© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Contracts Management and Administration
(Based on FIDIC Standard)
PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Sub-Clause 13.1
“Variation” or “Right to Vary”
The Unilateral Right of the Employer
to Alter a FIDIC Contract Agreement
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
LEARNING OBJECTIVES
1. Provide “Supporting” Case Law
examples to FIDIC Concept that
“Variations cannot be proposed by
the Employer simply to remove
works away from the existing Main
Contractor and allow this same
works to be given to another
Contractor”;
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
LEARNING OBJECTIVES
2. “Is a Particular ‘Instruction’ a
Variation or just an instruction?”.
3. Provide the specific UAE Civil
Codes references applicable to
FIDIC 1999 RB Sub-Clause 13.1 –
and discuss the differences
between the two areas.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
WHAT IS A “VARIATION?”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
IMPORTANT DEFINITIONS FOR
“VARIATIONS” – WHAT IS IT?
• Changes are required to the works
at some point on most construction
projects.
• Hence, a mechanism enabling the
employer to instruct, and the
contractor to implement, variations
is important.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
IMPORTANT DEFINITIONS FOR
“VARIATIONS” – WHAT IS IT?
• The power to vary is an essential
part of very construction contract
but the scope of the power to vary
differs considerably between
different forms.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
IMPORTANT DEFINITIONS FOR
“VARIATIONS” – WHAT IS IT?
• Sub-Clause 13.1 confers a very
wide power and it will only be in
unusual circumstances that the
Contractor will not be obliged to
follow a variation instruction.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
IMPORTANT DEFINITIONS FOR
“VARIATIONS” – WHAT IS IT?
• A variation (sometimes referred to as
a ‘Change Order’ ) is an alteration to
the scope of work originally
specified in the contract, whether
by way of an addition, substitution
or omission to the works, or through
a change to the manner in which
the works are to be carried out.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
DEFINING VARIATION
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
DEFINITION OF “VARIATION”
• There is no useful definition of the
term “Variation”. The definition in
Sub-Clause 1.1.6.9 is not very helpful:
–“’Variation’ means any change to the
Works which is instructed or approved
as a variation under Clause 13
[Variations and Adjustments]’”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
DEFINITION OF “VARIATION”
• This at least makes it clear that any
INSTRUCTION about the
Works not instructed or
approved as a variation under
Clause 13 is not a Variation.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
DEFINITION OF “VARIATION”
• This has implications when an
Engineer issues an instruction
under Sub-Clause 3.3. Sub-Clause
3.3 attempts to deal with this by
stating that:
–“If an instruction constitutes a
variation, Clause 13 [Variations
and Adjustments] shall apply”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
DEFINITION OF “VARIATION”
• Thus it seems that contrary to
Sub-Clause 1.1.6.9, a Variation is
not only a change to the Works
instructed under Clause 13 but
may also be instructed under
Sub-Clause 3.3.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
DEFINITION OF “VARIATION”
• In order words – “For an
instruction to amount to a
‘Variation’ - the Contractor
must act on it.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
“INSTUCTIONS” AND “VARIATIONS”
Obrascon Huarte Lain SA v HM
Attorney General for Gibraltar
• the Engineer issued a document entitled
“draft fill guidelines”, which gave
directions about undertaking certain
works, which if implemented would
have amounted to a Variation.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
“INSTUCTIONS” AND “VARIATIONS”
• The Contractor, however, chose not
to act upon the draft fill guidelines
when removing contaminated
material from site and dealt with
the contaminated material by
another accepted method.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
“INSTUCTIONS” AND “VARIATIONS”
• The Court of Appeal therefore
stated:
–“Accordingly the issue of the draft
fill guidelines did not constitute a
variation instruction.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
PURPOSE OF A VARIATION
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
PURPOSE OF “VARIATION”
• “…to enable an employer to avoid
having to enter into a new
contract with the same
contractor, or perhaps another
contractor, to have him perform
the variation…”.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
PURPOSE OF “VARIATION”
• If employer were to approach a new
contractor – he would face re-
tendering costs, possible increases in
prices, delay and clashes between the
original and new contractors on site.
