Contract Administration Manual Appendix 7 January 2010 Contract Administration Manual Appendix 7 Program Management Application (PMA) – Budgeting and Forecasting
Transcript
Page 1: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Contract Administration Manual Appendix 7

January 2010 Contract Administration Manual

Appendix 7

• Program Management Application (PMA) – Budgeting and Forecasting

Page 2: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Budget Control and Forecasting in PMA

MCI ConferenceNovember 26, 2008

Sharla Griffiths – Highway Operations EngineerRick Kowalik – MCI, Anthony Henday

Page 3: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Today’s Presentation

•Sharla – How the money goes from $250M total to $250K for line painting in your CMA•Rick – PMA: how to set up job numbers, allocate to activities, and forecast by activity

Page 4: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Budget Allocations•Programming gives the Budget Allocation Task Group (BATG) $250 Million for maintenance of provincial highways for 2008/09.•BATG – with Terry Becker heading this OPMC sub-committee, knows this value in summer 2007•BATG walks through the following process to get $250 Million allocated down to activities in your CMAs:

Page 5: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

$250M

Page 6: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

$250M

Remove Money for other programs:Bridges/Cities/Guardrail/Culverts/Signs/Reserves/etc.

Page 7: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

$250M

Remove Money for other programs:Bridges/Cities/Guardrail/Culverts/Signs/Reserves/etc.

Remove money for Fixed Costs: “C” job numbers/IOC/HMW/etc.

Page 8: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

$250M

Remove Money for other programs:Bridges/Cities/Guardrail/Culverts/Signs/Reserves/etc.

Remove money for Fixed Costs: “C” job numbers/IOC/HMW/etc.

Allocate money for winter (based on Standards and Constants)

Page 9: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

$250M

Remove Money for other programs:Bridges/Cities/Guardrail/Culverts/Signs/Reserves/etc.

Remove money for Fixed Costs: “C” job numbers/IOC/HMW/etc.

Allocate money for winter (based on Standards and Constants)

Remainder gets allocated into Summer Work(based on Standards and Constants)

Page 10: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

2008/09 Standards and Constants

Page 11: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Importance of Forecasting•Please use PMA so we can access everyone’s info from one place•We don’t have to ask every District/CMA for information; we just query PMA directly•PMA gives standard forecasting format•Gives us (“Edmonton” and BATG) idea of status final budget spending• Turn money tap up, down, or OFF

Page 12: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Using PMA for TRACKING BUDGETS AND FORECASTING

1. SET UP the JOB NUMBER IN PMA (summer, winter, major maintenance, special funding, etc)

2. ALLOCATE BUDGET $$ TO SPECIFIC ACTIVITIES (valid for the specific job number)

3. ENTER BUDGET FORECASTS (by activity or bid item / monthly or annually)

4. REPORTING

Budget tracking and forecasting in PMA is done at the job number level. Budget forecasting can be done by BID ITEM or by ACTIVITY.

The following slides will walk you through the steps necessary to begintracking and forecasting your budget within PMA (by activity). The basic steps to follow are…….

Page 13: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

SET UP JOB NUMBER (this step may be restricted to OM or OE in some districts)

• select the CMA(s) which will be able to charge work to this job number

• select activities that are applicable under this work order • select segment types (i.e. pavement, shop, CMA, etc.)• save budget allocation (total funds approved/allocated to

this job number)

Page 14: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Setting Up the Job Number in PMA

Select CMA

Select NEW

Page 15: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Setting Up the Job Number in PMA

Select CMA Select Eligible Activities

Page 16: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Setting Up the Job Number in PMA

Select Segment Type

Enter Budget Allocations

Page 17: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Setting Up the Job Number in PMA

Enter Job Number Budget Amount

Page 18: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Allocating Budget to Work Activities

SELECT Maintain Budget

Allocation

Page 19: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Allocating Budget to Work Activities

Provide Explanation for your Revision.

i.e. $$ transferred from unallocated $$

ENTER BATG Distributions

By Activity

Page 20: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Allocating Budget to Work ActivitiesADDING A NEW ACTIVITY

ADD a new budget item by using the pull-down to select from the available activities. NOTE…only activities that were defined when setting up the job number will appear in this pull-down.

