GOVERNMENT OF PAKISTAN MINISTRY OF COMMUNICATIONS Contingency Plan For Monsoon Season 2017 National Highway Authority
Transcript
Page 1: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell

GOVERNMENT OF PAKISTANMINISTRY OF COMMUNICATIONS

Contingency Plan

For Monsoon Season 2017

National Highway Authority

Page 2: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell

List of Vulnerable/Critical Locations:

In the light of past flood experience since 2010, following points have been

identified as vulnerable points and must be kept under close vigilance and

monitoring:

i. N-95 (Fatehpur to Kalam Section)

ii. N-90 (Shangla to Besham Section)

iii. N-35 (between Thakot & Raikot)

iv. N-45 (Dir to Chitral)

v. N-15 (Balakot – Jalkhad – Chilas)

vi. N-5 (Peshawar – Nowshera – Khairabad) KPK

(Kot Sabzal – Ranipur – Hala) Sindh

(Karachi – Thatta) Sindh

vii. N-55 (Ramak – Karak) KPK

(DG Khan – Ramak) Punjab

(Kashmor – Ghouspur – Shikarpur – Larkana – Dadu) Sindh

viii. N-65 (Sukkur – Jacobabad – Dera Allah Yar)

ix. N-50 (D.I. Khan – Mughalkot)

x. N-70 (Muzaffargarh – DG Khan – Sakhi Sarwar)

xi. N-75 (Islamabad – Murree – Kohala)

xii. S-1 (Gilgit – Skardu)

xiii. S-2 (Kohala – Muzaffarabad)

xiv. S-3 (Muzaffarabad – Chakothi)

Vulnerable/Critical Locations

Page 3: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell

Regional Office, Flood Emergency Cell will perform

the following functions:

Contractors are put on red alert to meet any

eventuality.

Mobilization of contractors from a pool of

emergency contractors on as and when required

basis.

Availability of adequate machinery/manpower/

material to cope with any emergency situation with

sufficient financial resources.

Submission of Daily Occurrence Report to Flood

Emergency Cell in NHA Head Office.

Flood Response Strategy

Page 4: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell
Page 5: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell

Get occurrence report from all

regional offices at 1000 hrs.

Get information from Met Deptt.

About discharge in rivers & 24

hrs. rainfall prediction.

Prepare NHA situation report

based on above & circulate to:

a) Pak Army Military Operations

b) DG Engineers, Pak Army

c) Press Information Deptt.

d) NDMA

e) Ministry of Communications

NHA Head Office

(Operation Wing)

NHA Regional

GM Office

Prepare a daily occurrence

report for regional NHA road

network

24x7 Flood Cell

Prepare occurrence report

for Regional Office

Dy. Director (Maint)

Office

Occurrence

Report Daily Occurrence

Report by 1000 hrs.

Road Condition

Flood Response Strategy – Flow Chart

Page 6: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell

THANK YOU

Page 7: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell

The requisite explosive/ accessories for the breaching

section Head Muhammad Wala had already been provided to

Army Authority 313-Asulat Engineers Battalion Multan

Cantonment by NHA on 5th February 2015.

As per annual practice, the explosives and other material at

sites of pre-determined breaching sections and stone

reserve stock/flood fighting material is arranged at all

critical reaches.

The Explosives/Accessories were purchased and provided to

concerned quarters for monsoon season 2016, however, the

same were not utilized and still available in the stock. No

further demand has been received so far.

NHA has already arranged the emergency contractors with

adequate equipment/machinery to deal with any

eventuality in case of operating breach at Sher Shah

Railway Bridge.

EXPLOSIVE / ACCESSORIES FOR BREACHING SECTIONS

Page 8: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell

Detail of Explosive/Accessories for HMW Bridge:

Following the detail of Explosive/Accessories purchased in

the year 2016 from Wah Industries Limited Wah Cantt:

EXPLOSIVE / ACCESSORIES FOR BREACHING SECTIONS

Sr. No. Item Description Unit Quantity

1. PE-3A(450 Gram Slab) Kg 6534

2. Primer CE-1 07 No 600

3. Wabocard Meter 5280

4. Safety Fuze Meter 250

5. Det-No.33 (Electric) No 50

6. MS Elec. Delay Det (3M) No 50

7. Connecting Cable Meter 2000

8. Firing Cable Meter 100

Page 9: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell

Shaheed Benazir Bhutto BridgeFlood Flow Measuring Facilities & Strengthening flood embankment upstream

Package-IIIPackage-I

Package-II

Pkg-IV

Package-V (2A-2B)

Ka

shm

oo

rR

aja

np

ur

Package-IV (Guide

Bank)

- Left 2.158 km- Right 2.148 km

FPB (R/S)

Fakhar BandFPB (L/S)

Minchen Band

LOCATION MAP

N-

55

Zahirpir

Kot Mithan

Alternate Alignment

Proposed Bridge Over

Canal STA. 7+375

Proposed Rail Way Line

ChachranSharif

Proposed Bridge Over

Canal STA. 28+200

Proposed Bridge Over Railway Line STA. 27+200

Page 10: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell

Secretary Irrigation Punjab, Chief Engineer

Bahawalpur & D.G. Khan including other official of

Irrigation Department from RYK & D.G. Khan along

with Member (CZ) & PD (SBBB) visited the site on

20/06/2017 and decided to construct RMB on an

emergency basis to avoid the chances of breaching of

Package-II B and also to save Kot Mithan Town from

the upcoming flood.

On an emergent basis, NHA has taken up the partial

construction of RMB towards Kot Mithan to save the

Kot Mithan Town due to afflux.

Continue….

Shaheed Benazir Bhutto BridgeFlood Flow Measuring Facilities & Strengthening flood embankment upstream

Page 11: Contingency Plan For Monsoon Season 2017 Plan 2017/NHA.pdf · Contingency Plan For Monsoon Season 2017 ... viii. N-65 (Sukkur –Jacobabad ... 24x7 Flood Cell

Approximately 5.5 Km in length, the construction

work of RMB (Flood Embankment on upstream side) is

in progress. Whereas, there is no work in progress for

the strengthening of LMB (towards Chachran Sharif) as

no emergency work has been declared.

The approval of revised global PC-I including the cost

of both flood protection bunds is under process in

CDWP.

After the formal approval, the funds will be transferred

to Irrigation Department Punjab for the construction

of both marginal bunds.

Shaheed Benazir Bhutto BridgeFlood Flow Measuring Facilities & Strengthening flood embankment upstream