+ All Categories
Home > Documents > Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in...

Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in...

Date post: 04-Jun-2018
Category:
Upload: flyingcuttlefish
View: 230 times
Download: 1 times
Share this document with a friend

of 113

Transcript
  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    1/113

    DRAFT FINAL

    Bayou Corne Sinkhole Containment SystemMaintenance and Contingency Plan

    S u b m i t t e d b y :

    Texas Brine Company L.L.C.

    December 13, 2013

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    2/113

    Investig

    Bayou Corne Sinkhole ContainmentSystem Maintenance and ContingencyPlan

    Submitted by:

    Texas Brine Company L.L.C.

    4800 San FelipeHouston, Texas 77056

    Prepared by:

    4900 Pearl East Circle, Suite 300WBoulder CO 80301(303) 447-1823

    Fax (303) 447-1836

    Tetra Tech Project No. 114-010647

    December 13, 2013

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    3/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 i

    TABLE OF CONTENTS

    TABLE OF CONTENTS ..............................................................................................................i

    1.0 Background ...................................................................................................................1

    2.0 Introduction ...................................................................................................................43.0 Responsibility Matrix ....................................................................................................5

    4.0 Surface Water Quality Monitoring ................................................................................6

    5.0 Monitoring Sinkhole Growth And Levee Subsidence .................................................8

    6.0 Containment System Inspection Activities................................................................11

    7.0 Routine Maintenance Activities..................................................................................13

    8.0 Corrective Measures for System Damage .................................................................14

    9.0 Emergency Response Actions ...................................................................................16

    10.0 Addressing Potential Impacts to Bayou Corne .........................................................17

    LIST OF TABLES

    Table 1 Materials and Supplies for Containment RepairTable 2 Consultants and Contractors Available to Assist with Repairs

    LIST OF FIGURESFigure 1 Sinkhole Containment System Plan ViewFigure 2a Containment Berm and Sinkhole PlanFigure 2b Containment Berm and Sinkhole ProfilesFigure 3 Inclinometer, Tiltmeter and Water Level Instrument LocationsFigure 4 Proposed Southern Berm Relocation Option

    LIST OF APPENDICES

    Appendix A Surface Water Monitoring PlanAppendix B Sinkhole Water Quality Depth Profile Sampling Recommended Requirements

    Document (RRD-Gas-02)Appendix C Geotechnical Engineering Stability Report (To be added when report has been

    completed at the end of December 2013)Appendix D Storm Water Pollution Prevention PlanAppendix E Evaluation of the Bayou Corne Maximum Sinkhole Extent in Lateral Directions;

    and Comments on Maximum Bayou Corne Sinkhole Extents

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    4/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 1

    1.0 BACKGROUND

    Directive 5 of the Fourth Amendment to the Declaration of Emergency and Directive issued bythe State of Louisiana Department of Natural Resources Office of Conservation (Directive 5)requires Texas Brine Company, L.L.C. (TBC) to initiate installation of a containment systemaround the Bayou Corne sinkhole. Directive 5 further requires the sinkhole containment systemto prevent to the greatest extent practicable any dissolved concentrations of total petroleumhydrocarbons (TPH), elevated chlorides, or total dissolved solids (TDS) in the surface waterwithin the sinkhole and surrounding area from migrating in such a manner that will damage theenvironment.

    In response to Directive 5, an integrated containment system was developed and implementedby TBC. Since completion of the containment system, it has become apparent that naturalconditions also play a role in preventing the hydrocarbons and chlorides from escaping thesinkhole. As a result, the primary components of the containment system consist of:

    The naturally occurring hydraulic gradient whereby surface waters flow from areas

    surrounding the sinkhole towards, and then down into, the sinkhole. This hydraulic

    gradient results from the connection between the sinkhole waters and the Mississippi

    River Alluvial Aquifer (MRAA).

    A network of floating hydrocarbon control booms positioned within the containment area

    on the surface water to trap and contain any floating petroleum hydrocarbons that may

    surface. The booms can be moved around within the containment area to achieve

    maximum effectiveness. Petroleum hydrocarbons trapped by the booms are removed

    using vacuum trucks and skimmers and transferred to tanks. The petroleum

    hydrocarbons in the tanks are periodically transferred to tank trucks and transported to

    FAS Environmental.

    Earthen levees that surround the sinkhole area, separating surface water above and

    adjacent to the sinkhole from the surrounding marsh areas (see Figure 1). The levee

    system includes two water transfer structures, each consisting of two 12-inch diameter

    transfer pipes with valves that run through the levees which can be manually opened

    and closed to allow water transfer from the marsh into the sinkhole to assist in

    maintaining the sinkhole water level. There is also a levee overflow structure that

    provides an armored section of levee to channel high water overflows should extremely

    high water conditions be encountered.

    Initial containment of the sinkhole surface waters was achieved in February 2013, with thecompletion of the levees occurring in September 2013. Daily measurements of the water levelswithin the containment area and in the marsh just outside of the containment systemconsistently demonstrate that the water levels within the containment system drop below thoseof the marsh. If left unadjusted, the water levels within the containment area would continue todrop over time, resulting in a differential of water surface elevations on either side of thecontainment levees. As mentioned above, this is due to the hydraulic connection between thesinkhole waters and the MRAA which has a typical static water level 5 10 feet below thesurrounding marsh water level.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    5/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 2

    To maintain the water level differential between the marsh and the containment area atcontrolled levels, water is periodically transferred from the marsh into the containment area,either through transfer pipes that were installed through the containment system levees, or bypumping. The intention is to manage the water surface elevation differential in the 6 to 18inches range.

    Since the sinkhole formed, and since the containment levee system was installed, the followinghave been observed:

    The concentrations of dissolved constituents, such as TDS and chlorides, are lower atthe surface, and increase as depth increases in the sinkhole waters.

    The amount of floating petroleum hydrocarbons that are appearing on the surface of thesinkhole water has declined significantly over time, and that at the time of thepreparation of this Contingency Plan the amount of those hydrocarbons was veryminimal. The TBC team responsible for hydrocarbon management at the sinkhole hasreported that there has been no new release of hydrocarbons observed since lateAugust 2013. Oil sheens have been seen since that time has been attributed to trappedoil in the floating vegetation.

    Water levels in the sinkhole continuously drop versus the levels in the marsh just outsidethe containment levees unless water is allowed to transfer from the marsh into thecontainment system.

    The observations listed above indicate the following:

    1. A downward vertical gradient exists between the sinkhole and the marsh that reflects a

    draining condition wherein the sinkhole, even without an artificial containment levee,

    receives marsh water and conveys it deeper, rather than discharging water up and into

    the marsh. The dissolved phase constituents in the sinkhole, such as dissolved solids,

    hydrocarbons and chlorides, will tend to move along with the flow of water downward

    into the sinkhole rather than upward toward the surface and out towards the marsh. Thisaccounts for the lower concentrations of TDS near the surface of the sinkhole and higher

    concentrations of TDS at depth. The flow gradient towards the sinkhole therefore

    provides the primary containment method for the dissolved constituents in water. Over

    time, it is possible that the hydraulic connection between the sinkhole and the MRAA will

    cease as the portions of the MRAA that are exposed in the sinkhole become sealed off

    by deposited sediments from the surface.

    2. The potential non-aqueous phase constituents in the sinkhole (e.g. free-phase

    hydrocarbons) will tend to overcome the downward advection of water and move to the

    upper surface of a water column because they are lighter than water. Non-aqueous

    liquid petroleum hydrocarbons will tend to collect (and float) on the surface of the water

    in the form of sheens or globules. Multiple rows of floating booms have been placed in

    various locations at the surface of the sinkhole water to trap the hydrocarbons. The

    trapped hydrocarbons are then removed from the sinkhole waters and sent off site. The

    booms therefore provide the primary containment method for the floating hydrocarbons.

    The rate at which the floating hydrocarbons are observed to be present on the sinkhole

    surface waters has reduced substantially from late 2012 through the time that this

    Contingency Plan was prepared. This observation could be an indication that most of

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    6/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 3

    the petroleum hydrocarbons that were present in the subsurface strata that were

    disturbed by the sinkhole have already made their way to the surface, where they were

    subsequently captured and removed from the top of the sinkhole water.

    3. The earthen levee portion of the containment system creates an additional level of

    containment for both the dissolved constituents and the floating hydrocarbons. With thelevees in place, water flow from the marsh towards the sinkhole is hampered, and if no

    water is allowed to transfer (through pipes under the levees or by pumping), the

    differential in the water levels between the marsh and the area enclosed by the

    containment levees, quickly grows, with the water level within the containment area

    being lower than that in the marsh. Therefore the levee system provides a secondary

    level of containment that allows the primary methods (hydraulic gradient and floating

    booms) to work more effectively.

