UNRESTRICTED / ILLIMITÉ
Construction Technologies related to Site Preparation, Civil and Structural Works
Azhar KhanManager, EC 6 Containment Design / Constructability, AECLJune 2011
IAEA Workshop on Construction Technologies for Nuclear Power Plants
Hosted BY SNPTC, Shanghai, ChinaJune 22-24, 2011
Scope of Presentation
Project and Construction Schedule
Site Preparation
Construction Technologies for Civil and Structural Works
Construction technologies for Nuclear Power Plant Buildings
UNRESTRICTED / ILLIMITÉ 2
UNRESTRICTED / ILLIMITÉ 3
Overall Project Schedule
Construction Schedule
UNRESTRICTED / ILLIMITÉ 4
Site Preparation
UNRESTRICTED / ILLIMITÉ 5
UNRESTRICTED / ILLIMITÉ 6
Background to Site Planning and Development
• Phases of site planning and development works:– Advanced site development– Supply-chain infrastructure– Off-site management for module fabrication– Module delivery, assembly and outfitting– Power island construction
– Open top construction:
– Need at least 1 VHL crane– Modularization and prefabrication:
– Fully developed site infrastructure to support offloading , assembly and outfitting to exact standards before first nuclear concrete.
– Module lay-down areas to be “hardstand”, fully trafficable and heavy load capable.
– Support facilities required for off site module fabrication and module assembly
– Large area needed for storage, prefabrication and pre-assembly of modules
UNRESTRICTED / ILLIMITÉ 7
Site Development Schedule
• Site development affects construction schedule:– If lay-down areas are not available for storage, prefabrication
and pre-assembly of modules - site construction schedule will be affected
– Excavation of power block to be completed before site development
UNRESTRICTED / ILLIMITÉ 8
Pre-requisites for Site development and Plant Construction
• It is recommended that the following be completed prior to commencement of site development and plant construction:
– Subsurface (soils and bedrock) testing and analysis to assess site optimum location
– Environmental assessment– Site survey, and site survey control programme established– Transportation study for modules, equipment and personnel– Upgrades and load testing of routes required to handle heavy loads of
existing roads, bridges or overpasses and barge offload facilities– Significant cuts and fills necessary to provide a flat and level site free of
encumbrances and obstructions– Design for both permanent and temporary construction facilities– Electronic three dimensional (3-D) model for all permanent and
temporary sites, structures and components– Site drainage, trenching for utilities– Site development schedule– Excavation plan
UNRESTRICTED / ILLIMITÉ 9
Pre-requisites for Site development and Plant Construction, cont’d.
– Temporary services facilities and assembly areas– Site development permits, licensing documentation for site
preparation and construction licenses– Procurement of equipment and facilities required for site
preparation– Develop quality assurance program
– Quality Assurrance procedures– Quality surveillance procedures/check lists– Quality control procedures/check lists
Methods Utilized for Site Infrastructure Implementationand Layout for Site Construction
• All weather construction method:–Construction environment isolated from ambient weather–Buildings have temporary enclosures – Qinshan CANDU–Open top Construction
• Methods for construction personnel mobility:–Scaffolding–Mobile scissor lifts, bucket trucks–Access to personal services (tool sheds, toilets, wash water)–Mobile communication systems
UNRESTRICTED / ILLIMITÉ 10
Methods Utilized for Site Infrastructure Implementationand Layout for Site Construction, cont’d.
• Transportation:– Stick build approach– Modularization approach– Combined approach– Heavy haul path– Need barge unloading facility and heavy haul road(s)– Railroads
• Site mapping and measuring:–Existing conditions including topography–Existing buildings and infrastructure–Existing underground infrastructure–Layout of reference points and markers–Laser and global positioning system mapping (GPS)
UNRESTRICTED / ILLIMITÉ 11
Methods Utilized for Site Infrastructure Implementationand Layout for Site Construction, cont’d.
• Three dimensional modeling:– It can be developed during early design stages so that the entire
plant can be designed using available software– There would be cases where the vendor already has a design with
approved two dimensional (2-D) drawings that need to be partially modified to account for country specific requirements.
– In such cases, it is recommended that the design drawings are input to the 3-D modelling software to derive the required modifications.
– The only disadvantage in using 3-D modelling is that considerable time is needed to develop interference-free plant layout, to work out the BOM to be procured, and to develop ‘working drawings’ to be used in the field.
