Consultation on DCC’s delivery plan for SMETS1 Services
Date: 12 May 2017
Classification: DCC PUBLIC
Consultation opens: 12 May 2017
Consultation closes: 26 May 2017
SMETS1 Planning Consultation
DCC PUBLIC Page 2 of 24
Table of Contents
1 Introduction ........................................................................................................... 3
2 Refining Delivery Options .................................................................................... 5
3 Overview of the Plan ............................................................................................. 7
4 SMETS1 Service Users - Activity and Engagement ......................................... 11
5 Assumptions, Dependencies and use of Contingency .................................... 12
6 Consultation process and next steps ............................................................... 13
7 List of consultation questions ........................................................................... 14
Annex A – Planned activity in detail .......................................................................... 15
Annex B – SMETS1 delivery plan – Milestone Table ................................................ 22
Annex C – Plans on a Page ......................................................................................... 23
SMETS1 Planning Consultation
DCC PUBLIC Page 3 of 24
1 Introduction
A number of energy suppliers are installing smart meters to optimise their preparations for
the main rollout stage of the Smart Metering Implementation Programme (SMIP). These
meters are, or will be, SMETS1 compliant and currently operate outside of the DCC. While
this approach has driven out early learnings and benefits, SMETS1 meters installed by one
energy supplier are not always supported by another’s systems. This sometimes results in
consumers losing their smart functionality when they switch energy suppliers.
DCC considers that there are important shared benefits for industry and consumers from the
enrolment of SMETS1 meters into a DCC Service; particularly the ability for all SMETS1
customers to maintain their smart services following a decision to switch suppliers.
In November 2016 DCC issued for consultation a study of feasible options for the enrolment
of SMETS1 meters into a new DCC SMETS1 Service – the draft Initial Enrolment Project
Feasibility Report (IEPFR) – in accordance with the requirements in Section N of the Smart
Energy Code (SEC). DCC’s consultation on the draft IEPFR closed on 20 January 2017, and
since then DCC has been considering consultation responses regarding stakeholders’
preferences for any new DCC SMETS1 Service. DCC has today submitted its final IEPFR to
BEIS, which is also published on the DCC website.1
On 18 January 2017 DCC received a Direction from the Secretary of State, in accordance
with Condition 13 of the Smart Meter Communication Licence (the Licence), to prepare a
plan for the delivery of services to support SMETS1 meters. As with all of the plans
developed in accordance with Condition 13 of the Licence, DCC is required to first consult
with the SEC Panel and all SEC Parties regarding the proposed content of the plan. This
consultation document constitutes DCC’s formal consultation on the plan for a SMETS1
Service in accordance with this requirement.
The closing date for responses is 26 May 2017.
This consultation describes the plan, and the approach proposed by DCC which will allow the
SMETS1 Service to be delivered in the most economic and efficient way possible. The plan
recognises that several options for delivery of a SMETS1 Service remain, as described in the
IEPFR.
The plan is set out across four distinct phases as follows:
An Initiation Phase – in which the DCC submits its final IEPFR to BEIS, to enable a
BEIS decision on the options set out in the IEPFR. Additionally during this phase DCC
continues its exploration of the SMETS1 market to further understand time and cost
implications of integration path options, technical feasibility and both new and existing
service provider capabilities and to prepare for a discovery phase;
A Discovery Phase – which sees further commercial negotiation and initial
development activity by Smart Meter System Operators (SMSOs), incumbent and new
1 https://www.smartdcc.co.uk/about-dcc/future-service-development/enrolment-and-adoption/
SMETS1 Planning Consultation
DCC PUBLIC Page 4 of 24
Service Providers, enabling DCC to gauge capability and better inform BEIS as to
which delivery option(s) is/are most appropriate;
A Development Phase – where DCC commences development of Integration Path
solutions to improve understanding of delivery confidence and cost information and
including a BEIS checkpoint for decisions to proceed; and
A Transition & Enrolment phase – where DCC finalises the development and
integration testing of its solution(s), and suppliers carry out user integration testing with
the DCC before undertaking any necessary end-to-end testing and enrolment activities.
These phases are summarised in section 3 of this report and set out in more detail at Annex
A. A milestone table setting out planned dates for key activity is included at Annex B. A high
level (‘Level 0’) plan-on-a-page setting out these phases, with descriptions of the activities
expected to be undertaken by DCC and energy suppliers is set out at Annex C, alongside a
more detailed plan-on-a-page with additional workstream detail. This document also
considers the overall delivery confidence in the plan, and whether and how contingency
should be held and managed.
Throughout all of these phases DCC commits to ongoing consultation with energy suppliers
and other relevant stakeholders. This includes engagement on elements including user
facing design requirements and specifications; eligibility and timing for enrolment of specific
SMETS1 meter cohorts; and user testing. DCC recognises that all of these elements will
need to be captured in the Smart Energy Code (SEC) via changes delivered by BEIS,
therefore ultimately subject to decisions by BEIS.
Accordingly, we note that BEIS will remain the ultimate decision-maker in relation to the
design of the SMETS1 enrolment and adoption programme and carry out the following
activities:
development of changes to the ‘main body’ text of the SEC;
management of the SEC Subsidiary Documents (SSDs) and design baseline via the
Technical and Business Design Group (TBDG);
bringing the relevant SEC changes and SSDs into force at the appropriate times to
support activities such as testing and enrolment;
deciding on all design options including User Interface, Communication Services and
UTRN models; and
providing confirmation for DCC to provide a SMETS1 Service for specific meter
cohorts.
