+ All Categories
Home > Documents > Consultancy Service for Computerized Maintenance ...

Consultancy Service for Computerized Maintenance ...

Date post: 18-Apr-2022
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
12
Page 1 of 12 Consultancy Service for Computerized Maintenance Management System Under Enhancement & Strengthening of Power Network in Eastern Region project Terms of Reference 1- Background and Context Bangladesh’s economy has performed well over the past decade and the country embarks in an ambitious infrastructure development program to sustain the economic growth. This include the power sector which has to meet an electricity demand projected to grow by more than 10 percent per annum in the medium term due also to efforts to reach universal access.The installed generation capacity doubled over 5 years to reach 11.8 GW in 2016 and the Government’s plan is to double it by 2021 and reach 50 GW by 2041. Wheeling such capacity to the final users require not only to expand the transmission system but also to improve significantly the O&M of the system in order to ensure the quality and reliability of the electricity supply nationwide. Addressing the challenge is the responsibility of The Power Grid Company of Bangladesh (PGCB) which own, operate and expand the countr y’s power transmission assets 1 . Currently PGCB is managing 5,377 km of HV lines (mainly double circuit 400, 230 and 132 KV) and 141 substations. It is planned to add 3,098 km lines and 106 S/S by 2020 and additional 3,005km and 90 s/s by 2025. The details of the infrastructure projections are given in the table below and in Annex 2. Table 1: PGCB infrastructure projections up to 2025 Transmission Lines (km) Voltage and number of circuits 400 kV (Double Circuit) 230 kV (Double circuit) 132 kV Single Circuit Double Circuit Existing 349 1648 877 3266 Planned upto 2020 234 330 123 414 Planned upto 2025 2043 1174 3 888 Substations Voltage 400/230 kV 400/132 kV 230/132 KV 132/33 kV Existing 4 1 26 133 Planned upto 2020 1 1 14 60 Planned upto 2025 12 4 39 83 If PGCB keep current O&M practices, doubling the size of the infrastructure in less than 10 years implies major challenges to ensure sustainability of the transmission assets which is key to the reliability of the grid network. Indeed, the current practices are mainly based on time-based and breakdown maintenance with high impact on the system availability and the cost of service. The current organization/structure of the system maintenance is given in Annex-1. More than 2,000 staff are involved (including 1,141 engineers and 709 technical staff). The total expenditure 2 for maintenance almost double between FY 2011/12 and 2015/16 from 4.2 to 7.2 billion BDT (i.e. USD54 to 90.3 million). This does not include the losses due to unserved energy related to planned outages for maintenance which may increase due absence of live line maintenance capacity. Currently, data collection is done in PGCB from different Grid Maintenance Divisions (GMD) as per the requirement following QMS (Quality management System) guidelines. The Research & Technical 1 Institutional structure of the PGCB highlighting maintenance portion is shown in Annex 1 2 including Repair & Maintenance, Salaries & Benefits of O&M Staff, Depreciation etc.
Transcript
Page 1: Consultancy Service for Computerized Maintenance ...

Page 1 of 12

Consultancy Service for Computerized Maintenance Management System

Under Enhancement & Strengthening of Power Network in Eastern Region project

Terms of Reference

1- Background and Context

Bangladesh’s economy has performed well over the past decade and the country embarks in an

ambitious infrastructure development program to sustain the economic growth. This include the power

sector which has to meet an electricity demand projected to grow by more than 10 percent per annum

in the medium term due also to efforts to reach universal access.The installed generation capacity

doubled over 5 years to reach 11.8 GW in 2016 and the Government’s plan is to double it by 2021

and reach 50 GW by 2041.

Wheeling such capacity to the final users require not only to expand the transmission system but also

to improve significantly the O&M of the system in order to ensure the quality and reliability of the

electricity supply nationwide. Addressing the challenge is the responsibility of The Power Grid

Company of Bangladesh (PGCB) which own, operate and expand the country’s power transmission

assets1.

