1 | P a g e
CONSTRUCTION INDUSTRY DEVELOPMENT
BOARD (“CIDB”)
CASE SUMMARIES AND ANALYSES
JANUARY 2014 – MARCH 2014
2 | P a g e
SOLENTA AVIATION (PTY) LTD v AVIATION @ WORK (PTY) LTD 2014
(2) SA 106 (SCA)
Case No
754/2012
[2013] ZASCA 103
Court Supreme Court Of Appeal
Judge Meyer AJA
Heard August 23, 2013
Judgment September 12, 2013
Facts:
This is an appeal against a judgment of Louw J, sitting in the North J Gauteng
High Court, in which he upheld a special plea of prescription raised by the
respondent, (Aviation @ Work (Pty) Ltd), against a claim for payment of
damages brought against it by the appellant, (Solenta Aviation (Pty) Ltd).
On 13 March 2007 a combined summons was issued in the name of Solenta
Aviation Workshops (Pty) Ltd (Solenta Aviation Workshops) against the Aviation
@ Work. A plea with a claim in reconvention was in due course delivered by the
Aviation @ Work, followed by the delivery of a replication and a plea to the claim
in reconvention in the name of Solenta Aviation Workshops.
It was common cause on the pleadings that on or about 22 March 2006 and at
Wonderboom, Pretoria, Solenta Aviation Workshops, as lessor, and the Aviation
@ Work, as lessee, concluded a written agreement — referred to as the 'Aircraft
Dry Lease Agreement' — in terms whereof Solenta Aviation Workshops leased a
certain Cessna aircraft to Aviation @ Work.
Solenta Aviation Workshops in convention and Aviation @ Work in reconvention
claimed damages against each other resulting from the other party's alleged
breach of the contract.
3 | P a g e
The description of the lessor in terms of the contract is 'Solenta Aviation (Pty)
Ltd' and not Solenta Aviation Workshops as described in the combined summons
and in the particulars of claim.
On 18 August 2009 a notice of intention to amend was delivered in which notice
was given that the description of the plaintiff was to be amended to 'Solenta
Aviation (Pty) Ltd' by the deletion of the word 'Workshops' where it appears in
the summons and in the particulars of claim.
Aviation @ Work objected to the proposed amendment on the grounds that it
would amount to a substitution of one plaintiff for another, and that any claim
that Solenta Aviation (Pty) Ltd might have had against Aviation @ Work had
prescribed. An application for leave to amend the citation of the plaintiff was
then brought.
In granting the amendment on 31 March 2010 Potterill J held that the
description of the plaintiff amounted to a misnomer, rather than a substitution of
the correct plaintiff for the wrong one. She held that the true identity of the
plaintiff was recognisable from the particulars of claim and the contract, and that
service of the summons on Aviation @ Work had interrupted the running of
prescription in terms of s 15(1) of the Prescription Act. The amendment was
effected on 7 April 2010.
Aviation @ Work thereupon amended its plea by raising a special plea of
prescription to Solenta Aviation (Pty) Ltd's claim. Solenta Aviation (Pty) Ltd
delivered a replication in answer to the Aviation @ Work's special defence. It is
common cause on these further pleadings that Solenta Aviation Workshops and
Solenta Aviation (Pty) Ltd were both registered companies and therefore
separate legal entities. It is also common cause that the contract was concluded
between Solenta Aviation (Pty) Ltd and Aviation @ Work; that no contractual
relationship existed between Solenta Aviation Workshops and Aviation @ Work
at the time of instituting the action; and that Solenta Aviation Workshops was
not a creditor of Solenta Aviation (Pty) Ltd.
It is alleged in the special plea that service on Aviation @ Work of the summons
whereby Solenta Aviation Workshops claimed payment of damages arising from
Aviation @ Work's alleged breach of the contract — which breach is alleged in
the particulars of claim to have taken place on or about 13 May 2006 — did not
interrupt the running of prescription in terms of s 15(1) of the Prescription Act,
and that a period of more than three years had elapsed since the alleged breach
and the delivery of the notice of intention to amend the citation of the plaintiff,
or of the actual substitution of Solenta Aviation (Pty) Ltd for Solenta Aviation
Workshops.
4 | P a g e
Solenta Aviation (Pty) Ltd responded in its replication to the special plea that,
although incorrectly described in the summons and particulars of claim, it was
the company that instituted the action against Aviation @ Work on 13 March
2007 and that that process conveyed to the reader the intention of Solenta
Aviation (Pty) Ltd, as creditor, to claim payment from its debtor, Aviation @
Work. The defence of res iudicata in the form of what has become known as
issue estoppel was also raised. It was alleged that, in dismissing Aviation @
Work's objection to the proposed amendment, 'the court determined the
identical issue between the identical parties now raised in the special plea' and
that Aviation @ Work 'is accordingly, and in addition, issue estopped on the
issue raised in the special plea'.
The trial on two separated issues proceeded before Louw J. He was only
concerned with the issues of res iudicata and prescription, while the remaining
issues stood over for later determination. No evidence was led and the parties
confined themselves to the documents that formed part of the record. In
upholding the special plea of prescription, the court a quo followed the decision
of this court in Blaauwberg Meat Wholesalers CC v Anglo Dutch Meats (Exports)
Ltd and held that the summons that was served in this instance, objectively
considered, failed to communicate to the defendant (Aviation @ Work) the
intention of the plaintiff (Solenta Aviation (Pty) Ltd) to claim payment of the
debt. It held that the summons did not meet the objects of s 15(1) of the
Prescription Act and it did not interrupt prescription. In dismissing the plea of res
iudicata, the court a quo held that the application for amendment was
interlocutory and the finding of Potterill J was not one that finally disposed of an
issue in the action between the parties.
In the result, Solenta Aviation (Pty) Ltd's claim was dismissed with costs,
including the costs of two counsel. Solenta Aviation (Pty) Ltd appeals to this
court with the leave of the court a quo. This appeal concerns the same issues of
prescription and res iudicata.
In terms of s 12(1) of the Prescription Act, prescription begins to run when the
debt becomes due. It is common cause between the parties that the debt which
forms the subject of Solenta Aviation (Pty) Ltd's claim became due on 13 May
2006. Sections 10(1) and 11(d) provide for a period of prescription of three
years in the present case. The notice of the application to amend the citation of
the plaintiff was given on 18 August 2009, which was after the prescriptive
period. Section 15(1) provides as follows:
'The running of prescription shall, subject to the provisions of subsection (2), be
interrupted by the service on the debtor of any process whereby the creditor claims
payment of the debt.'
The question to be decided is therefore whether the combined summons served
on Aviation @ Work by which action was instituted in the name of Solenta
Aviation Workshops was a claim by the creditor of the debt, which it is now
5 | P a g e
common cause is Solenta Aviation (Pty) Ltd, in compliance with the provisions of
s 15(1).
The general rule or test applicable in the determination of whether there is
compliance with s 15(1) was reaffirmed by this court in Blaauwberg thus:
'For obvious practical reasons the Legislature ordained certainty about when and how the
running of prescription is interrupted. That certainty is of importance to both debtors and
creditors. It chose an objective outward manifestation of the creditor's intentions as the
criterion, viz the service on the debtor of process in which the creditor claims payment of
the debt. That is not a standard which allows for reservations of mind or reliance on
intentions which are not reasonably ascertainable from the process itself. Nor does it, as a
general rule, let in, in a supplementation of an alleged compliance with s 15(1), the
subjective knowledge of either party not derived from the process, such as, for example,
the content of a letter of demand received by the debtor shortly before service of the
process.'
In Standard Bank of SA Ltd v Oneanate Investments (Pty) Ltd, the case referred
to in the above quotation, Selikowitz J stated the test as follows:
'The test as to whether any given process interrupts prescription in respect of a particular
debt must be an objective one. The process in question must be objectively considered.
Knowledge which one or both of the parties may have dehors the process cannot affect its
interpretation or its interruptive effect. More particularly, the fact that plaintiff may
subjectively intend to claim a particular debt, and that defendant may, by virtue of
extrinsic knowledge, appreciate that plaintiff has wrongly identified the debt in his
summons, cannot convert the summons into one which interrupts prescription in respect of
any debt other than the one identified in the process. It is the process which interrupts
prescription, not the plaintiff's subjective intention to sue.'
