+ All Categories
Home > Documents > CONSTRUCTION - atlanticcoastpipeline.com · 3/16/2018 · CONSTRUCTION Road and Trail Crossing...

CONSTRUCTION - atlanticcoastpipeline.com · 3/16/2018 · CONSTRUCTION Road and Trail Crossing...

Date post: 11-May-2018
Category:
Upload: dodan
View: 215 times
Download: 2 times
Share this document with a friend
3
CONSTRUCTION Water Crossing Methods FLUME METHOD Used to cross small to intermediate flowing waterbodies that support cold water or other significant fisheries. Temporarily divert the flow of water through one or more large-diameter, steel flume pipes Allows trenching to occur in a relatively dry riverbed (beneath the flume pipes) Keeps excess sediment from entering the waterbody 50' 50' 10' 10' LIMIT OF CONSTRUCTION ROW LIMIT OF CONSTRUCTION ROW PLACE SEDIMENT BARRIERS ACROSS WORKING SIDE OF ROW AT THE END OF EACH DAY PROPOSED TRENCH SILT FENCE, DOUBLE STAKED STRAW BALES, OR BOTH AS NECESSARY ADDITIONAL TEMPORARY WORKSPACE ADDITIONAL TEMPORARY WORKSPACE SPOIL SPOIL TEMPORARY BRIDGE (IF NEEDED) MINIMUM WATER BARRIER FLOW CULVERT DAM AND PUMP METHOD Generally used on smaller waterbodies where mechanical pumps can keep up with stream flows. Pumps and hoses used instead of flume pipes to isolate and transport the stream flow around the construction area Creates a relatively dry work area Keeps excess sediment from entering the waterbody OPEN CUT OR WET TRENCH METHOD In-stream construction activities are limited to 24 hours on waterbodies 10 feet wide or less and 48 hours on waterbodies 10 to 100 feet wide. Trench is constructed while water continues to flow Pipe is pre-fabricated before trenching begins Backhoes typically work from one or both streambanks to excavate trench If the stream is too wide to excavate the entire trench from the banks, equipment may operate from within the waterbody with prior approval from appropriate regulating agencies LIMIT OF CONSTRUCTION ROW LIMIT OF CONSTRUCTION ROW PROPOSED TRENCH SILT FENCE, DOUBLE STAKED STRAW BALES, OR BOTH IF NECESSARY PUMP(S) STANDBY PUMP(S) BALES LINED WITH IMPERMEABLE LINER UPSTREAM DAM PLACE SEDIMENT BARRIERS ACROSS WORKING SIDE OF ROW AT THE END OF EACH DAY. ADDITIONAL TEMPORARY WORKSPACE ADDITIONAL TEMPORARY WORKSPACE SPOIL SPOIL TEMPORARY BRIDGE (IF NEEDED) DOWNSTREAM DAM ENERGY DISSIPATOR 50' 50' ADDITIONAL TEMPORARY WORKSPACE ADDITIONAL TEMPORARY WORKSPACE 100' TEMPORARY BRIDGE (IF NEEDED) LIMIT OF CONSTRUCTION ROW LIMIT OF CONSTRUCTION ROW PLACE SEDIMENT BARRIERS ACROSS WORKING SIDE OF ROW AT THE END OF EACH DAY PROPOSED TRENCH SPOIL SILT FENCE, DOUBLE STAKED STRAW BALES, OR BOTH AS NECCESSARY WITH FLOWING WATER 100' SPOIL
Transcript
Page 1: CONSTRUCTION - atlanticcoastpipeline.com · 3/16/2018 · CONSTRUCTION Road and Trail Crossing Methods OPEN CUT METHOD Unpaved roads, trails and driveways as well as roads in areas

CONSTRUCTION

Water Crossing Methods

FLUME METHOD

Used to cross small to intermediate flowing waterbodies that support cold water or other significant fisheries. • Temporarily divert the flow of water through

one or more large-diameter, steel flume pipes• Allows trenching to occur in a relatively dry

riverbed (beneath the flume pipes)• Keeps excess sediment from entering the

waterbody

50'

50'

10' 10'

LIMIT OF CONSTRUCTION ROW

LIMIT OF CONSTRUCTION ROW

PLACE SEDIMENT BARRIERS ACROSS WORKING SIDE OF ROW AT THE END OF EACH DAY

PROPOSED TRENCH

SILT FENCE, DOUBLE STAKED STRAW BALES, OR BOTH AS NECESSARY

ADDITIONALTEMPORARYWORKSPACE

ADDITIONALTEMPORARY WORKSPACE

SPOIL SPOIL

TEMPORARY BRIDGE(IF NEEDED)

