+ All Categories
Home > Documents > Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the...

Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the...

Date post: 10-Mar-2018
Category:
Upload: truongnguyet
View: 312 times
Download: 29 times
Share this document with a friend
24
Construction Method Statement H06 VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a Uncontrolled when downloaded or printed Page 1 of 24 CONTRACT NAME & No: Gatwick Stream Flood Attenuation Scheme PRINCIPLE CONTRACTOR: VolkerFitzpatrick Ltd. METHOD STATEMENT TITLE: Gatwick Stream Re-alignment and Diversion AUTHOR: Adewale Adenigbagbe DATE PREPARED: 02/07/2013 REVISION No: 000032 Contents 1.0 Contract details ................................................................................................................. 2 2.0 Scope of work.................................................................................................................... 2 3.0 Technical information / reports........................................................................................... 2 4.0 Working methods / sequence of work ................................................................................ 3 4.1 Permit to Work System ...................................................................................................... 3 4.2 Engineering Control ........................................................................................................... 4 4.3 Location of Services.......................................................................................................... 4 4.4 Earthworks for the Gatwick stream re-alignment and construction of new embankment ... 4 4.5 Riparian Planting ............................................................................................................... 5 4.6 Walkover Survey .............................................................................................................. 5 4.7 Electro-fishing.................................................................................................................... 6 4.8 Translocation of existing Gravels ....................................................................................... 6 4.9 Stream Diversion ............................................................................................................... 7 5.0 Access and egress arrangements ..................................................................................... 9 6.0 Traffic Management ........................................................................................................... 9 7.0 Lighting arrangements ....................................................................................................... 9 8.0 Plant and equipment ........................................................................................................ 10 9.0 MAterials ......................................................................................................................... 11 10.0 Third party safety ............................................................................................................. 11 11.0 ENVIRONMENTAL .................................................................................................................. 12 12.0 Housekeeping ......................................................................................................................... 13 13.0 HEALTH, SAFETY AND WELFARE ........................................................................................ 14 14.0 Emergency procedures ............................................................................................................ 14 15.0 SUPERVISION AND MONITORING........................................................................................ 15 16.0 TRAINING AND CERTIFICATION ......................................................................................... 16 17.0 APPENDICIES ....................................................................................................................... 17 17.1 Training certification ................................................................................................... 17 17.2 Plant/equipment certification ....................................................................................... 17 17.3 Risk assessments generic/site specific ...................................................................... 17 17.4 COSHH assessments ................................................................................................... 22 17.5 Method Statement Briefing Sheet ................................................................................ 23
Transcript
Page 1: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 1 of 24

CONTRACT NAME & No: Gatwick Stream Flood Attenuation Scheme

PRINCIPLE CONTRACTOR: VolkerFitzpatrick Ltd.

METHOD STATEMENT TITLE: Gatwick Stream Re-alignment and Diversion

AUTHOR: Adewale Adenigbagbe DATE PREPARED: 02/07/2013 REVISION No: 000032

Contents

1.0 Contract details ................................................................................................................. 2

2.0 Scope of work .................................................................................................................... 2

3.0 Technical information / reports ........................................................................................... 2

4.0 Working methods / sequence of work ................................................................................ 3

4.1 Permit to Work System ...................................................................................................... 3

4.2 Engineering Control ........................................................................................................... 4

4.3 Location of Services.......................................................................................................... 4

4.4 Earthworks for the Gatwick stream re-alignment and construction of new embankment ... 4

4.5 Riparian Planting ............................................................................................................... 5

4.6 Walkover Survey .............................................................................................................. 5

4.7 Electro-fishing .................................................................................................................... 6

4.8 Translocation of existing Gravels ....................................................................................... 6

4.9 Stream Diversion ............................................................................................................... 7

5.0 Access and egress arrangements ..................................................................................... 9

6.0 Traffic Management ........................................................................................................... 9

7.0 Lighting arrangements ....................................................................................................... 9

8.0 Plant and equipment ........................................................................................................ 10

9.0 MAterials ......................................................................................................................... 11

10.0 Third party safety ............................................................................................................. 11

11.0 ENVIRONMENTAL .................................................................................................................. 12

12.0 Housekeeping ......................................................................................................................... 13

13.0 HEALTH, SAFETY AND WELFARE ........................................................................................ 14

14.0 Emergency procedures ............................................................................................................ 14

15.0 SUPERVISION AND MONITORING ........................................................................................ 15

16.0 TRAINING AND CERTIFICATION ......................................................................................... 16

17.0 APPENDICIES ....................................................................................................................... 17

17.1 Training certification ................................................................................................... 17

17.2 Plant/equipment certification ....................................................................................... 17

17.3 Risk assessments generic/site specific ...................................................................... 17

17.4 COSHH assessments ................................................................................................... 22

17.5 Method Statement Briefing Sheet ................................................................................ 23

Page 2: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 2 of 24

1.0 CONTRACT DETAILS

• Name & address of site where works being undertaken: VolkerFitzpatrick Site Office, Land North of Radford Road & East of the Railway Line, Tinsley Green, Crawley, West Sussex, RH6 0HA

• Subcontractors name address and contact details VolkerFitzpatrick Ltd. Hertford Road Hoddesdon Hertfordshire EN11 9BX 01992 305000

• Subcontractors Health & safety advisor address and contact details Phil Douce VolkerFitzpatrick Ltd. Hertford Road Hoddesdon Hertfordshire EN11 9BX 07826 914707

• Date of commencement on site 26/04/2013 (as detailed on the F10)

• Duration of work 49 weeks

• Working hours 08:00 – 13:00, Saturday 08:00 – 18:00, Monday to Friday.