UNRESTRICTED / ILLIMITÉ 12
Main Construction Facilities
• Construction management centre:– Use the latest technology to provide direction and control of real time
field activities, tracking of equipment, visual and daily debriefing with field personnel
– Video conferencing– Real time management of critical path
UNRESTRICTED / ILLIMITÉ 13
Main Construction Facilities, cont’d.
• Civil:– Computerized concrete batch plants:
– Good quality concrete on a continuous basis with no human error
–Concrete/materials testing laboratories–Embedded parts fabrication shop–Reinforcing steel fabrication shop–Shop fabrication mock-up:
– Full scale or partial scale mock-ups can save on actual work time
–Structural steel fabrication/assembly shop–Paint shop–Contractor building–Warehouse–Housing for staff
UNRESTRICTED / ILLIMITÉ 14
Main Construction Facilities cont’d.
• Mechanical/Piping:–Pipe fabrication shop–Pickle bath facility–Paint shop–Contractor building–Warehouse–Housing for staff
UNRESTRICTED / ILLIMITÉ 15
Main Construction Facilities, cont’d.
• Electrical, Control and Instrumentation:–Electrical cabling shop–Instrument calibration shop–Contractor building–Warehouse–Housing for staff
UNRESTRICTED / ILLIMITÉ 16
Main Construction Facilities, cont’d.
• Owner:–Material management centre–Technical and administration building–Lay-down and assembly areas(modules, liner vessels,
equipment)–Warehouse–Housing for staff–Transportation depot–VHL crane–Tower cranes and telescopic cranes–Construction control room–Construction parking–Security fencing, gates and building
UNRESTRICTED / ILLIMITÉ 17
Main Construction Facilities, cont’d.
• Owner cont’d.:–Temporary power–Fire protection water and service water–Housing for staff–Transportation depot–Cafeteria for workers–First aid station
UNRESTRICTED / ILLIMITÉ 18
Construction Technologies for Civil and Structural Works
UNRESTRICTED / ILLIMITÉ 19
Civil and Structural Works
• Civil and structural works comprise the construction (fabrication, manufacture) of buildings, structures and their components and the supply of yard services (drainage, fencing, etc.)
• Longest duration on project schedule• Hence important to optimize by using advanced methods that
reduce the schedule• Very difficult and very time consuming to correct mistakes
–Quality assurance program is critical
UNRESTRICTED / ILLIMITÉ 20
Civil and Structural Works cont’d.
• The civil and structural works comprise the following:– Site clearing, grading and surveying; – Site protection works against flooding, tidal waves, typhoon, tsunami, etc.;– Excavation;– Earth soil/rock removal and disposal;– Site dewatering;– Remedial measures on foundation soil/rock;– Rock and soil slope stabilization;– Building under drainage;– Foundation works;– Building peripheral drainage;– Concrete works above foundation;– Structural steel fabrication and erection– Yard services– Backfill works– Roads and landscaping– Permanent security construction
UNRESTRICTED / ILLIMITÉ 21
Excavation
• Requires permits from local jurisdiction prior to start• Requires construction license from regulator prior to start in some
countries• Activity of long duration that can last between 6 to 12 months• Sometimes adjacent to operating nuclear power plants• Environment regulations and constraints• It is essential to minimize damage to final foundation material:
Protection from blasting near final level• Protection from flood and freezing• It is essential to provide protection to workers• It is essential to provide protection to nearby facilities
UNRESTRICTED / ILLIMITÉ 22
Excavation Cont’d.
• Conventional method:–Uses light machinery, blasting and hand excavation.
• Advance method:–Precision line blasting;–Chemical foam expansion for breaking rock.
UNRESTRICTED / ILLIMITÉ 23
Confirmation Of Soundness OfFoundation Materials And Remedial
Measures
• Visual examination– Identification of weak areas
• Open pit load tests to confirm foundation materials• Conventional remedial measures:
– Extra excavation to overcome weak areas;– Thicken and/or enlarged sub-base engineered to reduce differential
settlement and tilt of buildings.• Advanced method:
–Consolidation grouting;–Rock anchors;–Bridging of weak areas;–Instrumentation to measure differential settlement and tilt of
buildings.