Counsel for Solenta Aviation (Pty) Ltd placed great reliance upon the description
of the lessor as 'Solenta Aviation (Pty) Ltd' and that of the lessee as 'Aviation @
Work (Pty) Ltd' in the contract that was served upon Aviation @ Work, as well as
on the reference to 'domicilium citandi et executandi' in the description of each
party on the face of the combined summons, and in paras 1 and 2 of the
particulars of claim. The details of the creditor given in the summons and in para
1 of the particulars of claim were that:
'The plaintiff is Solenta Aviation Workshops (Pty) Ltd, a company, duly incorporated in
accordance with the laws of the Republic of South Africa with domicilium citandi et
executandi of (sic) Block 5 Stratford Office Park, Corner Cedar Avenue and Valley Road,
Broadacres, Johannesburg.'
Solenta Aviation (Pty) Ltd was sought to be introduced to the proceedings by the
deletion of the word 'Workshops'. For the rest the citation remained unchanged.
It is common cause that both corporate entities had the same registered
address, which was the one given in the combined summons and in the
particulars of claim. Solenta Aviation (Pty) Ltd's counsel submitted that the
description of the lessor in the contract and the reference to a 'domicilium
citandi et executandi' communicated to Aviation @ Work the correct identity of
the creditor, viz Solenta Aviation (Pty) Ltd.
6 | P a g e
To look only at the contents of the contract and to conclude that Aviation @
Work must have appreciated, or even did appreciate, who the true creditor was,
which is essentially what the argument on behalf of Solenta Aviation (Pty) Ltd
amounts to, can in my view not be conclusive of the enquiry as to whether
payment of the debt was claimed by the creditor.
The parties to an action are cited in the combined summons and particulars of
claim, and the cause of action is set out in the particulars of claim. It is true that
the debt which Solenta Aviation (Pty) Ltd seeks to claim is the same debt that
Solenta Aviation Workshops sought to enforce in the combined summons that
was served upon Aviation @ Work. This does not mean that the combined
summons was issued by 'the creditor' in compliance with s 15(1).
The description of the plaintiff as Solenta Aviation Workshops and of the
defendant as Aviation @ Work (Pty) Ltd on the face of the combined summons
and in the particulars of claim and the further averments about the written
agreement that was concluded between those two entities make it plain that
Solenta Aviation (Pty) Ltd was not the creditor that claimed payment of the debt
in terms of the combined summons, notwithstanding the reference to Solenta
Aviation (Pty) Ltd's name as the lessor in the contract. The citation of the
domicilium does not assist Solenta Aviation (Pty) Ltd.
The admissions by Aviation @ Work of the citations of the parties and of the
contract and its terms also do not avail Solenta Aviation (Pty) Ltd. They did not
bring about an automatic substitution of one plaintiff for another. Solenta
Aviation (Pty) Ltd's counsel in my view correctly conceded that the admissions
could also not be regarded as an unconditional acknowledgement of liability in
terms of s 14(1) of the Prescription Act. The admissions in any event admit the
parties to the contract to have been Aviation @ Work and Solenta Workshops
and not Aviation @ Work and Solenta Aviation (Pty) Ltd. They also do not assist
Solenta Aviation (Pty) Ltd.
The court sum up: in applying the objective test the claim made in the combined
summons was, on a plain reading, not that of the true creditor, which is Solenta
Aviation (Pty) Ltd, and service of that process on Aviation @ Work did not
interrupt the running of prescription. Solenta Aviation (Pty) Ltd's counsel
conceded that, if this be the finding, it will not be necessary to consider the
defence of issue estoppel.
Solenta Aviation (Pty) Ltd's counsel resisted the request on behalf of Aviation @
Work that a costs order in favour of Aviation @ Work include the costs of two
counsel. The judge stated that it considers the employment of two counsel on
behalf of Aviation @ Work to have been prudent and not extravagant.
7 | P a g e
The court ordered that the appeal should be dismissed with costs, including the
costs of two counsel.
Analysis:
This case is relevant to the cidb and the construction industry at large as it
considers the issue of prescription.
8 | P a g e
KATSHWA AND OTHERS v CAPE TOWN COMMUNITY HOUSING CO (PTY)
LTD AND FOUR SIMILAR CASES 2014 (2) SA 128 (WCC)
Case No
A 264/2012
Court Western Cape High Court, Cape Town
Judge Dlodlo J and Steyn J
Heard September 3, 2013
Judgment November 6, 2013
Facts:
These five appeals were consolidated for hearing in view of the applicability of
similar facts and legal principles. The representatives of the parties prepared one
argument relating to all the appeals.
The appeals originate from the Wynberg Magistrates' Court where it was agreed
that all relevant aspects related to the matters would be argued primarily on the
papers in the matter of Ndileka Constance Katshwa and Leon Katshwa (the
Katshwa matter). When the legal representatives referred to the record in their
arguments, reference was accordingly to the documentation filed in the Katshwa
matter.
The background facts relating to these appeals, as set out by the representative
of the appellants, were not disputed by the respondent's representative.
Each of the appellants concluded an Instalment Purchase Agreement (the IPA)
with the respondent for the purchase of an immovable property. The Katshwas
concluded the IPA on or about 21 June 2001.
The respondent alleges that the appellants fell into arrears in payment of the
instalments due by them, and accordingly the respondent issued letters of
demand calling upon all the appellants to remedy their breach. There was a
letter from the respondent's then attorneys, followed by a letter from the
respondent itself. The appellants remained in default of payment and the
respondent purported to cancel the IPAs. Action proceedings were instituted by
the respondent against the appellants in the Wynberg magistrates' court seeking
the ejectment of the appellants from the immovable properties occupied by
them.
The respondent thereafter instituted eviction proceedings by way of motion
proceedings pursuant to s 4(2) and (5) of the Prevention of Illegal Eviction from
and Unlawful Occupation of Land Act 19 of 1998 (the PIE Act). This relief was
opposed on behalf of the appellants and answering affidavits were filed.
9 | P a g e
On 9 March 2011 the Wynberg Magistrates' Court found that all the appellants
were unlawful occupiers in terms of s 1, read with s 4, of the PIE Act and
ordered the City of Cape Town to file a report and requested submissions in
regard to s 4(7) and (9) of the PIE Act.
On 30 September 2011 the Wynberg Magistrates' Court issued an order that the
appellants should vacate the respective immovable properties occupied by them
on or before 13 December 2011, failing which the sheriff was ordered to evict
them on or after 15 December 2011.
Notices of appeal to these orders were duly filed and the appellants now appeal
against the said March and September judgments.
The representatives of the parties agree that the provisions of the Alienation of
Land Act 68 of 1981 (the ALA) are relevant in this matter. It is not denied by the
respondent that the IPA is a 'contract' as defined in s 1 of the ALA. Whether the
provisions of ss 19, 20 and 26 of the ALA are applicable in the present matter is,
however, a subject of dispute.
Section 20(1) of the ALA relates to the recordal of the contract and provides in
ss (1)(a) that a seller, whether he is the owner of the land concerned or not,
shall cause the contract to be recorded by the registrar concerned in the
prescribed manner, with some exceptions that are not relevant at present. If a
period of 90 days has expired without the seller having caused the contract to be
recorded as prescribed, the purchaser may, inter alia, apply to the registrar
concerned to record the contract in the prescribed manner.
Sections 19 and 20 of the ALA fall under ch II of the ALA. The court was
referred to Merry Hill (Pty) Ltd v Engelbrecht2008 (2) SA 544 (SCA) and the
observations made by Brand JA in regard to the purpose of ch II of the ALA, as
set out in para 13:
'Let me start with a proposition which appears to be beyond contention, namely that the
purpose of ch 2 of the Act, which includes s 19, is to afford protection, in addition to what
the contract may provide, to a particular type of purchaser — a purchaser who pays by
instalments — of a particular type of land — land used or intended to be used mainly for
residential purposes. In this sense, ch 2, like its predecessor, the Sale of Land on
Instalments Act 72 of 1971, can be described as a typical piece of consumer protection
legislation. The reason why the legislature thought this additional statutory protection
necessary is not difficult to perceive. It is because experience has shown this type of
purchaser, generally, to be the vulnerable, uninformed small buyer of residential property
who is no match for the large developer in a bargaining situation.'