• The “Right to Vary” allows employer to
minimize costs and inconvenience to
Main Contractor/Subcontractors.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
EXAMINATION:
Sub-Clause 13.1
“RIGHT TO VARY”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
EXAMINATION
13.1 – Right to Vary (FIDIC 1999 RB)
• Variations may be initiated by
the Engineer at any time prior
to issuing the Taking-Over
Certificate for the Works,either by an instruction or by
a request for the Contractor
to submit a proposal.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
EXAMINATION
13.1 – Right to Vary (FIDIC 1999 RB)
• The Contractor shall execute and be
bound by each Variation, unless the
Contractor promptly gives notice to
the Engineer stating (with supporting
particulars) that the Contractor cannot
readily obtain the Goods required for
the Variation.
• Upon receiving this notice, the
Engineer shall cancel, confirm or vary
the instruction.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
EXAMINATION
13.1 – Right to Vary (FIDIC 1999 RB)
• Each Variation may include:
–(a) changes to the quantities of anyitem of work included in the Contract(however, such changes do not necessarilyconstitute a Variation),
–(b) changes to the quality and othercharacteristics of any item of work,
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
EXAMINATION
13.1 – Right to Vary (FIDIC 1999 RB)
• Each Variation may include:
–(c) changes to the levels, positions
and/or dimensions of any part of theWorks,
–(d) omission of any work unless it is tobe carried out by others,
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
EXAMINATION
13.1 – Right to Vary (FIDIC 1999 RB)
• Each Variation may include:
–(e) any additional work, Plant,Materials or services necessary for thePermanent Works, including any associatedTests on Completion, boreholes and othertesting and exploratory work, or
–(f) changes to the sequence or
timing of the execution of the
Works.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
EXAMINATION
13.1 – Right to Vary (FIDIC 1999 RB)
• Each Variation may include:
• The Contractor shall not make any
alteration and/or modification of the
Permanent Works, unless and until
the Engineer instructs or approves a
Variation.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
LEARNING OBJECTIVE 1
“Supporting” Case Law Examples
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY – OMITTED WORKS
AMEC BUILDING Ltd v. CADMUS
INVESTMENTS CO Ltd (1996)
In AMEC Building Ltd v Cadmus
Investments Co Ltd (1996) the
contractor claimed for loss of profit
in relation to a provisional sum
which was omitted from the
contract and the work given to
others to undertake.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY – OMITTED WORKS
AMEC BUILDING Ltd v. CADMUS
INVESTMENTS CO Ltd (1996)
AMEC claimed for loss of profit and
referred the matter to arbitration.
The arbitrator found in favor of
AMEC and the matter was then
referred to the court by Cadmus
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY – OMITTED WORKS
AMEC BUILDING Ltd v.
CADMUS INVESTMENTS CO Ltd (1996)
“…It seems to me that the arbitrator was perfectlycorrect in deciding that such an arbitrary withdrawal ofwork from the provisional sums and the giving of it to thethird party was something for which AMEC were entitledto be compensated and the compensation that he arrivedat namely the loss of the profit having accepted figuresput forward to him in evidence is one which is not opento be impugned on appeal as a matter of law…”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY – OMITTED WORKS
• Carr v J A Berriman (1953)
In this case the court held that if work
is omitted from the contract and given
to others to carry out the contractor is
entitled to be paid loss of profit.
The reasoning being that the
contractor is entitled to undertake all
the work in the contract unless the
terms state otherwise.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY – OMITTED WORKS
• Carr v J A Berriman (1953)
In transferring work to
others, the employer is in
breach of contract and loss of
profit would form part of the
damages which would
become payable.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
LEARNING OBJECTIVE 1
Can a “Variation” become
a “Separate Order?”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
STANDARD FORMS OF CONTACT
• The standard forms of contract
try to circumvent this argument
before it is raised.
• The ICE conditions state that no
variation shall vitiate or
invalidate the contract.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
STANDARD FORMS OF CONTACT
• Similar wording exists in the JCT
Forms which state that no variation
required by or subsequently
sanctioned by the Architect shall
vitiate the contract.
• The intention behind the wording is
that no variation will have the effect
of creating a separate contract.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
STANDARD FORMS OF CONTACT
• While this may be the intention,
in the final analysis it will be the
court or tribunal who decides
whether or not a separate
contract arises out of the varied
work.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
LEGAL PRECEDENCE
• There have been a number of
cases where this matter has
been placed before the court for
a decision.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
Thorn v London Corporation (1876)
• In this case the judge said “if the
additional or varied work is so
peculiar so unexpected and so
different from what any person
reckoned or calculated on, it may
not be within the contract at all”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
Thorn v London Corporation (1876)
• A mere increase in the quantities of the
work will not invalidate the original
contract even though substantial.