    This Maintenance and Contingency Plan describes actions that will be taken to monitor the

    condition of the containment system, the surface waters in the containment area and

    surrounding marsh, the growth of the sinkhole and the impacts from subsiding areas on the

    condition and effectiveness of the containment system. The plan also describes

    maintenance and repair activities to be performed to keep the containment system in good

    operating condition. In addition, this plan provides trigger points in the event that sinkhole

    growth and/or subsidence threatens to cause sections of the containment system levees to

    become ineffective or breached to the degree that repair of those sections becomes unsafe

    to workers, impossible or impracticable. If those trigger points are experienced, this plan

    provides contingency measures to be followed for expanding the levee system to new areas

    beyond the subsidence-impacted areas. This plan also addresses contingency plans for the

    relocation of a portion of Bayou Corne in the event that the sinkhole expands towards, and

    threatens to intercept, the bayou.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    7/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 4

    2.0 INTRODUCTION

    This Contingency Plan describes the following relative to the sinkhole containment system:

    Responsibility matrix for monitoring, inspection, maintenance, repair and emergencyresponse;

    Surface water quality monitoring;

    Water quality depth profile monitoring;

    Sinkhole growth monitoring;

    Inspection activities and schedule;

    Routine maintenance activities;

    Corrective measures for damaged containment system components;

    Emergency response actions; and

    Addressing potential sinkhole impacts to Bayou Corne.

    Each of these items is addressed in greater detail in the sections that follow in this ContingencyPlan.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    8/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 5

    3.0 RESPONSIBILITY MATRIX

    This section addresses the responsibilities for monitoring, inspection, maintenance, repair andemergency response actions associated with the sinkhole containment system. Thoseresponsibilities are as follows:

    Overall decision-makers with the authority to initiate actions designated by the applicableplans as needed:

    TBC Vice President of Operations, Bruce MartinPhone Number: (281) 808-5200Email address: [email protected]

    or

    United Brine Services Company LLC (UBC) President, Mark CartwrightPhone Number: (281) 744-4806Email address: [email protected]

    Overall management and direction of containment system integrity operations, includinginspection of containment system conditions, repair of damaged areas and emergencyresponse management; and monitoring sinkhole growth trends and assessing potentialimpact of sinkhole to Bayou Corne:

    TBC Response Manager, Charlie Burton and Neal StricklandPhone Number: 423-802-8426 (C. Burton); 404-538-2529 (N. Strickland)Email address: [email protected]; [email protected]

    Management and direction of containment system routine maintenance activities:

    TBC Response Operations Monitors, Maurice Valentine and Stella WilliamsPhone Number: 913-948-024(Maurice Valentine); 404-583-1230 (S Williams)Email address: [email protected]; [email protected]

    Management and direction of surface water quality sampling and water quality depthprofile sampling, analysis and reporting:

    Dave Angle of Michael Pisani & AssociatesPhone number: 281-242-5700Email address: [email protected]

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    9/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 6

    4.0 SURFACE WATER QUALITY MONITORING

    Directive 5 requires regular monitoring of surface water both inside and outside the containmentsystem for the following constituents:

    Total Petroleum Hydrocarbons (TPH);

    Chlorides; and

    Total Dissolved Solids (TDS).

    A Surface Water Monitoring Plan has been prepared in response to the Directive 5requirements. That plan describes the surface water sampling activities that are conducted bothinside and outside of the containment system levees to monitor the performance of thecontainment system in accordance with the requirements of Directive 5. A copy of the plan isprovided in Appendix A of this Contingency Plan.

    TBC also conducts water quality monitoring as specified in the Recommended RequirementsDocument RRD-Gas-02 Sinkhole Water Quality Depth Profile Sampling. A copy of RRD-Gas-02 is provided in Appendix B of this Contingency Plan. The objective of RRD-Gas-02 is toquantify and monitor the inorganic and organic chemical constituents and concentrations in thesinkhole for the entire water column from the water surface to the bottom of the sinkhole. Forthe purpose of monitoring the effectiveness of the containment system, the water quality in thetop 10 feet of sinkhole depth is of particular interest. If trends are observed that show significantincreases in the levels of chlorides, TDS or dissolved TPH in the top 10 feet of the watercolumn, it may be an indication that the hydraulic gradient has changed, and that water could becoming up out of the sinkhole towards the surface. If this condition continued, it could result inincreased concentrations for those constituents of interest further from the sinkhole and outtowards the containment levees. The sampling and analysis conducted under the SurfaceWater Monitoring Plan (see above) would be carefully reviewed to determine if the water qualityat the sampling locations both inside and outside of the containment levees has been impactedby the change in the water quality in the upper portion of the sinkhole profile.

    If the sampling activities conducted under the Sinkhole Containment Surface Water MonitoringPlan identify an upward trend in chloride, TDS or TPH fractions detected at the current samplingpoints located on the outside the containment levee, the following actions will be initiated:

    Immediately conduct another round of water quality sampling per the Surface WaterMonitoring Plan and conduct sinkhole water quality depth profile sampling for TDS,chlorides and TPH fractions (sinkhole conditions permitting) and increase the samplingfrequency to once per week.

    Notify the Louisiana Department of Natural Resources (LDNR) and LouisianaDepartment of Environmental Quality (LDEQ) if the sample results showing the upwardtrend of TDS, chlorides and/or TPH fractions outside of the containment system leveesare confirmed by an additional sampling round.

    Conduct an investigation as to the cause of the upward trend in the concentrations of theconstituents of concern outside of the containment levees. At a minimum, conductinspections of the containment system levees and water transfer pipes and valves todetermine if there are any apparent breaches in the system. If any breaches are found,refer to Section 8 of this Contingency Plan for response actions to be undertaken.

    Evaluate the sinkhole/containment system waters to determine if a change in thedirection of flow has occurred and what has caused it. Determine if the changed flow

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    10/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 7

    condition is a temporary effect (such as a change caused by sinkholeturbulence/activity), or if it is a more permanent change.

    The water quality sampling will continue at the increased frequency until the quality of thesurface water at the sampling stations on the outside of the containment system levees hasreturned to acceptable levels or if mutually agreed upon with LDNR and LDEQ.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    11/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 8

    5.0 MONITORING SINKHOLE GROWTH AND LEVEE SUBSIDENCE

    Subsidence of the ground below the containment system levees and other areas surroundingthe sinkhole has been observed. This has been especially prevalent along portions of the southlevee. When subsidence occurs in the areas where the containment levees are located, itresults in the elevation of the top of the levee dropping. If the subsidence continuesunaddressed, the elevation of the top of the levee could drop to a level that is below theelevation of the top of the marsh water. In that event, since the elevation of the top of the marshwater is higher than the elevation of the top of the containment area water, marsh water wouldflow over the top of the portion of the levee that has subsided and into the containment area.Primary containment of the sinkhole waters would still be in place at that time, due to thedownward flow gradient into the sinkhole and the presence of the floating hydrocarboncontainment booms remaining in place above the sinkhole. However, since the levee systemprovides secondary containment, backing up those primary containment conditions/measures, itwould be desirable to address the levee subsidence to maintain a separation between themarsh and the sinkhole surface water.

    TBC has instituted monitoring measures to track the elevations of the containment system

    levees and other areas surrounding the sinkhole so that corrective measures can beimplemented if the levee elevations drop too low. Those monitoring measures include thefollowing:

    Settlement Plate Surveys During the construction of the containment system levees,settlement plates were installed at various locations around the perimeter of thecontainment system (see Figure 1). The purpose of the settlement plates is to provideestablished points where elevations can be measured on a regular schedule. Theelevations taken over time are compared to identify levee settlement trends. Currentlythe settlement plate elevation measurements are conducted several times per month.

    Sinkhole and Surrounding Areas Bottom Elevation Profile Monitoring Currently,

    comprehensive topographic and bathymetric measurements are made of the sinkholeand surrounding areas, approximately monthly, by a licensed professional surveyor,assuming the sinkhole alert levels allow such work. This frequency may be reduced inthe future if overall stability and reduced sinkhole growth and/or subsidence of the areaaround the sinkhole is observed. A plan view topographic contour map is prepared thatshows the current and past locations of specific contour lines such that the growth of thesinkhole and the subsidence of surrounding areas can be monitored over time. Inaddition, cross-section profiles are prepared along established axes that cut through thesinkhole. These profiles show the location of specific elevation contours as measuredon different dates. The profiles allow for the identification of sinkhole and subsidencegrowth trends over time. Review of the chronological plan and profile plot drawingsallows sinkhole growth patterns to be tracked and estimates for future sinkhole growth to

    be projected. Figures 2a and 2b show a plan view and two cross section profiles thathave been prepared for areas adjacent to, and running through, the south levee showingthe trends of the bottom slope elevations in these areas over the past year.