It was argued on behalf of the appellants that these sentiments voiced by Brand
JA in the quoted judgment are of application in the appeals before court, where
the provisions of s 20 of the ALA were raised in the answering affidavits filed in
the magistrates' court and it was recorded that the applicant (now the
10 | P a g e
respondent), on its own admission, never complied with the requirement to
procure the recording of the IPA contract in terms of the provisions of s 20 of the
ALA. The respondent alleged that its failure to attend to the recordal of the IPAs
did not excuse the appellants from paying the agreed instalments.
In her judgment dated 9 March 2011 the presiding magistrate, Ms Pangarker,
commented, relating to the respondent's non-compliance with the requirements
of s 20 of the ALA and the breach by the respondent of the provisions of clause 8
of the IPAs, that nothing prevented the appellants (the respondents in the
magistrates' court) from themselves attending to the recordal of the contracts.
Clause 8.1 of the IPA reads as follows:
'The seller shall procure this contract to be recorded in accordance with the provisions of
section 20 of the Act. If the seller fails to do so the purchaser shall be entitled to procure
such recording.'
Clause 9 of the IPA provides that the seller shall be liable for the costs related to
the drafting of the contract and the recording of the contract in terms of s 20 of
the ALA.
It is apparent from the provisions of s 20 of the ALA that there is no requirement
as such on the part of a purchaser, such as the appellants, to ensure the
recordal of the IPA with the registrar. The terms of this section clearly do not
place any obligation on the purchaser to apply for the recordal of the contract
following the failure by the seller to attend to this obligation.
The relevant provisions of s 26 of the ALA read as follows:
'26 Restriction on the receipt of consideration by virtue of certain deeds of
alienation
(1) No person shall by virtue of a deed of alienation relating to an erf or a unit receive any
consideration until —
(a) such erf or unit is registrable; and
(b) in case the deed of alienation is a contract required to be recorded in terms of section
20, such recording has been effected.
(2) Any person who contravenes the provisions of subsection (1) shall be guilty of an
offence and liable on conviction to a fine not exceeding R1000 or to imprisonment for a
period not exceeding one year or to both such fine and such imprisonment.'
The circumstances when the provisions of ss (1) are not applicable do not apply
in this matter. In the premises it was submitted on behalf of the appellants that,
since there had been no recordal of the IPAs by the respondent, as contemplated
by the terms of s 20 of the ALA, the respondent, in view of the provisions of s
26(1) of the ALA, is not entitled to receive any consideration from the
appellants, and further, in view of the provisions of s 26(2) of the ALA, the
receipt of any purchase consideration by the respondent would constitute an
offence on the part of the respondent, making it liable on conviction to a fine or
even imprisonment.
11 | P a g e
Accordingly, it was convincingly argued on behalf of the appellants that the
respondent, by virtue of the provisions of s 26 of the ALA, has no right to the
receipt of any payments from the appellants, since the recordal of the contract,
as contemplated in s 20 of the ALA, had not been effected. The appellants
cannot be in arrears in the payment of instalments due under the IPA when
there is no obligation in law for them to make payments, and accordingly there
was no basis for the respondent to have issued letters of demand upon which it
relied when seeking an order in the magistrates' court. In view of what has been
stated above it was argued that respondent's purported cancellation of the
relevant IPAs is invalid.
The court was further referred to Bouwer v Aurae (Pty) Ltd1991 (4) SA 622 (W)
at 624F – H, where the provisions of s 20 of the ALA were considered and where
it was noted, in essence, that in terms of these provisions an agreement of the
sale of land intended to be used mainly for residential purposes must be
recorded by the Registrar of Deeds, failing which the seller is precluded from
receiving the purchase price payable in terms of the agreement and no valid
cancellation of the agreement can be effected upon non-payment.
The respondent correctly noted in its heads of argument that the essence of the
appellants' case was as set out above, namely that since the IPAs were not
recorded as required by s 20 of the ALA and, in view of the provisions of s
26(1)(a), payment of instalments by the appellants was never due and no
breach of contract occurred, with the result that the IPAs could not have been
cancelled. Respondent agrees that ch II of the ALA deals with the sale of land on
instalments, which the IPAs, that formed the subject of these appeals, are. It
submits though that in order for s 26(1)(a) to have any effect the IPAs must be
contracts that can be referred to as contracts 'required to be recorded in terms
of s 20'. Respondent argues that if s 20 does not apply in these instances, s
26(1)(a) will also have no effect.
The respondent submits that ch II, which includes s 20, is not applicable to the
relevant IPAs due to the provisions of s 4 of the ALA, which reads as follows:
'4 Application of Chapter
This chapter shall not apply in respect of a contract in terms of which the State, the
Community Development Board established by s 2 of the Community Development Act,
1966 (Act 3 of 1966), the National Housing Commission mentioned in s 5 of the Housing
Act, 1966 (Act 4 of 1966), or a local authority is the seller.'
It was submitted on behalf of the respondent that, on a proper interpretation of
the wording of s 4 of the ALA, the Cape Town Community Housing Co (Pty) Ltd
(Cape Town Community Housing Co), ostensibly a private company, must be
regarded as 'a functionary of the state'. The respondent argued in essence, the
first time in its heads of argument in the appeals, that the Cape Town
Community Housing Co is an organ of state.
12 | P a g e
Section 239 of the Constitution defines an 'organ of state' as meaning, inter alia,
any department of state or any other functionary exercising or performing a
function in terms of the Constitution or a Provincial Constitution, or exercising a
public power or performing a public function in terms of any legislation.
Appellants argue that a clear distinction needs to be drawn between the state
and the organs of state and that the appellation 'state' cannot without more be
interpreted to mean 'organ of state', since the concept of 'state' is wider than
that of an organ of state, and that the term 'state', which is referred to in s 4 of
the ALA, means the state as a persona contracting as the seller and not one of
its functionaries.
In Directory Advertising Cost Cutters v Minister for Posts, Telecommunications
and Broadcasting and Others1996 (3) SA 800 (T) ([1996] 2 All SA 83) at 810E –
F it was stated by Van Dijkhorst J that an organ of state —
'must be part of the governmental apparatus. An agent or independent contractor
performing some of the State's functions on its behalf will not be a functionary of the
State.'
In Holeni v Land and Agricultural Development Bank of South Africa2009 (4) SA
437 (SCA) ([2009] 3 All SA 22) para 17 it was stated by Navsa JA that:
'It should also be borne in mind that, when the Act was promulgated, the definition of
organ of State in s 239 of the Constitution was more than two decades into the future. It
can hardly be contended that the legislature, at that time, had in mind a broader meaning
of the State to coincide with what is presently contained in that definition. In any event,
the Constitution itself differentiates between the State and organs of State. The
Constitution can therefore not be used as authority for the proposition that the State in the
Act should be interpreted so as to include organ of State.'
The appellants submit that it does not appear from the record in these
proceedings that the Cape Town Community Housing Co, a private company, is a
state functionary. In fact, as can be noted from the affidavits filed in the lower
court's proceedings, respondent's financial manager, Mr Jurgens, stated under
oath that the respondent was not a state organ. Appellants contend, correctly in
our view, that it is evident from the wording of s 4 of the ALA that a distinction
must be drawn between the state and other possible organs of the state, such as
the Community Development Board and the National Housing Commission.
It was conceded by the appellants that the Cape Town Community Housing Co
may have been established as a joint venture between the City of Cape Town
and the National Housing Finance Corporation and it may be that it receives a
housing subsidy. This state of affairs however should not lead to the conclusion
that the Cape Town Community Housing Co should be regarded as 'the state' as
contemplated in s 4 of the ALA, an aspect previously conceded by the
respondent, when their financial manager stated categorically that it was not a
state organ.
