Point Engineering is a native Nigerian engineering consultancy in various oil & gas engineering disciplines. Based in Port Harcourt.
12
06/13/22 1 Point Engineering Ltd.
Transcript
Page 1: Construction Consultancy - Point

04/21/23

1Point Engineering Ltd.

Page 2: Construction Consultancy - Point

04/21/23

2Point Engineering Ltd.

con·sult·an·cy• A professional practice that gives expert

advice within a particular field – in our case, by providing engineering EPC services.

• The work of offering such service

Page 3: Construction Consultancy - Point

04/21/23

3Point Engineering Ltd.

Point Engineering Consultancy Point Engineering Limited has a broad range of capabilities

in the design and construction of many types of structures either with steel or reinforced concrete materials.

Point Engineering’s practice in the oil and gas engineering services dates back to the turn of the century. Some of the most notable projects among many are:

Total’s O.U.R. pipeline design and construction consultancy

Shell’s Trans-Niger Pipeline Loopline design Total’s USAN subsea manifold design Seplat 50,000-barrel buffer tanks design and

construction expert services Total Control Station Construction Supervision NPDC Dual Lane Concrete Bridge (for Heavy Truck

Traffic) Design MPN’s Post Underwater Inspection Risk Assessment of

79 platforms for Fitness for Purpose and Continuity of Use

And many more....

Page 4: Construction Consultancy - Point

04/21/23

4Point Engineering Ltd.

Point Engineering Ltd. - Experience

Page 5: Construction Consultancy - Point

04/21/23

5Point Engineering Ltd.

Point Engineering Proposal for Services

Point Engineering Limited are happy to propose to perform the following tasks during the construction phase of the 17-storey reinforced concrete building project:Pre-Construction Planning and Assurance

Review the building design and applicable Bill(s) of Quantities (BOQ).

Define/Verify precedence relationships among activities (to determine the Critical Path during the construction phase)

Estimate/Review estimate of activity durations

Review/Check/Write applicable construction scope(s) or work.

Page 6: Construction Consultancy - Point

04/21/23

6Point Engineering Ltd.

Point Engineering Proposal for Services

Point Engineering Limited are happy to propose to perform the following tasks during the construction phase of the 17-storey reinforced concrete building project:Construction Management and Supervision

Construction project management.Management of construction subcontractors and scheduling.Coordinate specialized laboratory testing and inspections (i.e. concrete cube tests for crushing strength conformity to standards).Coordinate field reviews.Respond if special circumstances ariseAssurance of compliance with design documents

Page 7: Construction Consultancy - Point

04/21/23

7Point Engineering Ltd.

What is Required Original Civil Design

Approved construction drawings - complete set Final (and approved) Bill of Quantities Final (and approved) list of standards and

specifications Final reinforcement schedule(s). Pre-Construction

Job directive information, i.e. mission, location, time schedule, manpower, equipment, materials, priorities, reports and special instructions

Site survey(s) Construction works schedule and milestones

Any additional items elucidated during initial discussions.

Page 8: Construction Consultancy - Point

04/21/23

8Point Engineering Ltd.

Activity-On-The-Node (AON) Format

AON format is recommended for successful construction project management for the following reasons:

Eliminates confusion, and allows PM to adjust for problems that may arise during the construction phase.

AON format is "activity" oriented.

This is the primary format used for planning military construction, and especially used for large projects, which means it has a proven track history.

Page 9: Construction Consultancy - Point

04/21/23

9Point Engineering Ltd.

Activity-On-The-Node Uses:

Construction planning.

Maintenance planning.

Project Design.

Logistics planning.

Page 10: Construction Consultancy - Point

04/21/23

10Point Engineering Ltd.

AON Advantages

Reduces risk of overlooking essential tasks.

Provides a blueprint for long-range planning.

Shows activity inter-relationships.

Focuses attention on critical activities.

Allows PM to make timely decisions.

Allows PM to manage manpower, material, and equipment resources more effectively.

Page 11: Construction Consultancy - Point

04/21/23

11Point Engineering Ltd.

AON Disadvantages

The AON format does not solve engineering problems that may occur.

Does not make planning decisions for you.

Does not provide anything substantial to the actual construction of the project itself.

Page 12: Construction Consultancy - Point

04/21/23

12Point Engineering Ltd.

End of Presentation

Thank You !