    Inclinometers, Tiltmeters and Water-Level Transducers Ground movement related tothe sinkhole may occur both in the form of sudden slope failures or gradual subsidence.Slope failures in particular present a risk to people and property. While slope failuresmay be sudden, they are usually preceded by more gradual movement that can bedetected by monitoring equipment. The current monitoring system that is in use in the

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    12/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 9

    vicinity of the sinkhole includes a network of inclinometers, tiltmeters and water-leveltransducers (see Figure 3). That instrumentation provides real-time early-warning ofground movement in the area by monitoring the rate and acceleration of subsurfacetilting or subsidence that are indicative of impending instability. Since the monitoringresults are available in real-time, these systems can be used to identify potential unsafeconditions and allows for people and equipment to be quickly relocated away from areas

    deemed unstable. Instrumentation located further away from the sinkhole and beyondthe areas where influence from the sinkhole has been recorded helps to delineate thesize of the area where ground movement is occurring due to the sinkhole.

    In addition to the currently-installed instruments, it is planned that two additionalinclinometer arrays will be installed between the south levee and Bayou Corne, asindicated on Figure 3. The inclinometer closest to the south levee will be installed priorto conducting the remaining work to repair the south levee so that it can be used tomonitor conditions at the levee to protect workers and equipment during the leveerepairs. In addition to the inclinometer, line-of-sight reflectors will be installed by MillerEngineers & Associates, Inc. and used to monitor the south levee conditions during theinstallation and construction activities to protect workers performing that work.

    Once the new inclinometers have been installed, they will provide data that will be usefulin monitoring the long-term stability of the existing south berm and any potential impacton Bayou Corne.

    The settlement plate surveys, sinkhole and surrounding areas elevation profile monitoring andinclinometer/tiltmeter/water level instrument readings will provide data on:

    The elevation of the top surface of the levees;

    The slope of the ground in the areas adjacent to the levees; and

    The presence, rate and acceleration of ground movement in areas adjacent to thesinkhole, the containment system levees and Bayou Corne. In addition, at the location

    of the proposed deep inclinometer arrays, the approximate depth of any shear failureplanes will be able to be detected.

    If the above data indicates that the following trigger points have occurred, contingency actionswill be initiated, as described below:

    1. If, after the currently planned repairs and restoration of the elevation of the south levee,a section of the containment levees has dropped 4 feet or more during a period of 30days or less, a new alignment route through a more stable area will be selected for thatlevee section.

    2. If the bottom slope in the area immediately adjacent to a levee section is determinedthrough geotechnical analysis to create a condition where that levee section is unstable,

    a new alignment route through a more stable area would be selected for that leveesection. A geotechnical engineering stability evaluation of the south levee is currentlybeing conducted and will be completed by December 27, 2013. The report that isprepared to present the findings of that evaluation will be added as Appendix C to thisplan when completed. Those findings will be used to determine the feasibility ofrepairing the south levee and if it is safe for workers to conduct the repair operations onthe levee.

    3. If a section of the levee becomes damaged due to seismic activity and cannot berepaired, or if seismic activity creates a situation where the levee is considered unstable,

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    13/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 10

    a new alignment route through a more stable area would be selected for that leveesection.

    4. If the any of the conditions described in items 1 through 3 above occurs for the southlevee, or a portion of the south levee, a new south levee will be constructed. The newlevee alignment will be selected just to the north of Bayou Corne, thus maintainingcontainment between the sinkhole and Bayou Corne (see Figure 4). If the new south

    levee needs to be constructed, at that time contingency plans for re-routing Bayou Cornewill be further developed in the event that the sinkhole growth continues and the newlevee becomes threatened.

    5. If a new south levee is constructed as stated above, and at some point in time the leveeelevation, sinkhole profile and/or inclinometer data indicate that the new levee is also injeopardy of failing, the plans will move forward for relocation of both Bayou Corne andthe south levee. This is further discussed in Section 10 of this Maintenance andContingency Plan.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    14/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 11

    6.0 CONTAINMENT SYSTEM INSPECTION ACTIVITIES

    The containment system primarily consists of earthen levees with sand cores covered by clay,limestone top surfaces, and vegetated side slopes. The side slopes on the sinkhole sideinclude geosynthetic clay liner (GCL) layer between the sand and clay, and the side slopes onthe marsh side contains a geotextile layer between the top of the clay and the bottom of thelimestone layers. While such construction is durable and stands up well under most conditions,periodic inspections are appropriate to help identify any erosion damage or other wear of thelevee materials that may occur. Early detection and correction of such damaged areas helpsprevent expansion of the problem.

    In addition to the levees, the containment system also relies on floating booms to trap andcontain floating hydrocarbons that may be released from the sinkhole. The booms areinterconnected and periodically moved around to be best positioned to effectively control themovement of the floating hydrocarbons. Over time the booms can become worn and damaged,lessening their effectiveness. Periodic replacement of the booms may be necessary to maintaineffective hydrocarbon control.

    The following are actions that could potentially result in damage to the containment systemcomponents:

    Vehicular traffic causing ruts on the levees;

    Storm water runoff causing erosion;

    Wave action causing erosion or damaging the hydrocarbon containment booms;

    Heavy winds, especially during tropical storm events, knocking trees down or blowingdebris onto the levees and damaging the hydrocarbon containment booms;

    Sinkhole sloughing events that may cause damage/interruption of the oil containmentbooms;

    Differential settlement or sudden subsidence of areas below sections of the levees; and

    Sediment and debris buildup at the ends of the water transfer pipes partially or fullyblocking the pipes and valves making them difficult to operate.

    Visual inspections of the levees are conducted at least once per week to observe the leveeconditions. Any damage is documented and reported to the TBC Response Manager so thatcorrective measures can be initiated to repair the damage. Damage that threatens to causeimminent loss of containment, or which has already caused loss of containment, will beaddressed immediately on an emergency response basis. Corrective and emergency responsemeasures are addressed later in this Contingency Plan.

    The floating booms are inspected at least once per week, if conditions allow. The observedconditions of the booms are reported to the TBC Response Manager, who decides ifadjustments in dimension or location of the booms are necessary. Damaged or worn sectionsof boom are also documented and reported such that repairs can be planned and initiated.Repair measures are addressed later in this Contingency Plan.

    The water levels for both the containment system and the adjacent marsh are recorded daily,and from those readings the differential of the water levels is calculated. TBC uses thisinformation to determine when to transfer water from the marsh to the sinkhole to keep thedifferential in the target range of 6 to 18 inches.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    15/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 12

    TBC has implemented a Storm Water Pollution Prevention Plan (SWPPP) for the sinkholecontainment system and related access roads, equipment pads, etc. (see Appendix D). Thatplan describes best management practices (BMPs) for control of storm water duringconstruction activities at the site and specifies that inspection and maintenance procedures willbe implemented to maintain adequate sediment and erosion controls. Specifically, BMPs will beinspected at least once per week for a minimum of four inspections per month. BMPs also will

    be inspected within 24 hours of the end of a storm event of 0.5 inches or greater. Inspectionswill be conducted by field personnel trained in the standards of performance and maintenancerequirements for individual BMPs. Inspectors will determine whether BMPs are in place, asrequired, properly maintained, and properly operating. Inspections will be documented using theInspection Report form provided to field personnel. In particular, inspectors will note areaswhere sediment transport may be occurring, as well as needed BMP maintenance orreplacement. Such maintenance or replacement normally will be initiated within 24 hours of theinspection findings. Inspectors will note specific indicators of storm water runoff, such as floatingsolids, settled solids, suspended solids, foam, or oil sheen.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    16/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 13

    7.0 ROUTINE MAINTENANCE ACTIVITIES

    The following routine maintenance activities are conducted when indicated as being necessarybased on the inspection observations:

    Mow vegetation on levee side slopes, as required;

    Restore vegetation in bare patches;

    Regrade surface soils on levee slopes to repair small erosion rills;

    Regrade and/or place additional limestone on top of the levees to repair ruts;

    Clear debris and sediment away from the valves and ends of pipe at the water transferpipes;

    Remove floating hydrocarbons that have been trapped by floating booms; and

    Add new and/or replace worn sections of floating boom.

    The above activities may be performed by either TBC personnel or contractors retained by TBC.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    17/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 14

    8.0 CORRECTIVE MEASURES FOR SYSTEM DAMAGE

    Damaged areas on the levee system will require repairs before the damage grows and thelevees become weakened or compromised. The nature and extent of the damage will dictatehow quickly the repair work needs to be initiated. For example, small bare patches invegetation or other small erosion-damaged areas require repair, but that work can be scheduledto occur in coordination with other activities at the site. Minor settlement of the levees can bemonitored to ensure that the levees are still functioning correctly. If the settlement continues tooccur, work to raise the levee heights can be scheduled. Examples of repairs that should beaddressed immediately include erosion damage that exposes or undercuts the geotextile or theGCL portions of the levees, large erosion cuts across the top of the levee, sections of the leveedamaged by trees or tree limbs that fall onto it during storms, and other such major damage.

    Ensuring the safety of workers involved in inspecting, monitoring and repairing the containmentsystem is paramount to TBC. Bruce Martin, Vice President of Operations, TBC or, in hisabsence, Mark Cartwright, President of UBS, will be responsible for determining when suchwork may be conducted. In making such determination they will consider data supplied bypassive seismic monitoring equipment, inclinometers and sinkhole survey information. All

    applicable OSHA regulations and any other applicable federal and state statutes shall befollowed in making such determinations.

