+ All Categories
Home > Documents > Controlled demolition of reinforced concrete buildings by ... · PDF fileControlled demolition...

Controlled demolition of reinforced concrete buildings by ... · PDF fileControlled demolition...

Date post: 06-Feb-2018
Category:
Upload: trinhcong
View: 222 times
Download: 0 times
Share this document with a friend
14
Controlled demolition of reinforced concrete buildings by the use of explosives. The Armed Forces Hospital building C5 case study. David José Bento Rodrigues Extended Abstract Supervisor: PHd Professor Doutor João Paulo Janeiro Gomes Ferreira Co-supervisor: Lieutenant Colonel Engineering Raul Fernando Rodrigues Cabral Gomes October 2014
Transcript

Controlled demolition of reinforced concrete buildings by

the use of explosives. The Armed Forces Hospital building

C5 case study.

David José Bento Rodrigues

Extended Abstract

Supervisor: PHd Professor Doutor João Paulo Janeiro Gomes Ferreira

Co-supervisor: Lieutenant Colonel Engineering Raul Fernando Rodrigues Cabral

Gomes

October 2014

Extended Abstract

1

Abstract

As time advances structures in Portuguese built areas start to show high levels of degradation. When

rehabilitation is no longer a viable option these structures need to be demolished.

Given the reduced knowledge of the use of demolition methods by explosives in Portugal, this study

seeks to compensate existing flaws in the project and execution phases.

This study starts with a brief introduction, wherein the explosive demolition project methodology is

analysed, highlighting the calculation method used which is the base of the software used to model

the collapse mechanism, as well as the calculation of the explosive charges. A case study is also

analysed allowing understanding all the sequential work done prior to the demolition, in essence its

planning and execution. The main impacts of this type of demolitions are also discussed and how

these are both controlled and minimised. Finally, a comparative economic analysis between explosive

demolitions and traditional demolitions is performed.

All demolition methods have their applications, advantages and disadvantages. However, the

explosive demolition methods applied to high reinforced concrete buildings can be a viable solution

due to the advantages they present in these situations when compared to other methods.

Keywords: explosive method, traditional method, structure demolition, reinforced concrete building

Explosive demolition of reinforced concrete buildings

2

1. Introduction

Engineering is not only about construction but also about demolition, enabling existing space to be

reused. Demolition can thus be defined as a set of removal works to be applied to an existing structure

leading to a new space availability. Demolition work can be partial or global and can be used on new

or old structures (Brito, 1999).

One of the possible methods to be used is controlled demolition using explosives, which was

developed in Europe throughout the reconstruction of the cities that were destroyed during the second

World War. Due to its advantages it later spread to the rest of the world (Jimeno et al., 1995), although

it is a technique that is still little used in Portugal.

This study has the objective of understanding how controlled demolition using explosives projects are

executed, highlighting the calculation method used by the demolition program and the calculation of

the explosive charges. All of the aspects during the preparation and execution of the program are also

looked at through the analysis of a case study. A cost analysis is also made in order to be able to

compare explosive demolition costs to more traditional demolition costs.

2. Explosive demolitions methods

The use of explosive demolitions has grown over the years, not only in building demolition but with

other types of structures like metal or reinforced concrete structures as well. Considered to be a fast,

practical and economical alternative to traditional demolitions, its main focus is the use on large

structures such as sky-scrapers, chimneys, and silos, large solid reinforced concrete structures like

naval infrastructure foundations, and even the quick demolition of bridges (Lauritzen & Schneider,

2000, cited by Gomes, 2010).

Explosive demolitions consist of using controlled explosives by placing small explosive charges

(generally less than 50 g), which are usually placed in the structural elements that are to be

demolished and confined to drillings made for this purpose (Jimeno et al., 1995; Gomes, 2010).

After this placement the charges are detonated through an initiation system. The explosive charges

present in the vertical elements detonate, causing a “structural vacuum” called a demolition belt, within

which through gravity the structure collapses, fragmenting due to its own weight, or, when appropriate,

enabling it to fall on one side, enabling easier access to the debris which can then be taken apart

using traditional methods (Gomes, 2000).

So as to obtain a controlled demolition, one where the structure when demolished acts as predicted, it

is necessary to choose the correct collapse mechanism. Existing collapse mechanisms are implosion,

telescopic, tumbling, and progressive collapse.

