CONSTRUCTION PROGRESS
UPDATE
Vol. 02
January 2016
TO VALUED BUYERS OF
BODAIJU RESIDENCES
©Torreya Asset Holdings Co., Ltd.
Construction Schedule Payment Schedule
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
2017
Jan
Feb
Mar
Nov.
2015
Oct.
Dec
2016
Jan
Feb
Parking 1
Parking 2
Garden Deck
Vol.02 January 2016
Bodaiju Site Progress Report - Building A and B -
1
GENERAL SCHEDULE (October 2015 – March 2016) CONSTRUCTION PROGRESS
Currently, the foundation and pilling works are being carriedout at the site and are expected to be completed by
January 2016. As of end-December 2015, we have
completed 73.5% of piling work.
Piling works
Architectural
works
Interior works
MEP
works
Completion of
foundation
Completion of
1st floor structure
Completion of
7th floor structure
Completion of
RF floor structure
Preliminary
works - Mine investigation
- Ultimate load test, etc.
RC
Superstructure
※Construction’s Schedule might vary to take weather conditions and other factors into account.
Building ABuilding B
※The diagram above only serves to illustrate the construction progress. Actual construction may not be carried out as per the illustration.
P1
P2
1F
2F
3F
5F
6F
7F
8F
9F
10F
11F
12F
13F
RF
P1
P2
1F
2F
3F
5F
6F
7F
8F
9F
10F
11F
12F
13F
RF
©Torreya Asset Holdings Co., Ltd. 2
PILING WORK OF BUILDING B PILE CAP EXCAVATION WORKSince the completion of piling works for Building A, Pile Cap Excavation Work has commenced to provide a stable foundation. Pile Cap is the starting point of all footing (foundation) related works.
Piling work of Building A was completed and piling work ofBuilding B has commenced. Overall piling work of Building A andB is 73.5% complete.
Vol.02 January 2016
Bodaiju Site Progress Report - Building A and B -
©Torreya Asset Holdings Co., Ltd. 3
PILE CAP SOIL COMPACTION (BUILDING A) LEAN CONCRETE WORK (BUILDING A)
After excavation and soil compaction, the foundation isprepared with Lean Concrete for Pile Cap Reinforcement.
After excavation, compaction is properly carried out on the soil. We have also started on the soil survey work before commencing with Lean Concrete Work as an additional safety measure.
Vol.02 January 2016
Bodaiju Site Progress Report - Building A and B -
©Torreya Asset Holdings Co., Ltd. 4
PILE CAP REINFORCEMENT WORK (BUILDING A) FORM WORK (BUILDING A)
Erection of Pile Cap Form Work has started.While piling at Building B is smoothly underway, installation of Pile Cap Reinforcement at Building A is also in good progress.
Vol.02 January 2016
Bodaiju Site Progress Report - Building A and B -
©Torreya Asset Holdings Co., Ltd. 5
SAFETY PRACTICE ACTIVITIES
Regular safety briefings are held on site, where safety shoes,uniforms and helmets are distributed to workers.
Vol.02 January 2016
Bodaiju Site Progress Report - Building A and B -
©Torreya Asset Holdings Co., Ltd. 6
CUSTOMERS SITE VISIT EVENTOur customers were also invited to visit our construction siteby our engineers, in order to gain a better understanding ofconstruction progress.
On 19th December 2015, valued customers were invited to oursales gallery, where they were offered refreshments and briefedon current construction progress and activities.