    Container Terminal No. 9

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    2/60

    Container Terminal 9 - Some fast fact:

    1. Site area: total 150 hectares, including 120 hectaresreclaimed land

    2. Other associated works: re-alignment of the approach

    fairway, access road, paved areas for container handling,surface drainage and storm water culvert systems

    3. Reclamation method: dredging of alluvial clay, land

    formed mainly by sand-filling by conveyor or pump boat.

    4. Source of filling materials: from marine borrow area in the

    west of Hong Kong.

    5. Dumping location: south of Tsing Yi and Cheung Chau.

    6. Compaction method:, majority by Surcharge (max 9m up

    to 6 months), vibro-vibration, installation of band drainsand surface compaction

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    3/60

    Container Terminal 9 - Some fast fact (continue):

    5. Provide 6 parking berths along 1,940m waterfront withwater depth averaged 15.5m

    6. Forming of the berth deck: deck frame constructed on pile

    top, precast plank placed on top of the deck frame (with200mm RC topping) that formed the berth deck. The

    decks are sub-divided into 60m x 30m bay for easy control

    of construction.

    7. Foundation: raking piles and vertical piles driven by

    driving rack mounted on barge boat

    8. Other data:

    - Consultant Maunsell Consultant Asia Ltd.

    - Contractor Hyundai/CCECC JV- Contract sum about $3.95 billion

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    4/60

    Current Layout of the Container Terminals (CT 1 to 9) in Kwai Chung Basin

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    5/60

    Overview of the Container Terminals (CT 1 to 9) in Kwai Chung

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    6/60

    Trailing Suction Hopper Dredger for doing the dredging works

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    7/60

    Layout of Container Terminal 9 and its associated supporting facilities

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    8/60

    Typical Section for Vertical Seawall and Quay Deck Structure

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    9/60

    Doing the marine piling as

    foundation for the quay deck

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    10/60

    Marine piling asfoundation for the

    quay deck

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    11/60

    Ship equipped withpumping devices for

    sand filling

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    12/60

    Temporary drain pipeto discharge seawater

    after the sand filling

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    13/60

    Initial completion of the

    land formed by sandfilling and the

    commencement of other

    associated civil works

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    14/60

    Overview of the CT 9 site

    with the marine piles for

    the quay deck in position

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    15/60

    Filling work boundedby the seawall

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    16/60

    Dredging before the

    forming of the base for

    the vertical seawall

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    17/60

    Filling work in progress

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    18/60

    South portal of Route 8

    Nam Wan Tunnel

    The southern portion of the

    Terminal where the interchange

    to the future Route 8 located

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    19/60

    Detail showing the formation

    of the vertical seawall

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    20/60

    Compaction to the newly

    formed land by vibration

    plate and vibro-

    compaction method

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    21/60

    Forming the box-culvertusing cut-and-cover

    method

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    22/60

    Forming the box-culvertusing cut-and-cover method

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    23/60

    Other storm waterdischarge and drainage

    work in the newly

    reclaimed land

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    24/60

    Other storm water

    discharge and drainagework in the newly

    reclaimed land

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    25/60

    Marine piling work

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    26/60

    Completion of the marine piles pending

    for the erection of a temporary workplatform for the forming of the quay deck

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    27/60

    Newly formed land

    approaching the

    vertical seawall

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    28/60

    Detail showing theabutment between the

    quay deck and the

    vertical seawall

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    29/60

    Erection of a temporary workplatform to facilitate the

    forming of the quay deck

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    30/60

    Erection of a temporary work

    platform to facilitate the

    forming of the quay deck

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    31/60

    Work activities as seen

    on the temporary work

    platform

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    32/60

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    33/60

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    34/60

    Erection of formwork for theforming of the framing

    beams for the quay deck

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    35/60

    Formwork detail of theframing beams for the

    quay deck

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    36/60

    The framing beam for quay deck as seen

    after the removal of the formwork

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    37/60

    Loading of

    surcharging

    material as a

    means of

    compaction

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    38/60

    Forming the quay deck

    by precast plank and

    RC topping

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    39/60

    Forming the quay deck

    by precast plank and

    RC topping

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    40/60

    Detail of quay deck with the steel

    reinforcing bar in place before concreting

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    41/60

    Completion of the phase 1 reclamation work with the

    first 3 berths of terminal handed over for operation

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    42/60

    Finishing and touching up of the

    facility before the handing over

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    43/60

    Precast channel for

    surface water discharge

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    44/60

    Precast channel for

    surface water discharge

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    45/60

    Paving works

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    46/60

    Final fitting out and phase hand-over of berth

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    47/60

    Final fitting out and

    setting up of other

    supporting facilities

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    48/60

    Final fitting out and

    setting up of othersupporting facilities

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    49/60

    The terminal facilities under partial

    operation as seen in mid 2004

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    50/60

    The terminal facilities under

    operation as seen in late 2004

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    51/60

    Overview of the Container Terminal 9 as seen from the hill side. The

    unoccupied land in the foreground is reserved for use as the interchanging

    concourse for the future Route 8 scheduled for handing over in late 2007.

    Terminal facilities including the

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    52/60

    Terminal facilities including the

    cargo handling yard under

    operation as seen in 2007

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    53/60

    Terminal facilities including the

    cargo handling yard under

    operation as seen in 2008

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    54/60

    Container Terminal 9 as viewed from the Stonecutter Island side

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    55/60

    Container Terminal No. 1 to 5 as seen from the Tsing Yi side

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    56/60

    Container Terminal No 7 and 8 completed for operation in late 1990s(photo taken in mid 2007)

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    57/60

    Container Terminal No 8 as seen in mid 2007 with the approachbridge heading toward Stonecutters Bridge in place

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    58/60

    Container Terminal No 9as seen from the deck

    of Stonecutters Bridge

    New Nam Wan Tunnel

    Stonecutters Bridge of Route 8 passing through Container Terminal 9

    with interchanging slip road for vehicular users

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    59/60

  • 8/10/2019 Construction Presentation_Container Terminal.pdf

    60/60

    End of Presentation for

    Container Terminal 9