Currently PGCB is managing 5,377 km of HV lines (mainly double circuit 400, 230 and 132 KV) and

141 substations. It is planned to add 3,098 km lines and 106 S/S by 2020 and additional 3,005km and

90 s/s by 2025. The details of the infrastructure projections are given in the table below and in Annex

2.

Table 1: PGCB infrastructure projections up to 2025

Transmission Lines (km)

Voltage and number of circuits

400 kV (Double Circuit)

230 kV (Double circuit)

132 kV

Single Circuit Double Circuit

Existing 349 1648 877 3266

Planned upto 2020 234 330 123 414

Planned upto 2025 2043 1174 3 888

Substations

Voltage 400/230 kV 400/132 kV 230/132 KV 132/33 kV

Existing 4 1 26 133

Planned upto 2020 1 1 14 60

Planned upto 2025 12 4 39 83

If PGCB keep current O&M practices, doubling the size of the infrastructure in less than 10 years implies major challenges to ensure sustainability of the transmission assets which is key to the reliability of the grid network. Indeed, the current practices are mainly based on time-based and breakdown maintenance with high impact on the system availability and the cost of service.

The current organization/structure of the system maintenance is given in Annex-1. More than 2,000 staff are involved (including 1,141 engineers and 709 technical staff). The total expenditure

2for

maintenance almost double between FY 2011/12 and 2015/16 from 4.2 to 7.2 billion BDT (i.e. USD54 to 90.3 million). This does not include the losses due to unserved energy related to planned outages for maintenance which may increase due absence of live line maintenance capacity.

Currently, data collection is done in PGCB from different Grid Maintenance Divisions (GMD) as per the requirement following QMS (Quality management System) guidelines. The Research & Technical

1Institutional structure of the PGCB highlighting maintenance portion is shown in Annex 1

2including Repair & Maintenance, Salaries & Benefits of O&M Staff, Depreciation etc.

Page 2: Consultancy Service for Computerized Maintenance ...

Page 2 of 12

Support Department (RTS) is responsible for collection of critical maintenance data centrally. They have developed a online data collection and analysis system which is not fully operational yet.

It exists General guidelines for different PGCB departments regarding maintenance as detailed in table2. However, no certification/qualification program for staffs is in practice yet. Table 2: Existing maintenance guidelines for PGCB Departments

SN Department Guideline of Maintenance Details

1

GMD

Procedure for surveillance inspection of substation and office

Annexure-2(a)_QP-SIS-1

Procedure for substation maintenance Annexure-2(b)_QP-SSM-1

Procedure for transmission line maintenance Annexure-2(c)_QP-TLM-1

2 SPMC

Procedure for system protection & metering Annexure-2(d)_QP-SPM-1

3 TRTUD

Procedure for telecommunication and RTU equipment maintenance

Annexure-2(e)_QP-TRD-1

4 SCADA Procedure for SCADA equipment maintenance Annexure-2(f)_QP-SMD-1

5 CNST

Procedure for communication network management system maintenance

Annexure-2(f)_QP-CNS-1

6 RTS Procedure for work of technical services Annexure-2(g)_QP-RTS-1

In total, PGCB needs to change O&M strategy to cope with the rapid expansions of the transmission

system. Handling the expanded system with current maintenance practices and tools will lead to low

level of reliability and unbearable level of staffing. Activities are undertaken to improve the operating

rules under the implementation of FGMO and upgrading of SCADA/Dispatch system. Efforts are also

ongoing to come up with standardization of design and technical specifications of major equipment.

This activity will complement by focusing on a comprehensive maintenance and asset management

policy to deliver reliable power at an optimal cost.