Page 21: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Allocating Budget to Work Activities

……….if an Accepted worksheet exists that references this activity then it gets

just a bit more complicated.

If this work order is a CLOSED, PMA takes the Pay Quantity off the Worksheet Item. HOWEVER if a Final Quantity exists on the Worksheet Item,

PMA will use that instead.OR

If this generated work order is not Closed, PMA will use the greater value of Pay Quantity (Final

Quantity if one exists) or the Quantity on the Work Order.

(The latter case assumes that more work will be recorded in the worksheets, and the ordered quantity is still the true committed amount.)

WHAT IS COMMITTED??This is the dollar amount considered

‘committed to be spent’. It primarily comes off the Work Order Line Items, i.e. the quantity of a bid item on a generated work order multiplied

by the unit price. (Only non-warranty work is considered.)

However…….

Page 22: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Forecasting your Budget in PMA by Activity

Select yourJob Number

Page 23: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Forecasting your Budget in PMA by Activity

WHAT IS COMMITTED??This is the dollar amount considered

‘committed to be spent’. It primarily comes off the Work Order Line Items, i.e. the quantity of a bid item on a generated work order multiplied

by the unit price. (Only non-warranty work is considered.)

WHAT IS SPENT??This is the amount that sums up all the

work that has been performed and is in one of various stages of payment:

• Submitted and Accepted on a Worksheet (may or may not have been paid on a Progress Estimate

yet)

• Progress Estimate Value Adjustments on Finalized Progress

Estimates

• Progress Estimate Quantity Adjustments on Finalized Progress

Estimates

Page 24: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Forecasting your Budget in PMA by Activity

TO FORECAST ANNUALLYEnter your annual forecast in the “Remainder of Year Forecast” column. Once a value is entered in this column the ability to forecast monthly is

disabled.

TO FORECAST MONTHLYTo move to the monthly forecasting

screen, select the link under the “Revised Budget” column.

The link to monthly forecasting is removed if an annual forecast is entered.

If a monthly forecast has beenEntered the ability to enter an AnnualForecast is removed.

Page 25: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Entering A Monthly Forecast in PMA

Months that have already been paid on a progress payment will appear as a

non-editable field.

Future months will appear as editable fields where the forecast values are

to be entered.

Page 26: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Entering A Monthly Forecast in PMA

“Spent”Represents the total of all crewsheets

that have currently been accepted. (this includes sheets that have been

accepted but not yet paid on a progress estimate)

Page 27: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Budget Reports Available in PMA

Select CMA

Page 28: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Months where a progress payment has already been made. Forecast months

Budget by Activity

Activity budget status (neg represents over-expenditure)

Page 29: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Page 2 …..MONTH TO MONTH Expenditures Reports….

Total Revised Budget Allocated to this job number Total Expenditure

Forecast

Total SPENT To Date

Total SURPLUS orDEFICIT

Page 30: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

MONTH TO MONTH Expenditures Reports…….

Why are there 2 Novembers on my Month to Month Expenditures Report ????

This column will containthe forecast for the REMAINDER of the

current month.

These columns will contain the total monthly value of all previously generated progress Payments.

This column will contain the total value of all Progress payments made during the current month.

Page 31: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

ACTIVITY SUMMARY REPORT

100% Allocated73.1% Spent to date

Year End Forecast 93.9%, $302,306 Surplus

Page 32: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

JOB NUMBER SUMMARY REPORT

PROJECTED SURPLUS

% of BudgetForecast to be

SPENT

% of BudgetSPENT to date

Page 33: Contract Administration Manual Appendix 7 …Appendix 7 • Program Management Application (PMA) – Budgeting and Forecasting Budget Control and Forecasting in PMA MCI Conference

Contact Information

Sharla Griffiths, Highway Operations Engineer780-415-1057, [email protected]

Rick Kowalik, MCI – Anthony Henday Drive780-417-2861, [email protected]