benchmarks shall be clearly identified and kept intact throughout the life of the project. If permanent benchmarks are disturbed (regardless of fault), immediate notification shall be given to the Contracting Officer so that the benchmarks may be corrected.

4.0 SCOPE OF WORK:4.1 Description of Scope of Work: Contractor shall provide all supervision, labor, materials, tools,

transportation, and incidentals necessary to provide, furnish, install, construct, commission & validate and demolish communication utility lines and related works throughout Sample Air Base, which include, but are not limited to, providing trenching and conduit to designated facilities on Sample Air Base. Communications conduits provided shall terminate in existing Comm. Rooms or closet. Provide a pull string within associated communications cables. Provide a grounding rod and ground bus in each communication room or closet where one does not exist. Bond communication ground bar inside communication room or closet to main electrical ground bar in electrical room using #4/0AWG (120mm2) bare conductor installed within EMT (Electrical Metallic Tubing) or approved metallic cable tray or wireways.

5.0 SCHEDULE:5.1 Schedule Format: The Contractor shall prepare and submit for approval, a Critical Path Method

(CPM) Master Schedule listing all items and activities associated with the project, inclusive of all government furnished items and information, submittals for major items, long lead procurement activities, drawing revisions and facility shutdowns using a Work Breakdown Structure (WBS) based on the Construction Specification Institute (CSI) format. All tasks required under this project shall be included in the WBS. The Contractor shall utilize both MICROSOFT PROJECT scheduling software and AF Form 3064/3065, Contract Progress Schedule, to build and maintain the Master Schedule. Unless otherwise indicated by the Government, the Contractor will maintain the same schedule format (MICROSOFT PROJECT or AF Form 3064, Contract Progress Schedule) throughout the contract.

5.2 The Contractor shall perform planning, scheduling and reporting functions utilizing Gantt Charts, Critical Path Analysis, Resource Histograms and Look Ahead Schedules. Items within the project schedule shall have predecessor and successor activities to support a full CPM overview. Items in the schedule shall be resource loaded with the manpower required.

5.3 Baseline Schedule: The Contractor shall save a baseline schedule and show actual start and finish dates for activities verses the baseline.

5.4 Contractor shall provide a schedule of project work for approval. The Contractor shall bring a proposed progress schedule to the pre-construction conference.

5.5 Due to Force Protection concerns at Sample Air Base, Contractor can experience long delays while gaining access to the base of up to 4 hours. Contractor shall account for such possible delays. Any documented government delays in excess of 4 hours shall be reviewed with the Contracting Officer for possible time extensions.

Page 13 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

5.6 Normal daytime working hours will be adhered to. Normal hours are from 0700-1700 hours Saturday through Thursday. If the Contractor wishes to work at night time or during other unscheduled times, he must first get permission from the Contracting Officer. Contractor shall provide written request to Contracting Officer at least 72 hours in advance.

5.7 The Contracting Officer may request an updated construction schedule if it is determined that the construction schedule deviates more than 10% off the baseline. The project manager will determine the percentage complete and the deviations.

6.0 PERFORMANCE TIMES:6.1 The government preferred total period of performance (POP) will depend on the individual task

order. The Contractor may propose a shorter or longer POP in the RFP. Should the Contractor propose a longer POP, the proposal must include justification for the extended duration of the project. The final POP duration will be approved through the Contracting Office. The Contractor shall proceed with the project as stated in the SOW after NTP is provided by the government. The Contractor shall not postpone or interrupt their work performance unless official notice, to that effect, is provided to them by the U.S. Government.

6.2 On Site Construction: The Contractor will only be given access to the installation for construction activities to include mobilization and demobilization. On site construction will start no later than 10 days following the issue of the construction NTP. Construction shall not be permitted to commence until submittals specified at the task order level have been reviewed by the government and clearance issued to start construction.

7.0 SUBMITTALS:7.1 The Contractor shall submit all manufacturer’s documentation, training manuals and training

procedures, quality control, safety, security, and environmental protection procedures to the Contracting Officer (CO). The project manager shall determine number and type of copies of each submittal required by utilizing an AF Form 66. The Contractor shall submit these items at a time determined by the CO and the submission shall be documented on the Contractor’s schedule

7.2 If applicable, the Contractor shall make all corrections required by the Government and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal. After the Government approves a design submittal, the Government will not consider any re-submittal for the purpose of substituting materials or equipment unless accompanied by an explanation of why a substitution is necessary.