SMETS1 Planning Consultation
DCC PUBLIC Page 5 of 24
2 Refining Delivery Options
DCC’s draft IEPFR set out a number of options for how the existing SMETS1 infrastructure
and devices could be integrated into a DCC-provided SMETS1 Service. For some, such as
communications services and pre-payment options, decisions on which to incorporate into
the DCC SMETS1 Service will not affect the delivery plan. However, decisions relating to two
of the key areas where optionality existed will impact delivery. These are the User Interface
and the Integration Path.
User Interface
For the purpose of the proposed plan, DCC has assumed that User Interface Options 1
(DUIS-type provided by DSP) and 2 (DUIS Type provided by another party) from the IEPFR
remain open. DCC recognises the need for a timely delivery of its SMETS1 Service, and
considers that, were User Interface Option 3 (non-DUIS type) to be selected, the duration of
the requirements and design activity to specify the new SMETS1 message format (in
collaboration with stakeholders) would be excessively long. This would result in a delay to
the publication of a DCC SMETS1 User Interface Specification of at least 3 months. Should
BEIS require User Interface Option 3 to be progressed, then the DCC would need to update
its delivery plan. In the case of Options 1 and 2, optionality remains over whether this
interface is developed by the existing DSP or a new provider.
Integration Path
The IEPFR included options for DCC to integrate to incumbent SMSOs (Integration Path
option 5 in the IEPFR (IP5)), or for DCC to integrate to SMETS1 meters directly (Integration
Path option 4 in the IEPFR (IP4)), replacing the incumbent SMETS1 SMSOs with an
alternative solution. In addition, a hybrid approach where a mix of direct to SMSO and direct
to meter approaches is used for different meter cohorts was also deemed feasible.
The diagram overleaf sets out the key design optionality still under consideration by DCC.
The final design will include: one of the two user interface options; either reuse of existing
DSP functionality or the introduction of a new data services capability; either one, two or all
three of the integration paths between the data services capability and the meter; and one of
two UTRN generation solutions. In terms of decision making, none of these areas of
optionality are mutually exclusive i.e. any path from user through to meter is currently
considered viable.
SMETS1 Planning Consultation
DCC PUBLIC Page 6 of 24
The two User Interface and Integration Path options may employ different approaches to the
re-use or replacement of the incumbent SMETS1 SMSOs and existing DSP and could also
include a new service provider developing elements of the solution (e.g. the functionality that
converts DUIS/MMC messages to and from specific SMSO business language). In addition,
DCC recognises that a hybrid approach could ultimately be implemented. Which of the user-
facing options will ultimately be selected will be determined by BEIS following input from
DCC (and industry stakeholders) on technical feasibility considerations; delivery capability
and timing; commercial considerations; and the cost effectiveness of each approach. DCC
has already begun consideration of the integration options on a meter-cohort by meter-cohort
basis and proposes that this approach continues, to enable BEIS to make cohort-based
decisions to proceed, as indicated in the Development Phase on the plan.
The proposed plan sets out a number of parallel activities to reflect that options remain open
at this stage. The plan also highlights that DCC will be providing updates and improved
information to BEIS on cost and deliverability of the various options at relevant stages, which
will enable final BEIS decision(s).
DCC Users
DCC User Interface
SMETS1 CH
Ui
NEW DCC User
InterfaceSMETS1 CSPs
New Interface for SMSO /
SMETS1 Service
SMETS2 CSPs
DCC User InterfaceSMETS2
CH
IP
SMETS2
SMETS1
Ui1
Ui2
IP5a
IP5b
IP4
SMETS2 DSP
SMETS1 DSP
SMETS2 DSP
Key and Security Manager U
TRN
G
ener
ato
r
Device Translation
Comms Manager
Request Manager
SMSO
DUIS Format Request /
MMC Response
DUIS Format Request & Response
DCC Users
SMSO
PKI Manager
PKI Manager
Comms Manager
Request Manager
SMETS1 Service Provider
SMETS1 Service Provider
PP1
PP2
DSP Translation
Device Translation
Comms Manager
Request Manager
Device Translation
Comms Manager
Request Manager
DSP Translation
Device Translation
DSP
Translation
New
SMETS1 Planning Consultation
DCC PUBLIC Page 7 of 24
3 Overview of the Plan
This section summarises the expected activity in the 4 phases of the plan, which sets out a
number of parallel activities to drive out improved cost and delivery capability information to
support decision making by BEIS. The 4 phases reflect this by focussing on:
Initiation – starting high level design and user engagement while commencing initial
commercial discussions with the existing and potential providers of SMETS1 services –
the key milestone being a BEIS decision on which IEPFR options DCC should continue
to pursue;
Discovery – refining design products and using the June decisions from BEIS to drive
commercial negotiations towards contract finalisation and gaining insight into the
delivery capability of existing DSP, incumbent SMSOs and new service providers –
leading to the provision of updated information to BEIS on delivery options and costs;
Development – consulting with customers on SEC Subsidiary Document requirements
whilst undertaking core development and testing activity with new and or existing
service providers (with development and testing activity phased so that those that are
independent of the SEC requirements commence earlier, prior to baselining of the SEC
Subsidiary Documents); and
Transition and Enrolment – following BEIS direction to proceed, DCC will finalise
development and testing activity, prior to user testing and initial (and enduring) service
operations.