2.0 SCOPE OF WORK

Give a brief description of the scope of works covered by this method statement This Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing Gatwick stream including the connection of the existing alignment to the new section of Gatwick stream. It also includes the planting works to the new stream and ecological works required during silt translocation and diversion works. This excludes landscaping and top soiling operations. The majority of the equipment, plant and labour will be provided by PJ Brown during the main excavation, the level of resources will be based on the programme requirements. Management of the works will be by VolkerFitzpatrick.

3.0 TECHNICAL INFORMATION / REPORTS

Other documents which are relevant to the development of the method statement:

Page 3: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 3 of 24

The following documents may be used by the Engineer when setting out and surveying:

Construction drawings Utility drawings Underground service drawings Ground contamination reports CBR data Trench support design Detail any on site monitoring requirements Noise Noise survey points will be erected around the site and samples collected for analysis. Results will be reported to VFL/GAL for information and action where required. Where identified, noisy works RAMS will specify the requirement for hearing protection. Works areas will have noise warning signs erected. Vibration Equipment to be used will be assessed and vibration levels and working limits will be briefed to users. Where identified, RAMS will specify the requirement for HAVs protection. Air sampling Air sampling points will be erected and samples collected for analysis. Results will be reported to VFL/GAL for information and action where required. Health surveillance The GAL Occ. Health Nurse will be available for Health Surveillance and testing on request. VFL Occ. Health Nurse will visit site regularly to perform random D&A testing.

4.0 WORKING METHODS / SEQUENCE OF WORK

4.1 Permit to Work System

A permit to dig will be requested by Browns and issued by VFL for all earthworks activities, and will be in accordance with the GAL Permit to dig Procedure. The permit will be issued prior to any works being carried out and will include all relevant details and limitations to the works to be undertaken. A sketch or drawing, with all services identified and marked, together with details of protective measures in place, will be attached and issued with the permit to dig.

All existing services, installations, boundaries and known hazards likely to be affected by the works will be located, marked and protected by VFL, who will also liaise with all statutory authorities, Gatwick Airport Ltd - GAL and other service providers as necessary.

The permit to dig will be issued and copied to the Foreman / Supervisor responsible for the works, with additional copies issued to all operatives involved in carrying out the works. The work areas will be walked and the activities covered by the permit will be discussed and explained in order that everyone involved will be aware of the limitations and content of the permit to work. If the works are disrupted or suspended for any significant period of time, then on return the existing permit will be reviewed, and a new permit issued if necessary, to take into account any change in circumstance that may have occurred during any such suspension of the works. The Daily Task Briefing will ensure that all permits to work have been checked and are current. If buried services are encountered during the process all operations will cease and GAL staff will be informed. The services will be recorded and identified if possible. GAL will advise as to the course of action. If the service is damaged then all personnel will retreat to a safe distance and GAL staff will be informed of the occurrence and actions taken as defined in the GAL site procedure.

Page 4: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 4 of 24

All services encountered on site are to be considered ‘Live’ until instructed otherwise by the GAL Manager.

4.2 Engineering Control

Engineering control (setting out) will be carried out by VFL Site Surveyors and Site Engineers. The control for the excavations will be provided by the use of batter rails and, profile boards and travellers. Excavations and fill areas will be by way of slope rails set at 20m centres and profiles set at 10m center for formation trimming. In addition, plant may be equipped for use with laser or GPS control for line and level. All relevant information including chainage, offset and details of traveller to be used will be shown on the setting out (written on batter rail/profile board) by the site engineer. Primary and secondary survey control stations will be checked and established by the VFL Senior Land/Engineering Surveyor. Tertiary Control Stations will be established and checked by VFL Surveyors and these stations will be checked by the Senior Land/Engineering Surveyor. Temporary Stations will be established by VFL site engineers but will not be used until the VFL Land/Engineering Surveyor has checked and approved the station for use.

4.3 Location of Services

Existing services, manholes and structures will be located, identified, marked and protected where necessary prior to the commencement of work by VFL. Compliance with any special requirements and documented safety advice from public utility companies, VFL and GAL. Information on retained services must be recorded and the service drawings updated centrally and locally (a copy must be retained on site).

4.4 Earthworks for the Gatwick stream re-alignment and construction of new embankment

The new stream will be excavated in three main phases, with the tie-ins completed last of all, when the existing river is ready to be diverted. Each phase will be as follows, commencing 8 metres away from the existing stream. (See marked – up sketch of excavation / embankment p hases in sections as below – page 7.) The vegetation and topsoil will be stripped from the works area in advance of the main excavation. A permit to dig will be issued by VFL and the area will be set out by the principle contractor as follows – the foul main exclusion zones will be established and marked. The tree protection areas (if any) will also be established and marked. Areas of the existing stream banks that potentially contain Himalayan Balsam seed will be marked on site. The areas of existing Himalayan Balsam seed banks that fall within the new stream embankment will be stripped first, set aside in designated quarantine zones (in areas adjacent to the north of the new stream area), fenced off and clearly marked with signage. Once these areas have been cleared the equipment will be thoroughly cleaned prior to the remainder of the areas being stripped and set aside for re-use. The edge of the excavation will be marked and batter rails provided for excavator and banksman to work to. A laser level will also be set up by the site engineer to enable work to a rough surcharge level. A GPS guided dozer will also be employed where practical to do so. During the topsoil and subsoil strip, areas that require an archaeological watching brief to be in place will be arranged to suit. Where the banks of the channel are required to be raised above existing ground level, suitable site-won material will be spread and compacted in layers in accordance with the engineer’s specification. The area to be raised will be overfilled by at least 1 metre in width, to ensure full compaction to the edges, and it will then be cut back to the required profile as described below. The new embankment is approximately 30 metres wide at the top with profiled stream banks and a meandering stream channel contained within it. A 360 degree excavator will be located in the middle of the new stream embankment, and excavate the clay to the required profile. The new river banks vary in gradient throughout the length of the channel, and so depending on the circumstances, the channel will

