Contract Management: EOT & COST-SHARING (Under COTMA) EDWIN LEE,PARTNER ELDAN LAW LLP
Transcript
Page 1: Contract Management: EOT & COST-SHARING (Under COTMA)

C o n t r a c t M a n a g e m e n t :E O T & C O S T - S H A R I N G( U n d e r C O T M A )

E D W I N L E E , P A R T N E R

E L D A N L A W L L P

Page 2: Contract Management: EOT & COST-SHARING (Under COTMA)

R O A D M A P

01 COTMA 122 DAYS EOT vs CONTRACTUAL EOT

02 EOT FOR ACTIVITIES OUTSIDE OF 7 APRIL to 6 AUG 2020?

03WHAT IF CONTRACTOR IS ALREADY IN DELAY? (CONCURRENT DELAY)

04 PROVING ENTITLEMENT TO COST-SHARING CLAIM

06 CLAIMING IN ADJUDICATION AND OTHER PROCEEDINGS

07 NOTIFICATION OF RELIEF TO AVOID LD

Page 3: Contract Management: EOT & COST-SHARING (Under COTMA)

PART 8A:

122 DAYS EOT

Page 4: Contract Management: EOT & COST-SHARING (Under COTMA)

1 2 2 D A Y S O F E O T

• Completion date for “construction works” is extended by 122 days

• Extension covers the period 7 April 2020 to 6 August 2020

Page 5: Contract Management: EOT & COST-SHARING (Under COTMA)

N o O v e r l a p

• If Contract provides for grant of EOT, contractual grant of EOT takes

precedence, i.e. 122 days will be less whatever has been granted under the

contract

• Some contracts may have provisions for EOT – eg. SIA (“shortage of labour”,

“shortage of goods”), PSSOC (“compliance with requirements of law,

regulations, or public authority”)

• Claiming contractual EOT (which may have notification requirements) no

longer so important for period 7 April 2020 to 6 August 2020

• But should claim for contractual EOT if delaying event entitles contractor to

prolongation costs

Page 6: Contract Management: EOT & COST-SHARING (Under COTMA)

P e r i o d O u t s i d e 7 A p r i l - 6 A u g

• If the delaying event falls outside 7 April – 6 August 2020,

contractual EOT should be applied for

Page 7: Contract Management: EOT & COST-SHARING (Under COTMA)

C o n c u r r e n t D e l a y :

• What if the contractor was already in delay, and would not have

completed the works before 6 August 2020?

• Contractor would still be entitled to this 122 days of universal EOT

Page 8: Contract Management: EOT & COST-SHARING (Under COTMA)

PART 8B:

COST-SHARING

Page 9: Contract Management: EOT & COST-SHARING (Under COTMA)

P R O V I N G E N T I T L E M E N T

Pre-Conditions to entitlement to Cost-Sharing:

1. “unable to complete any of those construction

works by the completion date”

2. “inability is to a material extent caused by a

COVID-19 event”

3. “incurred or incurs any qualifying cost” in

connection with the performance of the

construction works

* ”COVID-19 event” includes compliance with SG law or that of another

country that is made by reason of Covid-19: Section 2, COTMA.

Page 10: Contract Management: EOT & COST-SHARING (Under COTMA)

P E R I O D O F C L A I M

• Prescribed period where cost-sharing

may be claimed is 7 April 2020 to 31

March 2020 (>11 months)

• This is longer than the earlier ex-gratia

cost sharing grant for public-sector

contracts, under BCA Circular 25 Sept

2020 (which was for 9 months only)

• But note the pre-conditions

highlighted earlier

Page 11: Contract Management: EOT & COST-SHARING (Under COTMA)

C L A I M I N A D J U D I C A T I O N

• Cost-sharing claim “must”* be claimed in a

payment claim

• May be submitted to adjudication under

the SOP Act

• But may also be claimed as a “debt due” in

arbitration or court proceedings

* Section 39D(6)

Page 12: Contract Management: EOT & COST-SHARING (Under COTMA)

A D J U D I C A T I O N

• Overrides Section 17(2A) of the SOP Act

preventing claims for loss or expense

• Adjudication Determination is interim

and temporary only

• Cost-sharing entitlement and amount

may be challenged in arbitration/ court

proceedings

Page 13: Contract Management: EOT & COST-SHARING (Under COTMA)

W H A T A B O U TL I Q U I D A T E D

D A M A G E S ?

• Outside the 122 days of EOT

• If there is delay

• And no other entitlement to EOT

• Liquidated damages for delay will apply

• Eg. Contractor may claim cost-sharing up till 31 March

2021, but Employer may also seek to impose liquidated

damages for delay during the same period.

• To avoid imposition of LD before 31 March

2021, Contractor should claim relief under Part

2, Section 6 of COTMA.

• To obtain relief, Notification for Relief under

COTMA must be issued before 31 March 2021.

Page 14: Contract Management: EOT & COST-SHARING (Under COTMA)

T H A N K Y O U

E D W I N L E E ,

P A R T N E R , E L D A N L A W L L P

e d w i n l e e @ e l d a n l a w . c o m

w w w . e l d a n l a w . c o m