3.1 Initiation Phase
The Initiation Phase is currently underway and includes DCC’s finalisation of its analysis of
IEPFR responses, along with the continuation of a range of activities:
Design and Consultation – the activity that DCC will undertake as it develops and
refines its proposals for the design of the SMETS1 Service, and translates these into
proposed regulatory requirements for SEC Subsidiary Documents (SSDs). Customer
engagement and consultation will be key in ensuring these are fit-for-purpose.
Existing Data Service Provider Activity – initial technical and commercial
engagement with the Data Service Provider (DSP) regarding changes that may be
needed to enable the SMETS1 Service delivery options (e.g. new requirements for a
User Interface) should the existing DSP be selected to provide various services.
SMSO activity – planning work with the existing SMETS1 service providers, to gather
information regarding connectivity, service management and preferred methods of
contracting should they be selected to provide various services.
New provider activity – procurement of a software development partner to support
various aspects of the SMETS1 Service, should this be required.
Foundation Communications Service Provider (FCSP) activity – working with
existing SMETS1 FCSPs with the aim of getting updated indicative enduring pricing
and negotiating contracts for any services needed to support software development.
SMETS1 Planning Consultation
DCC PUBLIC Page 8 of 24
Network and Hosting Activity – working with the market with the aim of getting
updated indicative enduring pricing for hosting the SMETS1 Service and managing the
network connections for the SMETS1 Service.
The culmination of the Initiation Phase will be an initial decision from BEIS on the IEFPR that the DCC has submitted which will inform and refine DCC’s activities in the Discovery Phase. For planning purposes, we have assumed that BEIS will require approximately one month to consider the IEPFR and respond to DCC after submission.
User activity
During the Initiation Phase DCC will be continuing the ongoing bilateral engagement it has
been undertaking with prospective SMETS1 Service users as well as current and prospective
service providers.
Initiation Phase Milestones
Milestones in the Initiation phase of the plan include:
the submission of the final IEPFR to BEIS (published on 12 May 2017); and
a BEIS Decision to DCC by 16 June 2017.
3.2 Discovery Phase
The Discovery Phase comprises DCC’s continued and more intensive engagement with
prospective and existing service providers, including early development activity, to gauge
capability and cost-effectiveness of solutions, taking into account the outcome of the BEIS
Decision on IEPFR options in June. Workstream activity includes:
Design and Consult – BEIS has indicated to the DCC that it will itself take forward the
development of the main body SEC changes for the provision of the DCC SMETS1
service; with DCC developing and submitting to BEIS proposed requirements in SSDs.
DCC proposes to work with customers and other stakeholders to develop the proposed
high-level design(s) to inform BEIS’ drafting of the main body changes, and to develop
a first tranche of SSDs. DCC expects this first tranche to cover key ‘user-facing’ SSDs
with a consultation planned in September 2017. DCC will engage with stakeholders
throughout the Initiation Phase to define the scope of, and share timing for, subsequent
tranches of SSDs. DCC proposes that SSDs are consulted on, submitted to BEIS and
once approved by BEIS, then subject to change control via the transitional Technical
and Business Design Group before being introduced into the regulatory framework.
Existing DSP Activity – primary activities proposed include the conclusion of the DSP
Impact Assessment process. This will agree the operational costs and services for the
DSP elements of the enduring SMETS1 solution should the DSP be selected to
provide these services. The other key activity proposed is early DSP system
development work on elements of the proposed SMETS1 solution.
SMSO activity – negotiating contracts for enduring service provision from incumbent
SMSOs should IP5 be chosen. DCC is also expecting to contract with SMSOs to
undertake initial development work to inform BIES decision making. This development
work will aid in demonstrating capability of and confidence in prospective service
providers.
SMETS1 Planning Consultation
DCC PUBLIC Page 9 of 24
New provider activity – primary activities proposed are the early development of
aspects of the SMETS1 user interface (should BEIS select this as an option) and data
processing and message translation services, should the new provider be selected to
provide these services. Additionally early development of other services would take
place (for example key management services, security audit services etc.).
FCSP activity – negotiation of enduring communications service provision with
incumbent FCSPs.
Network and Hosting Activity – procurement of any new services required.
User activity
During the Discovery Phase DCC will be engaging with prospective users to support DCC’s
development of draft SSDs, so that they are suitably mature prior to formal consultation and
baselining. DCC would also expect that at this stage in the plan prospective users would
undertake assessments of the impacts to their businesses (in terms of system and process
changes and resource requirements) and engage with DCC on enrolment approach and
timing.
Discovery Phase Milestones
The key milestones in the Discovery Phase of the plan (and conclusion of the phase) are:
the submission of updated information on delivery capability and solution option costs
to BEIS following further engagement with prospective service providers on
24 August 2017 (to support final decision making in late 2017); and
the opening of a consultation on the first tranche of SMETS1 requirements in SSDs on
31 August 2017.
3.3 Development Phase
This phase of the plan covers the commencement of the core development activity (design,
build, test and release) that will be undertaken by DCC and selected SMETS1 Service
Providers. As DCC has yet to appoint service providers and the design decisions remain
open, it is not possible to set out a granular and precise delivery timetable for the
development activity required to deliver the SMETS1 Service. However, based on
engagement with stakeholders and (potential) Service Providers to date and our team’s
experience in IT delivery, DCC plans to:
be in a position to formally consult on the first tranche of SSD content;
be able to continue development and testing activity with potential Service Providers
(including SMSOs); and
regularly inform BEIS of all commercial developments, so that they can feed this
information into their industry wide cost-benefit analysis.