Page 5: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 5 of 24

either be dug to the required profile using batter rails and a 360 excavator, or where practical (i.e. not too steep) it may be possible to use a GPS guided dozer. Excavated materials to be used as fill in the permanent works will be end tipped (dump truck) or bottom dumped (scraper) onto the fill area. The materials will then be spread and levelled in loose layers, using tracked dozers, to a depth that, after compaction, will not exceed the depth that is specified for the particular item of compaction equipment. Each layer will then be compacted using appropriate self-propelled / towed / smooth drum / tamping (sheep’s foot), deadweight or vibrating rollers or any such combination suitable for the material classification and rate of deposition and in accordance with the contract specification requirements. On completion of each compacted layer, compliance testing will be carried out to confirm that the specified material density has been achieved. Placement and compaction of fill will continue as described above until the line and level of the fill has been achieved. Fill areas will generally be overfilled (300mm summer – 600mm winter) to leave a weather protection layer in place prior to formation preparation.

Whenever fill is to be deposited against the face of a natural slope, or sloping earthworks face, such faces shall be benched immediately before placing the subsequent fill. Excavation within the foul main exclusion zone will, in the most part, be carried out using an excavator working from outside the exclusion corridor. However, it will be necessary to cut the batter using an excavator sitting at right-angles to the stream and therefore the excavator will need to sit above the existing sewer pipes at times in order to do this. It may be considered by the engineer that the large surface area of the tracks, spreads the excavator’s weight sufficiently for no additional measures to be put in place. If not, then protection platforms for the excavator to sit on will be provided (constructed to the same specification as the lorry and plant crossing points – i.e. sleepers). Trial holes to confirm the depth of the foul mains will be carried out in advance. It is assumed that the crown of the foul mains is at least 1m below the new river bed.

4.5 Riparian Planting The new stream banks will be cut into newly compacted and existing clay, the stream channel and stream banks will not receive topsoil. Only the outer banks embankments and slopes will receive topsoil. The planting areas for plant mixes A and B will be demarcated along the newly constructed channel, using wooden stakes. Whilst the planting areas are being demarcated, the average water level along the channel will also be marked out. This will help to aid with the planting of the marginal plug species. The anti-bird fencing will be installed as per the Stream Plug Planting Proposals plan, with intermediate fencing posts installed on opposite banks at appropriate intervals. Blue rope will have flutter tape attached to it before being attached to the intermediate fencing posts with fencing staples. Plants will be put in place as per the Stream Plug Planting Proposals Plan, with individual species planted according to their specific requirements e.g. marginal species will be located adjacent to the water’s edge, with less tolerant species planted higher up the bank. Plants will be planted using a spade or dibber, with a ‘V’ trench created. The plant will be taken out of its container and placed into the sediment, with the soil lightly compacted around it. Once the riparian planting has been completed, the area above the average water level will be hydro-seeded with the riparian meadow mix at a rate of between 5-6 g/m2. Once the hydro-seeding has been undertaken, no machines will be allowed to work within the area, until it has become established. The hydro-seeding will be undertaken after the completion of existing gravel translocation works to ensure the areas are not damaged during these works. Once planting has been undertaken the planted areas will be regularly watered with a fine spray to ensure that the new plugs and plants remain moist and do not dry out or die off prior to the diversion of the existing steam. If necessary the watering of these newly planted areas will continue until the new plants have properly established themselves.

4.6 Walkover Survey

Page 6: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 6 of 24

Due to the spawning season for brown trout commencing in late autumn, a walkover survey be conducted prior to electric fishing to ensure minimal impact on fish. Two staff members will follow standard methodology to assess the habitat of the 600m section of the existing Gatwick Stream.

The site will be divided into 300m sections for this survey. Any significant structures or discharges impacting on the site will be recorded. Following this survey and onsite discussions, a stop-net and trash screen will be located upstream from the proposed tie in at section 1 on the attached map below. The trash screen will consist of heavy-duty weld mesh or similar, and will be installed directly upstream (+-5m) of the stop net. The trash screen will be inspected on a daily basis and emptied of any accumulated debris. In addition, a stop net will be located downstream of the works. This will be placed downstream from the proposed flow control structure, but upstream of the sewage outlet. This net will ensure that the area remains inaccessible to the fish. This stop net will consist of fine mesh and will be used to segregate the river system prior to the electrofishing exercise. The stop net will be appropriately secured to prevent fish entry. The net will be inspected on a regular basis. At this point, the necessary EA FR2 Fishery consents will be applied for and will be in place prior to any electrofishing exercise being undertaken.

4.7 Electro-fishing

Electrofishing will only take place in suitable conditions i.e. where the water levels are ~1m-2m in height. We will use standard electro-fishing methodology and use boat mounted pulsed DC electric fishing equipment (3Kw Generator, Electrafish <10amp Pulsed DC Control box, 2 x 400mm anodes, 2 x3m cathode).Water conductivity/Dissolved Oxygen/Conductivity would be tested before selecting appropriate settings on the electric fishing kit. Multiple runs will be carried out throughout the 600m section and remove as many fish as possible into on-board aerated tanks. The fish will then be transferred into tanks mounted on an off-road vehicle and taken downstream or upstream to be released. Suitable areas are to be agreed with the Environment Agency. If there is a possibility of over-stocking the existing habitats (upstream or downstream) the Environment Agency will assist in the relocation of the electro-fished stocks to a suitable and sustainable location identified by the Environment Agency. Following the completion of the tie-ins, the excluded stream areas will be monitored for signs of fish, with additional electrofishing exercises taking place if needed, to relocate any remaining fish up-stream or downstream of the excluded stream channel, to locations previously agreed and assistance provided as necessary by the Environment Agency.