7.3 The Contractor shall provide electronic files of the design submissions, plans, and other related construction drawings in AutoCAD 2004 or later version, and also provide a duplicate file submission in PDF format to the CO. The following paragraphs describe the specific design submittals required for the various phases of design. The level of design effort will be specified at the individual task order level.

7.3.1 Conceptual Design Submittals (35%)

7.3.1.1 Site location map and location plan showing geographic location of project relative to existing facilities, roads, streets, etc.

7.3.1.2 Demolition plans at a legible scale showing quantities, locations and type of materials to be removed.

7.3.1.3 Site Plan: All structures, landscape, paved areas and site appurtenances including a general description of the type of paving being proposed.

7.3.1.4 Utilities Plan: showing connection points, estimated capacities, and routing of all utilities.

Page 14 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

7.3.2 Preliminary Design Submittals (65%):

7.3.2.1 Survey: Contractor shall survey the site to locate all existing conditions on the site.

7.3.2.2 Site location map and location plan showing geographic location of project relative to existing facilities, roads, streets, etc.

7.3.2.3 Demolition plans at a legible scale showing quantities, locations and type of materials to be removed.

7.3.2.4 Site plan: All road, parking, sidewalks and loading zones

7.3.2.5 Grading plan: showing all topographic and grading information

7.3.2.6 Utilities Plan: showing connections, routing and capacities of all utilities

7.3.2.7 Details: all civil engineering details required to complete the installation of the work

7.3.3 Final Design Submittal (95%):

7.3.3.1 The contract drawings submitted for review shall include the drawings previously submitted which have been revised and completed as necessary. The A/E is expected to have completed all of his constructability and coordination checks and have the drawings in a ready-to-construct condition.

7.3.3.2 The drawings shall be complete at this time, incorporating all design review comments generated by the Preliminary design review.

7.3.3.3 The drawings shall contain all the details necessary to assure a clear understanding of the work throughout construction.

7.4 The Contractor shall provide catalog cuts, supplier data, test reports, and other information required by the CO during construction. Submittals shall clearly show that the materials or equipment supplied meet or exceed the specifications and project requirements.

7.5 The Contractor shall provide all site assessments and work plans with calculations and AutoCAD 2004 drawings. The Contractor shall provide as-built drawings, training manuals, warranties, preventive maintenance plans, and Operations and Maintenance manuals in English. The Contractor shall provide two (2) legible copies of operation and maintenance manuals for all new equipment, finishes, fixtures, and hardware bound and cataloged in 2004 CSI format on A4 sized paper. The Contractor must provide copies of all specifications, calculations, and manuals used. All calculations, standards, and correspondence shall be in English.

8.0 STANDARD PRODUCTS:8.1 Materials and equipment shall be standard products of a manufacturer regularly engaged in the

manufacture of such products, which are of a similar material, design and workmanship. Furnish a MSDS, OSHA Form 20 or accepted equivalent, for each hazardous or potentially hazardous material or chemical utilized by the Contractor. This includes solvents and treated materials, such as preservative treated wood (MSDS for the preservative) or fungicide treated

Page 15 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

rubber goods (MSDS for fungicide). Contracting Officer or the project manager must approve all materials prior to installation.

8.2 Technical instructions pertaining to the use or installation of products, materials, or equipment used or installed in the execution of work under this contract are furnished in response to a requirement stipulated herein, and form a part of these specifications as though specifically set forth herein. In the event of conflict between the specifications or drawings and technical instructions, the Contractor shall bring such conflict to the attention of the Contracting Officer for resolution before proceeding with the work involved.

9.0 NON-RESTRICTIVE SPECIFICATIONS:9.1 Reference in the design specifications of this SOW to equipment, material, articles, or patented

processes by trade name, make, or catalog number shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may, at its option, use any equipment, material, article, or process that, in the judgment of the Contracting Officer, is equal or exceeds the requirement of these specifications, unless otherwise specifically provided in this Statement of Work.

10.0 PROHIBITED MATERIALS:10.1 The Contractor shall certify that products do not contain mercury, hexavalent chromium,

toluene, chlorinated solvents, hydrolysable chlorine derivatives, ethylene based glycol ethers and their acetates, nor any carcinogen. When tested, the lead content shall not exceed 0.06% by weight of the dry film and the test for chromium content shall be negative. Additionally, prohibited are any electronic devices such as, but not limited to, cellular phones, data collectors, and calculators, as determined by Security Forces.

11.0 BASE REQUIREMENTS:11.1 Waste;

11.1.1 The Contractor shall be responsible for the collection and disposal of all debris, rubble, residue and waste material generated in the performance of work under this contract. Contractor shall remove and disposed of legally and properly of all such materials from the installation. The Contractor is not permitted to deposit any such materials in base trash collection containers or at any on base location without prior approval of the Contracting Officer.