DCC expects that BEIS will use this information to undertake a final decision to proceed for
each meter cohort in late Q4 2017.
User activity
SMETS1 Planning Consultation
DCC PUBLIC Page 10 of 24
In the Development Phase prospective service users will need to support, where relevant,
the development of further SSD development activity, as well as providing formal responses
to consultations on first-tranche SSDs. It is during this phase that DCC envisages
prospective service users may commence development work on changes to their systems to
enable them to interface with DCC’s SMETS1 Service.
Development Phase Milestones
Milestones in the Development Phase of the plan include:
the baselining of the first tranche of SSDs on 31 October 2017; and
the provision of updated cost information to BEIS in November 2017
The end of this phase is a BEIS decision to proceed for each of the SMETS1 meter cohorts in late Q4 2017.
3.4 Transition and Enrolment
The final phase of the draft plan is Transition and Enrolment. In this phase, design, build,
development and test activity will continue, leading up to the SMETS1 Service reaching
‘Initial Operational Capability’ (IOC), which is the window of time during which DCC expect to
be able to offer a SMETS1 Service in respect of at least one cohort of SMETS1 meters.
There may be multiple releases of Operational Capability (to bring further cohorts on-
stream). The date of Operational Capability releases may therefore be cohort specific and
will depend, in part, on the integration path chosen. DCC has made a planning assumption
that the Final Operational Capability (where DCC is able to offer a SMETS1 Service in
respect of the final cohort) will follow 1 year after IOC.
User activity
In this phase it will be necessary for prospective users to execute the required changes to
their systems and processes to utilise the SMEST1 Service, and participate in testing prior to
migrating cohorts of meters.
Transition and Enrolment Phase Milestones
Milestones in the Transition and Enrolment Phase of the plan include:
earliest Initial Operational Capability from 27 Apr 2018 (or 31 August 2018 where all
contingency is used); and
earliest Final Operational Capability from 26 Apr 2019 (or 30 August 2019 where all
contingency is used).
SMETS1 Planning Consultation
DCC PUBLIC Page 11 of 24
4 SMETS1 Service Users - Activity and Engagement
It is DCC’s view that the SMETS1 Service must meet the needs of DCC’s customers. Not
only those who enrol SMETS1 Meters, but also those who take on enrolled SMETS1 meters
where consumers change supplier and other parties which may wish to access functionality
on enrolled meters.
4.1 Engagement on Design and Enrolment Matters
DCC recognises and understands the important of effective engagement with prospective
Users of the SMETS1 Service to inform its development. For those SMETS1 Service Users,
DCC will be continuing its bilateral engagement across the phases of the plan (as set out in
the User activity sections of Section 3, above). DCC will use this engagement to build an
understanding of when and how meters might be migrated into the SMETS1 Service. In
terms of decision making, DCC proposes that it continues to support user considerations of
these matters and feed user requirements and requests into BEIS (along with other relevant
considerations, such as impact on development, cost and risk).This will enable BEIS to make
final decisions based on assessment of this information, in the context of its wider smart
metering benefits case.
More broadly, input from all stakeholders will be sought across all phases, including formally
in response to consultations on products and proposals, at governance fora (i.e. SMDG, IMF
etc.), and working level engagement, such as DCC’s SMETS1 design forum (which will play
an analogous role to DCC’s Smart Metering Design Forum, and allow DCC and stakeholders
to consider SMETS1 related matters collectively during the design and delivery of the
service). The Direction received from BEIS to prepare this plan includes a requirement to
provide for reporting of progress to BEIS via the Implementation Managers Forum (IMF).
DCC welcomes this requirement, and proposes that key elements of this plan are
incorporated into the Joint Industry Plan managed by IMF. DCC are implementing
Government policy and by the programmes’ incorporation into BEIS’s Transitional
Governance structure, DCC expects that plan progress is reported to the Smart Metering
Delivery Group (SMDG), and where required issues and risks are escalated from IMF to
SMDG for consideration. BEIS has previously indicated that a new sub-group of the
Technical and Business Design Group (TBDG) will be convened to focus on matters
specifically relating to SMETS1, and DCC expects to be regularly and fully involved in this
forum, updating on design progress and sharing design artefacts for discussion.
DCC will ensure that internal governance aligns with external engagement by ensuring the
SMETS1 Programme Director attends SMDG. Internal DCC governance is overseen by a
DCC Programme Board chaired by the Programme Director with a representative from BEIS
invited to attend. This board is supported by an Enrolment and Adoption Forum where DCC
and BEIS meet bilaterally to consider risks and issues, and tracks progress against the plan.
4.2 Engagement on Security matters
BEIS will provide direction as to the acceptable residual risk of the enrolment options and the
associated security controls that DCC should adopt when enrolling and adopting SMETS1
Services and it will be necessary for DCC to accommodate this within their solution. DCC
was required to consider security risks under section N2.10 of the SEC in the development of
SMETS1 Planning Consultation
DCC PUBLIC Page 12 of 24
the IEPFR. In complying with the requirement, DCC has engaged with industry experts on
security matters through the SEC Panel’s Security Sub-Committee (SSC) during its
development of the IEPFR (as specifically required in Section N2.12 of the SEC). DCC sees
great value in continuing and increasing its dialogue with the SSC to share and discuss
security information with industry stakeholders that it could not do via public consultation.
DCC therefore proposes to request to the SEC Panel that it maintains engagement with the
SSC and shares security related elements of consultations with them, in the same way it has
done for the consultation and review of its IEPFR material.