2- Objective of the assignment

PGCB intend to hire a consultancy firm to review current policies, procedures and practice which includes but not limited to the followings:

a) Maintenance activities of various departments of PGCB that maintain critical elements of Bangladesh National Grid System[Critical elements means, failure of such element can cause power outage or increase the risk of power outage]

b) Procurement activities that can affect the quality of critical elements ofBangladesh National Grid System

c) Human resource recruitment and development activities of PGCB that can affect the maintenance of critical elements of Bangladesh National Grid System

In accordance with the above the consultant will also assess organization of the maintenance

departments, establish baseline for cost and performance. It will then propose a new strategy in line

with international standards, based on an inclusive process involving all relevant department of PGCB

and combining reactive, predictive and pro-active approaches. This will include (i) the progressive

introduction of Reliability-Centered-Maintenance (RCM) analysis based on available data, (ii) the

definition of a new policy framework, (iii) institutional re-organization of the maintenance, (iv) standard

guidelines and procedures during all the equipment/systems lifetime and (v)arrange adequate training

workshops to implement RCM in PGCB

3- Detailed Scope of work

The assignment will be undertaken in three (3) different phases as described hereunder:

3.1. Phase 1 will focus on:

Page 3: Consultancy Service for Computerized Maintenance ...

Page 3 of 12

i. The review of current maintenance policies and procedures,

ii. The assessment of organization of the maintenance departments and available resources

(tools, human resources, logistics, etc.)

iii. The assessment of technical officer/staff recruitment policy and practice of PGCB and

recommend necessary measures to update the same to ensure quality human resource

engagement for maintenance of critical elements of Bangladesh National Grid System.

iv. The assessment of training/performance appraisal policy and practice of PGCB and

recommend necessary measures to update the same to ensure quality human resource

engagement for maintenance of critical elements of Bangladesh National Grid System.

v. The analysis of available data &power outage reports in different format to undertake

equipment oriented or system-oriented analysis.

vi. The establishment of baseline for cost and performance

vii. The identification of areas of improvements and technical organizational options available

for implementation in the short and medium term. This will include, but not limited to,

system design, new maintenance approaches (reactive, predictive and pro-active), live

maintenance, computerized maintenance management system, on-line monitoring,

strategic maintenance planning, training and certification etc. Costing and tentative

implementation plan should be proposed.

viii. Feasibility of RCM based on available & collectable data, identification of major assets or

systems to be covered and tentative road map of its implementation.

ix. Elements of a draft maintenance policy framework for PGCB.

x. Establish procedures on Maintenance Management System for System Protection,

SCADA and telecommunication departments of PGCB.

xi. 2-days workshop to discuss the outcome of first phase and agree on a short-term plan for

options to be prioritized, RCM strategy and elements of the draft policy framework to be

developed in phase 2.

3.2 Phase 2 will focus on:

i. Finalization of the maintenance policy framework and strategy including:

- Reorganization and assessment of human resources recruitment and

development needs for 2020 and 2025.

- Feasibility of the setting up of a strategic maintenance planning, training &

certification department (SMPTCD) under PGCB maintenance wing

- Identification of the tools needed and development of their specifications.

- Recommendation on basic design criteria of critical elements of Bangladesh

National Grid System to ensure quality .

- Development of standard maintenance guidelines and procedures (including

RCM for specific assets and/or sub-systems)

- Definition of a training/certification program to support RCM

- Consolidated roadmap/implementation schedule;

- Definition of an investment plan 2019-2025

ii. Development of procurement packages needed in the short term:

- To computerize the maintenance management system (on-line maintenance data

base, on line monitoring of high value assets,)

- Implement live line maintenance practices (equipment &training for pilotcrews to

be based in different regions)

- Implement RCM practices (equipment &training for maintenance staff to be based

in different regions)

- Implement a strategic maintenance planning, training and certification program

3.3 Phase 3:Assistance to bid evaluation and contract negotiation (time based)

Page 4: Consultancy Service for Computerized Maintenance ...

Page 4 of 12

4- Deliverables

4.1. Inception report (T0+1 months)

The assignment will start with a kick off mission in Bangladesh to discuss the assignment and

collect data. The mission will include a half a day workshop on Maintenance practices in utilities

similar to PGCB and a specific discussion on RCM implementation in Transmission system

companies.