11.2 Hazardous Materials;

11.2.1 Materials classified as hazardous by US and Host Nation’s environmental rules, regulations, or laws, shall be handled for disposal in accordance with those rules, regulations, or laws. Any cost provisions to meet these requirements shall be the sole responsibility of the Contractor. Any project delay to meet these requirements shall also be the sole responsibility of the Contractor.

11.2.2 Hazardous Materials used for Construction Activities: Materials classified as hazardous by US or Sample Country environmental rules, regulations, or laws, shall be handled in accordance with those rules, regulations, or laws. In accordance with AFI 32-7086, Hazardous Materials Management (paragraph 2.5.5), the Contractor shall submit for approval MSDSs for those materials considered hazardous to the Contracting Officer PRIOR to the hazardous material ENTERING the installation. All hazardous material will be stored in a safe and environmentally responsible manner within construction sites and laydown yards.

11.2.3 The Contractor shall submit MSDSs for those materials considered hazardous to the Contracting Officer prior to the hazardous waste leaving the installation. The Contractor is responsible for all such materials that are residue from Contractor furnished supplies and materials brought to the job site by the Contractor, and for any such materials identified herein or by the drawings.

Page 16 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

11.3 Subcontractor Coordination;

11.3.1 The Contractor shall coordinate the work of sub-contractors and shall ensure the coordination of the work between the various trades. The Contractor shall study, examine, and evaluate the contract drawings to establish the work, coordination, or materials required and necessary to provide a product complete in the usual and customary manner, and shall provide for all such requirements as though expressly detailed herein or on the drawings. The Contracting Officer will provide contract interpretation.

11.4 Security and Parking;

11.4.1 The Contractor shall follow existing security and parking procedures and instructions applicable to Sample Air Base.

11.4.2 The Contractor shall be responsible for the physical security of all materials, supplies, and equipment, including property that he is utilizing.

11.4.3 The US Air Force shall not be held liable for any delays prior to the Contractor reaching the Contractor entrance and notification that he is ready to proceed through the gate.

11.5 Vehicular Traffic;

11.5.1 Traffic Control Devices: The Contractor shall comply with the local laws and regulations, to include US Air Force regulations, regarding the safe operation of equipment in and around roadways associated with the construction site. Contractor owned and/or operated vehicles violating speeding, parking or traffic regulations on Sample Air Base may be removed from the installation at the Contractor’s expense. Should this be the case, the US government will not be held liable for the time delay to the Contractor nor such costs that might occur based on the vehicle removal.

11.5.1.1 The Contractor shall coordinate with the Contracting Officer or project manager to ensure proper warnings to motorists are posted and adequate traffic control is used when vehicles are present. US Army Corps of Engineers Safety Manual, EM 385-1-1, will provide the minimum requirements for temporary traffic controls.

11.5.1.2 The Contractor shall address known traffic impedances within the site/location drawing and the safety plan. Coordinate submittal dates per the AF Form 66.

11.5.1.3 Signs, warning lights, barricades, and other traffic control devices shall be provided by the Contractor. Warning lights will be operational at all times during non-daylight hours. Barricades shall be highly luminescent and clearly visible at night. Signs shall also be highly luminescent, blaze orange in color with black English lettering, and clearly visible from at least 50 ft (15 m) away.

11.5.1.4 Temporary traffic control signs (warning and hazard signs) shall be furnished and installed, at the discretion of the Contracting Officer, by the Contractor while projects are underway. These warning signs shall be placed near the beginning of the work site and well ahead of the work site for alerting approaching traffic from both directions. Paving and painting equipment shall be marked with large warning signs indicating slow-moving equipment in operation.

11.5.1.5 Road Diversions/Closures: Contractor shall notify the Contracting Officer at least 14 days prior to work if construction will impact traffic on the roadways. Contractor shall state in writing the exact dates of the road closure, duration of closure and provide a traffic diversion map showing the location of the diversion (if available), closure, posting of signage, phasing plan (if applicable), and other pertinent information for the impedance.

11.5.1.6 All costs including, but not limited to, design, procurement, equipment, installation, maintenance and removal, associated with the temporary traffic control signs, barriers, barricades, warning lights, diversions etc are the sole responsibility of the Contractor.

11.6 Sanitary Provisions;

Page 17 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

11.6.1 The Contractor shall provide temporary toilets that satisfy Sample Country health requirements for the use of project personnel. Location, type, proposed maintenance, etc shall be approved by the Contracting Officer prior to placing toilets. Temporary toilets shall be removed at the completion of the project. All costs incurred in connection with the temporary toilets shall be paid by the Contractor.