    The following actions would be taken in the event that damage to the containment systemcomponents occurs such that the ability of the levees to keep the marsh waters from flowinguncontrolled into the containment system is compromised:

    Ensure that at least two rows of oil containment booms are deployed along the damagedor impacted levee.

    Closely review the water quality monitoring data to see if the change in flow patterns isadversely impacting the water quality near the breached portion of the levee.

    Monitor settlement and movement of the impacted sections of levee and repair/rebuildthe damaged sections as soon as its safe to do so.

    If deemed necessary, increase the frequency of the sinkhole depth surveys to track thechanges to the sinkhole and slope of the slides.

    If it becomes unfeasible or completely unsafe to repair or rebuild a damaged or subsidedlevee section that is allowing water to flow uncontrolled from the marsh into thecontainment area and if the water quality monitoring data show increasing trends in theconcentrations of TDS, chlorides and/or detectable levels of TPH fractions in surfacewater samples collected directly outside a sinkhole containment levee, then TBC wouldcommence actions to construct a new levee in a more stable location further away fromthe sinkhole and determine if a mitigation plan for the affected area is merited.

    In the event that portions of the levee system experience damage to the extent that they areallowing water to pass through them, TBC will provide regular updates to LDNR and LDEQ andparticipate in review meetings as warranted to communicate the status of the sinkholecontainment system monitoring and repair activities and what additional action, if any, iswarranted. The construction of a new levee segment located further from the sinkhole willrequire the clearing of a corridor through the marsh, resulting in the loss of additional trees andother disturbance of the marsh environment. Therefore, such levee relocation should not bedone prematurely if other measures can be identified to satisfy the containment requirements ofDirective 5.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    18/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 15

    To be prepared to expeditiously repair major damage to the containment system, TBC will havethe following readily available, either on site or at locations close to the site:

    Sand, clay, limestone and geotextile fabric in quantities capable of being used to repair adamaged levee section. Since the length of a damaged section can vary quite a bitdepending on the cause of the damage, there should be a sufficient quantity of these

    materials available in on site stockpiles to support up to two days of repair work, andadditional quantities readily available at nearby off site sources that could be brought tothe site prior to the onsite stockpile quantities being depleted.

    Oil booms, absorbent pads, silt fencing and turbidity curtain in quantities that would beneeded to support levee repair work and emergency containment measures such asmight be required during levee system failure.

    Construction equipment, tools, support vehicles and water craft to be used to repair thelevees, deploy the oil boom and turbidity curtain.

    Adequate trained labor to safely manage, direct and perform the repair activities. Thiscan include TBC employees, consultants and contractors.

    Table 1 provides a listing and the approximate quantities of materials and supplies that are to be

    kept readily available for repair and emergency response activities. Table 2 provides a listing ofconsultants and contractors that TBC may utilize, as necessary, to assist with containmentsystem repairs.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    19/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 16

    9.0 EMERGENCY RESPONSE ACTIONS

    If sections of the containment levee system subside or become damaged such that theybecome breached and allow water to flow uncontrolled from the marsh into the containmentsystem, response measures will be implemented. The timing of that implementation isdependent on conditions at the sinkhole at the time. Such measures could include actions suchas deployment of additional oil booms, turbidity curtains, continuing to monitor water levels,and/or repair or replacement of sections of levees.

    If levee repairs are considered, the following will occur:

    The inspector or other person that discovers the damaged area notifies the TBCResponse Manager of nature and extent of containment system damage.

    The TBC Response Manager will assess the source/cause of the subsidence or damageto ensure that it is safe for workers and equipment to mobilize to repair the levee.

    After confirming the damage assessment, the TBC Response Manager will contact thefollowing regulatory agencies to notify them of the incident:

    - LDNR- Louisiana Department of Environmental Quality (LDEQ)- Assumption Parish Office of Emergency Planning

    The TBC Response Manager will contract a qualified engineering firm to determine thebest method of addressing and repairing the damage.

    The TBC Response Manager will contact a qualified contractor, provide them with therepair information and authorize them to mobilize to the site with the equipment,manpower and supplies necessary to implement the repair work.

    As soon as it is safe to do so, repair activities will commence. Initially the on-sitestockpiles can be utilized for the repair work, with additional material being brought tothe site to replenish the material used and to continue to supply the repair work.

    As the repair work progresses, the retained engineering firm will conduct inspections anddocument the work being performed.

    Once containment has been restored and the repair work completed, documentation ofthe activities completed will be prepared.

    A review of the cause of the damage or containment loss will be conducted. A reportsummarizing the identification of the damage, the emergency response actions, andidentified cause of the damage will be prepared.

    If levee repairs are not possible, or cannot be conducted safely, and the conditions specified inSection 8 regarding the decision to relocate sections of the levee system further away from thesinkhole apply, TBC will work with LDNR to select a new levee alignment route, and designplans and specifications will be prepared and used to direct the construction of the new levee

    section.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    20/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 17

    10.0 ADDRESSING POTENTIAL IMPACTS TO BAYOU CORNE

    The following trigger points will be used to determine actions to be taken with regard to possiblerelocation of a section of Bayou Corne:

    1. If any of the trigger points described in Section 5 of this Maintenance and ContingencyPlan occur for the south levee and result in a decision to construct a new south levee,the new levee would be located approximately as shown in Figure 4. As that figureindicates, the new south levee would go from Oxy Taft 10 well pad (located at thesouthern end of the TBC plant access road) and continue to the west staying to the northand west of Bayou Corne, roughly paralleling the Bayou, and continuing on to the northto connect with the containment systems west levee. Selecting this route will helpensure that containment of the sinkhole surface waters is maintained prior to thosewaters reaching Bayou Corne. Note that, should this new south levee be required, thefinal alignment would be selected based on available information at that time.

    2. The decision to construct a new south levee would initiate further development ofcontingency plans for re-routing Bayou Corne. A final decision to relocate Bayou Cornewill occur if Item 3 below occurs.

    3. If any of the trigger points listed in Section 5 of this Maintenance and Contingency Planresult in the determination that the new south levee shown in Figure 4 is threatened bycontinued subsidence, actions will be initiated to determine what, if any, interimmeasures are needed to ensure containment and for the relocation of Bayou Corne.

    As a contingency measure in the event that Bayou Corne does eventually need to be relocated,TBC has already contracted Tetra Tech to evaluate options and provide conceptual guidancefor re-routing of a portion of Bayou Corne. That evaluation included:

    A field inspection of project site;

    A cursory review of available information;

    Identification of preliminary alternatives for reroute of Bayou Corne, includingidentification of an initially preferred alternative based on available information;

    Development of a list of recommended studies and information required for selection ofpreferred alternative and final design; and

    Development of order-of-magnitude cost estimate for design and construction of theinitially preferred reroute alignment.

    The current size and shape of the sinkhole, and the growth it has exhibited since it formed inAugust 2012 through the time that this Contingency Plan was prepared (November 2013) do notindicate an impact to the Bayou Corne waterway in terms of TPH, chlorides and/or TDS. BothLDNRs consultants and those retained by TBC have reviewed the current conditions of thesinkhole and the brine cavern that has been the receptor of the sediments that created thesinkhole, and have concluded that Bayou Corne would not be encroached upon even usingexceedingly conservative assumptions.1

    1See Brandshaug, T., 2013.Evaluation of the Bayou Corne Maximum Sinkhole Extent in

    Lateral Directionsand Van Sambeek, 2013, Comments on Maximum Bayou Corne Sinkhole Extentsattached hereto as Appendix E.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    21/113

    Bayou Corne Sinkhole Containment System Maintenance and Contingency Plan Texas Brine Company L.L.C.

    Tetra Tech December 13, 2013 18

    Therefore, at this time further evaluation or engineering for a Bayou Corne reroute option doesnot appear warranted.

    If the current south levee needs to be relocated, TBC will further develop plans for possiblerelocation of the bayou. The actions that would be taken at that time include:

    1. Conduct survey of channel bed profile and representative cross sections.2. Investigate and apply design criteria for existing pipelines such as minimum burial depth

    and other protection requirements,3. Refine channel re-reroute design for selected re-alignment route, as necessary. This

    would include a review of existing and proposed bed elevations, substrate material,existing pipeline depths, and to the extent possible with the available data, channelvelocities and potential scour depths.

    4. Develop final design recommendations for channel alignment and dimensions.5. Develop plans and specifications, and determine excavation quantities and construction

    timelines.6. Initiate the permitting process with Office of Coastal Management (OCM) and US Army

    Corp of Engineers (USACOE) for the relocation of Bayou Corne.

