+ All Categories
Home > Documents > Construction of On-Site Stormwater Treatment and Flow Control Facilities

Construction of On-Site Stormwater Treatment and Flow Control Facilities

Date post: 19-Feb-2016
Category:
Upload: thiery
View: 31 times
Download: 1 times
Share this document with a friend
Description:
Construction of On-Site Stormwater Treatment and Flow Control Facilities. Dan Cloak, P.E. Principal Dan Cloak Environmental Consulting. Topics. Why do we have permanent on-site facilities to treat stormwater? Facility designs and how they work - PowerPoint PPT Presentation
Popular Tags:
41
Construction of On-Site Stormwater Treatment and Flow Control Facilities Dan Cloak, P.E. Principal Dan Cloak Environmental Consulting
Transcript
Page 1: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Construction of On-SiteStormwater Treatment andFlow Control Facilities

Dan Cloak, P.E.PrincipalDan Cloak Environmental Consulting

Page 2: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Topics Why do we have permanent on-

site facilities to treat stormwater? Facility designs and how they

work Operating characteristics and

errors in design and construction Draft checklist for facility

inspection

Page 3: Construction of On-Site Stormwater Treatment and Flow Control Facilities

NPDES requirementsin a nutshell Minimize imperviousness Control pollutant sources Treat stormwater prior to

discharge from the site Match peaks and durations to

pre-project conditions (HMP) Maintain treatment and flow-

control facilities in perpetuity

Page 4: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Low Impact Development Stormwater

treatment and flow control

Minimize imperviousness

Disperse runoff Use Integrated

Management Practices (IMPs)

Page 5: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Residential Development

Page 6: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Large hillside project

Page 7: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Swaleor In-groundPlanter

Page 8: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Reservoir, 12" min. depth

Reverse bend trap or hooded overflow

18" sandy loam, minimum infiltration rate 5" per hour

12" open-graded gravel, approx. ½" dia.

Perforated pipe

Downspout

Building exterior wall

Cobbles or splash block

Filter fabric

Concrete or other structural planter wall with waterproof membrane

Additional waterproofing on building as needed

Drain to storm drain or discharge; bottom-out or side-out options

Planter Box

Page 9: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Dry Well

Page 10: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Sizing criterion for treatment

Planting medium

0.2 inches/hour

i = 5 inches/hour

BMP Area/Impervious Area =0.2/5 = 0.04

Page 11: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Application of sizing factor

Page 12: Construction of On-Site Stormwater Treatment and Flow Control Facilities

LID for flow control

Can LID facilities mitigate increased peaks and volumes of flows from impervious areas?

How would we demonstrate that? What are the design criteria?

Before

After

Page 13: Construction of On-Site Stormwater Treatment and Flow Control Facilities

HSPF analysis of unit-acre runoff 33 years hourly rainfall Pre-project condition 100% impervious condition Hydrologic soil groups A, B, C, D Swales, Bioretention Areas,

In-ground and Flow-through Planters Underdrain with flow-restrictor in C&D soils

Dry wells, infiltration trenches and basins

Page 14: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Results: Control of Peak Flows

0.00

0.20

0.40

0.60

0.80

1.00

1.20

0 1 2 3 4 5 6 7 8 9 10

Recurrence Interval (years)

Peak

Flo

w (c

fs)

ImperviousMitigated Post-Project SitePre-Project Site0.5Q2

IMP Reduces Impervious Runoff to Less Than Pre-Project Levels

Page 15: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Results: Flow Duration Control

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35 0.40

% Time Exceeded

Flow

(cfs

)

ImperviousMitigated Post-Project SitePre-Project SiteQ100.1Q2

IMP Reduces Impervious Runoff to Less Than Pre-Project Levels

Page 16: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Sizing Factors for Flow Control

IMP Sizing FactorsIn-Ground Planter

Group A: 0.08Group B: 0.11Group C: 0.06Group D: 0.05

Flow-Through Planter

Group C: 0.06Group D: 0.05

Vegetated/Grassy Swale

Group A: 0.10 to 0.14

Group B: 0.14 to 0.21

Group C: 0.10 to 0.15

Group D: 0.07 to 0.12

Bioretention Basin

Group A: 0.13Group B: 0.15Group C: 0.08Group D: 0.06

IMP Sizing FactorsDry Well Group A: 0.05 to

0.06Group B: 0.06 to 0.09

Infiltration Trench

Group A: 0.05 to 0.06Group B: 0.07 to 0.10

Infiltration Basin

Group A: 0.05 to 0.10Group B: 0.06 to 0.16

Page 17: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Adjustment to annual rainfall