11.7 Pollution Abatement;

11.7.1 The Contractor shall perform work in accordance with US Air Force and local environmental regulations so as to minimize pollution, degradation, and exploitation of the environment. The Contractor shall also demonstrate leadership in preventing, controlling, and abating environmental pollution by supporting regional pollution abatement programs and by accelerating corrective measures to meet established standards and criteria.

11.8 Fire Prevention;

11.8.1 The prevention of fire is imperative during construction projects. The Contractor is responsible for enforcing fire safety in the work area.

11.8.2 The Contractor must report all fires to the US Air Force Fire Department. Attempt to extinguish the fire only if it is safe to do so. Go to the nearest phone and notify the Fire Department at 911. Have someone meet the Fire Department upon arrival to provide additional information.

11.8.3 The Contractor shall have serviceable fire extinguishers readily available at all times.

11.8.4 Burning of trash and rubbish at the construction site is strictly prohibited.

11.8.5 The Contractor may not use gasoline or diesel fuel for cleaning parts or surfaces.

11.8.6 Electrical extension cords may be used on a temporary basis to power tools and equipment. Do not overload extension cords. Frayed, cut, or spliced extension cords are prohibited.

11.9 Safety Features;

11.9.1 The US Army Corps of Engineers Safety Manual, EM 385-1-1, shall be followed for all construction activities.

11.9.1.1 The Contractor shall prepare a Health and Safety Plan (HSP) or Accident Prevention Plan (APP) in accordance with USACE EM 385-1-1 Appendix A. The Contractor shall maintain written certification that the approved HSP has been reviewed with all personnel that work at the project site prior to their mobilization. The Safety Plan shall also address construction operations that increase risk for personnel in and around the site including, but not limited to, excavating for utility trenches, hand digging, traffic diversions, road blockages and signage, lighting and barricades during limited visibility timeframes. USACE EM 385-1-1: If the Contractor does not have an electronic copy of the manual, one can be provided by the Government. The Contractor should request in writing to the Contracting Officer and specify the version(s) needed. The Government has available 2 versions -- 2008 English and 2003 Arabic versions.

11.9.2 Site Safety, Fire, Environmental and Public Health Inspections: At any time the construction site and laydown yard (if applicable) can be inspected by the Contracting Officer or designated representative for fire, safety, environmental or public health discrepancies. Any discrepancies noted will be fixed immediately. If discrepancies cannot be fixed immediately the Contractor shall remove the items from the installation. Any costs or time delays associated with correcting discrepancies are the sole responsibility of the Contractor.

11.10 Escorts;

11.10.1 The Contractor will provide the contracting office or project manager the Contractor’s weekly worker plan at least 7 working days in advance so the Air Force can schedule escorts.

11.10.1.1 The weekly worker plan format and extent of details will be discussed at the Pre-Construction meeting. The Contractor can expect to provide a weekly plan that shows

Page 18 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

the project location(s) and number of anticipated workers at the location and any scheduled deliveries (time, date). If workers will be transiting between sites and/or a laydown yard, the contractor will need to identify them in the plan since additional mobile escorts need to be allocated.

11.10.1.2 Changes to the Worker Plan: The Contractor will notify the Contracting Officer or project manager 72 hours in advance when total Contractor workers increase or decrease by different multiples of 5 or if an unscheduled delivery needs to be made. It is the Contractor’s responsibility to notify the Contracting Officer or project manager at least 24 hours in advance of the time and location that the escorts shall meet the Contractor. The Contractor shall make all attempts to promptly meet this appointment. If the Contractor is more than one hour late, the Contractor will not be allowed access to Sample Air Base that working day. The Contractor will not be able to resume work until a new escort arrangement can be made. The US Air Force will not be held liable for any claim attributable to the Contractor’s failure to follow these guidelines for arranging and meeting escorts.

11.11 BCE Work Clearance Request;

11.11.1 The Contractor shall obtain a Base Civil Engineer Work Clearance Request (AF Form 103) from the Contracting Officer or designated representative at the pre-construction conference prior to commencement of any site work. The contractor shall be responsible for routing the request for approval.

11.11.2 Dig Permit: The Contractor shall apply for and maintain active dig permits during excavation activities. The Contractor shall have a copy of the dig permit present onsite during all excavation activities. If the Contractor damages a marked, known utility, the Contractor shall repair said utility to the previous condition at his own expense. If a Contractor damages an unmarked utility the US Air Force shall repair said utility. If the Contractor damages any utility, the Contractor shall contact the Contracting Officer or designated representative immediately.