    If the new south levee shown in Figure 4 is constructed, and if any of the trigger points listed inSection 5 of this Maintenance and Contingency Plan result in the determination that this newsouth levee is threatened by continuing subsidence, the plans for the relocation of Bayou Cornewill be made final, requests will be made to the appropriate agencies to conduct the relocationactivities, and the work will commence.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    22/113

    TABLES

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    23/113

    Table 1. Materials and Supplies for Containment Repair

    ITEM STORAGE LOCATION APPROXIMATE QUANTITY

    STOREDSand Geophone Pad # 3 2,500 Tons

    Clay Geophone Pad # 3 2,500 Tons

    Limestone Geophone Pad # 3 & Pad 2

    Near Geophone 1 Pad

    1,500 Tons

    Geosynthetic Clay Liner Geophone Pad # 3 2100 Linear Feet x 15 Feet

    Wide

    Geotextile Geophone Pad # 3 525 Linear Feet x 15 Feet

    Wide

    Oil Boom (soft) Maintenance Shop 1,000 Linear Feet

    Oil Boom (hard) Maintenance Shop 1,700 Linear Feet

    Absorbent Pads Maintenance Shop 5 Bags, 100 Pads Per Bag

    Turbidity Curtain Maintenance Shop 1,000 Linear Feet

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    24/113

    Table 2. Consultants and Contractors Available to Assist with Repairs

    NAME Role Contact Information

    Tetra Tech, Inc. Design, Construction Oversight Gregory Farrell, P.E.Phone 610-908-2596

    Email [email protected]

    Renes Trucking Supply trucks, sand, clay and

    limestone

    Rene Esneault

    Phone 225-474-3500

    Email [email protected]

    Rocks Trucking General Contractor Rock Scioneaux

    Phone 985-513-2711

    Email [email protected]

    Action

    Environmental

    Deployment of booms; Oil and

    Debris Removal

    Chas Leblanc

    Phone 225-385-0850

    Email [email protected]

    Miller Engineers &

    Associates, Inc.

    Surveying Joel Miller

    Phone - (337) 828-1950

    Email - [email protected]

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    25/113

    FIGURES

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    26/113

    PLAN VIEW

    INITIAL CONTAINMENT SYSTEM LEVEE/ROADCENTERLINE

    INITIAL CONTAINMENT SYSTEM LEVEE/ROADCROWN

    INITIAL CONTAINMENT SYSTEM LEVEE/ROADBOTTOM OF SLOPE

    EDGEOF TEXASBRINEROADS ANDPADSUSEDAS PART OF CONTAINMENT SYSTEM

    APPROXIMATELOCATIONOF EXISTING PIPELINE

    APPROXIMATESETTLEMENT PLATELOCATION(SEEDTL 2 ON SHT 4)

    LEGEND

    0

    SCALE:

    ### #### 240'

    #########

    N

    8911 North Capital of Texas HighwayBuilding 2, Suite 2310

    Austin, TX 78759(512) 338-1667 (512) 338-1331 fax

    BYREFERENCE REVISIONSNO. DATE

    PROJECT NO.:

    ENGINEER'S SEAL

    DATE:

    ISSUED BY

    APPROVED BY:

    CHECKED BY:

    DRAWN BY:

    DESIGNED BY:

    FILE NAME:

    TETRA TECH

    ISSUED FOR SCALE: AS SHOWN

    GTF

    SHD

    GTF

    GTF

    114-010647

    -

    - - - -

    TEXAS BRINE COMPANY, LLC.SINKHOLE CONTAINMENT SYSTEM

    114-010647 10

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    -

    - - -

    - -

    - -

    - -

    - -

    - -

    - -

    B-XX

    ALTERNATIVECONTAINMENT SYSTEM LEVEE/ROADCENTERLINE

    FINAL LEVEE ELEVATIONS

    NORTH

    EAST

    SOUTH

    WEST (ORIGINAL SECTION)

    S ECTI ON A PP ROXI MA TE S TA TI ON/LOCATION TOP OF CLAY E LE VA TI ON

    +5.0'

    T EX AS B RI NE A CC ES S R OA D E XI ST IN G E LE VA TI ON

    STA 18+00 - START OF NEW WEST LEVEE

    WEST (NEW SECTION) +6.0'

    +6.0'

    +6.0'

    SOUTH STA 46+00 - 48+00 TRANSITION FROM +6.0' TO +5.0'

    SOUTH +5.0'

    WEST (ORIGINAL SECTION) +6.0'

    NORTH/WEST CORNER STA 15+00 - STA 16+00 +5.0'

    APPROXIMATEBORING LOCATION

    STA 16+00 - STA 18+00 TRANSITION FROM +5.0 ' TO +6 .0 'WEST (ORIGINAL SECTION)

    SP-XX

    STA.

    1+00

    STA.2+00

    STA.3+00

    STA.4+00

    STA.

    5+00

    STA.6+00

    STA.

    7+00

    STA.10+00

    STA.11+00

    STA.12+00

    STA.13+00

    STA.14+00

    STA.

    15+00

    STA.28+00

    STA.27+00

    STA.26+00

    STA.25+00

    STA.24+00

    STA.23+00

    STA.22+00

    STA.21+00

    STA.20+00

    STA.19+00

    STA.18+00

    STA.17+00

    STA.16+00

    STA.

    42+00

    STA.43+00

    STA.

    44+00

    STA.

    45+00

    STA.

    47+00

    STA.48+00

    STA.49+00

    STA.50+00

    S T A . 5 2 + 0 0

    STA.33

    +00

    STA.

    31+0

    0

    STA.

    32+0

    0

    STA.34+00

    STA.35+00

    STA.36+00

    STA.37+00

    STA.

    38+00

    STA.39+00

    STA.

    40+00

    STA.41+00

    FLORIDAGASPIPELINE

    FLORIDAGAS

    PIPELIN

    E

    ACADIAN

    GA

    SPIPELINE

    FLORIDA

    GASPIPELINE

    ACCESSROAD

    T E X A S B R

    CROSSTEXPIPELINE

    ACADIAN

    GAS

    PIPELINE

    FLORIDAGASPIPELINE

    MARSH

    MARSH

    CONTAIN

    MENT

    AREA

    G-03 PAD

    GCL ANGLE INSTALLATION

    GCL ANGLE INSTALLATION

    EXISTING SHEET PILE WALL(PROTECT IN PLACE)

    AREA OF PONDED WATER

    OGPAD3

    EXISTING ACCESS

    ROAD AND PAD

    STA.

    9+00

    STA.

    8+00

    STA.0+00

    STA.

    46+00

    STA.61

    +00

    STA.62+00

    STA.63+

    00

    ST

    A.64+00

    STA.65+0

    0

    STA

    .66+00

    STA.67+0

    0

    STA.69

    +00

    STA.7

    0+00

    STA.71

    +00

    STA.72+0

    0

    STA.73

    +00

    STA.74

    +00

    STA.75

    +00

    STA.76

    +00

    STA.77

    +00

    STA.7

    8+00

    STA.79

    +00

    STA.29+00

    STA

    .68+00

    ORW-9 PAD

    ORW-9 WELL

    STA.30+0

    0

    ORW-5 PAD

    ORW-5 WELL

    FLARE PAD 5

    MAURICEROAD

    CONTAINMENT AREA

    TEXAS

    BRINE

    PLANT

    STA.8

    0+00

    STA

    .81

    +00

    STA.60+00

    INTERIM WATERTRANSFER STRUCTURE #2

    INTERIM WATER TRANSFER STRUCTURE #1

    LEVEE OVERFLOW STRUCTURE FLORID

    AGASPIP

    ELIN

    E

    G-01 GEOPHONE WELL

    G-01 GEOPHONE PAD

    OG-2 WELL PAD

    OG PAD 9

    LEVEE ROAD BETWEEN G-01

    GEOPHONE PAD AND OG PAD 9

    MARSH

    MARSH

    B-01

    B-02B-03

    B-04

    B-05

    B-06

    B-07

    B-09STA.5

    1+00B-10

    B-11B-12

    B-13

    B-14

    B-15

    B-16

    B-17

    B-18

    B-19

    SP-01

    SP-04

    SP-05

    SP-06

    SP-4-N

    SP-3-NSP-2-N

    SP-1-N

    S

    SP-13

    SP-14

    SP-16

    SP-6-N

    SP-5A-N

    SP-5-N

    STA.

    1+00

    STA.2+00

    STA.3+00

    STA.4+00

    STA.

    5+00

    STA.6+00

    STA.

    7+00

    STA.10+00

    STA.11+00

    STA.12+00

    STA.13+00

    STA.14+00

    STA.

    15+00

    STA.28+00

    STA.27+00

    STA.26+00

    STA.25+00

    STA.24+00

    STA.23+00

    STA.22+00

    STA.21+00

    STA.20+00

    STA.19+00

    STA.18+00

    STA.17+00

    STA.16+00

    STA.

    42+00

    STA.43+00

    STA.

    44+00

    STA.

    45+00

    STA.

    47+00

    STA.48+00

    STA.49+00

    STA.50+00

    S T A . 5 2 + 0 0

    STA.33

    +00

    STA.

    31+0

    0

    STA.

    32+0

    0

    STA.34+00

    STA.35+00

    STA.36+00

    STA.37+00

    STA.

    38+00

    STA.39+00

    STA.