Extended Abstract

3

Whenever explosive demolition methods are used there is the need for preparatory work. This are

meant to facilitate the demolition process, improve the control of the collapse mechanism, reduce the

quantity of explosives needed and limit possible damage caused through the removal of components

that could be dangerous during the detonation or the removal of the debris. Some of the prep work is:

implementation of the construction site, sterilization, pre-weakening, charge tests, trial fire,

determining devices and explosive quantities, drilling of the elements to be demolished and the

placing of containment systems of fragments at the source.

An explosive can be defined as a substance, or a mixture of substances, susceptible to rapid changes

with an extremely short time frame (centiseconds or milliseconds) during which a large volume of gas

is produced (hundreds or thousands of time superior to the volume that the explosive occupied) and

energy is released, usually in the form of heat (Barros, 1984). When the speed of transformation is

within cm/s the explosion is considered combustion, and when it is between 100 and 1000 m/s it is

considered deflagration, and if it occurs at a speed of 2 to 9 km/s it is designated as an explosion. This

explosion occurs due to the action of a stimulus, known as initiation, which is generally small and can

be achieved through percussion, shock, friction, heat or sympathy explosion. Devices called

detonators are used for this initiation, and via a primary explosive charge a chemical chain reaction

leads to a secondary explosion, which in turn detonates the explosive charge. These initiation systems

can be electrical, non-electrical (pyrotechnic, NONEL and detonating cord) and electronic.

3. Explosive demolition project

3.1. Project Phases

The starting point for an explosive demolition project is the selection of the collapse mechanism, as

this is the key element in defining the preparation work for the structure, specifically the pre-

weakening, drilling, definition of the firing system and impact control measures (Gomes, 2013). To

identify the collapse mechanism three factors that influence its choice are surrounding, structural

and environmental evaluation.

Gomes (2000), cited by Brown (1995) refers that, the objective of defining the correct collapse

mechanism is to obtain an efficient controlled collapse, maximise structure fragmentation, control

material projections and avoid damage to adjacent infrastructures.

During the execution of the explosive demolitions project, modelling is done through the use of

software, so that the behaviour of the structure during the collapse can be understood and to

subsequently define the timings that lead to the fire plan. At the same time the explosive charges

necessary to create the demolition belt and the collapse mechanism are calculated, and these are

later verified with trial fire. Figure 3.1 illustrates the iterative process used to define the collapse

mechanism.

Explosive demolition of reinforced concrete buildings

4

Figure 3.1 - Definition of the collapse mechanism and the explosive demolition project phases

A further objective is to determine the fire plan, as well as the element to drill and fill with explosives,

how to cause as little disturbance as possible, both before and after the event, by reducing material

projections, shockwaves and ground vibrations. The values obtained are then used in the three

evaluations referred to previously.

3.2. Applied Element Method

Computer assisted simulation is an important tool to ascertain the behaviour of buildings subject to

extreme conditions such as earthquakes, structural impacts, explosions or progressive collapses, as in

the case of demolitions. To make up for existing weaknesses in the finite element method (FEM) and

the discrete element method (DEM), a new method, Applied Element Method (AEM) was developed,

which is capable of predicting with a high degree of precision continuous and discrete structural

behaviour, which is the basis of Extreme Loading for Structures (ELS), software owned be Applied

Science International (ASI).

The applied element method manages the behaviour of structural collapses over different phases,

automatically calculating all of the elastic stage, crack initiation and propagation, reinforcement

yielding, formation of plastic nodes, buckling and post-buckling, separation of elements, the

collision/contact between elements and the collision with the ground and adjacent structures (Lupoae,

2009; ASI, 2006).

In the applied element method, the structures are modelled as a set of reduced elements, which arise

from a dividing of the structure, as Figure 3.2 a) and b) illustrate. The elements are connected via sets

Extended Abstract

5

of springs, of normal and shear springs, which are located at contact points and distributed over the

sides of the two elements (Figure 3.2 c)).

a) b) c)

Figure 3.2 - Structural model of the AEM: a) Structure; b) Elements created by the AEM; c) Distribution of the

springs (Adapted: Tagel-Din, 2009)

One of the great innovations in terms of the characteristics of the AEM is the automatic detection of

contact among elements, as well as the dissipation of energy when contact occurs among the

elements and the ground. Another characteristic of the AEM is the creation of independent meshes for

each element, which makes the entire modelling process much quicker, as it is not necessary to adjust

the mesh of other elements (Tagel-Din, 2009).

3.3. Explosive charges

As previously referred to in 3.1, the explosive charges are calculated simultaneously with the

modelling and the pre-weakening processes being especially relevant its calculation as it is necessary

to create the demolition belt, which can then cause the collapse mechanism and therefore the

demolition to occur as predicted.

