+ All Categories
Home > Documents > Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized...

Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized...

Date post: 08-Aug-2020
Category:
Upload: others
View: 2 times
Download: 0 times
Share this document with a friend
13
Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons learned from auctioning transmission for the integration of renewables Rafael Ferreira Luiz Barroso [email protected] PES GM 2015 Panel: Planning Transmission for Co-optimization with Resource Expansion – Part II July 28 th 2015
Transcript
Page 1: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil

Lessons learned from auctioning transmission for the integration of renewables

Rafael Ferreira‡

Luiz Barroso

[email protected]

PES GM 2015

Panel: Planning Transmission for Co-optimization with

Resource Expansion – Part II

July 28th 2015

Page 2: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

Outline

• The name of the game is timing • The good old coordination and its failure • Let the transcos bear the risk? • Let the generators bear the risk? • Stronger involvement of the planning function • It isn’t over yet…

2

Page 3: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

• Coordination of transmission and (renewable) generation expansion in Brazil has been facing difficulties – Public & private agents; market-oriented and regulated environments

– Coordination, design of incentives, allocation of risks anything but simple

• Lately, timing has been one of the main issues: – Transmission delays large amounts of stranded renewable generation

The name of the game is timing 3

Centralized, determinative

T planning (Para)govern-mental bodies

Ministry Plan. Agencies‡

Organize T auctions

Design penalties, incentives

Regulator

‡ Planning Agencies: here, reference to Energy Research Agency (planner) and National System Operator (ISO)

Compete in G auctions

Connect to grid Energy sales

(Renewable) gencos

Compete in T auctions

Build & operate T facilities

Fixed revenues

Transcos

Page 4: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

The good old coordination… • At first, coordination based on transmission implementation

being quicker than generation implementation worked well

4

Time

Generation auction

COD

3 years for G implementation by genco

Decentralized expansion Location, capacity

known after auction

Transmission planning

Centralized planning

Transmission auction

Decentralized imple-

mentation

Competitive process

2 years for T implementation by transco

Competitive process

Page 5: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

… and its failure • Generation auctions began to be held 2.5 or 2 years ahead of COD • Actual implementation times for transmission increased notably

– Delays largely (but not solely) related to environmental licensing process

• Stranded (ready to operate, but disconnected from grid) generation

– Trading cannot happen. Who pays? Who bears the risk? – Since 2008-2009, it had been the consumers (buyers). But in ~2013 the

amount of stranded generation was such that this was no longer viable.

5

Page 6: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

Let the transcos bear the risk? • Competition in auctions for

transmission concessions has several advantages… but also limitations: – The multiplicity of agents and the

scale of transcos does not allow them to bear the risks of stranded generation

– Ex.: monetary amount of purchases of mere 100 MW in the spot market in one year (implementation delays ≫ 1 year are common) are more than 100% of the annual revenues of 85% of the transcos.

6

~85% of transcos

• Delays in environmental licensing are not always attributable to transcos bureaucratic process with interactions with several governmental bodies and diffuse responsibilities

Page 7: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

• Naturally, there are incentives for transcos to comply with implementation deadlines in Brazil: – Chronology:

• But these do not suffice to cover the exposure of the contractual counterparties when generation gets stranded. – And these incentives alone do not seem to have been sufficient to

mitigate the problem of delays.

2012 (+): Preclusion from participation in subsequent auctions

Let the transcos bear the risk? 7

Early incentives (that persist nowadays): Execution of completion bonds (5% of estimated capex of facilities) Regulated revenues received only after actual commencement of commercial operation Discounts and penalties due to delays

2014 (+): More clear conditions for execution of completion bonds

2015 (+): Completion bonds increase to 10% of capex

Page 8: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

Let the generator bear the risk? • Another option would be to simply let the generator

bear the risk (and introduce no other improvements): – Implemented in some generation auctions. – But the risks of foregoing revenues (transmission delays

exceeding 1 year are not uncommon) in the beginning of the project lifetime hurt cash flows significantly

• Some entrepreneurs find risks too high drop out of auctions

– Though gencos can theoretically seek to choose the most “safe” connection points for their projects, they have no way of influencing the implementation of transmission

• And in Brazil there are no instruments such as FTRs that allow them to hedge against the risks of insufficient transmission capacity

8

Page 9: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

Stronger involvement of planning function • The current solution was obtained with a stronger commitment

of the planning function to the process: – Generators still bear the risks of transmission delays. Plus… – “Transmission allowances”:

• Before auction: ISO determines the maximum generation capacity that can be contracted at each substation (and “electrical areas”)

• During auction: candidate projects at each substation compete, with basis on prices, for transmission capacity

– Centralized agency with responsibility for determinative transmission expansion planning does proactive planning of bulk transmission system

• Attempts to involve central planner in environmental licensing: – Currently: licenses obtained by T auction winners only after T auction – Ongoing discussions about making central planner responsible for

obtaining T environmental licenses before transmission auctions

9

Page 10: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

Some challenges under this approach • Determination of “transmission

allowances” is complex: – Exact contractible capacity:

depends on amounts contracted in other substations, grid interactions determination before auction not technically unequivocal

• An iterative determination of “allowances” within auction process could solve this… – … but make process too

complex and opaque for investors.

• Current auction process: 1. Sealed-bid stage, projects

with lowest bids until “allowance” is met continue in following stages

2. Descending clock stage 3. Final sealed-bid stage

10

Source: ONS

Page 11: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

Some challenges under this approach • Proactive bulk transmission planning:

– Central planning of transmission with as much antecedence as possible with respect to generation auctions transmission auctioned and construction begins before generation auctions winners are known

– Best efforts of central planner, best information available • Information asymmetry? • How to avoid “picking winners”? • Risks of underutilization of transmission facilities borne basically by consumers.

11

Investments are sizable: hundreds of km of OHTL, hundreds of MVA of transformation capacity

Proactive transmission expansion decisions

Best info on high-quality wind potential

Source: EPE

Page 12: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

Conclusions (it isn’t over yet) • The “transmission allowances” were not used in all auctions:

– When not used, generators perceive higher risks of being stranded. – When used, theoretically higher risks of:

• Sub-optimal auction results (ex ante calculation); strategic behavior (segregation of demand). • Up to now, no complaints by agents or governmental bodies regarding the topics above.

• Experiences with proactive planning still incipient, but: – First transmission facilities auctioned: annual revenues of ~145 BRL million – Large number of renewables connecting to these facilities won auctions

these specific facilities allowed access to very high-quality wind resources – Will concerns with “picking winners” appear later?

• Attempts to make central planner responsible for obtaining environmental licenses for transmission before auctions: – Would reduce risks of transcos. But would speed up whole expansion process?

12

Page 13: Coordinating centralized planning and decentralized … · 2015-09-21 · Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil Lessons

Questions? Thanks!

13

Coordinating centralized planning and decentralized implementation of transmission expansion in Brazil:

Lessons learned from auctioning transmission for the integration of renewables

IEEE PES GM 2015, July 2015

R. Ferreira‡

L. Barroso

[email protected]


Recommended