11.11.3 Hot Work Permit: The Contractor shall obtain a Welding, Cutting and Brazing Permit (AF Form 592) prior to commencement of any hot work. Hot work includes, but is not limited to, welding, cutting, brazing operations and the use of tar kettles. The Contractor should submit their completed AF Form 592 to the Contracting Officer or project manager for approval and coordination.

11.12 Temporary Construction Fencing;

11.12.1 Temporary construction fencing is required around all work sites.

11.12.2 The location and layout of the temporary construction fencing will be annotated on the site/work plan and approved per the AF Form 66 prior to installation.

11.13 Excavations for Utilities;

11.13.1 All excavations outside the fenced construction site will have barriers, signage and significant lighting to be clearly seen during limited visibility.

11.13.2 It remains the Contractor’s responsibility to schedule ALL WORK to minimize the length of time excavations are open. Should excavations remain open for an extended period, the Contractor may be asked to close the excavation until such time as the work can begin again. Any costs or time delays associated with such work are the sole responsibility of the Contractor.

11.13.3 The Contractor will provide temporary access across excavations that impede major pedestrian thoroughfares. All costs incurred and time delays for the temporary access are the sole responsibility of the Contractor. The temporary access provisions will require approval and inspection by the Contracting Officer or project manager.

12.0 US AIR FORCE FURNISHED ITEMS AND SERVICES:

Page 19 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

12.1 At the Contracting Officer’s discretion, the US Air Force shall provide reasonable quantities of utilities to the Contractor. The Contractor shall conserve these utilities during construction. Construction water may be furnished to the Contractor at no cost to the Contractor. This does not mean drinking water for the Contractor’s work crews. Water for construction activities shall be coordinated with the Contracting Officer or project manager a minimum of 24 hours in advance. The Contractor shall furnish all equipment, material, and labor which is necessary to obtain and deliver water to the designated area(s) of work. Terms of this agreement are to be negotiated by the Contracting Officer.

12.2 The electrical equipment shall be suitable for the voltage and frequency as stated per the contract and as available at the project location. The Government will identify power and the Contractor will connect to the power source. The power connection and disconnection must be coordinated with the Contracting Officer.

12.3 Laydown Yard: If considered beneficial to the Government and requested by the Contractor in writing, the Government may designate a space on the installation as a laydown yard for use by the Contractor. This laydown yard would be used as a material and equipment stockpile area and would be subject to provisions as set forth by this SOW and as outlined by the Contracting Officer at the time of agreement. The location of the laydown yard will be determined upon request by the contractor and will be subject to government and host nation approval before the contractor will mobilize.

12.4 Government Provided Design: Any design drawings provided by the Government as part of this bid package are at the schematic design level. They are provided to clearly communicate the project’s program and scope and minimum requirements. The Government provided design drawings are not final. The facility and site design shall be the responsibility of the Contractor as this is a Design/Build contract.

13.0 CONTRACTOR FURNISHED ITEMS AND SERVICES:13.1 General: The Contractor shall furnish labor, supervision, tools, materials, equipment,

transportation, fuels, lubricants, fluids, solvents, and all other supplies and services necessary to perform operations required to complete work as indicated within the drawings and these specifications. At sites where existing US Air Force utilities do not exist, the Contractor shall be responsible for providing utilities. The Contractor shall be responsible for installing and maintaining temporary cords, lines, or other equipment in a safe condition. Prior to final acceptance, all temporary cords, lines, supplies, solvents, paint, fuel, lubricants, parts, material, tools, or other equipment shall be removed.

13.2 Site Superintendent: The Contractor at all times shall provide and designate in writing to the Contracting Officer a fully qualified on-site. Site Superintendent shall be responsible for the performance of the work. Designate in writing to the Contracting Officer the name of the person and all alternates. Provide the name of the individuals at the pre-construction conference.

13.3 The Site Superintendent shall have full authority to act for the Contractor and must be fluent to speak and read the English language. The Site Superintendent shall be on-site during normal work hours and for contingencies requiring work beyond normal work hours. The Contractor at all times shall have a representative explaining the work operations to persons performing the work in the language that those performing the work are capable of understanding.

13.4 The Contracting Officer shall have the right to determine whether the proposed representative is technically proficient to speak and communicate in the English language. The Contractor shall immediately replace any individual not acceptable to the Contracting Officer.