    40+00

    STA.41+00

    STA.

    9+00

    STA.

    8+00

    STA.0+00

    STA.

    46+00

    STA.61

    +00

    STA.62+00

    STA.63+

    00

    ST

    A.64+00

    STA.65+0

    0

    STA

    .66+00

    STA.67+0

    0

    STA.69

    +00

    STA.7

    0+00

    STA.71

    +00

    STA.72+0

    0

    STA.73

    +00

    STA.74

    +00

    STA.75

    +00

    STA.76

    +00

    STA.77

    +00

    STA.7

    8+00

    STA.79

    +00

    STA.29+00

    STA

    .68+00

    STA.30+0

    0

    STA.8

    0+00

    STA

    .81

    +00

    STA.60+00

    STA.51+00

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    27/113

    AREA & VOLUME CALCULATIONS:

    Unable to calculate quantities due to Code 1 access restrictions.

    AERIAL IMAGE TAKEN ON 11/02/13.

    NOTE: CONTAINMENT ROAD NOT USED IN CONTOURS AND VOLUME CALCULATIONS.

    1) Bubble activity observed on north side of sinkhole.2) Bottom elevation by fathometer was approximately -190'.3) Bottom elevation by wireline was approximately -207'.

    11-11-13 SURVEY NOTES:

    4) Eastern side of sinkhole off-limits due to Code 1 safety requirements.

    8911 North Capital of Texas Highway

    Building 2, Suite 2310Austin, TX 78759

    (512) 338-1667 (512) 338-1331 fax

    PROJECT NO.:

    FIGURE

    REVISION

    DATE:

    ISSUED BY

    APPROVED BY:

    CHECKED BY:

    DRAWN BY:

    DESIGNED BY:

    FILE NAME:

    TETRA TECH

    ISSUED FOR SCALE: AS SHOWN

    GTF

    SHD

    GTF

    GTF

    114-010647

    TEXAS BRINE COMPANY, LLC.SINKHOLE CONTAINMENT SYSTEM

    114-010647 12/11/2013

    -

    N

    0

    SCALE:

    50' 100' 200'

    1" = 100'

    CONTAINMENT BERM AND

    SINKHOLE PLAN2A

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    28/113

    CONTAINMENT BERM AND

    SINKHOLE PROFILES8911 North Capital of Texas HighwayBuilding 2, Suite 2310Austin, TX 78759

    (512) 338-1667 (512) 338-1331 fax

    PROJECT NO.: DATE:

    ISSUED BY

    APPROVED BY:

    CHECKED BY:

    DRAWN BY:

    DESIGNED BY:

    FILE NAME:

    TETRA TECH

    ISSUED FOR SCALE: AS SHOWN

    GTF

    SHD

    GTF

    GTF

    114-010647

    TEXAS BRINE COMPANY, LLC.SINKHOLE CONTAINMENT SYSTEM

    114-010647 12

    CROSS SECTION S-NSCALE: H 1" = 60', V 1" = 60'

    CROSS SECTION SSW-NNESCALE: H 1" = 60', V 1" = 60'

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    29/113

    BAYOU CORNE

    FLORIDAGASPIPELINE

    ACADIAN

    GAS

    PIPELINE

    ACADIANGASPIPELINE

    CROSSTEXPIPELINE

    FLORIDAGASPIPELINE

    CONTAINMENT AREA

    MARSH

    TEXASBRINEPLANT

    WESTCONTA

    INMENT(ABANDONED)

    MARSH

    EXISTING ACCESSROAD AND PAD

    OG PAD 3

    MARSH

    G-01

    GEOPHONEWELL PAD

    ORW-5 PAD

    OG-2 WELL PAD

    OG PAD 9

    ACADIAN

    GAS

    PIPELINE

    ACADIANGASPIPELINE

    CROSSTE

    XPIPELINE

    WESTCONTAINMENT BERM

    NORTH CONTAINMENT BERM

    WESTCONTAINMENTBERM

    SOUTH CONTAINMENT BERM

    TE

    XAS

    BRIN

    EA

    CCE

    SSR

    OAD

    ( EAST

    CO

    NTA

    INM

    ENT

    BER

    M)

    ACCESSROAD

    CONTRACTOR

    STAGING AREA

    ACCESSROAD

    WESTCONTAINMENT

    BERM

    WESTC

    ONTAINMENT

    BERM

    CONTAINMENT AREA

    60 (T, WL)

    35 (WL)

    53 (WL)

    52 (WL)

    55 (WL)

    21 (T, WL)

    22 (T, WL)

    36 (WL) 34 (WL)

    37 (WL)

    54 (WL)

    32 (WL)

    59 (T, WL)

    31 (WL)

    29 (WL)

    89 (WL)

    33 (T, WL)1 (I, WL)

    11 (I, WL)40 (WL)

    50 (WL)

    39 (WL)

    2 (T)

    48 (WL)

    44 (WL)77 (T)

    99 (P)

    88 (T)

    26 (T, WL)

    18 (WL)

    25 (WL)

    30 (WL)

    PROP (I)

    PROP (I)

    INCLINOMETER, TILTMETE

    AND WATER LEVEL

    INSTRUMENT LOCATIONS

    0

    SCALE:

    100' 20

    1" = 20

    N

    8911 North Capital of Texas HighwayBuilding 2, Suite 2310

    Austin, TX 78759(512) 338-1667 (512) 338-1331 fax

    PROJECT NO.: DATE:

    ISSUED BY

    APPROVED BY:

    CHECKED BY:

    DRAWN BY:

    DESIGNED BY:

    FILE NAME:

    TETRA TECH

    ISSUED FOR SCALE: AS SHOWN

    GTF

    SHD

    GTF

    GTF

    114-010647

    TEXAS BRINE COMPANY, LLC.SINKHOLE CONTAINMENT SYSTEM

    114-010647 12

    LEGEND: I INCLINOMETER

    P PRECIPITATION

    T TILTMETER

    WL WATER LEVEL

    EQUIPMENT LOCATION

    AND DESIGNATION

    PROPOSED INCLINOMETE

    LOCATION

    36 (T, WL)

    PROP (I)

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    30/113

    BAYOU CORNE

    FLORIDAGASPIPELINE

    ACADIANGASPIPELINE

    ACADIANGASPIPELINE

    CROSSTEXPIPELINE

    FLORIDAGASPIPELINE

    CONTAINMENT AREA

    MARSH

    TEXAS

    BRINE

    PLANT

    WESTC

    ONTA

    INMENT(ABAN

    DONED)

    MARSH

    EXISTING ACCESSROAD AND PAD

    OG PAD 3

    MARSH

    G-01 GEOPHONEWELL PAD

    ORW-5 PAD

    OG PAD 9

    ACADIAN

    GAS

    PIPELINE

    ACADIANGASPIPELINE

    CROSSTEXPIPELINE

    PROPOSED SOUTHERN

    BERM RELOCATION OPTION

    WEST CONTAINMENTBERM

    NORTH CONTAINMENT BERM

    WESTCONTAINMENTBERM

    SOUTHCONTAINMENT BERM

    TEXASBRI N

    EACCESS

    ROAD

    ( EAST

    CONTAINM

    ENTBERM)

    ACCESS

    ROAD

    CONTRACTOR

    STAGING AREA

    ACCESSROAD

    WEST

    CONTA

    INMENT

    BERM

    WESTCONTAINMENT

    BERM

    MAXIMUM OVAL SHAPE SINKHOLE SHAPE

    PER ITASCA CONSULTING GROUP

    MEMORANDUM DATED AUGUST 5, 2013

    OG-2 WELL PAD

    CONTAINMENT AREA

    PROPOSED SOUTHERN BER

    RELOCATION OPTION

    0

    SCALE:

    80' 16

    1" = 16

    N

    8911 North Capital of Texas HighwayBuilding 2, Suite 2310

    Austin, TX 78759(512) 338-1667 (512) 338-1331 fax

    PROJECT NO.: DATE:

    ISSUED BY

    APPROVED BY:

    CHECKED BY:

    DRAWN BY:

    DESIGNED BY:

    FILE NAME:

    TETRA TECH

    ISSUED FOR SCALE: AS SHOWN

    GTF

    SHD

    GTF

    GTF

    114-010647

    TEXAS BRINE COMPANY, LLC.SINKHOLE CONTAINMENT SYSTEM

    114-010647 12

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    31/113

    APPENDIX A

    SURFACE WATER MONITORING PLAN

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    32/113

    SURFACE WATER MONITORING PLAN

    IN RESPONSE TO:

    LOUISIANA DEPARTMENT OF NATURAL RESOURCES

    DECLARATION OF EMERGENCY FOR BAYOU CORNE

    FOURTH AMENDMENT, DIRECTIVE N0 5:

    For

    TEXAS BRINE COMPANY, L.L.C.

    Provided By:Tetra Tech, Inc.