MINIMUMWATER BARRIER

FLO

W

CULVERT

DAM AND PUMP METHOD

Generally used on smaller waterbodies where mechanical pumps can keep up with stream flows.• Pumps and hoses used instead of flume pipes to

isolate and transport the stream flow around the construction area

• Creates a relatively dry work area• Keeps excess sediment from entering the

waterbody

OPEN CUT OR WET TRENCH METHOD

In-stream construction activities are limited to 24 hours on waterbodies 10 feet wide or less and 48 hours on waterbodies 10 to 100 feet wide.• Trench is constructed while water continues

to flow• Pipe is pre-fabricated before trenching begins• Backhoes typically work from one or both

streambanks to excavate trench• If the stream is too wide to excavate the entire

trench from the banks, equipment may operate from within the waterbody with prior approval from appropriate regulating agencies

LIMIT OF CONSTRUCTION ROW

LIMIT OF CONSTRUCTION ROW

PROPOSED TRENCH

SILT FENCE, DOUBLE STAKEDSTRAW BALES, OR BOTH

IF NECESSARY

PUMP(S)

STANDBY PUMP(S)

BALES LINED WITH IMPERMEABLE LINER

UPSTREAM DAM

PLACE SEDIMENT BARRIERSACROSS WORKING SIDE OF ROWAT THE END OF EACH DAY.

ADDITIONALTEMPORARYWORKSPACE

ADDITIONALTEMPORARYWORKSPACE

SPOIL SPOIL

TEMPORARY BRIDGE(IF NEEDED)

DOWNSTREAM DAM

ENERGY DISSIPATOR

50'50'

ADDITIONALTEMPORARYWORKSPACE

ADDITIONALTEMPORARYWORKSPACE100'

TEMPORARY BRIDGE (IF NEEDED)

LIMIT OF CONSTRUCTION ROW

LIMIT OF CONSTRUCTION ROW

PLACE SEDIMENT BARRIERS ACROSS WORKING SIDE OF ROW

AT THE END OF EACH DAY

PROPOSED TRENCH

SPOIL

SILT FENCE, DOUBLE STAKED STRAW BALES, OR BOTH AS NECCESSARY WITH FLOWING WATER

100'

SPOIL

Page 2: CONSTRUCTION - atlanticcoastpipeline.com · 3/16/2018 · CONSTRUCTION Road and Trail Crossing Methods OPEN CUT METHOD Unpaved roads, trails and driveways as well as roads in areas

CONSTRUCTION

Road and Trail Crossing Methods

OPEN CUT METHOD

Unpaved roads, trails and driveways as well as roads in areas with a high water table will be crossed using the open cut method and then restored to preconstruction condition.• May require temporary road

closure• If no reasonable detour

feasible, at least one lane will be kept open to traffic except for a brief period when the pipe is installed into the trench

• Most open cut crossings completed and the road restored within a few days

SUBSURFACE BORING METHOD

Most paved roads and highways will be crossed by conventional subsurface boring beneath the roadbed. • Excavate boring pits on each side of the

road; use boring equipment to bore a hole under the roadbed then pull the section of pipe (or series of pipe sections) through the hole

• Results in little to no disruption of traffic on road

M:\TYPICALS\CLIENTS\D-F\DOM\ACP\TYPICAL_CONSTRUCTION\TYP_BORE_PIT_ROAD_CROSSING.VSD

DATE: 03/16/2018

REVISED: 03/16/2018

SCALE: NTS

DRAWN BY: JPB

For environmental review purposes only.

SILT FENCE, DOUBLE STAKED STRAWBALES, OR BOTH AS NECCESSARY

Figure X.X-XAtlantic Coast Pipeline Project

Typical Road CrossingBore Method

60'

PERMANENTEASEMENT LIMITS

EXTRAWORKSPACE

EXTRAWORKSPACE

TEMPORARYCONSTRUCTIONBOUNDARY

TEMPORARY CONSTRUCTION BOUNDARY PERMANENTEASEMENT LIMITS

BORE PIT BORE PIT

BORE PIT BORE PIT

ROAD

ADDITIONALTEMPORARYWORKSPACE

ADDITIONALTEMPORARYWORKSPACE100'

TEMPORARY BRIDGE (IF NEEDED)

LIMIT OF CONSTRUCTION ROW

LIMIT OF CONSTRUCTION ROW

PLACE SEDIMENT BARRIERS ACROSS WORKING SIDE OF ROW

AT THE END OF EACH DAY

PROPOSED TRENCH

SPOIL

SILT FENCE, DOUBLE STAKED STRAW BALES, OR BOTH AS NECCESSARY WITH FLOWING WATER

100'

SPOIL

Page 3: CONSTRUCTION - atlanticcoastpipeline.com · 3/16/2018 · CONSTRUCTION Road and Trail Crossing Methods OPEN CUT METHOD Unpaved roads, trails and driveways as well as roads in areas

CONSTRUCTION

Horizontal Directional Drill Sequence

Pilot Hole

Preream

Pullback

PILOT STRING BIT

SURVEY TOOLWASH PIPE BIT

WASH PIPE

PILOT STRING

WASH PIPE

REAMER

DRILL PIPE

REAMERDRILL PIPE PRODUCT

PIPELINE

SWIVEL

PILOT HOLE

PREREAM

PULLBACK

PILOT HOLE


Recommended