13 | P a g e
The judge agreed with the appellants that the respondent's attempts to rely on
Part 7 of a document titled 'Housing Subsidy Scheme', annexed to its heads of
argument in the appeals, was flawed and that this guideline should be ignored,
as the document appears to be no more than a guideline, was not proved in
evidence, was not accepted by the appellants and cannot now be relied upon on
appeal.
The respondent's view remains that on a proper interpretation of s 4 of the ALA
the respondent should be regarded as a functionary of the state for the specific
purposes of providing social housing. Accordingly, it is argued that the IPAs are
exempt from the provisions of ch II of the ALA.
With reference to the comments of the respondent's financial manager, in its
replying affidavits in the magistrates' court, that the respondent is not a state
organ and can only exist to provide houses if it receives payment for the houses
that it provided, it is contended that the statement was made in a different
context and only reflected the expression of an opinion, which was incorrect. It
was argued that the respondent cannot now be precluded from relying on the
provisions of s 4 of the ALA in these proceedings, based on these incorrect
comments.
Finally it was submitted on behalf of the respondent that the correct meaning of
the phrase 'the state', for the purposes of the disputed issue in these appeals,
should be determined by considering the intention of the legislature, ie the
context of the ALA in which it is found.
As noted previously, the argument relating to the applicability of s 4 was not
raised during the hearing of the matter in the magistrates' court. The appellants
were brought under the impression by the respondent that it agreed that the
provisions of s 4 applied.
The ALA prescribes in s 4 that ch II shall not apply in respect of a contract in
terms of which 'the State . . . or a local authority is the seller'. Save for
recording that certain sections of the National Credit Act will prevail to the extent
of any conflict with this section, no elaboration as to the meaning of the use of
the word 'state' is provided. Section 1 of the ALA, setting out detailed definitions
of the words and phrases contained in the Act, is silent on the meaning and
ambit of the use of the word 'state'.
Legislation usually does not unambiguously and specifically address all matters.
Occasionally the meaning of words used in a statute or a contract or other
document do not have a plain, straightforward meaning, but may be ambiguous
or vague, resulting in the judiciary having to resolve the ambiguities and
pronounce on the perceived intended meaning of the words.
14 | P a g e
The Constitution of the Republic of South Africa, 1996, provides in s 39(2) that
when interpreting legislation every court must promote the spirit, purport and
objects of the Bill of Rights. In general, the courts attempt to promote public
interest when interpreting the wording of a statute.
There are numerous rules of statutory interpretation. It is trite that the words or
language of a statute should be given its 'ordinary meaning' where possible and
where such a construction will not lead to an absurdity, repugnancy or
inconsistency with the rest of the statute. It is also common sense that the
words used in a particular section or clause need to be interpreted in the context
of the statute or document as a whole, as such an interpretation would usually
reflect the true intention of the legislature or contracting parties, if a contract
needs to be interpreted.
In Natal Joint Municipal Pension Fund v Endumeni Municipality 2012 (4) SA 593
(SCA) ([2012] 2 All SA 262; [2012] ZASCA 13) the proper approach that the
court should follow when interpreting statutes, contracts or other documents is
set out in detail. Wallis JA comments as follows (para 18):
'The present state of the law can be expressed as follows: Interpretation is the process of
attributing meaning to the words used in a document, be it legislation, some other
statutory instrument, or contract, having regard to the context provided by reading the
particular provision or provisions in the light of the document as a whole and the
circumstances attendant upon its coming into existence. Whatever the nature of the
document, consideration must be given to the language used in the light of the ordinary
rules of grammar and syntax; the context in which the provision appears; the apparent
purpose to which it is directed and the material known to those responsible for its
production. Where more than one meaning is possible each possibility must be weighed in
the light of all these factors. The process is objective, not subjective. A sensible meaning is
to be preferred to one that leads to insensible or unbusinesslike results or undermines the
apparent purpose of the document. Judges must be alert to, and guard against, the
temptation to substitute what they regard as reasonable, sensible or businesslike for the
words actually used. To do so in regard to a statute or statutory instrument is to cross the
divide between interpretation and legislation . . . .'
Wallis JA emphasised that context and language should be considered together,
the one not dominating the other. The broad purpose of the relevant legislation
is highly relevant to the process of interpretation, 'as is the mischief at which the
legislation is aimed' (para 22). Ultimately the courts give effect to legislative
purpose within the constraints imposed by the language adopted by the
legislature. In this process the interpreting judge must avoid the tendency to be
driven by what that judge regards as a desirable result in a specific case.
'In resolving the problem, the apparent purpose of the provision and the context in which
it occurs will be important guides to the correct interpretation. An interpretation will not be
given that leads to impractical, unbusinesslike or oppressive consequences or that will
stultify the broader operation of the legislation or contract under consideration.'
15 | P a g e
The court was of the view that the purpose of the ALA is clearly as stated in the
preamble to the Act, to regulate the alienation of land in certain circumstances.
Chapter I deals with the formalities required in respect of deeds of alienation.
Chapter II deals with the provisions relating to sale of land on instalments.
Chapter III deals with general provisions.
The primary aspect for determination in these appeals has thus been distilled to
be the ambit and meaning of the word 'state' in s 4 of the ALA, which section
provides that ch II (containing s 20, relating to the recordal of the contract) shall
not apply in respect of a contract in terms of which, inter alia, the state is the
seller. No definition is given of the meaning intended to be attributed to the
word 'state'.
In the Directory Advertising judgment supra at 809D Van Dijkhorst J comments
that private companies incorporated under the Companies Act can 'hardly be
statutory bodies' as contemplated in the Constitution because in their day-to-day
functioning they are not integrated into the state's structure or authority. At
810C – F he comments, inter alia, that an organ of state is not an agent of the
state, it is part of government (at any of its levels). A functionary of the state is
part of the 'governmental apparatus':
'An agent or independent contractor performing some of the State's functions on its behalf
will not be a functionary of the State.'
A private company is governed by its articles of association. In view of what is
stated hereinabove and viewing the word 'state' in the context of the ALA, the
purpose of the relevant sections, such as ss 20 and 26, to protect vulnerable,
financially disadvantaged and relatively unsophisticated purchasers from private
companies, with or without state shareholders.
Further, the court expressed the view that the use of the word 'state' in s 4
refers to closed categories of entities and that the wording of 'state' in this
context cannot be widened to include organs of state and definitely not private
companies, such as the respondent in this matter, regardless of the interest in it
by certain organs of state and regardless of whether or not its purpose is to
generate profit.
The respondent was an independent contractor performing certain governmental
obligations, including the provision of housing. There is no evidence before court
that the respondent forms part of government at any level or is controlled by
government, or that it should be regarded as an organ of state. On the contrary,
the respondent's own factual averments lead to the conclusion that it is not an
organ of state, but is, in fact, a private company. The respondent has not shown
that there is any foundation in fact or in law why it should be regarded as the
state.
16 | P a g e
Section 4 of the ALA does not assist the respondent. The respondent has not
offered argument in answer to those advanced by the appellants in the heads of
argument filed on their behalf.
The court ordered that all the appeals should succeed, and that the orders of the
magistrate in these appeals, under the recorded case numbers, should be
altered to read:
1. The applications are dismissed.
2. The applicant is ordered to pay the costs of the applications.
Analysis:
This case is relevant to the cidb and the construction industry at large as it
considers drawing up the distinction between ‘organ of state’ and the ‘state’.
17 | P a g e
COUNTRY CLOUD TRADING CC v MEC, DEPARTMENT OF
INFRASTRUCTURE DEVELOPMENT 2014 (2) SA 214 (SCA)
Case No
751/12
[2013] ZASCA 161
Court Supreme Court Of Appeal
Judge Brand JA, Leach JA, Tshiqi JA, Theron JA and Saldulker JA
Heard November 8, 2013
Judgment November 26, 2013
Facts:
The respondent is a Member of the Executive Council in the province of Gauteng
with responsibility for the provincial Department of Infrastructure Development,
which was formerly part of the Department of Public Transport, Roads and
Works (the department).
The appellant is a close corporation, Country Cloud Trading CC (Country Cloud).