4.8 Translocation of existing Gravels Prior to the silt and gravel excavation and translocation exercise, a detailed tool box talk will be given to the machine operators, outlining the methodology and associated ecological risks. An emphasis will be placed on minimising bank damage and ensuring that appropriate biosecurity methods are in place. A silt curtain will be installed (+10m) from the downstream stop net or as required to prevent any silts from migrating downstream and entering the Gatwick stream during translocation and diversion activities. The excavation of the existing gravels will be under the supervision of an experienced ecological clerk of Works. The existing gravels will be placed at locations as agreed by the Environment Agency, into the newly constructed channel and will be allowed to settle and will remain wetted, prior to the tie-in works being undertaken. Suitable gravels from the existing stream will be excavated using the bucket of a 360 degree excavator, which will sit alongside the stream. The gravel will be loaded into a 6 – 9 tonne dumper and driven to the new stream where it will be deposited at agreed locations i.e. shallow riffle sections. Where the distance between the existing stream and the new stream location within the re-aligned stream is short, the excavator will track between the two locations with the gravel in its bucket and a dumper will not be required. In deeper transition and pool sections within the re-aligned stream, the stream bed will remain as-dug as natural clay and over time, these areas will silt-up naturally. The existing gravels translocated to the shallower riffle sections, will not be placed uniformly in the new stream channel but will be sloped to allow a natural channel to form through the riffle sections during low flow periods. This will also aid in the free passage of fish through these shallow areas during low flow conditions. During the translocation and placement of gravels the Environmental Agency will be in attendance to offer advice on the location and shape of the low flow channels formed through the riffle sequences.

Page 7: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 7 of 24

4.9 Stream Diversion The tie-ins will be completed by reducing the “plug” from 8 metres long to 1 metre long, or of sufficient length to ensure bank stability and to safeguard against any seepage into the new channel from the existing stream. These reduced sections will be planted and have existing silt placed in them prior to the final diversions taking place. At the time of the final diversion works, the excavations shall be carried out in such a way as to allow for a controlled, steady flow of water into the re-aligned route. The final 1 metre section will be dug down and shaped to just above the top of the river water level and then the last section below the water level will be dug out using the excavator. The tie-ins will be completed from down-stream to up-stream, so that the water can back up into the new channel and be allowed to settle prior to the excavation of the up-stream ‘plug’ which would then allow the controlled flow of water directly into the new channel. The in-filling of the existing stream will be undertaken from the up-stream end to the downstream end of each section, so that the existing stream can be properly drained down prior to being sealed off at both ends, from the new stream channel.

Page 8: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 8 of 24

Sketch of stream re-alignment excavation/embankment phases in sections

Page 9: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 9 of 24

5.0 ACCESS AND EGRESS ARRANGEMENTS

Site access and egress will be communicated at site induction and on Site Plans which are updated regularly and placed onto site notice boards. The Site Plan will detail the locations of pedestrian routes, vehicle and plant routes, welfare facilities, lighting and emergency equipment. The Thames Water shared access road must be kept clean and clear at all times. There will be no left turns onto Radford Road. Chapter 8 traffic signals and road signage will be in place during the works. Signage will be observed and due regard made to the presence of other road users, particularly at junctions. All haul routes and access ramps must be co-ordinated by PJ Brown and approved by VFL. Haul roads between excavation and deposition areas will be developed taking the shortest direct and even grade route wherever possible. They will be constructed on existing terrain and/or made up using materials arising from the excavations if suitable. Continued trafficking and grading (and wetting) of haul roads will eventually, depending on season and materials used, produce a stable polished surface of low rolling resistance that will, if properly maintained, give good service to dump trucks and other site traffic. Wherever possible haul roads will be for the exclusive use of earthmoving plant, however if other site traffic cannot avoid travelling on such haul roads, priority and right of way must be given to heavy plant. Unauthorised parking of vehicles and storing of materials on haul roads create safety hazards, blind spots and will be rigorously controlled. Where site roads are shared and heavily trafficked by other vehicles including delivery lorries and vans, personnel vehicles, mobile cranes and the like, earthmoving plant will be subject to the same site traffic regulations as the other road users, not least speed limits and priority at junctions.

6.0 TRAFFIC MANAGEMENT Main risks and consideration include the following:

• Segregation of personnel • Pedestrian crossing points • Vehicle crossing points & control. • Impact on the local environment. • Vehicle parking & Maintenance. • Haul route maintenance.

7.0 LIGHTING ARRANGEMENTS

Where permitted, any work activities that continue at dusk, when dark, or in unlit areas, will be illuminated by tower lights installed in fixed positions around the site and all plant and equipment lighting will be operational, clean and maintained. Extra tower lighting will also be installed as required around works areas. See site plans. Working procedures will be modified or adapted to take into account additional hazards created by working under artificial light and at night. Intrinsically safe lighting will be required for any Confined Space access. Emergency lighting will be detailed in the Site Fire Plan for the welfare facilities.

Page 10: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 10 of 24

8.0 PLANT AND EQUIPMENT

Main items of plant

• Van/Truck • 3600 tracked excavator • ADT 25T tracked excavators. • Compactors • Electrofishing apparatus • Boats • Nets, • Tractor and landscaping implements, • Hydroseeding pump • Spades • Drills.

Ancillary plant & equipment

• CAT/Genny Scanners. • Rotating Laser & Tripod. • Levelling Staff & Pogo. • GPS. • Dumpy Level & Tripod • Profile boards • Pegs • Sledge hammer • Spray paint

8.1 PPE:

As a minimum the following PPE is to be worn: • Hi-visibility upper body clothing with reflective tape which complies with BS EN 471:2003 class 2 • Safety Helmet which complies with BS EN 397:1995 • Safety footwear which complies with BS EN ISO 20345:2004 and provides support to the ankle, mid-sole

protection and has a covered steel / Kevlar toe cap. • Hand protection that conforms to EN388 intermediate design; minimum protection cut resistant 3 required • Eye protection, safety glasses that conform to EN166, 1.F • Where persons are exposed to working in inclement weather conditions, protective equipment that

complies with BS EN 343: 2003 Class 3, 3 shall be provided. • VFL require all personnel to wear Hi-visibility upper and lower body clothing with reflective tape which

complies with BS EN 471:2003 class 3

8.2 Task Specific PPE: • Gloves (EN 420-rigger type when handling slabs / concrete) • Ear protection (EN 352-2) must be worn when using the cutting saw (85dBA) or breaking out concrete,

drilling holes on concrete • Dust Masks (EN149 FFP3D) must be worn by operatives working in the immediate vicinity of Hazardous

Waste and during cutting works. • Disposable overalls must be worn by all operatives who come into contact with the contaminated ground. • For Confined Space Entry PPE required will be gloves, disposable coveralls where there is contamination

(e.g. Foul drainage), harness & lanyard, hard hat, eye protection and boots.