The inception report will be delivered one month after the kick off mission and will include the

following:

Overview of consultant’s understanding of the assignment; Detailed Project work plan and schedule Methodology and details of studies/analysis to be performed in this project Preliminary assessment of the information and data collected

PGCB will be given 2 weeks to send comments

4.2. Interim report on Review and assessment of existing maintenance

organization and feasibility of RCM. (T0+ 5 months)

It will cover task (i) to (vi) of phase 1 scope of work. It will include the result of the detailed

review/assessment of current PGCB maintenance strategy and practices as well as cost and

performance baselines. It will also propose improvement and determine the feasibility of RCM

and its scope.

PGCB will be given 2 weeks to send comments.

4.3. Draft final report of Phase 1 (T0 + 7 months)

Based on PGCB comments on the interim report, the consultant will finalize elements of a

draft maintenance policy framework and issue the draft final Phase 1 report to be discussed

during a 2 days’ workshop in country two weeks after.

4.4. Final Phase 1 Report (T0+8 months)

Final report of phase 1 to be submitted 2 weeks after the workshop and inclusion of its

conclusions.

4.5. Report on PGCB Maintenance framework and Strategy (T0+ 12 months)

A draft will be prepared based of the elements detailed in 3.2 (i) and discussed during

a one-day workshop. The final draft will be submitted 2 weeks after the workshop.

4.6. Bids documents (T0+15 months)

Draft Bid Documents and Request for Proposals related to the 3 activities detailed under 3.2

(ii) will be prepared and discussed with PGCB based on the need assessment and

specifications developed under 3.2 (i). Additional documents may be prepared at the request

of PGCB.

Draft documents will be submitted at T0+13 months and PGCB will be given 3 weeks to

comment. Final documents will be submitted by T0+15 months

Page 5: Consultancy Service for Computerized Maintenance ...

Page 5 of 12

5- Key staff for the assignment

The Key Expert Staff Needs and the estimated person months are as follows:

Project Manager 10 person months

Substation O&M Expert 6 person months

Transmission Line O&M Expert 6 person months

Live line Maintenance Expert 3 person months

Quality Assurance/ Factory Acceptance and Audit Expert 1 person months

Procurement Expert 2 person months

Data Management Expert 4 person months

Total Expert Person Month 32 person months

Minimum Qualification of Experts

The minimum required qualification for the Experts is shown in the following table:

Designation Minimum Qualification

1) Project Manager

Education:

・Graduate in Electrical Engineering

Experience:

General Experience : Minimum 20 years in Power sector.

Specific experience:

・Experience in 110kV and/or higher voltage substation/transmission line

related engineering (Operation & Maintenance/design/construction): 15

years

・Experience in preparing strategic maintenance planning/ development of

standard maintenance or Reliability-Centered-Maintenance (RCM)

guidelines and procedures/ preparing maintenance policy framework for

critical element of grid system (220kV or higher voltage grid substation/

transmission line) : 1 project.

・Experience in implementing computerized maintenance management

system for grid system (220kV or higher voltage grid substation/

transmission line) : 1 project.

・Experience of leading a consultants’ team as Project Manager or Deputy

Project Manager: 2 projects (at least one as PM)

Page 6: Consultancy Service for Computerized Maintenance ...

Page 6 of 12

・Experience of working overseas for at least 2 projects

2) Substation O&M

Expert

Education:

・Graduate in Electrical/Mechanical Engineering

Experience:

General Experience : Minimum 15years in Power sector.

Specific experience:

・Experience as operation & maintenance engineer for grid substation (110

kV and/or higher voltage grid substation): 10 years

・Experience in preparing strategic maintenance planning/ development of

standard maintenance or Reliability-Centered-Maintenance (RCM)

guidelines and procedures/ preparing maintenance policy framework for

critical element of grid substation (220kV or higher voltage: 1 project

・Experience in preparing procedures of Maintenance Management System

for System Protection, SCADA and telecommunication system of grid

substation (110kV or higher voltage) : 1 project.