The appeal originates from a building contract between the department and a
construction company, Ilima Projects (Pty) Ltd (Ilima). In terms of this contract,
Ilima undertook to complete the construction of the partially built Zola Clinic in
Soweto at a contract price of R480 million. In order to comply with its
obligations under the contract, Ilima borrowed R12 million from Country Cloud.
In terms of the loan agreement between these two parties, Country Cloud stood
to make a profit of R8,5 million.
After Country Cloud had paid the R12 million to Ilima, the department cancelled
the construction contract, which ultimately led to the liquidation of Ilima.
Following upon these events, Country Cloud instituted an action against the
department in the South Gauteng High Court, Johannesburg for delictual
damages in an amount of R20,5 million, together with interest at 15,5%.
The matter came before Satchwell J who dismissed the claim with costs. The
present appeal against that judgment, which has since been reported as Country
Cloud Trading CC v MEC, Department of Infrastructure Development [2012] 4 All
SA 555 (GSJ), is with the leave of the court a quo.
A proper understanding of the issues arising requires a broad outline of the
background facts. What eventually proved to be a rather sad tale of woe for all
parties concerned started on 10 May 2006 when the department awarded a
tender to build the Zola Clinic in Soweto, which was designed as a 300-bed
district hospital, to a joint venture of four companies at a contract price of about
18 | P a g e
R335 million. Ilima was one of the four companies in the joint venture. In terms
of the ensuing contract, the project had to be completed by May 2008. But the
joint venture never really got off the ground. In March 2008 Ilima's three
partners withdrew, which left it as the last contractor standing. At that stage
only 20% of the hospital had been completed.
The head of the department at the time, Mr Sibusiso Buthelezi, was then landed
with the responsibility of appointing a contractor to complete the building
project. The Departmental Acquisition Council (DAC), which concerned itself with
the procurement of goods and services for the department, recommended to
Buthelezi that the contract should once again go through the tender process. On
the other hand, the recommendation by senior officials of the department was
that, due to the urgency of the situation, the completion contract should, without
further ado, be awarded to Ilima as the only surviving member of the joint
venture. This is what Buthelezi then did. Although Buthelezi himself did not
testify at the trial, it appears from the documentary evidence that he was of the
view that, as the accounting officer of the department, he was entitled to
override the advice of the DAC and that due to the exigency of the situation, he
should do so. In motivating this decision in subsequent correspondence,
Buthelezi pointed out, for instance, that the people of Soweto were in dire need
of a hospital which was destined to be completed by May 2008; that by that time
only 20% of the work had been done; and that going out on tender was bound
to give rise to further delay and additional costs.
Ilima was confident that it was able to complete the construction of the hospital
on its own. Yet it needed immediate financial assistance in an amount of R12
million to do so and the department was clearly aware of this need. Hence the
department made various concessions to assist Ilima in obtaining a loan so as to
facilitate the expeditious completion of the hospital.
Firstly, the department undertook, as part of the construction contract, to pay
Ilima a so-called 'site re-establishment and mobilisation fee' equal to 5 % of the
contract price of R480 million — that is, R21,5 million — within 30 days of
concluding the contract. Secondly, the department allowed its managing agent,
Tau Pride (Pty) Ltd (Tau Pride), to give a formal undertaking to Country Cloud
that the loan of R12 million be paid directly to it out of the site rehabilitation and
mobilisation fee of R21,5 million when Ilima became entitled to this fee.
On this basis Country Cloud agreed, in terms of a loan agreement with Ilima, to
advance an amount of R12 million to the latter to perform its obligations under
the completion contract. In turn, Ilima undertook to repay the amount of R12
million when the site rehabilitation and mobilisation fee became payable. In
addition, Country Cloud would receive a handsome profit of R8,5 million which
Ilima undertook to pay by 1 May 2009. The construction contract for the
completion of the Zola Clinic, which ended up as the source of this litigation, was
19 | P a g e
then concluded between Ilima and the department on 4 August 2008. It soon
became known as 'the completion contract'. Following upon the conclusion of the
completion contract, Country Cloud advanced the R12 million to Ilima.
Trouble started on 4 September 2008 when the department cancelled the
completion contract before it had made any payments thereunder, either to
Ilima or, via Tau Pride, directly to Country Cloud. This despite a certificate by the
principal agent in terms of the construction contract, that an amount of R21,5
million became due and payable by the department. The comprehensive letter of
cancellation on behalf of the department was written by Buthelezi. In essence it
relied on two misrepresentations by Ilima prior to the conclusion of the
completion contract, which were alleged to be both intentional and material. The
first related to a representation conveyed through a tax clearance certificate
from the South African Revenue Service (SARS), to the effect that Ilima had
complied with all its tax obligations and was in good standing with SARS. This
was alleged to be untrue in that, at the time, Ilima's tax affairs were in serious
disarray. The second was that it had received a level 8 accreditation from the
Construction Industry Development Board.
Subsequently, Country Cloud had been liquidated for being unable to meet its
financial obligations to its creditors. This happened in March 2010. Prior to its
liquidation, summons was issued on behalf of Country Cloud against the
department for contractual damages in an amount of R1,4 billion on the basis of
its alleged unlawful repudiation of the completion contract. What happened to
this claim is not entirely clear. Apparently it went to mediation, which proved to
be unsuccessful.
Country Cloud's particulars of claim reveal clear difficulty in the formulation of a
claim in delict. As it happened, the basis finally relied upon was only introduced
by way of an inelegantly drafted amendment shortly before Country Cloud closed
its case in the court a quo. Not revealing the scars of amendments, the
formulation eventually followed the following lines:
(a) The department owed Country Cloud a so-called 'duty of care' not to cancel the
completion contract without any lawful ground prior to payment of the site rehabilitation
and mobilisation fee to Ilima.
(b) On 4 September 2008 the department intentionally, and, in breach of its duty of care,
unilaterally cancelled the completion contract without any lawful grounds.
(c) But for the conduct of the department, Ilima would have received payment of an
amount of R21,5 million and would have been able to pay the R12 million and R8,5 million
which it owed to Country Cloud.
In the original version of its plea the department persisted in the defence that
the completion contract had been validly cancelled on grounds of Ilima's material
and intentional misrepresentations. As in the cancellation letter, the two
misrepresentations relied upon again related to the content of the tax clearance
certificate provided by Ilima and the representation that Ilima had been
20 | P a g e
accredited by the Construction Industry Development Board with a level 8
rating. Moreover, and in any event, the department denied that it was liable in
delict to Country Cloud for the damages claimed. Shortly before the
commencement of the trial the department amended its plea so as to introduce
a further defence. According to this new defence the completion contract was in
any event invalid because
'the tender awarded to Ilima was contrary to the procurement regulations and policies of
the . . . Department' in that 'it was not advertised and [did not invite] . . . other companies
to bid for the tender; and it was not evaluated and adjudicated by the appropriate internal
structures of the department'.
Prior to the commencement of the trial the department admitted that Ilima
possessed the required level 8 rating. Hence the evidence at the trial focused on
(a) the validity of the tax clearance certificate, and (b) the department's
contention that the award of the tender to Ilima was invalid from the start. As to
the first issue, it was common cause that Country Cloud produced a tax
clearance certificate issued by SARS on 5 December 2007 which was valid for a
period of one year — that is until 5 December 2008 — which obviously extended
beyond the conclusion of the completion contract on 4 August 2008.
In support of the contention that there was nothing wrong with this certificate,
Country Cloud presented the evidence of Dr Tembalegise Lupepe, who was the
founder of and driving force behind Country Cloud. For the contrary proposition,
the department relied on the testimony of one Mr Wayne Broughton, a senior
employee of SARS. The only other witness of note was Mr Mohlomphegi Thulare,
a departmental official, who was called by the department to testify in support of
its non-compliance defence.
At the end of the trial the court a quo was thus enjoined to decide three issues:
(a) whether the award of the completion contract to Ilima was valid and lawful;
(b) whether the contract was validly cancelled on the basis that the clearance certificate
provided by Ilima was invalid; and
(c) whether the department could be held liable in delict for the damages allegedly sustained
by Country Cloud as a result of the repudiation of the contract by Buthelezi on behalf of the
department.