    June 25, 2013

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    33/113

    TABLE OF CONTENTS

    1 INTRODUCTION.................................................................................................................................... 1

    2 BACKGROUND...................................................................................................................................... 2

    2.1 Pre-Containment Surface Water Monitoring Program .................................................................. 2

    2.2 Containment System .................................................................................................................... 2

    3 CONTAINMENT SYSTEM PERFORMANCE MONITORING PROGRAM ...................................................... 4

    3.1 Field Parameters........................................................................................................................... 5

    3.2 Laboratory Analyses ..................................................................................................................... 6

    3.3 Surface Water Sample Collection Methods ................................................................................... 6

    4 SINKHOLE MONITORING PROGRAM ..................................................................................................... 7

    4.1 Sinkhole Vertical Profiling Sample Collection Methods.................................................................. 8

    5 QAQC AND DATA MANAGEMENT....................................................................................................... 10

    5.1 Field QAQC................................................................................................................................. 10

    5.2 Laboratory QAQC........................................................................................................................ 10

    5.3 Data Management...................................................................................................................... 11

    TABLES

    Table 1 Containment System Monitoring Summary

    Table 2 Sinkhole Monitoring Summary

    FIGURES

    Figure 1 Surface Water Monitoring Locations

    APPENDICES

    Surface Water Sampling Field Form

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    34/113Page 1

    1 INTRODUCTION

    This Work Plan has been prepared for Texas Brine Company, L.L.C. (TBC) by Tetra Tech, Inc. (Tetra Tech) in

    response to the issuance, by the Louisiana Department of Natural Resources (LDNR), pursuant to the

    authority granted under Louisiana Revised Statute 30:1, eq seq., and more particularly Louisiana Revised

    Statute, 30:6.1, of a Declaration of Emergency. The Declaration of Emergency is related to subsidence that

    has occurred immediately adjacent to the TBC Oxy Geismar No.3 well site and associated salt cavern.

    A containment system consisting of existing and new levees has been constructed around the sinkhole to

    meet the requirements of Directive 5 of the Fourth Amendment to the Declaration of Emergency to

    prevent to the greatest extent practicable, any dissolved concentrations of total petroleum hydrocarbons

    (TPH), elevated chloride, or total dissolved solids (TDS) in the surface water within the sinkhole and

    surrounding area from migrating in such a manner that will damage the environment.

    This Monitoring Plan is specific only to Directive No.5 of the Fourth Amendment to the Declaration ofEmergency and presents the steps to be taken by TBC, with technical assistance from its consultants, Tetra

    Tech and Michael Pisani and Associates, Inc. (MP&A). This Monitoring Plan describes the surface water

    sampling activities proposed to monitor the performance of the containment system.

    This monitoring plan refines the current sample locations and frequencies of sampling in accordance with

    Directive No.5 of the Fourth Amendment to the Declaration of Emergency. The existing sampling

    conducted by MP&A and the containment system design are discussed as background in section 2.0. The

    containment system monitoring program is discussed in section 3.0, the sinkhole monitoring program is

    discussed in section 4.0, and QAQC and data management are discussed in section 5.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    35/113Page 2

    2 BACKGROUND

    2.1 Pre-Containment Surface Water Monitoring Program

    The existing surface water monitoring program at the sinkhole is conducted by MP&A. MP&A has collected

    field parameters twice per week at up to nineteen (19) sinkhole transect locations and at two (2)

    background locations since August 2012 which have included the following:

    Conductivity,

    TDS,

    ORP,

    pH, and

    Temperature.

    MP&A has collected biweekly surface water samples at up to nineteen (19) sinkhole transect locations and

    two (2) background locations since August 2012 which have included the following:

    pH Method SM 4500H,

    Specific conductance (mhoms/cm) Method SM2510B,

    TDS Method SM 2540C,

    Anions (bromide, chloride, sulfate) Method SW-846 9056A,

    Hydrogen sulfide Method SM4500S H,

    Sulfide Method SM4500 S,

    Benzene, ethylbenzene, toluene, and xylenes (BTEX) Method 8260B, and

    Total petroleum hydrocarbon (TPH) fractions Method TX 1006/Massachusetts EPH/VPH.

    In addition to the field parameters and laboratory samples taken at the existing sinkhole surface water

    sample locations, MP&A also completed vertical profiling of the sinkhole water column on three separate

    occasions. The vertical profiling was proposed by MP&A to identify surface water stratification. In addition

    to the laboratory analyses at the transect locations, the following additional analyses were completed for

    vertical profiling samples:

    Dissolved gases (methane, ethane, propane, and butane) - Method RSK175,

    Volatile Organic Compounds (VOCs) full suite of Method 8260B,

    Semi Volatile Organic Compounds (SVOCs) Polycyclic aromatic hydrocarbon (PAH) suite of

    Method 8270C,

    Alkalinity (bicarbonate and carbonate) Method SM 2320B, and

    Cations (calcium, iron, magnesium, manganese, potassium, and sodium) Method SW-846 6010B.

    Tetra Tech proposes to continue vertical profiling on a regular schedule as discussed in section 4.0.

    2.2 Containment System

    The containment system installation was completed in response to Directive No.5 of the Fourth

    Amendment to the Declaration of Emergency.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    36/113Page 3

    The containment system for the sinkhole provides a continuous low permeability perimeter of structures

    designed to contain surface waters surrounding the sinkhole up to an elevation of four (+4) feet during

    normal, non-storm event conditions. The containment system incorporates, to the extent practicable,

    existing roads and well pads to minimize new construction and additional disturbance of swamp areas. In

    the event of a storm event where water reaches a pre-determined high level, the containment system will

    allow the controlled water transfer from the containment area to the swamp areas adjacent to the

    southwest corner of the containment dike where the released water can mix with the naturally occurring

    flow outside of the dike. The main constituents of concern are high chloride concentrations in the sinkhole

    at depth and hydrocarbons which float on the surface. The release structure design incorporates controls

    to help prevent release of chlorides and floating materials (e.g., hydrocarbons) by its vertical position.

    Newly constructed dikes that are part of the containment system utilize a corridor that is approximately 40-

    foot-wide. Trees and vegetation were cleared from the construction corridor prior to the placement of

    sand bedding material that was used to create a working surface above the water table that served as the

    base of the dike and as the platform for continuing the construction of the dike further along the alignment.The upper components of the dikes are constructed on top of the base sand layer. The following describes

    the dike design elements from bottom to top.

    The base layer of sand fill placed on the swamp floor (height of sand was dependent on water

    depth at the time of construction).

    A geosynthetic clay liner (GCL) placed over the sand along the entire dike slope that faces the

    sinkhole, creating an extremely low permeability surface to the dike.

    A layer of geotextile fabric placed over the sand on the dike slope on the side facing the swamp,

    which is used to help stabilize the sand fill material there.

    Both the geotextile and the GCL are secured in place at the bottom of each side slope through theuse of anchor trenches. Additional fill is placed over the anchor trenches and carried up the slopes

    to provide a protective layer for the geotextile fabric and GCL.

    The top of the sand component of the dike is capped with approximately 18 to 24 inches of

    compacted clay, which anchors the top of the geotextile fabric and GCL, and provides a stable top

    surface for the dike.

    A layer of geotextile fabric is placed over the top of that clay layer to provide a separation barrier.

    A layer of limestone approximately 6 to 12-inches thick covers the geotextile separation layer to

    create a surface for supporting vehicular traffic to allow access around the containment area

    perimeter.

    Existing access roads (Rig Road and the Texas Brine Access Road) have been used to form the eastern and

    western perimeters of the containment system. GCL was also added to the side slopes facing the sinkhole

    for these roads to continue the low permeability barrier around the entire perimeter of the containment

    area. In addition, Rig Road was raised and improved upon in many areas in a manner similar to that

    described above for the newly-constructed dikes. The containment system boundary is shown on Figure 1.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    37/113Page 4

    3 CONTAINMENT SYSTEM PERFORMANCE MONITORING PROGRAM

    The objective of the surface water monitoring program is to monitor the surface water in and around the

    containment system to document that the containment system is preventing to the greatest extent

    practicable any dissolved concentrations of TPH, elevated chloride, and TDS in the surface water within thesinkhole and surrounding area from migrating in such a manner that will damage the environment.

    The proposed performance monitoring surface water sample locations were chosen at cardinal locations

    around the containment system (see Figure 1). Paired sample locations were chosen to compare the

    surface water chemistry at five (5) locations inside and outside of the containment system. The sample

    locations were named with the following sample prefix ID:

    CSSW - Containment System Surface Water.

    The proposed performance monitoring schedule of the containment system will consist of the collection of

    field parameters and water samples at ten (10) sample locations around the containment system and four

    (4) background locations. The scope, frequency, and type of monitoring for each sample location is

    summarized in Table 1.

    In addition to performance monitoring, field parameters and water samples will be taken immediately prior

    to a water transfer from the containment system to the outside swamp and once daily during the transfer

    at sample locations CSSW-01 and CSSW-02.

    The field parameters and laboratory analyses included as part of the performance monitoring and

    immediate release events are discussed in sections 3.1 and 3.2 respectively.