5 Assumptions, Dependencies and use of Contingency
DCC has captured a series of core assumptions on which the plan is built, as well as the key
external activities and milestones which are outside the control of DCC, on which successful
delivery of these phases depends. These are as follows:
Assumptions:
DCC Delivery Approach – DCC deploys an iterative, flexible development approach
where delivering new capability and as opportunities allow for other elements of the
service whilst building in the need for consultation with, and an approach that works
for, DCC’s stakeholders.
There is no dependency between finalising high level requirements and
procuring new capability, as this procurement activity is covering base development
capability and as such these activities can run in parallel.
Similarly, there is no dependency between a BEIS IEPFR June decision and
procuring new capability
A User Interface which uses the DCC User Interface Specification message
format is selected as part of the IEPFR options decision – DCC will capture only
detailed requirements and design for User Interface options 1 and 2 (DUIS-based
interfaces), and not option 3 (‘new’ non-DUIS interface). DCC considers that were User
Interface Option 3 to be selected, the duration of the requirements and design activity
would be extended relative to that shown in DCC's delivery plan, resulting in a delay to
the publication of a DCC SMETS1 User Interface Specification of at least 3 months.
That the timely delivery of milestones in this plan can be achieved in the context
of the testing environments available and the various DCC System Releases
scheduled during lifetime of the plan, and that any related risks that are identified can
be mitigated or retired.
Where DCC integrates to an incumbent SMSO, there are initially no material changes
required to the SMSO technical security model.
SMETS1 Planning Consultation
DCC PUBLIC Page 13 of 24
Dependencies:
Energy Suppliers, SMETS1 SMSOs/CPSs and prospective Software developers
engage with DCC to enable DCC to provide robust cost information to inform
decisions on the makeup of the SMETS1 Service prior to the Transition & Enrolment
Phases.
Energy Suppliers, SMETS1 SMSOs/CPSs, the SMETS2 DSP and prospective
Software developers support DCC’s iterative design, build, test and release
process.
BEIS decisions are undertaken in a timely manner in accordance with the plan,
accepting that prior agreed information has been exchanged in accordance with the
plan.
DCC has developed this plan based on best-case delivery timescales for the key elements
within it. Noting the outstanding optionality contained within it, DCC’s dependency on other
industry participants’ engagement in delivering it and on BEIS in the form of timely decision
making and direction, DCC proposes that 4 months’ time contingency be held against the
plan, managed by DCC but drawn-down only after industry consultation recognising the
impacts this may have on supplier and wider stakeholder plans. DCC proposes this is done
through IMF and SMDG given their role and oversight of industry delivery as a whole.
Noting the lack of granularity in the plan beyond 2017, DCC expects those elements of the
plan will be subject to revision at regular points, to reflect IEPFR options decisions,
stakeholder feedback from consultations, updated assumptions, and in light of negotiations
with prospective service providers. However, DCC would like to note that any review would
take place in accordance with the requirements of Condition 13 of the DCC Licence (e.g.
following direction by BEIS to undertake a review). At this stage in the delivery of the
programme, taking into account the dependencies listed above, there is no evidence to
suggest that DCC should require further time than that factored into a contingent plan (i.e.
that IOC would commence no later than August 2018).
Following consultation and approval of the proposed plan by BEIS, DCC proposes to work
with IMF members to incorporate the key elements of the SMETS1 plan into the Joint
Industry Plan.
6 Consultation process and next steps
This consultation closes on 26 May 2017. Please email your response to
Contents of responses may be (where not marked confidential) shared with other
stakeholders. Please state whether all or any part of your response is confidential. Please
note that responses in their entirety (including any text marked confidential) will be shared
with the Department for Business, Energy and Industrial Strategy (BEIS) and may be made
available to the Gas and Electricity Markets Authority (the Authority).
If you have any questions in relation to this consultation, please contact Tom Rothery on
SMETS1 Planning Consultation
DCC PUBLIC Page 14 of 24
7 List of consultation questions
Q1
Please provide your views on DCC’s proposed approach to delivery, for
example whether the phases are appropriate and the parallel activity with
prospective SMETS1 Service Providers. ?
Q2 Do you think the milestones in the plan are appropriate – are there any
additional milestones you would expect to see at this stage?
Q3 Please provide your overall views on the timetable for the plan. DCC is
specifically interested in views relating to timing and assumptions
underpinning user readiness for test activity.
Q4 Do you agree with the assumptions and dependencies set out in the
consultation? Please provide a rationale for your views. Are there others
which have not been included?
Q5 Please provide any comments you have on the proposals for user
engagement.
SMETS1 Planning Consultation
DCC PUBLIC Page 15 of 24
Annex A – Planned activity in detail
Further detail on the activities and milestones within each phase is provided below.
1 Initiation Phase
The Initiation Phase is currently underway and involves DCC’s finalisation of its analysis of
IEPFR responses, along with the continuation of a range of activities across the work-areas
(and swim-lanes in the plan) described below.