The court a quo decided first to consider the issue in (a). It then concluded that
the award of the contract to Ilima was indeed invalid and unlawful. In
consequence, the court found it unnecessary to embark upon the other two
issues at all.
Without any intent to be uncharitable, the defence on which the department
eventually succeeded was — perhaps in retaliation to the similar lackadaisical
approach to pleadings adopted by Country Cloud —introduced at a very late
stage by means of an ineptly drafted amendment to the plea, and then
presented in an even worse way. The factual basis advanced for the alleged
unlawfulness of the award of the completion contract was that it was not
21 | P a g e
advertised and that it did not go through the tender and bidding process. The
legal basis pleaded was that the award of the tender was therefore 'contrary to
the procurement regulations and policies' of the department.
At the trial the department sought to establish this defence through the evidence
of Thulare. It then emerged that the legal basis for the defence had nothing to
do with 'departmental policy' but instead derived from a myriad of statutory
provisions, including the Public Finance Management Act 1 of 1999 (the Act);
Preferential Procurement Policy Framework Act 5 of 2000; regulations
promulgated under these Acts; practice notes issued by the National Treasury,
and so forth. Relying on these statutory provisions, the theme of Thulare's
testimony proved to be that —
(a) as a general rule, procurement of goods and services by the department had to follow
the prescribed advertising and competitive bidding process which was not adopted in the
award of the completion contract;
(b) although the prescribed process could be departed from in cases of emergency, the
circumstances surrounding the award of the completion contract did not constitute a case
of emergency;
(c) the DAC, of which Thulare was a member, had recommended to Buthelezi that the
completion contract should once again go through the prescribed process, which advice
Buthelezi had refused to follow.
Undoubtedly as a result of the way in which this defence was presented, the
court a quo gained the impression, which proved to be mistaken, that the
authority to decide whether or not deviation from the prescribed process was
justified, did not rest with Buthelezi but with the DAC. Since the DAC, 'to which
Buthelezi . . . was accountable, did not approve the deviation from inviting
competitive bids', so the court held, the completion contract was concluded
without authority.
In consequence the department could not be held liable under the completion
contract. On appeal it was common cause, however —
(a) that ss 38 – 44 and the practice notes issued by National Treasury bestowed the
authority to deviate from the prescribed procedure on the 'accounting officer';
(b) that in terms of s 36 of the Act, Buthelezi was indeed the accounting officer; and
(c) that Buthelezi therefore had the authority to ignore the DAC's advice that the
completion contract should again go out to tender.
The interpretation of the relevant statutory provisions thus accepted by counsel
for both parties — which the court regard as correct — essentially deprived the
judgment of the court a quo of its whole substructure, ie that Buthelezi had no
authority to deviate from the prescribed procedure. Nonetheless, the department
contended that the award of the contract was unlawful on the basis that the
circumstances surrounding the award did not qualify as a case of emergency. In
support of this contention it relied on the evidence of Thulare.
The court held that there are at least three reasons why the above reliance on
the evidence of Thulare cannot be sustained. First, Thulare's opinion is
22 | P a g e
inadmissible on matters of law. Secondly, insofar as his opinion pertained to
matters of fact, it was equally inadmissible since he was not called as an expert
witness. Thirdly, the court cannot see why his opinion should be preferred to
that of Buthelezi and other senior members of the department who held the view
that the completion of the Zola Clinic was indeed required as a matter of
urgency.
In this light the court concluded that the department's defence resting on an
unlawful award of the completion contract, should not have been upheld.
The department's further defence, based on the proposition that the completion
contract was validly cancelled, can be disposed of with even less ado. It will be
remembered that this defence was based on the premise that the tax clearance
certificate submitted by Ilima was false. At the trial the department set out to
establish this defence through the evidence of Broughton, a senior official in the
employment of SARS. Since Broughton was not directly involved with the issue
of the certificate, the high-water mark of his evidence was, however, that the
certificate should not have been issued. The basis he advanced for this view was
that, at the time the certificate was issued, Ilima's tax affairs were in serious
disarray. Under cross-examination he conceded, however, that a tax clearance
certificate could nonetheless be issued if Ilima had come to an arrangement with
SARS. He further conceded that he could not exclude the possibility that such an
arrangement had in fact been reached. These concessions in turn led to the
concession by counsel for the department — which was, in my view, rightly and
fairly made — that the defence based on cancellation of the completion contract
could not be sustained.
This leads to a consideration of the department's further defence that, in any
event, it cannot be held liable in delict for the damages claimed because Country
Cloud had failed to establish the element of wrongfulness, which is essential for
Aquilian liability. The contention must of course be understood in the light of the
evolution of our law with regard to delictual liability for pure economic loss that
started with the decision of this court in Administrateur, Natal v Trust Bank van
Afrika Bpk F 1979 (3) SA 824 (A). Prior to Trust Bank Aquilian liability was
limited, as a general rule, to loss resulting from physical injury to the person or
property of the defendant. But in Trust Bank it was extended to liability for pure
economic loss. What Rumpff CJ immediately realised in that case (at 833A) was
that this extension gave rise to the danger of 'oewerlose aanspreeklikheid'
(limitless liability). Experience tells us that economic effects are not subject to
the laws of physics. They can be much more widely spread. Hence the problem
of the extension was one of limitation. Or, as this court said in Fourway Haulage
SA (Pty) Ltd v SA National Roads Agency Ltd 2009 (2) SA 150 (SCA) para 17,
when we abolished the absolute exclusion of liability for pure economic loss, we
abandoned the bright line of limitation. That gave rise to the question: where is
the next bright line to be drawn?
23 | P a g e
What Rumpff CJ decided in Trust Bank was to cast the element of wrongfulness
in the role of an instrument of control to prevent limitless liability. In this way
the role of wrongfulness became far more pivotal than the one it traditionally
performs with reference to conduct causing physical harm. In the latter situation
wrongfulness is rarely contentious. In fact, in these cases wrongfulness is
presumed with the result that the onus is on the defendant to exclude the
inference of wrongfulness arising from physical harm. But in the case of pure
economic loss, wrongfulness performs the function of a safety valve, a control
measure, a long stop which enables the court to curb liability where despite the
presence of all other elements of the Aquilian action, right-minded people will
regard the imposition of liability as untenable. Decisions building upon Trust
Bank demonstrate the clear recognition by different members of this court that
wrongfulness in the context of delictual liability for pure economic loss is
ultimately dependent on an evaluation based on considerations of legal and
public policy. The enquiry is thus: do these policy considerations require that
harm- causing conduct should be declared wrongful and consequently render the
defendant liable for the loss, or do they require that harm should remain where
it fell, ie with the plaintiff?
Yet, for some or other reason there was a clear reluctance, during the early
stages of the development of the delictual action for pure economic loss, to
admit that we are dealing with considerations of policy. Perhaps the reluctance
was motivated by fear that an express reference to vague notions of policy
would fuel the criticism of those who contended that the extension of liability in
Trust Bank would result in the substitution of judicial discretion for principle. But
whatever the reason, in Trust Bank Rumpff CJ (at 833A) introduced the concept
of a 'legal duty' as the yardstick to determine when policy considerations will
require the imposition of delictual liability for pure economic loss. With the
passage of time, further attempts were made to formulate some practical
yardstick for this purpose. Included amongst these was the concept of the 'boni
mores' or 'legal convictions' of the community; and the 'general criterion of
reasonableness', which poses the question whether or not it would be reasonable
to impose liability on the defendant. Unfortunately, these yardsticks gave rise to
confusion. While the concept of a 'legal duty' was often confused with the
concept of a 'duty of care' in English law — which straddles both wrongfulness
and negligence — the 'general criterion of reasonableness' was frequently
associated with the reasonableness of the defendant's conduct, which is an
element of negligence.
Our case law illustrates that this confusion had practical consequences in that it
often led to a complete negation of either negligence or wrongfulness. The court
raised this because, despite the frequent warnings against this confusion by this
court over the last 10 years, it again raised its head right throughout the
proceedings in this case.