UNRESTRICTED / ILLIMITÉ 24
Remedial Measures For Slopestabilization
Objective:–Safety of workers, equipment and project assets during the
construction phaseConventional methods:
–Reducing slope of cuts–Use of anchored steel mesh
• Advanced methods–Consolidation Grouting–Grouted rock anchors–Earth reinforcing
UNRESTRICTED / ILLIMITÉ 25
Concrete Types
• Responsibility of site engineering to develop the specified mix designs• Nuclear plants are using more concrete; Hundred of thousands of cubic meters• Functional & performance requirements of buildings are different hence it is
economical to specify different mixes• Concrete mixes should be developed and approved at least 6 months before
concreting program• Supply of constituent materials (aggregates, sand, water, fly ash, etc) must be
confirmed a minimum of 12 months before start of concreting program• Portland cement is normally used• Heavy shielding concrete• Higher performance concretes (45-60 MPa) are being specified recently for
containment buildings
UNRESTRICTED / ILLIMITÉ 26
CONCRETE TYPES cont’d.
• Conventional Concrete Mixes– Portland cement– 25 to 35 MPa– Heavy shielding concrete
Advanced Concrete Mixes:– High workability concrete;– High performance concrete: 45 to 60 Mpa;– Fly ash concrete; large volume pours;– Pervious or “no fine” concrete;– Pre-cast concrete;– Self-Consolidating Concrete;– Self levelling concrete.
UNRESTRICTED / ILLIMITÉ 27
Concrete Placement Methods
• Conventional placement method:– Use of buckets and tower cranes to place concrete
• Advanced Concrete Placement Method:– Concrete placed with pumps
UNRESTRICTED / ILLIMITÉ 28
Bonding Between Concrete Pours
• Conventional method:– Expose aggregates to receive the next pour
• Advanced method:– Green cutting
UNRESTRICTED / ILLIMITÉ 29
Reinforcing Steel
• Conventional reinforcing steel method:– Placing steel bars with lap splices– Bar size 44 mm and above are connected by exothermic welding
• Advanced reinforcing steel methods:– Using mechanical & cad weld splicing– T-headed shear bars– Use of automatic rebar tie machines– Large prefabricated rebar modules
UNRESTRICTED / ILLIMITÉ 30
Embedded Parts
• Conventional embedded parts:– Plate type with manually welded strips or studs for anchoring in
concrete– Embedded anchor bolts for equipment and structural steel– Penetrations for piping and conduits
• Advance embedded parts method:–Plate type with studs welded with stud gun–Steel plate reinforced walls: Supports are connected directly
to the plate
UNRESTRICTED / ILLIMITÉ 31
Expansion Anchors
• These are anchors drilled into concrete to support structures, systems and components
• Objective:– Should reduce the use of expansion anchors to only support conduits and
non-seismically qualified systems and non vibrating equipment– Anchors should not cut reinforcing steel
UNRESTRICTED / ILLIMITÉ 32
Foundation Construction
• Conventional foundation construction methods:– Spread footings, combined footings, mat foundations, pile
foundations– In the case of mat foundations, multiple pours are used
• Advanced foundation construction methods:– Advances in concrete technology and placement methods have– led to single pours for large mats– Advances in the development of seismic isolations permit the– isolation of foundations for structures and equipment and thus– protect them from high seismic events
UNRESTRICTED / ILLIMITÉ 33
Foundation Construction – Seismic Isolators
UNRESTRICTED / ILLIMITÉ 34
EC 6 for High Seismicity Regions;Common Reactor Building and Service Building Foundation,
Lower Base Slab c/w Isolator Pedestals
Foundation Construction – Seismic Isolators cont’d.
UNRESTRICTED / ILLIMITÉ 35
Concrete Construction Above Foundation
• Formwork• Conventional formwork:
– Slab formwork consists of wood/metal forms supported by shoring– Wall formwork consists of wood/metal face forms held together with
form ties– Forms are stripped after concrete has set and achieved sufficient
strength so that it can support its dead load plus a small live load• Advanced types of formworks:
– Q-deck or left in shutters– Steel plate reinforced walls (no reinforcing steel in walls)– Steel plate modular floors– Pre-fabricated permanent formwork
UNRESTRICTED / ILLIMITÉ 36
Walls & Columns
• Conventional Method:– Place conventional form and pour concrete through trunks up to
height of 6 to 7 meters.• Advanced Construction:
– Steel plate reinforced walls;– Self consolidating concrete;– Self levelling concrete.