Design and Consultation
The Design and Consult swim-lane sets out the activity that DCC will undertake as it
develops and refines the design of the SMETS1 Service, and translates these into regulatory
requirements in SEC Subsidiary Documents (SSDs). Customer engagement will be key in
ensuring these are fit-for-purpose. In the Initiation Phase, DCC will continue high-level design
activity, which covers the development of high-level requirements for the SMETS1 system as
a whole. Many of these requirements relate to the user-facing elements of the plan, (for
example, the user-interface for the SMETS1 Service, and those relating to any pre-payment
Unique Transaction Reference Number (UTRN) generation that forms part of the service)
and during this phase DCC will begin the process of developing and sharing draft high-level
design proposals with stakeholders. DCC proposes to do this via a regular SMETS1 User
Forum, which will be analogous in form and function to DCC’s Smart Metering Design
Forum, and provides a means for DCC to share initial thinking with industry, and for industry
to support the refinement of DCC’s proposals.
Existing Data Service Provider Activity
To enable delivery of the SMETS1 Service as quickly as possible, DCC has commenced
initial engagement with its Data Service Provider (DSP) regarding changes that may be
needed to enable the SMETS1 Service (e.g. new requirements for a User Interface). These
have taken the form of two concurrent information requests, as follows:
A Preliminary Assessment, covering the modification of the existing DSP SMETS2
service to support SMETS1, which will deliver:
a more detailed view of technical feasibility;
refined estimate of the timescales that would be required for the implementation
of the Change;
a “rough order of magnitude” cost to design, build, test and release the modified
DSP service;
a “rough order of magnitude” impact on the cost to operate the DSP service;
a fixed price for the initial preparation, negotiation and finalisation of an Impact
Assessment; and
the timescales for the initial preparation and delivery of an Impact Assessment;
and
A Project Request, to agree the project to undertake design, build, test and release of
modification of the existing DSP SMETS2 service to support SMETS1.
The DSP will also undertake a project to define:
SMETS1 Planning Consultation
DCC PUBLIC Page 16 of 24
Modifications needed to the DCC User Gateway Interface Design Specification
(DUGIDS) to accommodate SMETS1 Meters; and
A generic SMETS1 Interface Specification (between DSP and SMETS1 service
providers).
SMSO activity
In the Initiation Phase of this swim-lane DCC proposes to increase its planning work with
energy suppliers and the SMETS1 service providers with whom they contract, to gather
information regarding:
connectivity, service management and adoption preferences of market participants
(which would include planning for moving commercial management of meters from
suppliers to DCC and tri-partite negotiation and planning for commercial management
of enrolled meters; and
preferences for sequencing in any staged transition, and the rate at which enrolment of
meters might take place (in conjunction with taking similar views from energy
suppliers).
DCC will work with SMSOs with the aim of:
getting updated indicative enduring pricing from them; and
negotiating software development contracts (signature will be subject to the outcome of
the first BEIS Decision milestone).
SMSOs will also be invited to assist with the DSP provider project to define:
Modifications needed to DUGIDS to accommodate SMETS1 Meters; and
A generic SMETS1 Interface Specification (between DSP and SMETS1 service
providers).
New provider activity
DCC’s view is that it should procure a software development partner to support the SMETS1
Service, because there are elements of the DCC SMETS1 Service that do not currently exist
in DCC Systems including, but not limited to:
the functionality required to translate service requests submitted to DCC by Users into
the relevant SMSO service request format or SMETS1 device command;
interfaces to SMSOs and/or SMETS1 FCSPs; and
the functionality required to generate prepayment UTRNs for SMETS1 Meters.
In the period to early June, DCC will therefore undertake a procurement to select a Software
Development provider to support the development of any new capability not being provided
by existing DCC service providers or by SMSOs. This activity will include:
getting updated indicative build pricing from the market; and
negotiating a software development contract capable of signature by early June
(signature will be subject to the outcome of the BEIS Initial Options Decision
milestone).
Foundation Communications Service Provider (FCSP) activity
SMETS1 Planning Consultation
DCC PUBLIC Page 17 of 24
In the period to early June, DCC will work with existing SMETS1 FCSPs with the aim of:
Getting updated indicative enduring pricing from them; and
Negotiating contracts for any services needed to support software development.
Network and Hosting Activity
Through this activity, DCC will work with the market with the aim of getting updated indicative
enduring pricing for hosting the SMETS1 Service and managing the network connections for
the SMETS1 Service.
User activity
During the Initiation Phase DCC will be continuing the ongoing bilateral engagement is has
been undertaking with prospective SMETS1 Service users as well as current and prospective
service providers. It will be necessary for prospective users to support DCC by assessing
and steering the development of high-level design during this period.
Initiation Phase Milestones
Milestones in the Initiation phase of the plan include:
the submission of the final IEPFR to BEIS (published on 12 May 2017); and
a BEIS Decision to DCC on 16 June 2017.
The culmination of the Initiation Phase will be a decision from BEIS on delivery option(s)
which will inform and refine DCC’s activities in the Discovery Phase.
2 Discovery Phase
The Discovery Phase comprises DCC’s continued and more intensive engagement with
prospective and existing service providers to gauge capability and cost-effectiveness of
solutions, taking into account the outcome of the BEIS Decision on IEPFR options in June.
DCC will work closely with these parties to refine the information which will inform further
decisions on the composition of the SMETS1 Service and enabling delivery work to
commence.
Design and Consult
User facing requirements for the SMETS1 Service will need to be embodied within changes
to the SEC, both in the main body of the SEC and in new or amended SEC Subsidiary
Documents (SSDs).
BEIS has notified DCC that it does not intend to direct DCC under Section N5.1 of the SEC
to prepare Initial Enrolment Code Amendments, instead intending to develop supporting
amendments to the ‘main body’ of the SEC itself.
