Construction of On-SiteStormwater Treatment andFlow Control Facilities
Dan Cloak, P.E.PrincipalDan Cloak Environmental Consulting
Topics Why do we have permanent on-
site facilities to treat stormwater? Facility designs and how they
work Operating characteristics and
errors in design and construction Draft checklist for facility
inspection
NPDES requirementsin a nutshell Minimize imperviousness Control pollutant sources Treat stormwater prior to
discharge from the site Match peaks and durations to
pre-project conditions (HMP) Maintain treatment and flow-
control facilities in perpetuity
Low Impact Development Stormwater
treatment and flow control
Minimize imperviousness
Disperse runoff Use Integrated
Management Practices (IMPs)
Residential Development
Large hillside project
Swaleor In-groundPlanter
Reservoir, 12" min. depth
Reverse bend trap or hooded overflow
18" sandy loam, minimum infiltration rate 5" per hour
12" open-graded gravel, approx. ½" dia.
Perforated pipe
Downspout
Building exterior wall
Cobbles or splash block
Filter fabric
Concrete or other structural planter wall with waterproof membrane
Additional waterproofing on building as needed
Drain to storm drain or discharge; bottom-out or side-out options
Planter Box
Dry Well
Sizing criterion for treatment
Planting medium
0.2 inches/hour
i = 5 inches/hour
BMP Area/Impervious Area =0.2/5 = 0.04
Application of sizing factor
LID for flow control
Can LID facilities mitigate increased peaks and volumes of flows from impervious areas?
How would we demonstrate that? What are the design criteria?
Before
After
HSPF analysis of unit-acre runoff 33 years hourly rainfall Pre-project condition 100% impervious condition Hydrologic soil groups A, B, C, D Swales, Bioretention Areas,
In-ground and Flow-through Planters Underdrain with flow-restrictor in C&D soils
Dry wells, infiltration trenches and basins
Results: Control of Peak Flows
0.00
0.20
0.40
0.60
0.80
1.00
1.20
0 1 2 3 4 5 6 7 8 9 10
Recurrence Interval (years)
Peak
Flo
w (c
fs)
ImperviousMitigated Post-Project SitePre-Project Site0.5Q2
IMP Reduces Impervious Runoff to Less Than Pre-Project Levels
Results: Flow Duration Control
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40
% Time Exceeded
Flow
(cfs
)
ImperviousMitigated Post-Project SitePre-Project SiteQ100.1Q2
IMP Reduces Impervious Runoff to Less Than Pre-Project Levels
Sizing Factors for Flow Control
IMP Sizing FactorsIn-Ground Planter
Group A: 0.08Group B: 0.11Group C: 0.06Group D: 0.05
Flow-Through Planter
Group C: 0.06Group D: 0.05
Vegetated/Grassy Swale
Group A: 0.10 to 0.14
Group B: 0.14 to 0.21
Group C: 0.10 to 0.15
Group D: 0.07 to 0.12
Bioretention Basin
Group A: 0.13Group B: 0.15Group C: 0.08Group D: 0.06
IMP Sizing FactorsDry Well Group A: 0.05 to
0.06Group B: 0.06 to 0.09
Infiltration Trench
Group A: 0.05 to 0.06Group B: 0.07 to 0.10
Infiltration Basin
Group A: 0.05 to 0.10Group B: 0.06 to 0.16
Adjustment to annual rainfall
Group A, y = 0.0020x + 0.08Group B, y = -0.0005x + 0.11Group C, y = -0.0022x + 0.06Group D, y = -0.0022x + 0.05
0.00
0.02
0.04
0.06
0.08
0.10
0.12
0.14
-14 -12 -10 -8 -6 -4 -2 0 2 4 6
Mean Annual Rainfall (MAP) Relative to Martinez Gauge (in)
Sizi
ng F
acto
r
Group A soils
Group B soils
Group C soils
Group D soils
Key Operating Characteristics Runoff from the intended tributary
area must flow to the facility. The surface reservoir must fill to its
intended volume during high inflows. Runoff must filter rapidly through
the soil layer. Filtered runoff must infiltrate into the
native soil to the extent possible. Remaining runoff must be captured and
drained to daylight or a storm drain.
Tributary Area Drainage
area includes portions of roof and of parking lot
Ensuring flow to the facility Runoff may
enter by sheet flow or be piped.
Roof leaders can be piped directly or spill across pavement
Distribute flow evenly
Distribute flow evenly
Surface reservoir must fill
Surface reservoir must fill
Surface reservoir must fill
Surface reservoir must fill
Surface reservoir must fill
Surface reservoir must fill
Runoff must drain rapidly Typically no native
on-site material to be used
Imported material to be a mix of sand and organics
Minimum infiltration rate 5"/hour
Aim for 10"/hour at installation
On-site bucket test
No filter fabric
Promote Infiltration Protect excavation
from fine sediment and compaction
Re-excavate if used for sediment control during construction
Rip the bottom soils to promote infiltration
Underdrain Perforated pipe Solid pipe nearest 2' to
connections Bedded in gravel layer Connected to storm drain or
daylight Cleanouts Omit in sandy soils
Recap Runoff from the intended tributary
area must flow to the facility. The surface reservoir must fill to its
intended volume during high inflows. Runoff must filter rapidly through
the soil layer. Filtered runoff must infiltrate into the
native soil to the extent possible. Remaining runoff must be captured and
drained to daylight or a storm drain.
Additional Features Check dams Moisture barriers/cutoff walls Outflow-limiting orifices on
underdrains Specified depths or volumes for
surface reservoirs or gravel layers
Check plans for facility cross-sections and details
Checklist Pre-construction
Review facility details Review required inspections
Site Preparation Erosion and sediment controls Runoff diverted from facilities Facility areas marked Pipes and appurtenances
delivered and inspected
Checklist Excavation and Grading
Grade breaks and elevations correct Bottom of excavation elevation and
dimensions correct Native soil at excavation bottom ripped Embankment/wall elevations and
widths correct and level. Drainage material is Class 2 perm Bucket test on imported soil mix
achieves 8-12 inches per hour
Checklist Facility Installation
Location size and depths of appurtenances
Roof leaders and impervious areas drain to facility as intended
Underdrain, inlet, outlet, orifice, cleanouts, and overflow are located and installed correctly
Overflow at correct elevation Moisture barrier or cut-off walls
installed correctly
Checklist Facility Installation
Underdrain base elevation correct and drain bedded properly
Irrigation system on separate zone Gravel (Class 2 perm) depth correct Soil media installed and passes bucket
test Soil top elevation and surface reservoir
depth correct Inlets and overflows correctly located
Checklist Landscaping and planting
Vegetation complies with approved planting plan
Woody vegetation won’t block inlets and overflows
Checklist Final check
Areas draining to facility are cleaned (pavement) or stabilized (landscape)
Inlets installed and operational Configuration, size and depth of
facility correct Vegetation established and
irrigation operating Overflow installed and free of debris Runoff reaches the facility