Page 11: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 11 of 24

• Other specialist PPE e.g. Fire retardant coveralls, breathing apparatus, welding masks, respiratory protection, gloves, eye protection, harnesses and lanyards will be task specific.

• Face fit testing for respirators must be certificated and a copy given to VFL for filing. Test certification for all other PPE must also be copied and filed.

• PPE users will be inspected by the user for damage before use. • All PPE will be stored on site and will not be taken home for cleaning in case of cross contamination. • Details of training in the use, care & storage of PPE will be as per manufacturers recommendations

9.0 MATERIALS

• Wooden stakes & Profile boards (FSC approved or recycled timber) • Pegs • Sledge hammer • Spray paint • Topsoil and sub soil striped from site works will be re-used on site, unless found to be contaminated.

9.1 Arrangements for transportation, delivery schedule, storage and disposal • Materials will be transported to site locations by a site vehicle. • Segregated covered skips shall be provided with appropriate signage to allow the recycling of wastes. • The topsoil and sub soil stripped from site works shall be separately stored in the site compound until

needed for future works. • Any excess top soil or sub soil shall be removed off site by a designated sub-contractor and take to an

agreed site for disposal. • All materials shall be stored either in a safe designated area of the site compound or safely inside the site

store cabin. • Deliveries of any materials shall be between the site working hours: Monday to Friday 08:00 to 18:00.

10.0 THIRD PARTY SAFETY

Works areas will be fenced off where practicable, or buntings will be placed with warning signage particularly where heavy plant operations are taking place. Waterside access will be fenced off with warning signage erected, and life rings in place at regular intervals along the water’s edge. Ladders and access equipment will be removed and stored in a secured area. Exclusion zones

• Working areas Where practicable working areas will be fenced off (e.g. Manholes will have crowd barrier type fencing erected around them whilst opened by Engineers for inspections).

• Waterside All access to waterside will be restricted by fencing erected a meter away from the water’s edge. Signage will be in place warning that access permits are required.

• Bat roosts An exclusion zone will be erected to prevent access and disturbance of Bat roosts.

• Tree roots A fenced off exclusion zone will be erected to prevent damage to trees and roots.

• Foul mains Foul Mains will be protected with fencing to prevent plant from tracking over and causing damage. Installation of temporary barriers, covers, screens

Page 12: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 12 of 24

Lasers will be set so they don’t dazzle other personnel on site or aircraft, and will be switched off when not in use. Signage

• All site specific signage required shall be erected around the site compound and works areas as necessary. • All traffic management used on the road shall comply with chapter 8 and shall be checked daily.

Isolations

• No site works shall intrude into the exclusion zones of any live services until the service / asset owners will have been informed and the appropriate isolations have been put into effect. Noise / vibration

• Equipment to be used will be assessed and vibration levels and working limits will be briefed to users. Where identified, RAMS will specify the requirement for HAVs protection.

• Noise survey points will be erected around the site and samples collected for analysis. Results will be reported to VFL/GAL for information and action where required. Where identified, noisy works RAMS will specify the requirement for hearing protection. Works areas will have noise warning signs erected. Dust / fumes

• Dust and fumes will be suppressed using water suppression or filtration as required. • The appropriate control measures and PPE shall be in place, supplied and worn with any work activity

that has the potential to create dust or fumes. • Water bowsers will be used to suppress dry soil dust created on site. • Works will be carried out in an open well-ventilated area where possible, or a specific risk assessment will

be made for the task. Hazardous substances

• All substances will be secured into a COSHH or GAS cage with appropriate signage and spill/fire equipment installed.

• Some site works shall be carried out in close proximity with a foul main the appropriate PPE shall be supplied and worn at all times and the correct contamination procedures put in place.

11.0 ENVIRONMENTAL

Ecology- i.e. protection of flora, fauna or protected sites • No work is to be carried out before an Ecological survey has been carried out and a Certificate

issued by EA stating that no species or habitats protected by law have been found within the particular area of site being worked on at the time.

• There will be exclusion zones for site works around bat roosts and tree roots to ensure no damage is caused.

• Care will be taken to ensure no contaminants are introduced to the site and the Gatwick stream for the duration of the site works. Waste- i.e. what are the arrangements for onsite storage of waste and what are the arrangements for the removal of waste? (All other Duty of Care and waste management details to be included in the SWMP- EMS 03 Site Waste Management Plan)

• All waste water shall be removed from site and taken to the appropriate treatment plant by the designated / approved sub-contractor. Water - i.e. are there controlled waters likely to be impacted by the work activities. What controls are in place?

• The redirection of the Gatwick Stream will be a part of the works.

Page 13: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 13 of 24

• Fencing will be erected a metre away from the water’s edge and all personnel will only be allowed access with a permit. Noise / vibration- i.e. Is there a Section 61 Consent in place? Specify any conditions

• All construction works are to work away from the Oldlands Farm House • Vehicles are not allowed to turn left onto Radford Road • Shared Thames Water access road to be kept clear at all times • No working outside of site hours without consent

Archaeology- i.e. protection of historic and built heritage. Are there any Scheduled Monuments or Listed Buildings affected by the works?