13.5 Field Office: The Contractor may provide a temporary field office at the site for their use. The location, type, proposed maintenance, and other considerations shall be approved by the Contracting Officer prior to moving such a facility onto the site. At the completion of the project, the facility shall be removed from the site and the area adjacent to the office restored to that condition existing prior to the start of the project. Costs incurred in connection with the facility shall be paid by the Contractor.

Page 20 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

13.6 Employee Certification and Training: The Contractor shall certify in writing to the Contracting Officer that employees operating equipment are trained and qualified to operate that piece of equipment. Contractor vehicles shall be in top repair, and be able to be shut off and restart without outside aid. Vehicles in need of repair will be replaced not later than the following morning. Remove downed vehicle, if irreparable, from the base. If necessary, the Contractor will provide a flatbed trailer and rig or a tow truck at their cost to remove vehicle from the base. Vehicles will be in safe operating conditions at all times, have seatbelts, or be denied access to the base. At no time will Contractors perform routine maintenance on vehicles, which results in the dumping of any fluid onto the ground. Contractor will not transport rollers, paving equipment, or other slow moving construction equipment on and throughout base unless it is loaded on a flatbed or lowboy.

13.7 Drinking Water: The Contractor is responsible for providing potable drinking water and food for their workers. Water shall be brought to the site cold, in sufficient quantity, at the beginning of each day as to ensure the safety and health of workers. The Contractor shall be responsible to ensure that workers drink sufficient water to ensure that they remain productive and healthy throughout the course of their labor and their project.

13.8 Safety Briefing: The Contractor shall receive this briefing at the pre-construction conference prior to the notice to proceed. Additionally, the Contractor will adhere to the US Army Corps of Engineers Safety Manual, EM 385-1-1, for work performed on base.

14.0 CONDITIONS OF WORK:14.1 Base Regulations: The Contractor shall comply with all applicable Sample Air Base and US Air

Force regulations and directives pertaining to security, safety, traffic, fire prevention, personnel clearances, and environmental protection, which will be provided at the pre-construction conference.

14.2 The Contractor shall confine their operations, including material storage, to the area of work shown indicated in the contract. The Contractor will be furnished adequate storage areas for their equipment and materials, but shall be responsible for the receipt, unloading, security, and handling of his equipment and materials. The Contractor shall coordinate proposed storage areas with the Contracting Officer or project manager. The Contractor shall stock and place materials and equipment only in areas specifically approved by the Contracting Officer.

14.3 When notified by the US Air Force that a severe weather warning alert has been issued, the Contractor shall immediately take necessary action to tie down and secure all materials on the job site that could become airborne projectiles as a result of strong surface winds, thunderstorm, etc. This requirement also includes all non-regular working periods. The Contracting Officer shall negotiate any Contractor compensation and or claims due to extensive weather delays.

14.4 The Contractor shall be responsible for the covering of open bodied vehicles transporting any materials likely to create air pollution or become debris while on base.

14.5 Contractor shall remove and dispose of legally and properly all material and debris generated by this project from the base. Accomplish cleanup of the entire job site not less than once a week. Contractor shall be responsible to assure proper loading of vehicles used for transport of materials and debris. Any spillage en-route on the base shall be recovered and disposed of off base. Items shall be transported in tarp-covered or closed vehicles. Any materials dropped or blown off vehicles shall be immediately picked up by the Contractor. Paper, wrappings, cardboard, etc., shall be placed in tightly closed containers for daily disposal.

14.6 Equipment and tools used in the performance of the work shall be maintained in satisfactory working condition at all times. The equipment shall be adequate and shall have the capability of producing the requirements as set forth herein.

14.7 The Contractor shall accept no changes or alterations to the project in design or execution by anyone other than the Contracting Officer. Such changes suggested from outside sources shall be directed to the Contracting Officer.

Page 21 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

15.0 INSPECTIONS/QUALITY CONTROL/WORKMANSHIP/TESTING:15.1 The contractor shall comply with all applicable current construction codes listed within this

SOW.

15.2 Preparatory Inspection: This inspection shall be performed by the Contractor prior to beginning work on any definable phase of construction. It shall include a review of contract requirements; a check to ensure that all materials and/or equipment have been tested, submitted, and approved; a check to ensure that provisions have been made to provide required control testing; examination of work area to ascertain that all preliminary work has been completed; and a physical examination of materials and equipment to ensure that they conform to approved shop drawings or submittal data and that all materials and/or equipment are on hand. The Project Inspector shall be notified at least twenty-four (24) hours in advance of the preparatory inspections and such inspection shall be made a matter of record and sent to the Contracting Officer.