One of the methods used by the designers for the calculation of the explosive charges is usually of an

empiric nature based on the personal experience of each individual (Kasai, 1988). From this comes

the specific charge method, which is based on the concept of the specific charge (Qe), which

represents an estimation of the weight of explosives that is necessary to fragment a cubic meter of the

element to be demolished, in terms of the demolition belt that is to be used for each vertical element.

The specific charge is distributed equitatively among each drilled space in the element (Gomes, 2010).

Gomes (2010) states that, according to the cross-section, confining and axial stress, mechanical

properties of the element and, especially, the percentage of reinforcement, the specific charge value is

between 0,50 kg/m3 and 1,5 kg/m

3 per structural element, columns and walls. However, specific

charges should be adjusted to each case according to trial fire.

Volume represented by one

axial spring and two shear stress springs.

Steel spring

Concrete spring

Explosive demolition of reinforced concrete buildings

6

Another calculation method, the Portuguese method for charge calculation, developed by Gomes

(2010)1, is a method which is based on an older empirical expressions

2 and tests on real models, and

also results in an empirical formula. Through this formula it is possible to calculate the charge

necessary to fragment sections of stone or reinforced concrete, according to spacing between drill

points, specific characteristics of elements (concrete resistance, reinforcement, among others) and the

geometry of the section.

As such, the following equation is used to calculate the quantity of explosive necessary to fragment a

section (equation 3.1) (Gomes, 2010):

𝑄 = 𝑅2 × 𝐾 × 𝐿 (3.1)

In which:

𝑄 – Explosive charge per drill (kg) using TNT. This parameter does not take into account possible

defects drill covers, considering it perfect, not taking any aggravating coefficient for this factor;

𝑅 – Width of the gap chosen by the designer [m]. This usually corresponds to the distance from the

centre of the drill to the exposed face (columns) or to half the space between drills in square grids, for

example in solid concrete elements;

𝐾 – Coefficient that depends on the resistance and confining characteristics of the section (Table 3.1);

𝐿 – Section length [m].

Table 3.1 - Values for K for reinforced concrete columns and walls (Gomes, 2010)

K – Reinforced concrete columns and walls

% of reinforcement 1% 2% 3% 4%

Hoops 8 // 25-30 cm 8 // 10-15 cm 8 // 10-15 cm 8 // 10 cm

Concrete Quality Weak - Medium Medium Medium – Good Good - Very good

K 2,05 4,02 6 7,97

NOTES: The values for K can be reduced if the element hoops are lower than considered above, i.e. if spacing is greater than indicated. Excluded from this adjustment is the value of K (1%) that should not be optimised but possibly increased if the concrete is of good quality.

4. Case Study – HFAR Building C5

The objective of this chapter is to present a real case study of the demolition of a reinforced concrete

building using explosive demolition methods. The case study was building C5 of the Armed Forces

hospital, and the demolition process was accompanied by the author from start to the end.

The building consisted of two approximately symmetrical elements, separated by an expansion joint,

and there were two floors above ground level and accessed via stairways. The roof was inclined and

1 Developed by Gomes (2010) in the Explosives and Counter-Measures Training Centre of the Engineering

Practical School, current Engineering Regiment n.º 1. 2 The empirical formula used as the basis is known among military engineers as the “miners formula”.

Extended Abstract

7

not accessible. There was also a small underground basement. The building had a large site area of

approximately 620 m2 (Figure 4.1).

Figure 4.1 - Building C5

Compared to a conventional mechanical demolition, this method took substantially less time and work

volume, and limited the impact of the demolition (dust, noise, accident risk, safety, vibration

transmission) almost exclusively to the duration of the collapse and removal of the debris.

In terms of the available space for the debris, and taking into account the building type and the

collapse mechanism chosen, the existing surrounding area was sufficient for the debris area, not

exceeding a total area of 1000 m2, being deposited approximately in the area that the building had

occupied.

4.1. Description of the demolition

The explosive demolition of the HFAR C5 building had the following phases: construction site

implementation, structure sterilisation, structural pre-weakening, source containment works, placing of

explosive charges, detonation, and removal of the debris. The placing of the explosive charges and

consequent detonation can only be done after all previous phases have been concluded, and the

other phases were all done through conventional mechanical means.

The collapse of the structure was achieved by the detonation of the internal explosive charges that

were placed in all the vertical structural elements (columns and walls) on the ground floor and the first

floor. Timers with 400 ms intervals were introduced for the initiation process, so as to ensure that the

progressive collapse mechanism calculated ensued. The use of timers means that there was less

vibration transmission to the ground as there is less mass that simultaneously impacts, which leads to

a reduction in the pressurised wave that comes from the detonation and maximises the stress

increase due to bending.