• No work shall be carried out in areas identified as having special archaeological interest until such time as the archaeological survey/recording works have been completed and Certificates issued.

• Archaeologists on site and will be organising hand trial pit digs and also supervising excavations on site. • Separate RAMS will be provided for Archaeology works.

Dust/ emissions/ odour- i.e. are there any sensitive areas affected by these nuisance items? What controls are in place?

• Air sampling points will be erected and samples collected for analysis. Results will be reported to VFL/GAL for information and action where required.

• The GAL Occ. Health Nurse will be available for Health Surveillance and testing on request. • VFL Occ. Health Nurse will visit site regularly to perform random D&A testing.

Contaminated land- i.e. has contaminated land been identified? Are there specific working requirements such as its excavation, storage and removal?

• The sub soil surrounding the foul main shall be treated as contaminated waste due to evidence on ground surface of the foul main backing up. Appropriate measures shall be put in place to ensure its safe removal and treatment off site.

• Any other contaminates identified will be reported to GAL and removed on agreement. Fuel and chemical storage- i.e. are there specific areas for refuelling during working activity? Have sensitive areas such as watercourses, groundwater source protection zones and protected sites been identified with appropriate controls in place?

• There shall be a double bunded fuel bowser stored within an extra bunded area inside the site compound for refuelling of plant during the working day. A spill kit and the appropriate fire fighting equipment shall be placed securely next to it on the fuel bowser.

• A mobile double bunded bowser will be manoeuvred around site to refuel plant where required. Refuelling will not take place at least 10m near to riverside. A drip tray, spill kit and the appropriate fire fighting equipment shall be kept with the fuel bowser and deployed as required for refuelling.

• The river shall be adequately protected with exclusion zone fencing and signage.

12.0 HOUSEKEEPING

Specify any requirements for the storage of materials, plant and equipment

• All materials shall be stored safely and neatly within the designated zone in the site compound or inside the site store cabin.

• All Plant shall be stored safely and neatly at the end of the working shift inside the designated area at the site compound.

• All equipment shall be stored safely and neatly in the designated area within the site compound or in the site store cabin. Any equipment that uses diesel or petrol shall be stored on top of drip trays and have spill kit and fire equipment in place nearby.

• A Wheel wash will be installed at the site exit so mud and debris will be cleaned off vehicles before they leave site

• A Road Sweeper will be organised to regularly clean public roads affected by site vehicles and plant.

• What frequency will clearing and tidying of work areas take place

Page 14: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 14 of 24

• All Operatives on site shall be informed of the importance/urgency of good housekeeping during the mandatory site induction. This will ensure that the work areas are kept necessarily clean during works to maintain a safe area.

• A cleaner will be employed to clean the welfare facilities and office daily.

13.0 HEALTH, SAFETY AND WELFARE

Detail welfare provision for the workers under your control

• Welfare facilities including a canteen, drying room with lockers, shower, and a smoking area will be provided.

• Hot running water and tea/coffee making facilities will also be supplied and a microwave for heating / cooking food will also be provided.

Detail first aid arrangements for the workers under your control

• First Aid kits and eye wash will be deployed at the site offices, at specific Safe Haven points around site, and will also be kept in site vehicles.

• First Aiders will wear First Aid stickers on their hard hats to identify them.

• 13.1 Health and Safety Inductions

All personnel to undergo VFL/GAL site safety induction. The details of this site induction are detailed in the Construction Health & Safety Plan. Any construction activity must be carried out in accordance with current Safety Legislation and Regulations, Company Health and Safety Policy. Every task or operation must have a recorded Risk Assessments and a safe method of work established in the form of a method statement, task sheet. Access to the working areas will be prohibited to all non-essential personnel, and a competent foreman / ganger will be in attendance supervising the section of works under their direct control.

14.0 EMERGENCY PROCEDURES

Details as applicable for dealing with any foreseeable emergencies arising from the work covered by the method statement:

In the case of an emergency the following procedure will be adhered to:

All accidents or incidents must firstly be reported to a senior member of the VFL Site Team:

GIVING THE PRECISE LOCATION AND DETAILS OF THE SITU ATION AND ANY INJURIES SUSTAINED.

WHILE AT ALL TIMES REMAINING CALM, SPEAKING SLOWLY AND CLEARLY TO AVOID CONFUSION

THUS SAVING VALUABLE TIME

In turn the member of the VFL Site Team will call

GAL on 01293 501222

The VFL site team will then follow the GAL 0-60 emergency communications process and notify the GAL Project Manager within 60 minutes.

VFL First Aiders

(Names and photos will be erected on to site H&S notice boards)

Page 15: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 15 of 24

Nearest 24hr A&E Department:

Redhill Hospital, Canada Avenue, Redhill, Surrey RHI 5RH Tel: 01737 768511

For maps showing directions to the Hospital see site H&S notice boards.

Fire

• When fire alarms are sounding all personnel will leave offices and welfare facilities and go to Fire Assembly Points located around site. UXO

• Treat as fire alarm, report emergency and go to Fire Assembly Points when found. • Rescue from safety nets – N/A • Rescue for operatives suspended in harness and lanyard – N/A

Rescue from deep excavations • Treat as confined spaces.

Rescue from confined spaces

• Top Man will make emergency call to VFL as above. • Top Man to then winch out personnel as per Confined Space training.

Rescue from water • Person on riverbank to make emergency call to VFL as above. • Life Ring to be tossed by person on riverbank into river slightly upstream from person’s location • Person on riverbank then to sit down and pull life ring lanyard back to shore • All persons rescued from water to be treated by Emergency Services • Note: Weils Disease is a notifiable condition

Spillages • VFL Spillage procedures EMS-09 to be followed. See attached.