    Table 1 Containment System Monitoring Summary

    Sample ID Scope Monitoring Frequency

    CSSW-01 and

    CSSW-02

    Performance monitoring at

    the south end of the

    containment system.

    Field Parameters

    Monthly

    Laboratory Analysis

    Characterization of release

    water during a water transfer

    event.

    Field Parameters Immediately prior to

    a water transfer and

    once daily during

    each transfer.Laboratory Analysis

    CSSW-03 and

    CSSW-04

    Performance monitoringalong Rig Road and the west

    end of the containment

    system.

    Field Parameters

    Monthly

    Laboratory Analysis

    CSSW-05 and

    CSSW-06

    Performance monitoring at

    the north end of the

    containment system.

    Field Parameters

    MonthlyLaboratory Analysis

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    38/113Page 5

    CSSW-07 and

    CSSW-08

    Performance monitoring at

    the northern portion of the

    access road and the eastern

    edge of the containment

    system.

    Field Parameters

    Monthly

    Laboratory Analysis

    CSSW-09 and

    CSSW-10

    Performance monitoring at

    the eastern portion of the

    access road and eastern edge

    of the containment system.

    Field Parameters

    Monthly

    Laboratory Analysis

    BG-01

    Background concentration in

    the swamp south of the

    containment system.

    Field Parameters

    Monthly

    Laboratory Analysis

    BG-02

    Background concentration in

    the swamp south of thecontainment system along

    Bayou Corne.

    Field Parameters

    MonthlyLaboratory Analysis

    BG-03

    Background concentration in

    Bayou Corne at the closest

    location to the water transfer

    area.

    Field Parameters

    Monthly

    Laboratory Analysis

    BG-04

    Background concentration on

    Grand Bayou upstream of

    Bayou Corne.

    Field Parameters

    Monthly

    Laboratory Analysis

    3.1 Field Parameters

    Field parameters will be collected at each monitoring location according to the schedule in Table 1 using a

    hand held Ultrameter II or a YSI 556 multi-parameter sonde. Field parameters will include:

    visual hydrocarbon sheen,

    conductivity,

    TDS,

    ORP,

    pH, and

    temperature.

    The Ultrameter II and the YSI will be calibrated in accordance with the manufacturers recommended

    procedures at the beginning of each sampling day to ensure accuracy of the equipment. Calibration

    activities will be recorded on calibration logs and copies will be kept on file. Calibration of the meters will

    be conducted at the beginning and end of each sampling day. Additionally, verification of meter accuracy

    will be conducted in the middle of each sampling day.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    39/113Page 6

    3.2 Laboratory Analyses

    Samples collected for performance monitoring of the containment system and during a water transfer due

    to a major storm event will be collected according to the schedule in Table 1 and analyzed by Gulf Coast

    Analytical Laboratories (GCAL) for the following analytes:

    pH Method SM 4500HS,

    Specific conductance (mhoms/cm) Method SM2510B,

    TDS Method SM 2540C,

    anions (bromide, chloride, sulfate) Method SW-846 9056A,

    hydrogen sulfide unionized Method SM4500 S,

    sulfide Method SM4500 S,

    benzene, ethylbenzene, toluene, and xylene (BTEX) Method 8260B, and

    Total Petroleum Hydrocarbon (TPH) fractions Method TX 1006/ Massachusetts EPH/VPH.

    3.3 Surface Water Sample Collection MethodsAt each sample location, equipment calibration data, field parameters and sample collection data will be

    recorded on the surface water sampling field form in Appendix A of this plan. Sample forms will be utilized

    during performance monitoring events and if practicable, during an immediate transfer.

    Field parameters and lab samples will be collected directly from the top two (2) feet or less of the surface

    water at each sample location. The temperature will be the only parameter recorded immediately. Once

    pH, conductivity, TDS, and ORP have stabilized the values will be recorded on the field forms. Once the

    field parameters have been recorded a pre-cleaned plastic bottle will be used to transfer water samples

    from the bucket to each sample bottle. The plastic bottle and sample bucket will be rinsed at each site.

    Field meters will be rinsed using de-ionized water between sample locations.

    Samples will be collected in order location of low concentration to high concentration of hydrocarbons and

    chloride to minimize cross contamination. The sampling team will collect samples at the background

    locations first, followed by the outer containment system locations, and finally within the containment

    levee.

    Once samples are collected they will be immediately placed on ice in the lab issued sample cooler. Sample

    information will be added to the lab issued chain of custody and on sample bottles. At the end of each

    sampling day, fresh bags of ice will be changed out to ensure that the samples are delivered to the

    laboratory at the appropriate temperature.

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    40/113Page 7

    4 SINKHOLE MONITORING PROGRAM

    MP&As pre-containment surface water monitoring locations were chosen based on a transect system. Six

    cardinal directions were established from the center of the sinkhole and sample locations were named with

    the subsequent cardinal direction. Due to the recent containment of the sinkhole, the number ofmonitoring locations in the sinkhole will be reduced to a total of five (5) locations in four (4) cardinal

    directions (see Figure 1).

    The purpose of the sinkhole surface water sample locations will be to continue vertical profiling of the

    sinkhole to identify stratification of the water column. The proposed scope, frequency and monitoring

    activities are summarized in Table 2. The sinkhole sample locations will be differentiated from the

    containment system sample locations by using the following sample identification prefix:

    SHSW - Sinkhole Surface Water.

    Sinkhole monitoring activities will include the collection of the field parameters discussed in section 3.1,laboratory analyses discussed in section 3.2 and the following additional laboratory analyses:

    Dissolved gases (methane, ethane, propane, and butane) - Method RSK175

    Volatile Organic Compounds (VOCs) full suite of Method 8260B

    Semi Volatile Organic Compounds (SVOCs) Polycyclic aromatic hydrocarbon (PAH) suite of

    Method 8270C

    Alkalinity (bicarbonate and carbonate) Method SM 2320 B

    Cations (calcium, iron, magnesium, manganese, potassium, and sodium) Method SW-846 6010B

    Quarterly monitoring dates should adhere to the following schedule:

    1st

    quarter sample in the month of January

    2nd

    quarter sample in the month of April

    3rd quarter sample in the month of July

    4th quarter sample in the month of October

    Table 2 Sinkhole Monitoring Summary

    Sample ID Scope Monitoring Frequency

    SHSW 01 Vertical profiling of the center of

    the sinkhole.

    Field ParametersQuarterly

    Laboratory Analysis

    SHSW 02 Vertical profiling of the northernend of the sinkhole

    Field Parameters QuarterlyLaboratory Analysis

    SHSW 03 Vertical profiling of the western

    edge of the sinkhole

    Field ParametersQuarterly

    Laboratory Analysis

    SHSW 04 Vertical profiling of the eastern

    edge of the sinkhole

    Field ParametersQuarterly

    Laboratory Analysis

    SHSW 05 Vertical profiling of the southern

    edge of the sinkhole

    Field ParametersQuarterly

    Laboratory Analysis

  • 8/13/2019 Contingency PlanTexas Brine Contingency Plan for containing pollution at the collapsed salt dome in Napoleonville

    41/113Page 8

    4.1 Sinkhole Vertical Profiling Sample Collection Methods

    At each sample location, equipment calibration data, field parameters and sample collection data will be

    recorded on the surface water sampling field form in Appendix A of this plan.

    Vertical profiling samples will be collected as discrete grab samples. Samples will be collected at verticaldepths of approximately two (2), ten (10), twenty five (25), fifty (50), and one hundred (100) feet. The

    sample depths will vary depending upon the depth of the sinkhole at the time of sampling. The sample

    name will indicate the depth at each location by using the following labeling system:

    SHSW2-01 Sinkhole sample location 1 taken at a depth of 2 feet

    SHSW10-01 Sinkhole sample location 1 taken at a depth of 10 feet

    SHSW25-01 Sinkhole sample location 1 taken at a depth of 25 feet

    SHSW50-01 Sinkhole sample location 1 taken at a depth of 50 feet

    SHSW100-01 Sinkhole sample location 1 taken at a depth of 100 feet

    The following procedures have been determined by MP&A to be the most effective method of collecting

    samples at depth within the sinkhole:

    The discrete samples will be collected through teflon tubing secured to a weighted wire line.

    o New tubing will be used for each sample location in the sinkhole to minimize cross

    contamination of samples.

    The wire line will be advanced by winch (attached to an airboat) to the deepest (100 feet) position.

    The approximate airboat position will be maintained with an electric trolling motor, anchor line or

    other safe method determined by field personnel.

    A poly vinyl chloride (PVC) casing with end cap will be mounted on the bow of the boat.

    The PVC casing will extend from the surface of the water through any layer and/or sheen of

    hydrocarbon product floating on the water surface to reduce the risk of cross contamination.

    The weighted wire line and Teflon tubing will be advanced through the casing and used to knock off the

    end cap.

    The end cap will be attached to a string with the end inside the boat in order to recover the cap.

    The output end


Recommended