・Experience in preparing basic design criteria for critical element of grid

substation (220kV or higher voltage. : 1 project.

3) Transmission Line

O&M Expert

Education:

・Graduate in Electrical/Mechanical Engineering

Experience:

General Experience: Minimum 15years in Power sector.

Specific experience:

・Experience as operation & maintenance engineer for Transmission Line

(110 kV and/or higher voltage): 10 years

・Experience in preparing strategic maintenance planning/ development of

standard maintenance/Reliability-Centered-Maintenance (RCM) guidelines

and procedures for critical element of transmission line (220kV or higher

voltage) : 1 project.

・Experience in preparing basic design criteria for critical element of

transmission line (220kV or higher voltage) : 1 project.

4) Live Line

Maintenance

Expert

Education:

・Graduate in Electrical/Mechanical Engineering

Experience:

General Experience: Minimum 15 years in Power sector.

Page 7: Consultancy Service for Computerized Maintenance ...

Page 7 of 12

Specific experience:

・Experience in implementing/ provision of consultancy services in

implementing live line maintenance practices for Grid Substation/

Transmission Line (110kV and/or higher voltage): 10 years

・Experience in providing training the pilot crews/ maintenance personnel for

live line maintenance of Grid Substation/ Transmission Line (220kV or

higher voltage): 2 projects

5) Quality Assurance/

Factory

Acceptance and

Audit Expert

Education:

・Graduate in Electrical/Mechanical Engineering

Experience:

General Experience: Minimum 10 years in Power sector.

Specific experience:

・Experience as Quality Assurance/ Factory Acceptance/Technical Audit

Expert in power sector utilities/ electric power equipment manufacturing

industry: 5 years

・Experience in preparing quality procedure for the procurement of critical

elements of power system: 1 project.

6) Procurement

Expert

Education:

Graduate in Engineering/Business Studies

Experience:

General Experience : Minimum 15 years in public sector/private sector

procurement.

Specific experience:

Experience in bidding document preparation: 5 years

Experience as a Procurement specialist/consultant for the substation/

transmission line project : 5 years

Experience in the procurement of supply, installation contract/EPC

contract financed by multilateral financial institute, preferably World

bank, ADB, JICA, KfW.

Experience in evaluating bid proposals of supply, installation

contract/EPC contract concerning grid substation/ transmission line

(110kV or higher voltage) : 2 projects

7) Data Management

Expert

Education:

・Graduate in Electrical Engineering/ Computer Science/ Computer

Engineering

Experience:

General Experience : Minimum 7 years in Power sector/ other utilities.

Specific experience:

・Experience in development, management and maintenance of database of

Page 8: Consultancy Service for Computerized Maintenance ...

Page 8 of 12

equipment/ system in power sector: 3 years

・Experience in implementing/ provision of consultancy services in

implementing on-line maintenance data base and on line monitoring of high

value assets for transmission utilities (110kV or higher voltage): 1 project.

All the assigned experts are expected to have good command of English. One person cannot be

proposed for more than one position.

6- Time Schedule and Duration of the assignment

The consultant is expected start in December 2019 and the assignment is scheduled to be

completed within 24 months.

7. Support to be provided by PGCB

7.1. Counterpart team

PGCB will provide counterpart and support staff to work with the consultant. PGCB will in

particular assist with the following tasks:

Provision oftechnical and institutional data required

Participation in data analysis

Coordination and planning of different workshop.

Review of reports and consolidation of comments.

7.2. Documentation

PGCB shall facilitate access by the consultant to maintenance documents and provide

availablereports of previous studies which could facilitate the realization of the assignments.

7.3. - Office space

The Consultant will arrange for office space.

Annex 1: Power sector Structure

Annex 2: Existing &Planned Transmission lines & Substations under PGCB

Annex3: PGCB O&M Structure

Page 9: Consultancy Service for Computerized Maintenance ...