• Adverse weather conditions • Weather checks will be prior to works commencing and works planned accordingly. • No lifting in high winds. • VFL management will monitor site conditions continuously. • High water levels will be monitored.

Communications:

Land line – N/A Mobile phone

• Mobile phones are only permitted to be used on site within ‘Safe Haven’ and welfare areas. • Mobile phones will not be used whilst operating plant or vehicles. • Hands free devices are only allowed to be used in vehicles and not plant.

Radio

• Walkie Talkie type radios must be GAL licensed and approved

15.0 SUPERVISION AND MONITORING

State the numbers and names of supervisors required: • There will be one VFL site Engineer on site (Brian Lavery).

Site Supervision:

• The Site Engineer Brian Lavery will have CSCS and SSSTS competence as minimum.

Page 16: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 16 of 24

Details of health & safety monitoring they will carry out • Daily ‘High 5’ inspections of site (HSE-37)

Site safety inspections to be undertaken • Weekly site inspections will be carried out by the VFL site management team which will be rostered (HSE-

06). • 4 Weekly site inspections are planned by the regional H&S Manager, Environmental Manager and Quality

Manager. • Monthly site inspections will be carried out by Subcontractor H&S Managers • Quarterly audits will be carried out by the regional H&S Manager, Environmental Manager and Quality

Manager.

State whether visits by safety advisor / manager are programmed • Weekly site visits planned by the Safety Advisor. • 4 Weekly site visits are planned by the regional H&S Manager. • Monthly site visits will be carried out by Subcontractor H&S Managers • Quarterly visits will be carried out by the VFL Director.

Tool box talk (TBT’s) arrangements:

• TBT’s will be issued weekly and signatures collected for all briefed. Permit to work arrangement e.g. permit to dig, permit to lift, hot works permit

• All the necessary permits for any site works shall be issued and briefed to the entire workforce involved with signatures collected before the relevant works are allowed to be carried out.

• GAL P2W system to be used by VFL Permit Coordinator

16.0 TRAINING AND CERTIFICATION

Detail the general levels of training / competence required to carry out the work The Engineer carrying out the works will be assessed by their direct manager to ensure that they have the appropriate site experience and competence required for the task at hand.

Detail any specialist training required

• Explosive training • CAT & Genny training specific for the equipment used • Confined Space Entry Training • All other training requirements will be identified and organised as required.

Details of how the above will be demonstrated • All subcontractors and personnel entering site will be required to demonstrate competence at induction

and when applying for permits, and shall supply a competence matrix for all staff on site. • CSCS (and other approved cards schemes) shall be carried on site at all times, and available for

inspection. Spot checks on cards will be made during site inspections and audits. Only trained, certified personnel to operate plant on site Plant operators will request a permit (HSE-23) at site induction. CPCS (and other approved cards schemes) will be required for inspection before the permit is authorised and the cards shall be carried on site at all times, and available for inspection.

Page 17: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 17 of 24

17.0 APPENDICIES

17.1 Training certification

CSCS, CPCS, CISRS, CCDO, ESS, ARCA, FASET, IPAF, JIB, PASMA, NRSW, Confined spaces, Abrasive wheels, Hilti guns etc.

Copies of all competencies will be kept with induction records.

17.2 Plant/equipment certification

LOLER (test and thorough examination), calibration certificates

Copies of plant and equipment certification will be kept on file in the VFL site offices

• Lifting Plans will also be kept with certification. • Daily inspections will be carried out by all plant and vehicle operatives and recorded. A copy of the plant

certification, Lifting Plan and daily checks will be kept in a folder with each item of plant for inspection.

17.3 Risk assessments generic/site specific

Must cover all significant workplace risks as required by regulation as applicable, list not exhaustive:

• Manual handling • PPE • Work equipment • Lifting operations – N/A • First Aid • Noise • Vibration • Asbestos – N/A • Lead – N/A • Work at height • Excavations • Work adjacent to or over water • Demolition / dismantling of structures – N/A • Falls of materials • Site traffic & pedestrian safety • Weils disease • Ladders • Vehicle access to site • Engineers Setting Out & Surveying • UXO • Lone working • Working in low light/darkness

Page 18: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 18 of 24

Business Unit: Civils Contract No & Name: Gatwick Stream Date:05/07/2013

Risk Evaluation: Risk Level = Severity x Probabili ty Severity Score X Probability Score = Risk Rating Score

Date Initial Assessment: 05/07/2013 1 Minor Injury – cuts and bruises

2 Minor Injury – Sprains and Strains

3 Temporary Disability – Fracture

4 Permanent Disability – Loss of limb

5 Fatality

1 Improbable 2 Low

3 Medium

4 High

5 Almost certain

Low risk (L) – 1 to 9

Medium risk (M) – 10 to 19

High Risk (H) – 20 to 25 Date last revision:

Written by: Adewale Adenigbagbe

Risk Assessment No: RA-000032 Activity : C11152 – Gatwick Stream Re-alignment & Diversion Location: Gatwick Stream

Item

No.

Activity Identified Hazard Description Who is at Risk

Sev

erity

Pro

babi

lity

Ris

k R

atin

g

Control Measures

Residual Risk

Sev

erity

Pro

babi

lity

Ris

k R

atin

g

1 Leptospirosis.

Contact with animal urine / animal droppings or sewerage containing unknown chemicals and biological hazards such as

Site Personnel

4 3 12

• Follow good hygiene procedures, • Wear rubber gloves etc. • Wash hands /use antiseptic wipes before eating or smoking. • Thoroughly clean and cover any cuts/seek medical care as

required & carry a Leptospirosis Card.

4 1 4

2 Slips, trips and falls Tripping on uneven ground or over obstructions

Site Personnel & Visitors 4 2

8

• All operatives to wear steel toe capped boots or equivalent (Kevlar) Suitable footwear and regular cleaning and clearing of waste.

• Select the correct type of stone gradient for footpaths to enable a tighter compaction. • Suitable lighting throughout the site. • Handrails to any steps.