• The work ordered must be totally
different from that contracted for and
this being the case the contractor will
be entitled to payment on a quantum
merit basis and not the contract rates.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
Bush v Whitehaven Trustees (1888)
• In this case a contractor undertook to
lay a water main and divert certain
streams on the understanding that the
work would be carried out in the month
of June, Due to delays on the part of the
employer the contractor was unable to
proceed before the winter when wages
were higher and the works more
difficult due to the weather conditions.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
Bush v Whitehaven Trustees (1888)
• The court held that these
changed circumstances were
such that the contractor became
entitled to payment on a
quantum merit basis.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
Blue Circle v Holland Dredging (1987)
• A contract was let under the ICE
5th Edition for dredging work in
Lough Larne. The dumping of the
dredged material was to be in areas
agreed with the local authority.
• A variation was issued to facilitate
the dumping of the dredged
material to form a bird island.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
Blue Circle v Holland Dredging (1987)
• It was held that as the island
construction was completely
outside the original dredging Holland
was not obliged to accept the work
as a variation.
• Hence the island became the
subject of a separate agreement.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
McAlpine Humberoak v McDermott Int’l (1996)
• In this case a contract was let for
the construction of four huge
pallets in connection with the
construction of an oil rig.
• The number of drawings used
increased from 22 which were
available at tender stage to 161 for
the construction of the work.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
McAlpine Humberoak v McDermott Int’l (1996)
• In addition, the contractor
raised many TQs (technical
queries) in relation to the
drawings.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
McAlpine Humberoak v McDermott Int’l (1996)
• The lower court held that the
changes were so extensive that the
old contract had been replaced.
• When the dispute was referred to
the Court of Appeal a different
view was taken when it was
decided that the changes fell
within the variations clause.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY
• Costain Civil Engineering Ltd v
Zanen Dredging and Contracting Co
Ltd (1996).
• This case arose out of a subcontract inconnection with the construction of a tunnelunder the River Conway.
• The subcontract employed was the ICE BlueForm of Subcontract and the work comprisedsite preparation and dredging operations.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
• Costain Civil Engineering Ltd v
Zanen Dredging and Contracting Co
Ltd (1996).
• A part of the work was the backfilling of acasting bay which had been used for theconstruction of the concrete units whichformed the tunnel.
• It was decided that rather than backfilling thecasting bays the void would be used toconstruct a marina.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY –
• Costain Civil Engineering Ltd v Zanen
Dredging and Contracting Co Ltd
(1996).
• It was argued that the work relating to themarina should be valued at contract rates with anuplift of around 10%.
• The judged ruled that the marina was
not a variation but a separate contract
and that this method of valuing the
works was not appropriate.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
LEARNING OBJECTIVE 2
“Is a Particular Instruction
a ‘Variation’ or not?”.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Is an “Instruction” a “Variation?”
• One of the most common disputes
under construction contracts is
where the Contractor and the
Engineer differ on whether a
particular instruction is or is not a
variation.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Is an “Instruction” a “Variation?”
• If the Contractor considers that the
instruction constitutes a Variation
he will make an application for
payment on that basis, and, if the
Engineer refuses to pay, the issue
will become a matter for dispute.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Is an “Instruction” a “Variation?”
• Where, as is common, the
Engineer issues an instruction,
believing it to be a simple
instruction and not a Variation;
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Is an “Instruction” a “Variation?”
• However, it is subsequently
shown to be a Variation, but the
Engineer had no authority to do
so because of a limitation
imposed by a Particular
Condition in the Contract, the
Contract provides no clear
solution.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SCENARIO:
“WHAT CONSTITUTES A VARIATION?”
• Contractor begins trenching pipeline
for 2 meters depth – per his
understanding of the contract
instructions.
• Site Engineer makes a verbal “site
correction/instruction” and tells the
on-site contractor crew that they
need to be digging down to 3 meters
depth – not 2 meters.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SCENARIO:
“WHAT CONSTITUTES A VARIATION?”
• Site Engineer follow’s up verbal site
instruction with email in the same day –
to the contractor – “citing the
contractor’s error and requesting
immediate correction”.
• Contractor sees the email instruction
from the earlier verbal site instruction –
and immediately complies with the
“variation” order.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SCENARIO:
“WHAT CONSTITUTES A VARIATION?”
• Contractor also begins assessing
and accounting for costs due to
the variation order – and
instructs his contracts
administrator to draft up an
official claims notification to be
given to the Engineer upon finish.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SCENARIO:
“WHAT CONSTITUTES A VARIATION?”