Group A, y = 0.0020x + 0.08Group B, y = -0.0005x + 0.11Group C, y = -0.0022x + 0.06Group D, y = -0.0022x + 0.05

0.00

0.02

0.04

0.06

0.08

0.10

0.12

0.14

-14 -12 -10 -8 -6 -4 -2 0 2 4 6

Mean Annual Rainfall (MAP) Relative to Martinez Gauge (in)

Sizi

ng F

acto

r

Group A soils

Group B soils

Group C soils

Group D soils

Page 18: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Key Operating Characteristics Runoff from the intended tributary

area must flow to the facility. The surface reservoir must fill to its

intended volume during high inflows. Runoff must filter rapidly through

the soil layer. Filtered runoff must infiltrate into the

native soil to the extent possible. Remaining runoff must be captured and

drained to daylight or a storm drain.

Page 19: Construction of On-Site Stormwater Treatment and Flow Control Facilities
Page 20: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Tributary Area Drainage

area includes portions of roof and of parking lot

Page 21: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Ensuring flow to the facility Runoff may

enter by sheet flow or be piped.

Roof leaders can be piped directly or spill across pavement

Page 22: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Distribute flow evenly

Page 23: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Distribute flow evenly

Page 24: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Surface reservoir must fill

Page 25: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Surface reservoir must fill

Page 26: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Surface reservoir must fill

Page 27: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Surface reservoir must fill

Page 28: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Surface reservoir must fill

Page 29: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Surface reservoir must fill

Page 30: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Runoff must drain rapidly Typically no native

on-site material to be used

Imported material to be a mix of sand and organics

Minimum infiltration rate 5"/hour

Aim for 10"/hour at installation

On-site bucket test

Page 31: Construction of On-Site Stormwater Treatment and Flow Control Facilities

No filter fabric

Page 32: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Promote Infiltration Protect excavation

from fine sediment and compaction

Re-excavate if used for sediment control during construction

Rip the bottom soils to promote infiltration

Page 33: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Underdrain Perforated pipe Solid pipe nearest 2' to

connections Bedded in gravel layer Connected to storm drain or

daylight Cleanouts Omit in sandy soils

Page 34: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Recap Runoff from the intended tributary

area must flow to the facility. The surface reservoir must fill to its

intended volume during high inflows. Runoff must filter rapidly through

the soil layer. Filtered runoff must infiltrate into the

native soil to the extent possible. Remaining runoff must be captured and

drained to daylight or a storm drain.

Page 35: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Additional Features Check dams Moisture barriers/cutoff walls Outflow-limiting orifices on

underdrains Specified depths or volumes for

surface reservoirs or gravel layers

Check plans for facility cross-sections and details

Page 36: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Checklist Pre-construction

Review facility details Review required inspections

Site Preparation Erosion and sediment controls Runoff diverted from facilities Facility areas marked Pipes and appurtenances

delivered and inspected

Page 37: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Checklist Excavation and Grading

Grade breaks and elevations correct Bottom of excavation elevation and

dimensions correct Native soil at excavation bottom ripped Embankment/wall elevations and

widths correct and level. Drainage material is Class 2 perm Bucket test on imported soil mix

achieves 8-12 inches per hour

Page 38: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Checklist Facility Installation

Location size and depths of appurtenances

Roof leaders and impervious areas drain to facility as intended

Underdrain, inlet, outlet, orifice, cleanouts, and overflow are located and installed correctly

Overflow at correct elevation Moisture barrier or cut-off walls

installed correctly

Page 39: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Checklist Facility Installation

Underdrain base elevation correct and drain bedded properly

Irrigation system on separate zone Gravel (Class 2 perm) depth correct Soil media installed and passes bucket

test Soil top elevation and surface reservoir

depth correct Inlets and overflows correctly located

Page 40: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Checklist Landscaping and planting

Vegetation complies with approved planting plan

Woody vegetation won’t block inlets and overflows

Page 41: Construction of On-Site Stormwater Treatment and Flow Control Facilities

Checklist Final check

Areas draining to facility are cleaned (pavement) or stabilized (landscape)

Inlets installed and operational Configuration, size and depth of

facility correct Vegetation established and

irrigation operating Overflow installed and free of debris Runoff reaches the facility


Recommended