3/2/2012
1
Evaluating the Performance of Plaster Assemblies in Climate Zone 6
Welcome the OPUS GroupAugust 17, 2011
Stringent new changes to the way we construct buildings are on the horizon. The Minnesota Lath and Plaster Bureau and Third Level Design recognize the benefits and the pitfalls of these changes. It is this unique partnership that we feel will help you navigate the best strategy to meet those changes.
Steve PedracineCSI, CDT, CEI David Bryan
AIA, LEED
3/2/2012
2
The Minnesota Lath and Plaster Bureau and Third Level Design are Registered Providers with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-AIA members are available on request.
This program is registered with the AIA/ CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling using distributing or dealing in any material or product.
Understand the advantages of locating rigid insulation to the exterior of traditional wall assemblies.
Be aware of the energy code implications and thermal consequences of interrupting exterior insulation with framing members.
Set air tightness targets for a building enclosure.
Value the risk of moisture intrusion
Be able to define durability issues that diminish or increase Life Cycle of Stucco and EIFS
3/2/2012
3
Lawrence Berkley Laboratories
Building Green
Total Energy Use in Homes
3/2/2012
4
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
2010 2015 2020 2025 2030
Estimated Energy Use Reduction relative to Current Building Codes (IECC 2006 & ASHRAE 90.1 2004)
Architecture 2030
2007 Energy Independencence and Security Act for Federal Buildings
ASHRAE 90.1
ASHRAE 189.1 Green Building Code
Minnesota is currently using ASHRAE 90.1- 2004/2006 IECC The next evolution is ASHRAE 90.1-2007/2009 IECC or beyond
3/2/2012
5
R-value Requirementsfor Wall Assemblies
Climate Zone 6
2009 MN Com. Energy Code
ASHRAE 90.1 2004 ASHRAE 90.1 2007 Increase from
Commercial : IECC 2006 IECC 2009 IECC 2006
Walls, wood-framed R11.2 (U-0.089) R19.6 (U-0.051) 75%
Walls, metal-framed R11.9 (U-0.084) R15.6 (U-0.064) 31%
ASHRAE 90.1 2004 ASHRAE 90.1 2007 Increase from
Residential : IECC 2006 IECC 2009 IECC 2006
Walls, wood-framed R15.6 (U-0.064) R19.6 (U-0.051) 26%
Walls, metal-framed R15.6 (U-0.064) R17.5 (U-0.057) 12%
Generic Wall Components & Functions
3/2/2012
6
EIFS With Drainage Wall Assembly
Expanded Polystyrene Layercan be up to 4” thick
Nominal Correction Actual EPS (R3.6)Insulation Type R-value Factor R-value Thickness
Fiberglass Cavity Insulation 19 ??? ?
Other Materials 2.0 1.0 2.0
“Continuous” Exterior Insulation ? 1.0 ? ?
Total Wall R-value 19.6
Design an R19.6 wood stud wall (2x6’s,16”o.c.)
Case 1: Assume stud cavity is filled with fiberglass insulation
3/2/2012
7
Steel Stud Cavity Insulation Effectivenessfrom EZFRAME, California Energy Commission
20%
30%
40%
50%
60%
70%
80%
90%
100%
12 16 20 24Stud Spacing, inches
Cav
ity
Insu
lati
on
Eff
ecti
ven
ess
Fac
tor
2x4 wood studs 2x6 wood studs 2x4 metal studs 2x6 metal studs
See ASHRAE 90.1 2004, Tables 3.3 & 3.4
Nominal Correction Actual EPS (R3.6)Insulation Type R-value Factor R-value Thickness
Fiberglass Cavity Insulation 19 .81 15.4
Other Materials 2.0 1.0 2.0
“Continuous” Exterior Insulation 7.2 1.0 3.6 1”
Total Wall R-value 21.0
Design an R19.6 wood stud wall (2x6’s,16”o.c.)
