Description:
Contract Administration. Stacy Sassman Purchasing Agent Iowa State University Cory Harms Associate Director of Purchasing Iowa State University. Contract Administration Session Outline. What is a Contract Administration Plan Why have a Contract Administration Plan - PowerPoint PPT Presentation
Popular Tags:
21
Contract Administration Stacy Sassman Purchasing Agent Iowa State University Cory Harms Associate Director of Purchasing Iowa State University
Transcript
Page 1: Contract  Administration

Contract Administration

Stacy SassmanPurchasing AgentIowa State University

Cory HarmsAssociate Director of Purchasing Iowa State University

Page 2: Contract  Administration

Contract AdministrationSession Outline

• What is a Contract Administration Plan• Why have a Contract Administration Plan• Writing A Contract Administration Plan

– Purpose and Scope– Contacts and Responsibilities– Meetings– Vendor Requirements– Monitoring Performance– Dispute Resolution– Changes to the Contract– Closing the Contract

• Helpful Tips for a CAP• Common Issues• Questions

Page 3: Contract  Administration

Contract Administration• What is a Contract Administration Plan (CAP)– A loose set of guidelines– Flexible – allow the plan to fit the contract– Plan should be included in the contract– Plan should be agreed upon by Vendor– Plan should increase communication

• What is a Performance Assessment Plan (PAP)– Monitor the performance of the contract– Created to administer the CAP

Page 4: Contract  Administration

Contract Administration• When do you need a plan?– When the nature of the contract creates a need for

oversight• High Value Contracts• High Visibility Contracts• High Risk Potential in Contract• Customer Sensitive Contracts• Complex Contracts

– Term of the contract creates a need for review– Past experience creates need

Page 5: Contract  Administration

What is the Value of a Contract Administration Plan?

• Encourages open communication– Set a timeline for communication– Provide feedback – Maintain the relationship– Head off issues before they arise

• Provides a clear understanding of roles and responsibilities

• Identifies and minimizes the potential risks and problems

Page 6: Contract  Administration

Writing a CAPPurpose and Scope

• Describe the purpose of the contract administration plan and the contract (Requirements)

• State what you want from the contract:– Product/service delivered on-time– Quality product/service– Receive correct quantity– Accurate billing

Page 7: Contract  Administration

Writing a CAPContract Contacts and Responsibilities

• Describe the roles and the responsibilities of each person involved.– Purchasing Agent/contract manager– Department contact (for operational issues only)– Vendor contact

Page 8: Contract  Administration

Writing a CAPMeetings

• Kick-off meeting– Introduce contacts– Discuss scope of work in detail– Discuss contractual obligations of all parties

(Requirements)– Establish communication protocols (email, phone, etc)

• Additional meetings – quarterly, milestones, annually, etc.

Page 9: Contract  Administration

Writing a CAPVendor Requirements

• Requirements may be needed:– Before work can begin– After work has started/during the life of the contract– Upon Completion of the Contract– Months or years after the Work is completed

Page 10: Contract  Administration

Requirements• Before the work can begin– Certificates of insurance– Employee background checks– Surety/Payment bonds– Parking permits– Access cards or building keys– Equipment checks– Contractor registration number– Certifications/Licenses

Page 11: Contract  Administration

Requirements

• After the work has started– Milestone/progress meetings– Tests– Quarterly/Annual reports– Acceptance tests– Price audits– Payments – Surveys

Page 12: Contract  Administration

Requirements• Completion of the Work– Testing/Tests– Final reports– Payments – Completed work (design, drawings, equipment, rights)– University Data– Escrow Rights

Page 13: Contract  Administration

Requirements• Post Completion

–Completed Operations Endorsement–Protection of Records (University or Student)–Audit of Vendor Records

Page 14: Contract  Administration

Monitoring Performance • Period of performance/delivery dates• Inspection and acceptance• Milestones• Potential issues:– Wrong or unsatisfactory product delivered– Poor performance– Delays– Subcontractors– Property damage

Page 15: Contract  Administration

Writing a CAP Dispute Resolution

• Describe how disputes will be resolved• Who to contact• Actions to be taken if dispute is not resolved• Penalty clauses• Corrected work by another party

Page 16: Contract  Administration

Writing a CAPContract Changes

• Changes to:– Contract period of performance– Dollar amount of contract– Scope of work– Terms and conditions changes– Assignment

Page 17: Contract  Administration

Writing a CAPClosing the Contract

• Final deliverables• Property• Payments & invoices• Evaluation

Page 18: Contract  Administration

Helpful Tips

• Create a template for meeting notes• Track meetings and issues on a spreadsheet• Use the task function in Outlook• Documentation• Sample Plan

Page 19: Contract  Administration

Common Issues

• Poor communication• Level of involvement• Vendor not a good fit• Expectations of Dept. and Vendor not met

Page 20: Contract  Administration

Summary• What is a Contract Administration Plan?• Why have a Contract Administration Plan?• Writing A Contract Administration Plan

Purpose and Scope Contacts and Responsibilities Meetings Vendor Requirements Monitoring Performance Dispute Resolution Changes to the Contract Closing the Contract

• Helpful Tips for a CAP• Common Issues

Page 21: Contract  Administration

Questions