The Extreme Loading for Structures software is used to validate the defined collapse mechanism, and

with it, it’s possible to understand the behaviour of the structure during the collapse and also improve

the initial fire plan, so that structure fragmentation is as much as possible and that the whole process

is carried through safely and as planned.

Explosive demolition of reinforced concrete buildings

8

It was initially predicted through the models that there would be reduced fragmentation of non-

detonated structural elements due to the building’s low height. However, after the demolition these

elements became accessible by mechanical means and could be easily dismantled.

The initiation system in this case study was carried out using a mixed system, which consisted of

electronic and non-electrical detonators (NONEL) as illustrated in Figure 4.2.

Figure 4.2 - Schematics of the initiation system

All of the surface networks, installations and infrastructures that were to remain operational after the

demolition, such as the water and electrical supply networks, pavements and paved roads, were

protected by the use of a 60 cm dissipation layer using materials from the sterilisation phase.

The quantity of fragmentation charges used to create the demolition belt of the vertical elements was

obtained through the use of the methods in chapter 3.3, and they were calculated using the specific

charge and the Portuguese method. The quantities obtained were 45 g for larger columns and 35 g for

smaller columns, and these charges were verified through trial fire.

4.2. Impact control

When there is an explosive demolition it is necessary to control the impact that the explosion may

have, such as vibration, wave propagation, dust and projectile control. They do not occur over a

prolonged length of time like in demolitions via traditional methods but are confined to a short period of

time and can have large spike values.

Through the use of timers used with the explosive charges, dissipation of the debris pile, covering of

the explosive charges within the drillings using hardboard panels and mineral wool filling, hooked wire

and geotextile blanket placed in the vertical elements, and the use of big bags e swimming pools, the

varying impacts were mitigated.

Extended Abstract

9

4.3. Comparative cost analysis between explosive and traditional demolition

methods

One of the parameters that heavily influence the choice of the demolition methods is cost. As a result

it is important to do a comparative analysis of demolition costs of explosive and traditional methods.

Table 4.1 indicates the total cost of the materials used in the explosives demolition of the HFAR

building C5.

Table 4.1 - Costs of the consumed and non-consumed material

Total(partial) [€]

Explosives and accessories 2.353,84

Material - consumed 5.634,77

Material - non-consumed 1.267,40

Total [€] 9.256,02

Added to these values are costs related to personnel that come to a total of 4.874,08 €, and total costs

of 1.401,23 € related to displacements. The total cost of the demolition of HFAR building C5 was

therefore 15.531,33 €.

In terms of the mechanical part used in both demolition methods, the costs are estimated using tables

created by Engineer Miguel Costa for his Master’s dissertation “Structure Demolition Processes”.

The cost of the mechanical part used in the explosive method was 9.114,12 €, and the simulation of

the demolition using traditional methods had a total cost of 35.758,06 €.

The total cost of all the phases of the explosive demolition is 24.645,45 €, and when compared to a

traditional demolition which has a cost of 35.758,06 €, that although there is a clear difference in cost

of 11.112,61 €, may not be enough to justify one method over another. This is because the choice of

method can be conditioned by the equipment the company has available to execute the demolition for

example, the demolition of a 50 metre building may mean that the renting or purchase of the

equipment necessary may increase the costs enough to make another method less expensive.

A possible analysis of the explosive demolition cost can be done by the cost per square meter. The

first line of Table 4.2 shows the cost per square meter of the HFAR C5 building, as well as five other

alternatives.

Explosive demolition of reinforced concrete buildings

10

Table 4.2 - Demolition costs per m2

Floors (Nº)

Charged Floors (Nº)

Area [m2] Covered Area [m

2] Total cost [€] Cost [€/m

2]

3 2 618,49 1855,46 24.645,45 13,28

5 2 618,49 3092,43 24.645,45 7,97

6 3 618,49 3710,91 36.968,17 9,96

8 3 618,49 4947,88 36.968,17 7,47

9 4 618,49 5566,37 49.290,89 8,86

13 4 618,49 8040,31 49.290,89 6,13

It is clear that the costs per square meter of the covered area are less when the case study C5, which

had three floors and two had charges is compared with a building with five floors and two charged, as

they both have the same total costs but as the covered area is greater in the second case then the

cost per square meter decreases from 13,28 € to 7,97 €. As such, Table 4.2 illustrate that the more

floors a building has the lower its cost per square meter will be, only increasing depending on the

increase in the number of floors with charges.