Case 1: Assume stud cavity is filled with fiberglass insulation
3/2/2012
8
Base Wall Materials R = 2.0R19 Fiberglass x .81 R = 15.41” x R3.6 (Type I EPS) R = 3.6
Cost /SF per actual R = $0.44 Total = 21.0
Base Wall Materials R = 2.0R13 Fiberglass x .81 R = 10.52” x R3.6 (Type I EPS) R = 7.2
Cost /SF per actual R = $0.48 Total = 19.7
Base Wall Materials R = 2.0No Cavity Insulation R = 2.54” x R3.6 (Type I EPS) R = 14.4
Cost /SF per actual R = $0.50 Total = 18.9
Stucco Wall Assembly with Exterior InsulationFor exterior rigid foam up to 2” thick
Assembly PWA 104Fire rating: 1 to 2 hours – check details
3/2/2012
9
Nominal Correction Actual XPS (R5)Insulation Type R-value Factor R-value Thickness
Fiberglass Cavity Insulation 19 .81 15.4
Other Materials 2.0 1.0 2.0
“Continuous” Exterior Insulation 6.3 1.0 2.5 1/2 ”
Total Wall R-value 19.9
Alternative wall assembly: Zero cavity insulation, exterior XPS only
Nominal Correction Actual XPS (R5)Insulation Type R-value Factor R-value Thickness
Cavity Insulation (airspace) 1.0 2.5 2.5
Other Materials 2.0 1.0 2.0
Exterior Insulation ? ??? 15.1 > 2”
Total Wall R-value 19.6
Example: Design an R19.6 wood stud wall (2x6’s,16”o.c.)
Stucco Wall Assembly with Exterior InsulationFor exterior rigid foam thicker than 2”
Assembly PWA 106Fire rating: 2 to 4 hours – check details
3/2/2012
10
Continuous Insulation” in prescriptive requirements is “uninterrupted by framing”If framing interrupts insulation, thermal bridging corrections must be applied
Nominal Correction Actual XPS (R5)Insulation Type R-value Factor R-value Thickness
Fiberglass Cavity Insulation 19 .81 15.4
Other Materials 2.0 1.0 2.0
“Continuous” Exterior Insulation 3.7 1.0 3.7 3/4”
Total Wall R-value 21.1
Alternative wall assembly: Zero cavity insulation, exterior XPS only
Nominal Correction Actual XPS (R5)Insulation Type R-value Factor R-value Thickness
Cavity Insulation 1.0 2.5 2.5
Other Materials 2.0 1.0 2.0
Exterior Insulation 20 .81 16.2 4”
Total Wall R-value 20.7
Continuous Insulation” in prescriptive requirements is “uninterrupted by framing”If framing interrupts insulation, thermal bridging corrections must be applied
Example: Design an R19.6 wood stud wall (2x6’s,16”o.c.)
3/2/2012
11
Base Wall Materials R = 2.0R19 Fiberglass x .81 R = 15.43/4 ” R5 XPS R = 3.7
Cost /SF per actual R = $0.09 Total = 21.1
Base Wall Materials R = 2.0R13 Fiberglass x .81 R = 10.51.5” R5 XPS R = 7.5
Cost /SF per actual R = $0.11 Total = 20.0
Base Wall Materials R = 2.0No Cavity Insulation R = 2.54” R5 XPS x .81 R = 16.2
Cost /SF per actual R = $0.19 Total = 20.7(Includes extra sheathing and furring)
Moisture Movement Mechanisms
from: “Insulations, Sheathings and Vapor Diffusion Retarders”, Building Science Corporation 2003
Higher air pressure Lower air pressure
• Air flow through visible cracks and holes• Water vapor is carried by the air
Higher water vapor concentration
Lower water vapor concentration
• No air flow• Water vapor flow through tiny pores
3/2/2012
12
0.0
0.5
1.0
1.5
2.0
2.5
En
clo
sure
Air
Lea
kag
ec
fm/s
q.f
t. s
urf
ac
e a
t 7
5 p
a
U.S. Building Enclosure Air Leakage Comparison
2005 NIST Study: Existing Commercial Buildings < 4 stories (~.70 ACH)
NIST Study: Target airtightness, 26% to 37% Minneapolis HVAC Savings (~.12 ACH)
Av. for U.S. Residential Housing Stock (~1.7 ACH)
Av. for U.S. Residential Housing Stock since 1993 (~.5 ACH)
DOE Building America Residential Enclosure Standard (~.29 ACH)
"Regularly achievable..if airtightness details are tested", Residential, John Straube (~.22 ACH)
Passivhaus Standard (~.04 ACH)
ASHRAE 90.1 2007 compliance option
Commercial Residential
How do you design moisture-tolerant building enclosures?