DCC supports this approach, given BEIS’s greater expertise in this space, and on that basis,
the proposed plan for consultation places responsibility for main body code amendments on
BEIS. However, recognising that the technical expertise for developing the detailed interface
design (set out in SEC Subsidiary Documents such as DUIS) lies with the DCC, DCC
proposes that it develops proposed drafting for any new SSDs, or changes to existing
subsidiary documents, that are required for the SMETS1 Service.
SMETS1 Planning Consultation
DCC PUBLIC Page 18 of 24
During the Discovery Phase DCC proposes to work with customers and other stakeholders
to develop the high-level design(s) into a first tranche SSDs, in readiness for a formal
consultation on this content. DCC expects this first tranche to include the key documents that
will enable Users to commence their own system designs, primarily the DCC User Interface
Specification (DUIS), although others may be included.
Whilst this first tranche of SSD requirements is developed, DCC will continue to work on the
design of other components of the service. DCC will engage with stakeholders throughout
the Initiation Phase to define the scope of, and share timing for, subsequent tranches of
SSDs and their proposed consultation dates. DCC anticipates that the plan is updated as
timelines for further tranches are clear.
DCC proposes that SSDs are consulted on, approved by BEIS, and then subject to change
control via the transitional Technical and Business Design Group before being introduced
into the regulatory framework.
Existing DSP Activity
There are three primary activities in this area during the Discovery Phase:
In Q3 2017, subject to the outcome of the BEIS Options Decision milestone, DCC
commence the DSP Impact Assessment process to agree the operational costs and
services for the DSP elements of the enduring SMETS1 solution;
DCC may require updates to the other, secondary, components of its Data Services
that are not provided by the DSP (e.g. Smart Key Infrastructure) – any change
requests required for this will be managed in parallel and are not expected to be on the
critical path; and
Following approval of the Project Request raised in the Initiation Phase, the DSP will
commence early system development work on elements of the proposed SMETS1
solution. This enables DSP to work towards the enduring solution but also provides
useful benchmarking of its delivery capability and its performance will be an input into
the proposed 24 August 2017 submission of additional information to BEIS.
SMSO activity
In the period from early June to mid-August 2017, DCC intends to negotiate contracts for
enduring service provision from incumbent SMSOs – although we recognise that contract
finalisation may extend beyond this period. It is our assumption that DCC can finalise
positions with service providers in advance of BEIS decision points where materiality is low
and DCC can demonstrate that it is economically efficient to do so. DCC intends to engage
with BEIS on the materiality thresholds to ensure that due process is followed.
DCC is also expecting SMSOs to undertake initial development work in this phase (e.g. the
functionality to convert DUIS-type messages into their own business language). As with the
DSP and new service provider this activity enables earliest possible service delivery and
provides information on delivery capability as well as cost. This information will be passed to
BEIS to inform their understanding of the delivery timescales and risks associated with the
decision on enrolment of eachSMETS1 cohort.
SMETS1 Planning Consultation
DCC PUBLIC Page 19 of 24
New provider activity
Primary activity proposed is the early development of aspects of the SMETS1 user interface
(should BEIS select this as an option). In addition, DCC may require other, secondary,
services (for example key management services, security audit services etc.) – any
procurements required for this will be managed in parallel and are not expected to be on the
critical path.
FCSP activity
In the period from early June to mid-August, DCC will aim to negotiate enduring
communications service provision with incumbent FCSPs. The outcome of these
negotiations including proposed costs and key commercial arrangements will be shared with
BEIS.
Network and Hosting Activity
In Q3 2017 DCC intends to procure any new services required. Prior to procurement
information will be shared with BEIS to inform their final decision on the composition of the
SMETS1 Service.
User activity
During the Discovery Phase DCC will be engaging with prospective users to support DCC’s
development of draft SSDs, so that they are suitably mature prior to formal consultation and
baselining. DCC would also expect that at this stage in the plan prospective users would
undertake assessments of the impacts to their businesses (in terms of system and process
changes and resource requirements) and engage with DCC on preferred enrolment
approach and timing.
Discovery Phase Milestones
Milestones in the Discovery Phase of the plan include:
the submission of updated information to BEIS following further engagement with
prospective service providers on 24 August 2017; and
the opening of a consultation on the first tranche of SMETS1 requirements in SSDs on
31 August 2017.
3 Development Phase
This phase of the plan covers the commencement of the main core development (design,
build, test and release) that will be undertaken by DCC and selected SMETS1 Service
Providers. At this stage in the development of the plan, recognising the ongoing commercial
and technical work that will inform BEIS’s decisions on options that will follow, it is not
possible to set out a granular and precise delivery timetable for the SMETS1 Service.
However, DCC expects that at the start of this phase of activity, it will be in a position to
formally consult on the first tranche of SSD content.
DCC also considers that at the start of this phase it will be able to continue development and
testing activity with potential Service Providers (including SMSOs).
SMETS1 Planning Consultation
DCC PUBLIC Page 20 of 24
DCC proposes that during this phase, BEIS are kept informed of all commercial
developments, so that they can feed this information into their final policy analysis and
considerations for the SMETS1 Service. DCC expects that BEIS will use this information to
undertake a final decision for each meter cohort by the end of Q4 2017.
User activity
In the Development Phase prospective service users will need to support, where relevant,
the development of further SSD development activity, as well as providing formal responses
to consultations on first-tranche SSDs. It is during this phase that DCC envisages
prospective service users will commence development work on changes to their systems to
enable them to interface with DCC’s SMETS1 Service. DCC proposes that it works with
each energy supplier to develop a shared view of the operating model for that supplier’s
meters. DCC expects that the operating model will address at least the following areas:
Establishing the demand for DCC services and the pattern of usage; and
Planning for testing.
