CONSTRUCTION PROGRESS
UPDATE
Vol. 08July 2016
TO VALUED BUYERS OF
BODAIJU RESIDENCES
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
1
Dear valued buyers of Bodaiju Residences,
It is with great pleasure that I’m writing to you to share with you on the construction
progress for Bodaiju Residences.
Since the sales of Bodaiju Residences on 22nd August 2015, we had received over-
whelming support and much better than expected sales of Bodaiju Residences. With the
strong support, my construction team has been working endlessly to meet the construction
progress. After completing the UXO clearance and test piling works, we are currently
carrying out piling works in full force.
As part of our continuous engagement with you, I’m pleased to provide you with the
details of the construction in this report and endeavor to provide you with an update on
the construction every quarter.
Thank you for all the great support extended thus far.
Sincerely,
Toshihiko Muneyoshi
Founder/ Manager Director
Creed Group
©Torreya Asset Holdings Co., Ltd.
Construction Schedule Payment Schedule
Jul
Mar
Apr
May
Jun
Aug
Sep
Oct
Nov
Dec
2017
Jan
Feb
Mar
Nov.
2015
Oct.
Dec
2016
Jan
Feb
Vol. 08 June 2016
Bodaiju Site Progress Report - Building A and B -
2
GENERAL SCHEDULE (October 2015 – June 2017) CONSTRUCTION PROGRESS
We are completed the 1st Floor Structure Work by end of
this June 2016.
Piling works
Architectural
works
Interior works
MEP
works
Completion of
7th floor structure
Completion of
RF floor structure
preliminary
works - Mine investigation
- Ultimate load test, etc.
RC
Superstructure
※Construction’s Schedule might vary to take weather conditions and other factors into account.
Building ABuilding B
※The diagram above only serves to illustrate the construction progress. Actual construction may not be
carried out as per the illustration.
P1
P2
1F
2F
3F
5F
6F
7F
8F
9F
10F
11F
12F
13F
RF
P1
P2
1F
2F
3F
5F
6F
7F
8F
9F
10F
11F
12F
13F
RF
FOUNDATION WORK
COMPLETED. MARCH-2016
Completion of
foundation
Parking 1
Parking 2
Garden Deck
1st FLOOR STRUCTURE
COMPLETED. JUNE-2016
Completion of
1st floor structure
©Torreya Asset Holdings Co., Ltd. Vol. 08 June 2016
Bodaiju Site Progress Report - Building A and B -
3
FOUNDATION COMPLETION – March 2016 PHOTOS OF PROGRESS COMPLETION
©Torreya Asset Holdings Co., Ltd. Vol. 08 June 2016
Bodaiju Site Progress Report - Building A and B -
4
1 FL. SUPER-STRUCTURE COMPLETION-June 2016 PHOTOS OF PROGRESS COMPLETION
©Torreya Asset Holdings Co., Ltd. Vol. 08 June 2016
Bodaiju Site Progress Report - Building A and B -
5
PHOTOS OF PROGRESS COMPLETION - 1 PHOTOS OF PROGRESS COMPLETION - 2
©Torreya Asset Holdings Co., Ltd. Vol. 08 June 2016
Bodaiju Site Progress Report - Building A and B -
6
PHOTOS OF PROGRESS COMPLETION - 3 PHOTOS OF PROGRESS COMPLETION – 4
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
7
RE-BAR FABRICATION (BUILDING A & B) FORM-WORK FABRICATION (BUILDING A & B)
Form-Work fabrication was completed for 1FL Super-StructureWork and we keep continue to fabricate for upper floor.
Re-Bar fabrication activities at our workshop in construction sitewhich completed the 1FL Super-Structure and we keep continuefor upper floor.
Vol. 08 June 2016
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
8
1FL-BEAM & SLAB FORM WORK (BUILDING A & B) 1FL-BEAM & SLAB REINFORCEMENT (BUILDING A & B)
Reinforcement Work site activities of Building A & B on 1FLLevel of the buildings which completed.
1FL Beam and Slab Form Work installation activities in ourconstruction site. Currently we are preparing the Form Work forthe upper floor.
Vol. 08 June 2016
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
9
1FL-RE-BAR CHECK & CLEANING (BUILDING A & B) 1FL-CONCRETE TEST AT SITEMixed Concrete was tested at site before concreting of 1FLLevel. We are following the quality standard to verify thequality from steps to steps in our construction site.
Our engineers are doing the proper check and cleaning beforecasting concrete. We keep checking to bring quality for ourvalued clients.
Vol. 08 June 2016
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
10
1FL-MEP WORK (BUILDING A & B) 1F-CONCRETE WORK AT SITEConcrete Work for 1st Floor Level of Building A & B wascompleted in June 2016. This is our concrete casting activitiesat our construction site during night time.
Our engineer are laying the pipe for electricity in 1FL Slab beforeconcreting. This is MEP Work activity after checking and waitingfor concrete casting.
Vol. 08 June 2016
©Torreya Asset Holdings Co., Ltd.
Bodaiju Site Progress Report - Building A and B -
11
SITE VIEWS (BUILDING A & B)
In conclusion we already complete the 1st Floor Concreting Work (1FL Super-Structure Work) for Building A & B by 30th June 2016 as we plan inour schedule. We keep working hard with the standard quality and on our schedule for our valued clients.
Vol. 08 June 2016
A1
A2
B1
B2
B1 View – Building B
B2 View – Building B
A1 View – Building A
A2 View – Building A