5. Conclusions

The use of electronic initiation systems is an evolution that has led to greater precision in demolition

execution and to a greater level of safety, due to its extremely low timing errors and the capacity to not

only introduce different timers but their correction even after all of the firing system has been set up.

This initiation system is very safe because it is only activated when it receives the correct code and

the necessary energy, avoiding any accidental detonation.

The selection of the collapse mechanism is the key element in defining various tasks executed before

the demolition. It is defined after a precise and thorough evaluation of the structure, surroundings and

its environment, which leads to the fire plan as well as impact control measures.

The evolution of computer software has been remarkable over the years, and it is an essential tool for

engineers. The applied element method is an example of its use, as it allows occurrences within

structure to be analysed, such as crack initiation and the separation, collision and collapse of

elements.

The calculation of the explosive charges is not an exact process as there is a large number of

parameters that may influence it. However, it is possible to has an order of the quantity of explosive to

be use, this can be better assessed using trial fire tests.

The case study shows that it is possible to use explosive demolition even in conditions that are not

particularly favourable. Although the demolition occurs inside a hospital and the building is very close

to others (one of them fairly susceptible to vibrations), as well as the building not having the best

Extended Abstract

11

configuration for this type of demolition, it was possible to use explosive demolition without any

resulting problems and without bothering the hospital and its daily functions.

The case study analysed shows how each demolition phase interconnects and how important each

one is for a safe demolition that occurs sequentially as planned and obtains the maximum possible

fragmentation whilst causing minimum damage to adjacent structures and interfering as little as

possible with the surrounding environment and population.

Because of the way the entire explosives demolition process is executed it has a noticeably lower

accident risk than a traditional demolition, not only for those who work in the demolition but also for the

people that contact with the work throughout its execution. This higher level of safety is due to:

i. reduced number of work in elevated locations;

ii. the high degree of efficiency of the initiation systems, as well as the way they are set up on-

site and their control;

iii. the detailed planning of the entire demolition sequence;

iv. the security perimeter that is established during the demolition ensures that there are no

people on-site and in danger.

By analysing the various measures described in chapter 4.2 it is possible to conclude that performing

a conveniently demolition plan and using different containment systems to the material and the dust

generated allows to reduce vibrations transmitted to the adjacent structures as well as absorbing a

large part of the shockwave created, decreasing material projection and controlling the dispersion of

the dust created.

The cost analysis, although simplified, shows that for a building of at least 5 floors, explosive

demolition costs can be considerably lower than those of a traditional demolition, given that for these

cases a traditional demolition requires especial equipment. Furthermore, traditional demolitions take

much longer than explosive demolitions methods, which mean greater interference with local

installations.

In conclusion, each demolition method has its own scope. However, for reinforced concrete buildings

and from a set number of floors onward, explosive demolitions can be considerably advantageous

when compared to traditional methods.

Bibliographic references

ASI. (2006). Extreme loading for structures technical manual. Applied Science International.

Barros, D. P. de (1984). Explosives, fireworks and aggressive chemicals (in Portuguese). Lisboa,

Portugal: Academia Militar.

Brito, J. de (1999). Demolition methods in current buildings (in Portuguese). Advanced master in

construction and rehabilitation. Instituto Superior Técnico. Lisboa.

Explosive demolition of reinforced concrete buildings

12

Gomes, G. J. (2010). Technical manual of demolition by explosive methods (in Portuguese). Lisboa:

Academia Militar.

Gomes, G. J. (2013). Explosive demolition methods (in Portuguese). Lisboa: Academia Militar.

Gomes, R. (2000). Demolition of structures by the controlled use of explosives (in Portuguese).

(Master dissertation in constraction). Instituto Superior Técnico. Lisboa.

Jimeno C. L., Jimeno E. L. & Carcedo F. J. A. (1995). Drilling and blasting of rocks. New York, USA:

Tayler & Francis.

Kasai, Y. (1988). Demolition methods and practice. Proceedings of the second international RILEM

Symposium – V. 1. New York, USA: Taylor & Francis.

Lupoae, M. & Bucur, C. (2009). Use of applied element method to simulate the collapse of a building.

SISOM 2009 and Session of the Commission of Acoustics, pp13-18, May. Bucharest.

Tagel-Din, H. (2009). High Fidelity Modeling of Building Collapse with Realistic Visualization of

Resulting Damage and Debris Using the Applied Element Method. Applied Science

International. http://www.extremeloading.com/contents.aspx/els-dtra-report. Accessed in

22/03/2014.


Recommended