• Engineer does not consider his
site instruction any more than a
correction – as he believes he
did not issue a variation since
the contract calls for a 3 meter
depth, not a 2 meter depth.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SCENARIO:
“WHAT CONSTITUTES A VARIATION?”
Question:
• Is there a “variation” in this scenario?
• If so, is the contractor entitled to any
extension of time and cost?
• Is it possible for an “impasse” to take
place in this scenario, and if so, would an
Extension of Time and/or Costs be
granted by the client?
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
LEARNING OBJECTIVE 3
Provide the specific UAE Civil Codes
references applicable to FIDIC 1999
RB Sub-Clause 13.1
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
1. IS THE EMPLOYER ENTITLED TO VARY THE
WORKS TO BE DONE UNDER THE
CONTRACT? IS THERE ANY LIMIT ON THAT
RIGHT?
–The employer is entitled to vary the
works under the contract. Article 877
(Civil Code) states that;
“…the contractor must complete
the work in accordance with the
conditions of the contract…”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
1. EMPLOYER ENTITLED…THE CONTRACT?
IS THERE ANY LIMIT ON THAT RIGHT?
–Thus, if the contract provides that
the scope of works may be varied,
then the contractor must comply
with the conditions applicable to
the execution of variations.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• SC 13.1 – Second paragraph – adds thefollowing enforcement language – reinforcing UAECivil Code Article 877:
“…The Contractor shall execute and be
bound by each Variation, unless the
Contractor promptly gives notice to
the Engineer stating (with supporting
particulars) that the Contractor cannot
readily obtain the Goods required for
the Variation...”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• THE EXISTENCE OF A
VARIATION CLAUSE DOES NOT
GIVE THE EMPLOYER A FREE
HAND IN MAKING LARGE-SCALE
OR SIGNIFICANT CHANGES TO
THE NATURE AND SCOPE OF
THE WORKS.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• “…No such variation shall…vitiate…”
–Under common law in the U.K.
and elsewhere, a variation that
changes the whole character
or the works cannot be
interpreted as a variation.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• Sub-Clause 52.3 of the FIDIC Red
Book 4th
Edition
• Entitles the contractor to a fair
valuation of variations that increase
or decrease the Contract Price by
more than 15%.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• Sub-Clause 52.3 of the FIDIC Red
Book 4th
Edition
• Such “excess variations” are not
valued in accordance with the Bills
of Quantity as other variations but
are to be agreed between the
contractor and the employer;
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• However, if no agreement is
reached then such an amount is
to be determined by the
engineer, having due regard to
the site status and general
contractor over-heads.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• Under FIDIC Red Book 1999 –
SC 12.4, “Omissions” - Whenever
the omission of any work forms
part (or all) of a Variation, the
value of which has not been
agreed, if:
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• (a) the Contractor will incur (or
has incurred) cost which, if the
work had not been omitted,
would have been deemed to be
covered by a sum forming part
of the Accepted Contract
Amount;
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• (b) the omission of the work will
result (or has resulted) in this
sum not forming part of the
Contract Price; and
• (c) this cost is not deemed to be
included in the evaluation of any
substituted work;
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
•Then the Contractor shall
give notice to the Engineer
accordingly, with
supporting particulars.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• Upon receiving this notice,
the Engineer shall proceed in
accordance with Sub-Clause
3.5 [Determinations] to agree
or determine this cost, which
shall be included in the
Contract Price.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• Article 886 of the UAE Civil Code,
states:
–If an estimated quantity is
going to be exceeded ‘by a
significant amount’, the
Contractor should
immediately notify the
employer;
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• Article 886 of the UAE Civil Code,
states:
–If he does not do so - he
shall lose his right to
recover the excess costs
over the value of the
measured quantity.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• Article 886(2) further provides –
–The employer is then
entitled to ‘withdraw from
the contract and to suspend
the execution’;
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• Article 887 provides –
– “That the Contractor cannot
demand additional payment in the
carrying out of works unless the
employer has consented to
changes”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• Actual Language of the UAE
Civil Code – Article 887, states:
• 1 - When a contract is concluded
on a lump sum basis according to
an agreed plan , the contractor has
no claim to an increase in price
required for the execution of the
plan .
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE Civil Code – QUESTIONS
Relating to “Right to Vary”
• Actual Language of the UAE
Civil Code – Article 887:
• 2 - If a modification or addition is
made to the plan , with the consent
of the master , the current
agreement with the contractor , as
regards such a modification or
addition , shall be observed .