24 | P a g e
Fortunately, in the light of the confusion caused by the yardsticks, our courts
have since found their way open to acknowledge in express terms that
wrongfulness, in the context of delictual liability, is determined by considerations
of legal and public policy. This appears, for instance, from the following
statement by the majority of the Constitutional Court in Le Roux v Dey (Freedom
of Expression Institute and Restorative Justice Centre as Amici Curiae)2011 (3)
SA 274 (CC) (2011 (6) BCLR 577) para 122:
'In the more recent past our courts have come to recognise, however, that in the context
of the law of delict: (a) the criterion of wrongfulness ultimately depends on a judicial
determination of whether — assuming all the other elements of delictual liability to be
present — it would be reasonable to impose liability on a defendant for the damages
flowing from specific conduct; and (b) that the judicial determination of that
reasonableness would in turn depend on considerations of public and legal policy in
accordance with constitutional norms. Incidentally, to avoid confusion it should be borne in
mind that what is meant by reasonableness in the context of wrongfulness has nothing to
do with the reasonableness of the defendant's conduct, but it concerns the reasonableness
of imposing liability on the defendant for the harm resulting from that conduct.
Pivotal to Country Cloud's contention as to why considerations of public policy
dictate the imposition of delictual liability on the department, was the
proposition that Buthelezi cancelled the completion contract without any legal
justification and that he did so with the intent — at least in the form of dolus
eventualis — to repudiate the contract. Stated somewhat differently, in the
language of dolus eventualis, Buthelezi subjectively foresaw the possibility that
he had no legitimate grounds to cancel the contract, but reconciled himself to
that possibility and nonetheless continued to do so, regardless of the
consequences. That, so the argument went, distinguishes this case from the
situation where the degree of blameworthiness associated with the repudiation
of a contract can be placed no higher than negligence.
As to the factual basis for its contention regarding Buthelezi's state of mind,
Country Cloud relied on the following:
(a) The evidence by Thulare that Buthelezi came under severe pressure, not only from the
department itself, but also in the media, for not following the recommendation of the DAC
to put the completion contract out to tender and that he was desperately looking for
reasons to cancel.
(b) The allegation in Country Cloud's particulars of claim to the effect that the department
intentionally cancelled the contract without any legitimate grounds for doing so.
(c) The fact that it must have been patently clear to the department that the sting in that
allegation was pointed directly at Buthelezi and that the department nonetheless failed to
call him as a witness.
(d) The fact that the two grounds for cancellation of the completion contract advanced by
Buthelezi both proved to be entirely unfounded.
These circumstances, so Country Cloud argued, gave rise to the inference that
Buthelezi at least foresaw that the cancellation was unjustified and that he
reconciled himself to that possibility. Absent any explanation by Buthelezi, so the
argument went, that inference became the most probable one. Despite the
25 | P a g e
department's arguments to the contrary, it seems to the court that the logic of
Country Cloud's reasoning cannot be faulted. In consequence, the factual basis
of the policy consideration for which Country Cloud contends appears to be well
founded.
For the legal basis of the policy consideration based on the blameworthiness of
Buthelezi's state of mind, Country Cloud sought to find support in the following
statement by this court in Minister of Finance and Others v Gore NO 2007 (1) SA
111 (SCA) ([2007] 1 All SA 309) para 86:
'We do not think that it can be stated as a general rule that, in the context of delictual
liability, state of mind has nothing to do with wrongfulness. Clear instances of the contrary
are those cases where intent, as opposed to mere negligence, is itself an essential element
of wrongfulness. These include intentional interference with contractual rights and unlawful
competition.'
Again, the court find no fault with Country Cloud's point of departure that,
generally speaking, the nature of the defendant's fault and the degree of
blameworthiness of the conduct are policy considerations that can legitimately
be taken into account in deciding whether or not delictual liability should be
imposed.
Under the Aquilian action, so they say, the element of fault is satisfied by either
negligence or intent. As a general rule, no weight is therefore given, under the
rubric of fault, to the degree of blameworthiness or any reprehensible motive on
the part of the defendant. This is so because the element of fault leaves no
scope for considerations of policy. In determining wrongfulness, on the other
hand, these very considerations of policy do indeed come into play. But it goes
without saying, as is underscored by Loubser et al op cit 157, that
'(i)ntentionally causing harm to others will not always be wrongful' and that 'intent does
not necessarily indicate wrongfulness'.
In the end the nature of the fault and the degree of blameworthiness are
therefore considerations to be weighed up with all others in determining whether
delictual liability should be imposed.
With reference to the quotation from Gore NO, it will be realised that the present
is not the type of situation contemplated in cases such as Dantex. In those cases
a delictual remedy is afforded to a party to a contract who complains that a third
party — who is a stranger to the contract — has intentionally deprived him or
her of the benefits he or she would otherwise have obtained from performance
under the contract. Examples include preventing a lessee from taking occupation
of the leased property in terms of the lease (Dantex); enticing another person's
employees to breach the contract.
For Country Cloud to succeed, the court must extend delictual liability to a
contracting party for damages suffered by a stranger to the contract resulting
26 | P a g e
from the intentional repudiation of the contract by that contracting party. This,
as counsel for Country Cloud rightly conceded, has never been done before. And,
as Grosskopf AJA said in Lillicrap, Wassenaar and Partners v Pilkington Brothers
(SA) (Pty) Ltd1985 (1) SA 475 (A) at 504F – G:
'South African law [unlike English law] approaches the matter in a more cautious way, as I
have indicated, and does not extend the scope of the Aquilian action to new situations
unless there are positive policy considerations which favour such an extension.'
Aside from intent on the part of Buthelezi, the only other positive policy
consideration proposed by Country Cloud in favour of imposing delictual liability
on the department is that all departmental officials involved, including Buthelezi,
foresaw the damages that it would suffer if they were to repudiate the
completion contract.
The judge stated that foreseeability of harm has in the past been recognised by
this court as a factor in establishing wrongfulness. Nonetheless, the judge had
some reservation about this approach, mainly because it is bound to add to the
confusion between negligence and wrongfulness. Moreover, foreseeability is a
requirement for negligence and also plays a role in the determination of legal
causation. A defendant will therefore not be held liable for harm which was not
foreseeable.
The court held that since foreseeability of harm is a prerequisite for delictual
liability in all cases, that feature cannot render the claim by Country Cloud
deserving of special treatment. Imposition of delictual liability on the department
in this case will therefore as a general principle render contracting parties liable
in delict for harm suffered by strangers which flows from the repudiation of their
contracts.
The realisation that this is so immediately raises a feature which is generally
regarded as a strong pointer away from the imposition of delictual liability,
namely that of indeterminate liability. In fact, this consideration is directly linked
to the very reason for the initial doubt as to whether pure economic loss should
be actionable at all. If delictual liability were to be imposed on the department
for the loss suffered by Country Cloud, what about all others who lent money to
Ilima? And what about Ilima's employees? And what about its subcontractors?
In argument, counsel for Country Cloud was constrained to concede that there
would be no difference in principle between these potential claimants, on the one
hand, and Country Cloud, on the other. What exacerbated that difficulty was
counsel's further concession, rightly made, that there appears to be no reason
why the claims of all these potential claimants would not be cumulative with one
another and with the contractual claim of Ilima as well.
The problems of limitation thus arising are reminiscent of those referred to by
Schreiner JA in Union Government v Ocean Accident and Guarantee Corporation
27 | P a g e
Ltd1956 (1) SA 577 (A) at 585B – D. In that case the government claimed for
the loss it had suffered as a result of negligently inflicted injury to a government
employee (a magistrate). In explaining why this court declined to expand
Aquilian liability beyond the injured person himself to those who may indirectly
suffer harm as a result of the injury, Schreiner JA said (at 585F – H):
'Once one goes beyond physical proximity and considers the possibilities that may arise
out of the relationships, contractual or other, between the physically injured person and
other persons who may suffer indirectly, though materially, through his incapacitation, one
is immediately met with the prospects of an unmanageable situation. It is easy to imagine
the absurdities that would arise if all persons contractually linked to the injured person
could sue the careless injurer for the loss suffered by them. The case was put to us of the
injured building contractor who in consequence of his injury has to discontinue his
contract, so that his employees and the building owner and the architect and his sub-
contractors and their employees are all put to some loss.'