3/2/2012
13
Wall Assembly Test Facility in Charleston, South Carolinaby Oak Ridge National Laboratories
One of many sites used to validate WUFI results against actual performance
Field Validation Example:
Building enclosure performance is very sensitive to material properties, construction practices and interior relative humidity - so designs should be “fault tolerant”
Stucco is appropriate for our climate with proper detailing and construction practices
Vapor retarders integral to fiberglass batts, like Kraft paper, can suffer vapor bypass at the edges and don’t perform as well as sheet products that cover the entire wall
Smart vapor retarder systems (polyamide films) perform better than polyethylene
A Simulation Investigation of Stucco Cladding Wall System Vapor Transport Performance in a Cold Climate, Goldberg, University of MN, 2006 and Cloquet Residential Research Facility: Wall Systems Hygrothermal Performance Experimental Evaluation, University of MN, Goldberg and Huelman, 2009
3/2/2012
14
Certainteed
Driving rain penetration is an important part of the WUFI analysis
Minneapolis
3/2/2012
15
Base Wall Materials R = 2.0R19 Fiberglass x .81 R = 15.41” x R3.6 (Type I EPS) R = 3.6
Cost /SF per actual R = $0.44 Total = 21.0
Base Wall Materials R = 2.0R13 Fiberglass x .81 R = 10.52” x R3.6 (Type I EPS) R = 7.2
Cost /SF per actual R = $0.48 Total = 19.7
Base Wall Materials R = 2.0No Cavity Insulation R = 2.54” x R3.6 (Type I EPS) R = 14.4
Cost /SF per actual R = $0.50 Total = 18.9
Rout to R in = .2
Sheathing Conditions for .40 cfm/ft2 @ 75 Pa infiltration
3/2/2012
16
Rout to R in = .8
Sheathing Conditions for .40 cfm/ft2 @ 75 Pa infiltration
3/2/2012
17
Sheathing Conditions for av. residential building infiltration
Infiltration Control is Important !
3/2/2012
18
Stay on this side of linefor OSB or Plywood Sheathing
.50
Stay on this side of linefor Gypsum Sheathing
3/2/2012
19
For Climate Zone 6 and normal interior moisture levels:
1. Choose the most vapor-permeable components that do the job
2. Use a smart vapor retarder
3. Control Infiltration – detail, specify & test
4. Avoid interrupting exterior insulation with metal framing
5. Ratio of insulation R-value outside sheathing to R-value inside sheathing:
Fiberglass-faced gypsum sheathing: keep above 1.0Wood sheathing: keep above 0.5
If Thermax or an impermeable air / water barrier is used:And if insulation is desired in the stud cavity – check with hygrothermal analysis
Comparing Stucco and EIFS
3/2/2012
20
For a 4 story Ottawa Apartment Complex, CMHC
Operating Energy 74%
Initial Embodied Energy
16%
Recurring Embodied Energy
10%
Priorities:1. Minimize Operating Energy2. Minimize Embodied Energy
Source: National Institute of Standards and Technology (NIST), BEES v4.0 analysis, 2007
0
20
40
60
80
100
120
Stucco EIFS Brick
Grams of CO2 Emissions per SF of Wall Area
102.42
27.39
46.29
3/2/2012
21
Source: National Institute of Standards and Technology (NIST), BEES v4.0 analysis, 2007
Number of Truckloads to Supply 25,000 sf of Wall Area
0
2
4
6
8
10
12
14
16
Stucco EIFS Brick
6 1
1
16TruckLoads
Carbon Dioxide Emissions, All Stages of Life Cycle – Grams of CO²/sf Wall Area
Source: National Institute of Standards and Technology (NIST), BEES v4.0 analysis, 2007
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
Stucco EIFS Brick
49063X
1686
83035X
3/2/2012
22
STUCCO EIFS
Over 100 year track record of success• Projected 100 year life cycle.
•Today’s stucco uses EIFS finish.•Subject to the same maintenance and resurface/ re-dash schedule.•Life cycle not quantified over insulation board.
•EIFS has now been a part of the U.S.Construction market for 42 years.
•Projected 25 year life cycle•This has never been quantified.•There are many anecdotal examples of buildings surpassing this.
