Construction Status - Apr 2018 Puravankara Limited, 130/1, Ulsoor Road, Bangalore - 560 042, Call - 080 – 67724001, Email: [email protected]
Transcript

Construction Status - Apr 2018

Puravankara Limited, 130/1, Ulsoor Road, Bangalore - 560 042,Call - 080 – 67724001, Email: [email protected]

Building-1 P.C.C. below footing and Footing casting in progress Building-2 (Parking -2) slab shuttering work in Progress

Building-3 (parking - 3) slab shuttering is in Progress Building-4 1st typical floor Slab shear wall Reinforcement is in progress

Building-5 1st typical floor Slab completed Building-6 parking slab-2 (Pour-2) Reinforcement work in progress for parking-3 slab and shuttering work for parking-3 in progress

Building-7 Parking-2 slab shuttering in progress Building-8 1st typical slab (Pour-2) Pour-1 ready for casting

Building-9 1st typical floor slab (Pour -2) shuttering and Reinforcement in progress Building-10 Earth Work Excavation completed

Building-11 Earth Work Excavation completed Building-12 Earth Work Excavation completed

Building-13 Earth Work Excavation completed Club House PCC and Footing work in Progress

PURVA SILVERSANDSWORK PROGRESS REPORT - April '18

PURVA SILVERSANDS MARKETING PROGRESS REPORT -March 2018-(As On 30.04.2018)

S. No ACTIVITIESBuildings

1 2 3 4 5 6 7 8 9 10 11 12 13

1 Earth Work Excavation 100% 100% 100% 100% 100.00% 100% 100% 100% 100% 100% 100% 100% 100%

2 Plain Cement Concrete 60% 100% 100% 100% 100.00% 100% 100% 100% 100%

3 Raft/Footing Reinforcement 30% 100% 100% 100% 100.00% 100% 100% 100% 100%

4 Raft/Footing Concrete 30% 100% 100% 100% 100.00% 100% 100% 100% 100%

5 Plinth beam casting 100% 100% 100% 100.00% 100% 100% 100% 100%

6 Grade Slab Concreting

7 Column Concrete ( Plinth Top to -1st Parking Floor Slab ) 100% 100% 100% 100.00% 100% 100% 100% 100%

8 1st Level Parking Floor Slab Shuttering 50% 100% 100% 100.00% 100% 50% 100% 100%

9 1st Level Parking Floor Slab Reinforcement 100% 100% 100.00% 100% 100% 100%

10 1st Level Parking floor Slab Concrete 100% 100% 100.00% 100% 100% 100%

11 Column Concrete ( 1st Parking Floor Slab to 2nd parking slab) 100% 100% 100.00% 42% 100% 100%

12 2nd Level Parking Floor Slab Shuttering 80% 100% 100.00% 20% 100% 70%

13 2nd Level Parking Floor Slab Reinforcement 100% 100.00% 100% 60%

14 2nd Level Parking floor Slab Concrete 100% 100.00% 100% 50%

15 Column Concrete(2nd Parking Floor Slab to 3rd parking slab) 100% 100.00%

16 3rd Level Parking Floor Slab Shuttering 100% 100.00%

17 3rd Level Parking Floor Slab Reinforcement 100% 100.00%

18 3rd Level Parking floor Slab Concrete 100% 100.00%