Page 9 of 12

Annex 2: Existing &PlannedTransmission lines & Substations under PGCB

Transmission Lines

400 kV (Double Circuit) km

230 kV (Double circuit) km

132 kV (km)

Single Circuit Double Circuit

Existing 280 1593 504 3000

Planned upto 2020 968 744 - 1386

Planned upto 2025 1021 1051 - 933

Substations 400/230 kV 400/132 kV 230/132 KV 132/33 kV

Existing 1 1 23 116

Planned upto 2020 5 1 19 81

Planned upto 2025 7 2 31 50

1. Number & Size of Power Transformers

132/33 kV Power Transformers

Size of Transformer (MVA)

Existing Addition in Existing substations

Planned upto 2020 (New)

Planned upto 2025 (New)

20 3 - - 4

28 1 - - -

40 1 - 2 -

60 1 - - -

10/13.3 2 - - -

12.5/16.67 2 - - -

15/20 35 - - -

20/25 1 - - -

25/30 3 - - -

25/33 2 - - -

25/41 72 2 35 4

25/41.6 1 - - -

28/35 2 - - -

35/50 25 - 1 -

41/63 2 - - -

44.1/63 3 - - -

48/64 11 1 1 -

50/75 100 58 61 44

50/83 1 - - -

50/83.3 3 - - -

64/80 1 - - -

66/100 3 - - -

80/120 19 41 74 26

Total 294 102 174 78

230/33 kV Power Transformers

Size of Transformer (MVA)

Existing Addition in Existing substations

Planned upto 2020 (New)

Planned upto 2025 (New)

80 1 - - -

120/140 2 - 2 -

120/150 2 - 2 -

Total 5 - 4 -

Page 10: Consultancy Service for Computerized Maintenance ...

Page 10 of 12

230/132 kV Power Transformers

Size of Transformer (MVA)

Existing Addition in Existing substations

Planned upto 2020 (New)

Planned upto 2025 (New)

125 2 - - -

150 6 - 2 -

225 27 4 - -

300 10 - 2 3

255/300 2 - - -

225/300 - 5 19 11

250/350 - - 8 15

300/450 - 7 7 -

350/450 - - - 18

450 - - - 15

Total 47 16 38 62

400/132 kV Power Transformers

Size of Transformer (MVA)

Existing Addition in Existing substations

Planned upto 2020 (New)

Planned upto 2025 (New)

325 2 - 2 2

225/325 - - - 2

Total 2 - 2 4

400/230 kV Power Transformers

Size of Transformer (MVA)

Existing Addition in Existing substations

Planned upto 2020 (New)

Planned upto 2025 (New)

520 2 - 5 2

750 - - 7 10

1000 - - - 2

350/450 - - - 2

Total 2 - 12 16

Page 11: Consultancy Service for Computerized Maintenance ...

Page 11 of 12

Page 12: Consultancy Service for Computerized Maintenance ...

Page 12 of 12

Annex3PGCB O&M Structure

Executive Engineer, EMD/IMD/Shifting -

7nos.

Executive Engineer, CNST/SCADA - 2nos.

Executive Engineer, RTUD - 5 nos.

Executive Engineer, OFCL - 1 no.

Executive Engineer, System Protection

Division - 6nos.

Executive Engineer, Metering Division - 1no.

SCADA Circle, Communication Circle,

System Protection & Metering Circle,

Load Depatch Circle, Optical Fiber

Leasing Circle headed by

Superintending Engineers

Chief Engineer

Transmission-2

(Western Part of

Bangladesh)

Chief Engineer

Transmission-1

(Eastern Part of

Bangladesh)

2 Grid Circles and 1

HVDC Circle headed by

Superintending

Engineers

8 Grid Maintenance

Divisions headed by

Executive Engineers. The

respective substations and

transmission lines are

directly under them.

12 Grid Maintenance

Divisions headed by

Executive Engineers. The

respective substations and

transmission lines are

directly under them.

4 Grid Circles headed by

Superintending Engineers

Chief Engineer

System

Operation

Executive Director O&M


Recommended