UNRESTRICTED / ILLIMITÉ 37
Slab, floors and roofs
• Conventional Method:– Use conventional concrete mixes, conventional reinforcing steel with
lap splicing, conventional formworkAdvanced Method:
– Use Q-Deck or left in shutters in slabs not supporting seismically qualified systems
– Modular floors– Steel reinforcement concrete composite structures and Deck Plate
construction– Self compacting concrete– Pre-fabricated permanent formwork
UNRESTRICTED / ILLIMITÉ 38
Structural Steel Fabrication
• Braced frames consisting of columns, beams and bracing, and equipment supporting steel systems
• Conventional method– Cutting and welding of structural steel based on two-dimensional
fabrication drawings and using manual measurements– Use of clip angles– Maximize welding in shop
• Advanced method– Automated fabricating shop– Use of 3D and precision control maintained by lasers– Use of end plate connections
UNRESTRICTED / ILLIMITÉ 39
Structural Steel Erection
• Conventional method:– Use of temporary bracing to align and temporarily support the
braced frame structures– Use of conventional high strength steel bolts using torque method
such as turn of nut and calibrated wrenches – Maximize bolting and minimize welding at site
• Advanced method:–Facilitates modularization and parallel works–Use of buckling restrained braces (BRBs)–Use of twist off bolts
UNRESTRICTED / ILLIMITÉ 40
Water Proofing
• Required for underground structures, basements, large water transporting system, liquid retaining concrete tanks, etc.
• Conventional method:– Use of rubber water-stops– Use of external painted waterproofing on structures below ground– Use of sump pump installation
• Advanced method:– Use of superior waterproofing material with advance spraying
system– Use of fast setting epoxy injection material
UNRESTRICTED / ILLIMITÉ 41
Backfilling
• Used for areas between open cut and buildings;• Used in pipe trenches• Used in landscaping• Conventional method:
– Common backfill in open area– Granular backfill adjacent to building and covering piping in trenches
• Advanced method:–Cement / sand backfill mixture is used
UNRESTRICTED / ILLIMITÉ 42
Yard Services
• Storm water drainage system• Sewage system• Plant system, piping and cables• Plant roads• Conventional method:
– Backfilled trenches• Advanced method
–Tunnels
UNRESTRICTED / ILLIMITÉ 43
Construction Technologies for Nuclear Power Plant Buildings
UNRESTRICTED / ILLIMITÉ 44
CONTAINMENT BUILDING
• Foundation base slab + steel liner• Containment vessel or steel lined concrete• Containment wall + dome• Shield wall (in double containments)• Internal structures
UNRESTRICTED / ILLIMITÉ 45
FOUNDATION BASE SLAB + LINER
• Large reinforced concrete mat foundations (greater than 5000 m3)• Waterproofing membrane under foundation• Conventional Method:
– Multiple pours, placed to minimize shrinkage– Conventional concrete design mix
• Advanced Methods:– Single pour due to improved concrete technology / concrete mixes
with low shrinkage cement, reduced cement content, increased use of plasticizer admixtures, etc.
– Significant increase in concrete pump use– Increased reliability of batch plants
UNRESTRICTED / ILLIMITÉ 46
BASE SLAB
UNRESTRICTED / ILLIMITÉ 47
Example of RB Base Slab Rebar Mat
UNRESTRICTED / ILLIMITÉ 48
CONTAINMENT WALL
• Conventional Method:– Use pre-assembled gang wall forms & construct in multiple repetitive
concrete lifts between 6 to 7 meters– Concrete placement using trunks to pour concrete; not greater than
1 meter fall– Use vibrators for achieving homogeneity– Carpenter crews are employed for erecting forms– Large scaffolding to set up
• Advanced Method:– Slip-forming:
– Continuous placing of concrete at pre-planned rates– Hydraulic lift with jacks moving short section of formwork
UNRESTRICTED / ILLIMITÉ 49
Climbing Formwork
• Climbing formwork is a self supporting formwork system.
• Standard steel forms supported from frame
• After wall is poured, form is released and rolled back from face
• Jacks lift or climb the whole frame up one level
• Prefab rebar installed• Formwork panels are closed and next
concrete wall is poured• Standard cycle times
UNRESTRICTED / ILLIMITÉ 50
CONTAINMENT WALL SLIP-FORMING cont’d.