STUCCO EIFS
Weight:10.3 lbs./ sf
Deflection Criteria:l/360. Higher recommended for mult-story
Weight:2 lbs./ sf
Deflection Criteria 1/ 240
3/2/2012
23
STUCCO EIFS
STUCCO EIFS
3/2/2012
24
STUCCO EIFS
Skill Set: Difficult Multiple Trades Processes
Water-Resistive Barrier (WRB)
Flashing Fastening Insulation Board Accessories Lath Scratch Coat Brown Coat Finish
Skill Set: Medium Processes
Trowel/ Roll/ Spray Apply WRB
Flashing Backwrapping Adhere Insulation Board Aesthetic Grooves/
Features Base Coat/ Reinforcing
Mesh Finish
STUCCO EIFS ASTM E 84-07 Standard Test Method
for Surface Burning Characteristics (IBC 2603.3, 2603.5.4)
ASTM E 119-07, Standard Test Method for Fire Tests of Building Construction and Materials (IBC 2603.4)
NFPA 259-04, Test Method for Potential Heat of Building Materials Rated Assemblies (IBC 2603.5.3)
NFPA 268-07, Standard Test Method for Determining Ignitability of Exterior Wall Assemblies (IBC 2603.5.7)
NFPA 285-06, Standard Method of Test for the Evaluation of Flammability Characteristics of Exterior, Nonload-bearing Wall Assemblies Containing Combustible Components (IBC 2603.5.5) . Applies to Type I, II, III, IV > 1 story
Foam Plastic Coatings
Foam Plastic Coatings
Thermal Barrier Thermal Barrier
Foam Plastic Foam Plastic
Stucco Exception System
SystemNot tested
Dow Thermax is tested
3/2/2012
25
STUCCO EIFS
Crack Resistance: Fair Brittle nature subject to
minor structural movement.
Minimal fastener installation of insulation board transfers stress to coating.
Susceptible to shrinkage cracks due to volumetric change.
Crack Resistance: Good Coating flexible to
accept minor structural movement.
Notched trowel adhesion of insulation board minimizes transference of stress to coating.
3/2/2012
26
STUCCO EIFS
•Lapped Water-Resistive Barriers (WRB)Building paper, polymeric wraps.
WRB affected by exposure to weather.• Building Paper 30 days.•Polymeric wrap 4 months
WRB punctured by fasteners•Staples, discs.•Lath attachment
•Seamless Water-Resistive Barrier (WRB)•WRB Unaffected by exposure to weather.•Minimal punctures by fasteners•Insulation board adhered by notched trowel.
STUCCO EIFS
“It is clear from these results that (the proprietary EIFS) system specimen tested, allowed fast…and complete drainage. This matches our extensive testing experience that gaps as thin as a that of a dime (1 mm) drain water quickly and well.”
John Straube, P.Eng., Department of Civil Engineering and School of Architecture , University of Waterloo.
3/2/2012
27
STUCCO EIFS
Interlacing of hydrated crystals
40 F or better during installation
Must be kept from freezing
Requires water misting Polymer modification
(optional) Must cure 7-14 days
before finish applied
Evaporation 40 F or better for 24
hours
Ready to finish in 24 hours.
STUCCO EIFSSTUCCO/EIFS
3/2/2012
28
STUCCO EIFS
Lath, cement, aggregate, accessories, insulation board may all come from different sources.
Warranty: None
Insulation Board by another party, to manufacturers specs.
All remaining components by single source
Warranty: Dependent upon system
components Material / Material and
Labor Up to 15 years.
STUCCO EIFS
3/2/2012
29
STUCCO EIFS
STUCCO EIFS
3/2/2012
30
3/2/2012
31
Mock-up of the wall assembly should be constructed and reviewed prior to construction.
The construction of the wall assembly is an extension of the design process. It is essential that workmanship-sensitive materials and systems receive due attention in the construction process.
As such, periodic or full time inspection of a given EIFS installation should be considered mandatory by prudent designers and owners alike.
3/2/2012
32
Cost Lifetime Maintenance Continuous LifecycleInsulation CO2
EIFS Lower Cost 25-50 yrs Recaulk @ 20 yrs Up to 4” 1686Regular Cleaning (R15) easy gms/SF
Stucco Higher Cost 100 + yrs Recaulk @ 20 yrs Up to 2” 4906Regular Cleaning (R10) easy gms/SF