4 1 4

3 Manual Handling

Due to weight and/or awkwardness of objects being handled. Damage to health of employees due to incorrect lifting e.g. back strains, hand & arm injuries.

Site Personnel 4 2 8

• Machinery to be used at all times to carry out tasks. Tool box talks about manual lifting to be held.

• In general, any load exceeding 25 kg will be lifted mechanically. • Monitor working practice of workforce by supervisors. • Provide risk assessment. • Gloves are mandatory. • No lose clothing to be worn.

4 1 4

Page 19: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 19 of 24

4 Access & Egress from site

Damage to plant & employees health through collision of vehicles.

Site Personnel 5 2 10

• Plan, implement and control pedestrian and vehicular segregation.

• All operatives, staff and visitors to wear high visibility clothing – vests, coats etc.

• Provision of adequate space and effective barriers and signs. • Implement a one way system where possible. • Traffic Management Plan to be created & all operatives briefed. • Traffic Marshal to be in attendance where required. • Speed limits to be adhered too.

2 2 4

5 Accessing & Alighting from Vehicle Skeletal Fractures Site Personnel 4 3

12

• Use correct access point ie. Steps, • Maintain a 3 point contact with vehicle, • Do not jump from vehicle, Check ground before alighting.

• Keep boots & steps free from mud.

3 1 3

6 Working Zone Unauthorised personnel straying into operational area. Site Personnel 4 3

12

• Establish fencing around perimeter of each zone. • Monitor and review as work progresses. • Plan work sequence to ensure fencing is established before work starts

2 1 2

7 Excavation - striking underground services

Burns/ Electric Shock/ Fire/ Explosion/ Death Site Personnel 5 4

20

• Operate a permit to excavate system before any excavation undertaken.

• Services to be clearly marked out at working level. • Work Area to be CAT scanned for uncharted services. • Visually survey the area & then use CAT scan-mark findings on

the ground, Arrange for services to be isolated / re-route where possible, Hand dig within 1/2m of services following safe digging procedure.

• Consult ground investigation reports for details of contamination and remove by specialist techniques.

4 2 8

8 General Construction Duties

Operatives being struck by plant or vehicle during excavation works

Site Personnel 4 3 12

• Ensure all operatives maintain a minimum clearance of 600mm from swing radius of machine.

• Only banks man to be within proximity of machine. All personnel to make presence known to driver. • No reversing is permitted without the attendance of a banks man or alternatively a warning beacon light and sound is present.

3 2 6

Page 20: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 20 of 24

9 General Construction Duties

Debris from loading of dump trucks striking operatives/ vehicles or falling on access roads

Site Personnel / Puplic 5 2 10

• Ensure dump trucks are not overloaded. • Driver must wait until all loading is completed before pulling off. • Eye Protection must be worn at all times. • Operatives must not stand behind dump truck.

3 1 3

10 Plant Servicing Oil / Grease Leaks Site Personnel 4 2 8

• Spill kits will be available and must be used during an oil / grease spill and must be correctly disposed of after use. • This includes disposing of old oil filters empty oil tins/grease cartridges and used oil/grease/hydraulic fluid – dispose in Provided/designated COSHH bins. • If in doubt ask your Supervisor or Store man.

3 1 3

11

Refuelling of diesel generators, pumps and other ‘static’ or mobile plant.

Leakage of hydraulic oil and diesel Site Personnel 5 2 10

• All fuel tanks to be bunded. • Drip trays to be used on all static plant. • Drip trays to be maintained and emptied regularly. • Spill kits to be made available. • Ensure that an emergency procedure exists

4 1 4

12

Waste Disposal Incorrect disposal of materials Site Personnel / Puplic 4 2 8

• Contaminated waste skips to be provided • Materials to be stored away from surface water drains in a

bunded area. • Provide spill kits • Skips to be correctly labelled to segregate waste. Licensed

waste carrier to be contacted to empty skips regularly.

3 1 3

13 Working near stream Drowning Site personnel 3 2 6 • No lone working • Wear appropriate buoyancy aid • Cover cuts and abrasions

2 1 2

14 Working with pesticides Hazardous substances Site personnel 4 2 8

• Keep equipment secure and clean • Refer to and comply with product label. • Adhere to safe systems of work

3 1 3

Page 21: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 21 of 24

Additional Control Measures or Action Required Prior to Activity Commencement:

Activity No.

Control or Action Required Time Scales

Person to complete Action SM – site manager

SS – site supervisor

SO – site Operative

O – Other (specify)

Reference:

PPE:

Page 22: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 22 of 24

17.4 COSHH assessments

Assessments required for the hazardous substances to be used or are generated as a by-product of a process

COSHH data sheets for the following are attached at the end of this MS.

● Spray marker paint

● Diesel

● Engine Oil

● Petrol

● Glyphosate

Page 23: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 23 of 24

Record of briefing for those undertaking the work covered by the method statement below

17.5 Method Statement Briefing Sheet

Record of briefing for those undertaking the work covered by the method statement below

Contract No: C11025 Project: Gatwick Stream Flood Attenuation

Date of Briefing:

Method Statement Title: MS/C11025/000 – Gatwick Stream Re-alignment and Diversion.

Name (Print) Signature Company

Page 24: Construction Method Statement - · PDF fileThis Method Statement covers the earthworks for the re-alignment and diversion of a section of the existing ... Construction Method Statement

Construction Method Statement H06VF B/C use this procedure VF Rail n/a VH use this procedure VL use this procedure VS n/a VR n/a VI n/a

Issue no: 2 Date: Oct 2012 Parent document: Health and Safety Policy and Practice

Approved for IMS: IMS Manager Document owner: Head of HSEQS Workspace file: n/a

Uncontrolled when downloaded or printed Page 24 of 24

Name: Designation:

Print Print


Recommended