UNRESTRICTED / ILLIMITÉ 51
CONTAINMENT WALL SLIP-FORMING cont’d.
UNRESTRICTED / ILLIMITÉ 52
CONTAINMENT WALL SLIP-FORMING cont’d.
UNRESTRICTED / ILLIMITÉ 53
CONTAINMENT WALL SLIP-FORMING cont’d.
UNRESTRICTED / ILLIMITÉ 54
CONTAINMENT WALL cont’d.
• Advanced Method cont’d.:– Jump forming:– This method is being used to construct practically all steel lined
containment walls– Wall is formed in stages with the form lifted hydraulically or “jumped
up” to the next stage after concrete has reached sufficient strength– Use of prefabricated rebar modules
UNRESTRICTED / ILLIMITÉ 55
Jump Forming
UNRESTRICTED / ILLIMITÉ 56
Jump Forming in Parallel withLiner Construction and Installation
UNRESTRICTED / ILLIMITÉ 57
Jump Forming and Prefab Rebar Mat
UNRESTRICTED / ILLIMITÉ 58
Completion of Jump Forming
UNRESTRICTED / ILLIMITÉ 59
CONTAINMENT DOME
• Conventional Method:– Support formwork:
–Uses a space truss system and shoring supports from the base slab
• Advanced Method:– Use a permanent steel plate dome formwork, lifted into place with a
VHL crane– Jump form the dome– Use of prefabricated rebar modules
UNRESTRICTED / ILLIMITÉ 60
CONTAINMENT DOME cont’d.
UNRESTRICTED / ILLIMITÉ 61
INTERNAL STRUCTURES
• Conventional Method:– Use preassembled gang wall forms or hand set forms and construct the wall
in multiple repetitive lifts– Construction is up to underside of slabs, construct slab and then proceed
with columns and walls up to next slab– Conventional concrete mixes are used– Scaffolding is supported from the base slab and subsequently from the next
slab
Advanced Methods:– Use Q-deck or left in shutters supported by steel beams, for slabs not
supporting seismically qualified systems– Self consolidating concrete– Self levelling concrete– Proposed methods are to use modular floors and modules with mechanical
and electrical systems. These activities are performed off site and subsequently, the modules are transported to site and installed with a VHL crane
UNRESTRICTED / ILLIMITÉ 62
TURBINE BUILDING
Significant activities are:– Excavation (significant at coastal sites with large tidal variations)– Dewatering system– Base Slab– Turbine generator Pedestal– Structural Steel– Building Crane (200 tons or greater);
UNRESTRICTED / ILLIMITÉ 63
TURBINE BUILDING
Conventional Method:– Base slab is constructed in multiple pours;– For concrete structures use preassembled gang wall forms and
construct the wall in multiple repetitive lifts;– Turbine generator pedestal is concreted similar to other concrete
structures;– Structural steel is erected with conventional method of erecting
braced frames, stabilizing with temporary or permanent braces– Roof trusses are installed on columns after being preassembled on
ground;– Building Crane is lifted in to place with a heavy lift transportation
crane.
UNRESTRICTED / ILLIMITÉ 64
TURBINE BUILDING cont’d.
Advanced Method:– Base slabs – single pour or larger pours– Concrete structures – left in shutters, pumped concrete– Turbine pedestal – seismic isolators and self consolidating concrete,
pumped concrete– Structural Steel – modularized and installed with heavy lift crane,
use of buckling restraint braces, twist off bolts– Turbine building crane – installed with VHL crane
UNRESTRICTED / ILLIMITÉ 65
Turbine Building Excavation
UNRESTRICTED / ILLIMITÉ 66
TURBINE BUILDING CONSTRUCTION
UNRESTRICTED / ILLIMITÉ 67
Turbine Building Construction
UNRESTRICTED / ILLIMITÉ 68
Turbine Building Base Mat
UNRESTRICTED / ILLIMITÉ 69
TURBINE BUILDING CONSTRUCTION
UNRESTRICTED / ILLIMITÉ 70
Prefabricated Rebar Mat
UNRESTRICTED / ILLIMITÉ 71
Wall Rebar Mat
UNRESTRICTED / ILLIMITÉ 72
UNRESTRICTED / ILLIMITÉ 73