Development Phase Milestones
Milestones in the Development Phase of the plan include:
the baselining of the first tranche of SSDs on 31 October 2017; and
the provision of updated cost information to BEIS on 17 November 2017
The end of this phase follows BEIS go/no go decision for each of the SMETS1 meter cohorts in late Q4 2017.
4 Transition and Enrolment
The final phase of the draft plan is the Transition and Enrolment. In this phase, design, build,
development and test activity will continue, leading up to the SMETS1 Service reaching
‘Initial Operational Capability’ (IOC), which is when DCC expect to be able to offer a
SMETS1 Service in respect of one or more cohorts of SMETS1 meters. Based on the
engagement undertaken with stakeholders in the Initiation Phase to date, coupled with
DCC’s learnings from its Enrolment Options Testing (EOT) project, DCC expects that the
date at which IOC will be ready for cohorts of meters is dependent on two key factors:
the integration path chosen, because the critical path depends on the IEPFR
integration path and other options chosen, and
the particular requirements and constraints of the stakeholders for each meter cohort.
For integration path 5b the critical path is primarily driven by indicative timescales from
SMSOs for the necessary changes to their interfaces to support the translation of:
inbound ‘DUIS-like’ service requests; and
outbound responses/alerts into ‘MMC-like’ output format with a DUIS wrapper.
DCC expects that SMSOs are likely to also need to make changes to underlying data
structures within their Head End Systems to enable this translation, and may need to add
SMETS1 Planning Consultation
DCC PUBLIC Page 21 of 24
new low level device commands to fully support the SMETS1 core communication services
(subject to BEIS’ decision on the core service offering).
For integration paths 4 and 5a however, the critical path is primarily driven by new service
provision in which the DCC SMETS1 Service performs translation of DUIS-like service
requests into the relevant device command protocol or current SMSO interface format, and
of device and SMSO responses and alerts into MMC-like output format with a DUIS wrapper.
This minimises changes for SMSOs and EOT has provided a good initial evidence base for
the timeline to develop the translation layer both for devices and SMSOs, which will be
refined further through the Initiation, Discovery and Development phases.
User activity
In this phase it will be necessary for prospective users to execute the required changes to
their systems and processes to utilise the SMEST1 Service. Prospective service users will
then need to undertake testing, execute operational transition and prepare for service
operation and management. Following conclusion of service testing, and requisite readiness
checks and gateways undertaken, the DCC SMETS1 service will then be declared live. DCC
SMETS1 service users will then be able to conclude their own testing and service readiness
processes in readiness for enrolment and participate in the testing prior to connecting to the
service and migrating cohorts of meters.
Transition and Enrolment Phase Milestones
Milestones in the Transition and Enrolment Phase of the plan include:
earliest Initial Operational Capability from 27 April 2018 (or 31 August 2018 where all
contingency is used); and
earliest Final Operational Capability from 26 April 2019 (or 30 August 2019 where all
contingency is used).
SMETS1 Planning Consultation
DCC PUBLIC Page 22 of 24
Annex B – SMETS1 delivery plan – Milestone Table
DCC proposes that the following milestones form the plan that DCC must take all
reasonable steps to implement; in accordance with Condition 13 of the Licence (should the
Secretary of State approve the plan).
ID Milestone/event Description Date
1 IEPFR submission Issue of final document updated following
consultation 12 May 17
2 LC13 Plan published for
consultation
Issue of document to SEC Parties for
consultation 12 May 17
BEIS Options Decision Initial decision from BEIS on delivery option(s)
which will inform and refine DCC’s activities in
the Discovery Phase
16 Jun 17
3 Updated Information from DCC
to BEIS (1)
DCC to provide BEIS with available
information to support decision-making 24 Aug 17
4 Tranche 1 SSDs consultation
starts
First period of consultation engagements
begins 31 Aug 17
5 Tranche 1 SSDs consultation
closes
First period of consultation engagements
closes 31 Oct 17
6 Updated Information from DCC
to BEIS (2)
DCC to provide BEIS with available
information to support decision-making 17 Nov 17
BEIS Direction BEIS to provide direction to DCC to proceed
on a per cohort basis 9 Dec 17
7 Initial Operating Capability (1
st
Cohort)
Earliest delivery of DCC operational readiness
to provide a SMETS1 service in relation to the
at least one meter cohort
27 Apr 18
7a Contingent Initial Operating
Capability (1st Cohort)
Contingent earliest delivery of DCC operational
readiness (using 4 months contingency
allocation)
31 Aug 18
8 Final Operating Capability
Earliest delivery of DCC operational readiness
to provide a SMETS1 service in relation to the
final meter cohort (12 months after 1st cohort)
26 Apr 19
8a Contingent Final Operating
Capability
Contingent earliest delivery of DCC operational
readiness to provide a SMETS1 service in
relation to the final meter cohort (using 4
months contingency allocation)
30 Aug 19
Numbered milestones constitute those which form part of the formal plan that DCC proposes is
submitted to the Secretary of State and against which progress is assessed
SMETS1 Planning Consultation
DCC PUBLIC Page 23 of 24
Annex C – Plans on a Page
Level 0 plan
SMETS1 Planning Consultation
DCC PUBLIC Page 24 of 24
Level 1 plan