A further consideration which weighs heavily against the imposition of delictual
liability on the department, in the circumstances of this case, is the one that has
become known in the context of wrongfulness as the plaintiff's 'vulnerability to
risk'.
As developed in our law under the influence of Australian jurisprudence,
vulnerability to risk signifies that the plaintiff could not reasonably have avoided
the harm suffered by other means. What has by now become well established in
our law is that the finding of non-vulnerability on the part of the plaintiff is an
important indicator against the imposition of delictual liability on the defendant.
The import of this consideration is best illustrated, I think, by McHugh J in Perre
v Apand (Pty) Ltd (1999) 198 CLR 180 (HCA) para 118:
'Cases where a plaintiff will fail to establish a duty of care [or wrongfulness in the parlance
of our law] in cases of pure economic loss are not limited to cases where imposing a duty
of care would expose the defendant to indeterminate liability or interference with its
legitimate acts of trade. In many cases there will be no sound reason for imposing a duty
on the defendant to protect the plaintiff from economic loss where it was reasonably open
to the plaintiff to take steps to protect itself. The vulnerability of the plaintiff to harm from
the defendant's conduct is therefore ordinarily a prerequisite to imposing a duty. If the
plaintiff has taken or could have taken steps to protect itself from the defendant's conduct
and was not induced by the defendant's conduct from taking such steps, there is no reason
why the law should step in and impose a duty on the defendant to protect the plaintiff
from the risk of pure economic loss.'
In this case it is clear that there were at least two alternative remedies available
to Country Cloud to recover its loss. It could either have claimed repayment
from Ilima in terms of the contract of loan or it could have taken cession of
Ilima's claim against the department. The reason why it did neither is not
explained. The contention on behalf of Country Cloud was that, because of
Ilima's insolvency, it was not able to recover its claim in full. But there is more
than one answer to this contention. First, it still does not explain why Country
Cloud did not take cession of Ilima's claim against the department if the
liquidators elected not to pursue their claim. Secondly, there is no reason to
think that if Ilima or its liquidator had successfully pursued its claim for breach
28 | P a g e
of contract against the department, it would still be unable to repay Country
Cloud. Thirdly, if Ilima would remain unable to pay Country Cloud despite its
success against the government, the cause of Country Cloud's loss would no
longer lie in the department's breach but in Ilima's insolvency.
Once Ilima is — by means of an award of damages in contract — placed in the
position it would have been if the department had complied with its obligations,
any further damage that Country Cloud could suffer could no longer be laid at
the door of the department.
It follows that there is no room for the imposition of delictual liability on the
department for the loss claimed by Country Cloud. In the result the court agreed
with the court a quo's finding — albeit for reasons that are quite different — that
Country Cloud's claim could not succeed.
The court ordered that the appeal should be dismissed with costs, including the
costs of two counsel.
Analysis:
This case is relevant to the cidb and the construction industry at large as it
considers the imposition of delictual liability in circumstances where it has never
been imposed before, namely where a stranger to a contract had suffered
economic loss as a result of the intentional repudiation of the contract by one of
the contracting parties.
29 | P a g e
ALLPAY CONSOLIDATED INVESTMENT HOLDINGS (PTY) LTD AND
OTHERS v CHIEF EXECUTIVE OFFICER, SOUTH AFRICAN SOCIAL
SECURITY AGENCY, AND OTHERS 2014 (1) SA 604 (CC)
Case No
CCT 48/13
[2013] ZACC 42
Court Constitutional Court
Judge
Mogoeng CJ, Moseneke DCJ, Cameron J, Froneman J, Jafta J,
Nkabinde J, Skweyiya J, Van Der Westhuizen J, Zondo J, Madlanga J
and Mhlantla AJ
Heard September 10, 2013
Judgment November 29, 2013
Facts:
AllPay Consolidated Investment Holdings (Pty) Ltd (AllPay); an unsuccessful
bidder in a tender invited by the South African Social Security Agency (SASSA)
for the administration of social grant payments to beneficiaries challenged the
awarding of the tender to Cash Paymaster Services (Pty) Ltd (CPS) in the North
Gauteng High Court.
North Gauteng High Court had declared the process followed in awarding the
tender illegal and invalid but declined to set it aside because it would have
disrupted the payment of social grants.
AllPay appealed to the Supreme Court of Appeal (SCA) against the refusal to set
the award aside, and CPS cross-appealed against the declaratory order. The SCA
upheld the cross-appeal and dismissed the appeal, finding that the alleged
irregularities were not unlawful, and commenting that public interest dictated
that a procurement process should not be invalidated for minor inconsequential
flaws.
The SCA also rejected, inter alia, AllPay's challenge of SASSA's alleged failure to
assess the ability of Cash Paymaster's black economic empowerment partners to
perform the tender.
In AllPay's further appeal to the Constitutional Court, the court held that
'inconsequential irregularities' were of no moment conflated the test for
irregularities and their import. An assessment of the fairness and lawfulness of
30 | P a g e
the procurement process must be in terms of the provisions of the Promotion of
Administrative Justice Act 3 of 2000 (PAJA), independent of the outcome of the
tender process.
The proper approach was to establish, factually, whether an irregularity
occurred; and then to legally evaluate the irregularity to determine whether it
amounted to a ground of review under PAJA. This legal evaluation must, where
appropriate, take into account the materiality of any deviance from legal
requirements before concluding that a review ground under PAJA has been
established. (The materiality of compliance with legal requirements depended on
the extent to which the purpose of the requirements was attained; and was
primarily determined by assessing whether the purposes the tender
requirements were intended to serve had been substantively achieved.)
Once a ground of review under PAJA had been established, s 172(1)(a) of the
Constitution required the decision to be declared unlawful. The consequences of
the declaration of unlawfulness must then be dealt with in a just and equitable
order under s 172(1)(b), to which s 8 of PAJA gave detailed legislative content.
It was at this remedy stage that appropriate attention had to be given to the
public interest in the consequences of setting the procurement process aside.
The constitutional and legislative procurement framework (provided by s 217 of
the Constitution, the Procurement Act 5 of 2000 and the Public Finance
Management Act 1 of 1999) entailed supply chain management prescripts that
were legally binding. Once a particular administrative process was prescribed by
law, it was subject to the norms of procedural fairness codified in PAJA. The
central focus of this enquiry was not whether the decision was correct, but
whether the process was reviewable on the grounds set out in PAJA. If a court
found that there were valid grounds for review, it was obliged to enter into an
enquiry with a view to formulating a just and equitable remedy. That enquiry
must entail weighing all relevant factors, after the objective grounds for review
had been established.
The SCA's analysis fell short of considering the crucial role reserved for
transformation in the procurement process. Economic redress for previously
disadvantaged people was at the heart of our constitutional and legislative
procurement framework. The definition of broad-based black economic
empowerment under the Empowerment Act indicated an intention not merely to
afford inclusion or redistribution, but to involve black people in management and
control of businesses, and to facilitate skills development. There was an
obligation on SASSA to ensure that the empowerment credentials of the
prospective tenderers were investigated and confirmed before the award was
finally made.
31 | P a g e
Substantive empowerment, not mere formal compliance, was what mattered.
Given the central and fundamental importance of substantive empowerment
under the Constitution and the Procurement and Empowerment Acts, SASSA's
failure to ensure that the claimed empowerment credentials were objectively
confirmed was fatally defective. It was difficult to think of a more fundamentally
mandatory and material condition prescribed by the constitutional and legislative
procurement framework than objectively determined empowerment credentials.
The failure to make that objective determination fell afoul of s 6(2)(b) of PAJA
(non-compliance with a mandatory and material condition) and s 6(2)(e)(iii)
(failure to consider a relevant consideration).
The award of the tender to Cash Paymaster was declared constitutionally invalid,
such declaration suspended pending confirmation of a just and equitable
remedy.
Analysis:
This case is relevant to the cidb and the construction industry at large as it
considers whether an irregularity in the procurement process was reviewable on
the grounds set out in Promotion of Administrative Justice Act 3 of 2000.