Construction Impact
Page 1 of 2
June, 29, 2020
Weston Road Improvements and Intersection Improvements at
Jane Street and Trethewey Drive Contract: 19ECS-TI-104LR
Expected Start Date: July 6, 2020 Expected End Date: November 22, 2020 *Content/dates subject to change.
The City of Toronto is completing a number of infrastructure improvements on Weston Road between Lawrence Avenue West to Humberview Crescent. The City is also improving the intersection of Jane Street and Trethewey Drive/Denison Road East. The improvements are part of the Council-Approved 2019 budget and the City's Vision Zero Road Safety Plan that aims to create a safe and healthy city by eliminating all fatalities and serious injuries on city streets. For further details and to sign up for project updates, please visit the project website toronto.ca/westonroad
IMPORTANT INFORMATION ABOUT COVID-19 AND CONSTRUCTION WORK IN TORONTO As restrictions on construction have been lifted by the Province of Ontario, City-led infrastructure will continue to proceed. During construction, the contractor is responsible for the Health & Safety on site under the Ontario Occupational Health and Safety Act and is expected to implement COVID-19 mitigation practices. For more information on the City's response to COVID-19 please visit toronto.ca/covid-19. MAP OF WORK ZONE
WHAT TO EXPECT DURING CONSTRUCTION • The community will experience dust, noise and traffic delays. • The City will make efforts to reduce impacts. Your patience is appreciated.
http://www.toronto.ca/westonroadhttp://www.toronto.ca/covid-19
Construction Impact
Page 2 of 2
Work Hours: On Weston road, most work will take place from Monday to Friday, 7 a.m. to 7 p.m., with work after hours and on weekends as required. Overnight work will happen from July 13 to July 30, 2020, on Jane Street and Denison Road/Trethewey Drive starting at 7 p.m. to 7 a.m. Monday to Friday, with weekend work as required.
Traffic Management: Efforts have been made to manage traffic in the area for the safety of workers, road users and residents. Road users should expect delays and increased traffic on nearby main and side streets. Weston Road
• Traffic will be reduced to one lane of traffic in each direction from Lawrence Avenue West to Humberview Crescent.
Intersection Improvements at Jane Street Trethewey Drive • From July 13 to July 30, 2020, Jane Street and Denison Road/Trethewey
Drive will be reduced to one lane of traffic in each direction overnight, starting at 7 p.m. to 7 a.m. Monday to Friday, with weekend work as required.
TTC Service: TTC Service: This project may affect travel times on the 32C, 52A, 52B, 52D, 52G, 59, 59B, 73, 73C, 73D, 79A, 79B, 89, 352. Visit ttc.ca for accurate schedule information.
Pedestrians: The work may require temporary sidewalk restrictions, however any necessary sidewalk closures will provide alternate locations and ensure access is maintained during construction.
Cyclists: If travelling through these work areas, please share the traffic lane in the active work zones
NEED MORE INFORMATION? If you have questions about the upcoming work, please contact us.
Points of Contact Contact Information Contract 19ECS-TI-104LR Public Consultation Unit Steven Ziegler, 416-392-2896, [email protected] TTY Hearing Impaired Service 416-338-0889 (7 Days a week, 8 a.m. to 5 p.m., closed holidays) General inquiries 311 Website toronto.ca/westonroad
___________________________________________________________________________ Thank you for your patience. Building a great city takes time. Better infrastructure for all of us is worth the wait.
http://www.toronto.ca/westonroad
Weston Road Improvements and Intersection Improvements at Jane Street and Trethewey DriveIMPORTANT INFORMATION ABOUT COVID-19 AND CONSTRUCTION WORK IN TORONTOWHAT TO EXPECT DURING CONSTRUCTIONNEED MORE INFORMATION?