15.3 Preliminary and Final Inspections: The Contractor shall coordinate with the Contracting Officer no later seven (7) days prior to scheduled contract completion date to allow scheduling of preliminary and final inspections. Attendance at the Preliminary and Final Inspections is mandatory for the Contractor or his designated representative. At the Preliminary and Final Inspection, the Contractor shall demonstrate that all systems and subsystems installed under the contract are fully functional and usable.

15.4 Quality Control Plan: The contractor is responsible for quality control and shall establish and maintain an effective quality control system in compliance with Attachment 1 entitled “Quality Control Plan and in compliance with the Contract Clause entitled “Inspection of Construction.” The quality control system shall consist of plans, procedures, and organization necessary to manage all task orders to produce end products, which comply with the contract requirements. The system shall cover all construction operations, both on site and off site, and shall be keyed to the proposed construction sequence. The government will hold the project manager responsible for the quality of work on the job and is subject to removal by the contracting officer (CO) for non-compliance with quality requirements specified in the contract.

15.5 Workmanship: All work shall comply with the specifications and drawings provided. All work shall be performed by craftsmen skilled in the applicable trade and shall be supervised by a qualified Superintendent with experience in the related construction trades. The Superintendent is required to be on-site during the performance of all work to ensure that a quality product is provided. The Superintendent shall be able to speak, understand, and read the English language. The Superintendent shall have a complete current set of the contract documents and approved submittals on the job site at all times.

15.5.1 No careless or sloppy work will be tolerated. While the Contracting Officer, or project manager, may identify workmanship problems to the Contractor, Quality Control is the Contractor’s responsibility. Inspection or non-inspection by government of the work does not relieve the Contractor from ensuring the work complies with the contract documents. It is the responsibility of the Contractor to identify and correct all workmanship problems. Any workmanship problems identified are to be corrected in a timely manner, to the satisfaction of the Contracting Officer, at no additional cost to the Government.

15.5.2 The Contractor is responsible for coordination and sequence of events with relation to the performance of this project. The Contractor shall verify all dimensions and advise the Contracting Officer of any discrepancies prior to proceeding with that phase of work. If exact locations for positioning of equipment are not given, the Contractor must coordinate the locations through the Contracting Officer. All equipment must be positioned to allow easy access for maintenance and replacement of component parts.

15.6 Testing: Contractor shall perform all testing at the frequency specified in these specifications. Additional tests may be purchased by the government as a separate modification. Testing shall be performed by an approved independent commercial laboratory. When test results indicate that construction was not accomplished as specified for a given area, the material shall be

Page 22 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

removed, replaced and construction shall be redone to meet specification requirements, at no additional expense to the government. Tests on construction shall be performed (until compliance with specifications is met) at no additional cost to the government. Inspections and test results shall be certified by a registered professional architect or engineer. Within 24 hours of conclusion of physical tests, 2 copies of test results, including calibration curves and results of calibration tests, shall be furnished to the Contracting Officer.

16.0 EXISTING WORK AND RESTORATION OF DAMAGE CAUSED BY THE CONTRACTOR:16.1 The disassembling, disconnecting, cutting, removal or altering in any way of existing work shall

be carried on in such a manner as to prevent injury or damage to any portions of existing work, whether they are to remain in place, be re-used in the new work or be salvaged and stored. All portions of existing which have been cut, damaged or altered in any way during performance of work shall be repaired or replaced in kind, in an approved manner to match existing adjoining work. Work of this nature shall be performed by the Contractor at their expense and left in a condition similar to that which existed prior to the start of the work.

17.0 PROTECTION OF LAND RESOURCES:17.1 It is intended that land resources within the project boundaries of work performed under this

contract be preserved in their present condition or be restored to a condition after completion that will appear to be natural and not detract from the appearance of the project. Insofar as possible, the Contractor shall confine his activities to areas defined by the plans and specifications. Any landscape feature damaged or scarred by the Contractor’s equipment or operations shall be restored to its original condition at the Contractor’s expense. The Contracting Officer will decide what method of restoration shall be used. The Contractor shall remove all signs of temporary construction facilities such as haul materials, or any vestiges of construction resulting from the contract as directed by the Contracting Officer.

18.0 WARRANTY:18.1 In accordance with FAR 52.246-21, All work and equipment shall be guaranteed for a period of

one year or in accordance with manufacturers warranties. The Contractor shall submit a written warranty and any manufacturer’s warranties for items installed to the Contracting Officer for approval.

Attachment 1.

1. GENERAL REQUIREMENTSEstablish and maintain an effective quality control (QC) system in compliance with the Contract Clause titled "Inspection of Construction." QC consist of plans, procedures, and organization

Page 23 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

necessary to produce an end product which complies with the contract requirements. Cover all design and construction operations, both onsite and offsite, and be keyed to the proposed construction design and construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Officer for non-compliance with the quality requirements specified in the contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent must maintain a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.2. QUALITY CONTROL PLANSubmit no later than 14 days after receipt of notice to proceed, the Contractor Quality Control (CQC) Plan proposed to implement the requirements of the Contract Clause titled "Inspection of Construction."The Government will consider an interim plan for the first 30 days of operation after the notice to proceed. Design and construction will be permitted to begin only after acceptance of the CQC Plan or acceptance of an interim plan applicable to the particular feature of work to be started. Work outside of the accepted interim plan will not be permitted to begin until acceptance of a CQC Plan or another interim plan containing the additional work.

2.1 Content of the CQC PlanInclude, as a minimum, the following to cover all design and construction operations, both onsite and offsite, including work by subcontractors, fabricators, suppliers, and purchasing agents subcontractors, designers of record, consultants, architect/engineers (AE), fabricators, suppliers, and purchasing agents:

a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement the three phase control system (refer to para. 3.3) for all aspects of the work specified. Include a CQC System Manager who reports to the project superintendent.

b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.

c. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Copies of these letters must be furnished to the Government.

d. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, offsite fabricators, suppliers, and purchasing agents subcontractors, designers of record,consultants, architect engineers (AE), offsite fabricators, suppliers, and purchasing agents.

e. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer must be used.)

f. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

g. Procedures for tracking design and construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

Page 24 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

2.2 Acceptance of PlanAcceptance of the Contractor's plan is required prior to the start of design and construction. Acceptance is conditional and will be predicated on satisfactory performance during the construction design and construction. The Government reserves the right to require the Contractor to make changes in his CQC Plan and operations including removal of personnel, as necessary, to obtain the quality specified.

2.3 Notification of ChangesAfter acceptance of the CQC Plan, notify the Contracting Officer in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.

3 CONTROLContractor Quality Control is the means by which the Contractor ensures that the construction, to include that of subcontractors and suppliers, complies with the requirements of the contract. At least three phases of control must be conducted by the CQC System Manager for each definable feature of the construction work as follows:

3.1 Preparatory PhaseThis phase is performed prior to beginning work on each definable feature of work, after all required plans/documents/materials are approved/accepted, and after copies are at the work site. This phase includes:

a. A review of each paragraph of applicable specifications, reference codes, and standards. Maintain and make available in the field for use by Government personnel until final acceptance of the work.

b. Review of the contract drawings.

c. Check to assure that all materials and/or equipment have been tested, submitted, and approved.

d. Review of provisions that have been made to provide required control inspection and testing.

e. Examination of the work area to assure that all required preliminary work has been completed and is in compliance with the contract.

f. Examination of required materials, equipment, and sample work to assure that they are on hand, conform to approved shop drawings or submitted data, and are properly stored.

g. Review of the appropriate activity hazard analysis to assure safety requirements are met.

h. Discussion of procedures for controlling quality of the work including repetitive deficiencies. Document construction tolerances and workmanship standards for that feature of work.

i. Check to ensure that the portion of the plan for the work to be performed has been accepted by the Contracting Officer.

3.2 Initial PhaseThis phase is accomplished at the beginning of a definable feature of work. Accomplish the following:

Page 25 of 26

TRENCHING, DUCTWORK AND MANHOLE IDIQ

a. Check work to ensure that it is in full compliance with contract requirements.

b. Verify adequacy of controls to ensure full contract compliance. Verify required control inspection and testing.

b. Establish level of workmanship and verify that it meets minimum acceptable workmanship standards. Compare with required sample panels as appropriate.

d. Resolve all differences.

e. Check safety to include compliance with and upgrading of the safety plan and activity hazard analysis. Review the activity analysis with each worker.

f. The initial phase should be repeated for each new crew to work onsite, or any time acceptable specified quality standards are not being met.

3.3 Follow-up PhasePerform daily checks to assure control activities, including control testing, are providing continued compliance with contract requirements, until completion of the particular feature of work. Record the checks in the CQC documentation. Conduct final follow-up checks and correct all deficiencies prior to the start of additional features of work which may be affected by the deficient work. Do not build upon nor conceal non-conforming work.

3.4 Additional Preparatory and Initial PhasesConduct additional preparatory and initial phases on the same definable features of work if: the quality of on-going work is unacceptable; if there are changes in the applicable CQC staff, onsite production supervision or work crew; if work on a definable feature is resumed after a substantial period of inactivity; or if other problems develop.

Page 26 of 26


Recommended