JOINT MEASUREMENT SHEET (JMS)
We request your attendance to Joint Measurement to the following works:-
Subject: Site Clearing
Scope/Location/Structure: STA 91+700 ~ STA 97+700 Date: 02 March 2012 to 10 March 2012
Description / Remarks / Sketch
Summary Measurement of Site Clearing
2.01.(01) Clearing and grubbing classified dense field free area and rubber plantation
14,933.157 Sq.m
12,639.822 Sq.m
44,685.564 Sq.m
Subtotal = 1.250 m = 72,258.543 Sq.m
2.01.(02) Clearing and grubbing classified scattered free area and village area
2.01.(03) Clearing and grubbing classified rice field swampy area, cultivated area and grass field
4,952.095 Sq.m
34,885.834 Sq.m
18,654.622 Sq.m
15,463.449 Sq.m
4,762.884 Sq.m
42,262.822 Sq.m
52,918.471 Sq.m
103,391.590 Sq.m
35,318.853 Sq.m
Subtotal = 3.500 m = 312,610.620 Sq.m
With Attachment Without Attachment
Jointly Measured By Verified By:
Prepared By: Checked By:PMC
KGNRC CONSULTANT
Signature : Signature : Signature
Name : Name : Name
Designation : Designation : Designation
CIKAMPEK – PALIMANAN TOLL ROAD PROJECT
REF: CIPAL/JMS/01_____________
Pay Item No :
· STA 92+500 ~ 92+850 = 350 m =
· STA 93+000 ~ 93+200 = 200 m =
· STA 93+200 ~ 93+900 = 700 m =
· STA 91+700 – 91+800 = 100 m =
· STA 91+800 – 92+250 = 450 m =
· STA 92+300 – 92+500 = 200 m =
· STA 93+900 ~ 94+250 = 350 m =
· STA 95+300 ~ 95+400 = 100 m =
· STA 95+400 ~ 96+000 = 600 m =
· STA 96+000 ~ 96+700 = 700 m =
· STA 96+700 ~ 97+400 = 700 m =
· STA 97+400 ~ 97+700 = 300 m =
Please tick (√) where necessary;
√
KG - NRC CONSORTIUMKG - NRC CONSORTIUM
Date : Date : Date
* The JMS’s running no. shall be controlled, recorded and maintain by KGNRC.
CIPAL/FORM/JMS/NOV 2011/REV.0
JOINT MEASUREMENT SHEET (JMS)
We request your attendance to Joint Measurement to the following works:-
Subject: Site Clearing
Date: 02 March 2012 to 10 March 2012
Description / Remarks / Sketch
Summary Measurement of Site Clearing
2.01.(01) Clearing and grubbing classified dense field free area and rubber plantation
2.01.(02) Clearing and grubbing classified scattered free area and village area
2.01.(03) Clearing and grubbing classified rice field swampy area, cultivated area and grass field
With Attachment Without Attachment
Verified By:
PMC
Signature :
Name :
Designation :
REF: CIPAL/JMS/01_____________
Date :
JOINT MEASUREMENT SHEET (JMS)
We request your attendance to Joint Measurement to the following works:-
Subject: Site Clearing
Scope/Location/Structure: STA 91+700 ~ STA 97+700 Date: 02 March 2012 to 10 March 2012
Description / Remarks / Sketch
Summary Measurement of Site Clearing
2.01.(01) Clearing and grubbing classified dense field free area and rubber plantation
14,933.157 Sq.m
12,639.822 Sq.m
44,685.564 Sq.m
Subtotal = 1.250 m = 72,258.543 Sq.m
2.01.(02) Clearing and grubbing classified scattered free area and village area
2.01.(03) Clearing and grubbing classified rice field swampy area, cultivated area and grass field
4,952.095 Sq.m
34,885.834 Sq.m
18,654.622 Sq.m
15,463.449 Sq.m
4,762.884 Sq.m
42,262.822 Sq.m
52,918.471 Sq.m
103,391.590 Sq.m
35,318.853 Sq.m
Subtotal = 3.500 m = 312,610.620 Sq.m
With Attachment Without Attachment
Jointly Measured By Verified By:
Prepared By: Checked By:KG (PM)
SUBCON KG (SITE SUPERVISOR/ENGINEER)
Signature : Signature : Signature
Name : Name : Name
Designation : Designation : Designation
CIKAMPEK – PALIMANAN TOLL ROAD PROJECT
REF: CIPAL/JMS/01_____________
Pay Item No :
· STA 92+500 ~ 92+850 = 350 m =
· STA 93+000 ~ 93+200 = 200 m =
· STA 93+200 ~ 93+900 = 700 m =
· STA 91+700 – 91+800 = 100 m =
· STA 91+800 – 92+250 = 450 m =
· STA 92+300 – 92+500 = 200 m =
· STA 93+900 ~ 94+250 = 350 m =
· STA 95+300 ~ 95+400 = 100 m =
· STA 95+400 ~ 96+000 = 600 m =
· STA 96+000 ~ 96+700 = 700 m =
· STA 96+700 ~ 97+400 = 700 m =
· STA 97+400 ~ 97+700 = 300 m =
Please tick (√) where necessary;
√
Date : Date : Date
* The JMS’s running no. shall be controlled, recorded and maintain by KGNRC.
CIPAL/FORM/JMS/NOV 2011/REV.0
JOINT MEASUREMENT SHEET (JMS)
We request your attendance to Joint Measurement to the following works:-
Subject: Site Clearing
Date: 02 March 2012 to 10 March 2012
Description / Remarks / Sketch
Summary Measurement of Site Clearing
2.01.(01) Clearing and grubbing classified dense field free area and rubber plantation
2.01.(02) Clearing and grubbing classified scattered free area and village area
2.01.(03) Clearing and grubbing classified rice field swampy area, cultivated area and grass field
With Attachment Without Attachment
Verified By:
KG (PM)
Signature :
Name :
Designation :
REF: CIPAL/JMS/01_____________
Date :
JOINT MEASUREMENT SHEET (JMS)
We request your attendance to Joint Measurement to the following works:-Subject: Site ClearingScope/Location/Structure: STA 91+700 ~ STA 97+975 Date: 02 March 2012 to 10 March 2012Description / Remarks / Sketch
Summary Measurement of Site Clearing
2.01.(01) Clearing and grubbing classified dense field free area and rubber plantation
14,395.628 Sq.m 14,933.157
13,373.088 Sq.m 12,639.822
50,736.334 Sq.m 44,685.564
Subtotal = 1.250 m = 78,505.050 Sq.m 72,258.543
2.01.(02) Clearing and grubbing classified scattered free area and village area
2.01.(03) Clearing and grubbing classified rice field swampy area, cultivated area and grass field
5,190.502 Sq.m 4,952.095
39,048.549 Sq.m 34,885.834
17,569.597 Sq.m 18,654.622
16,340.403 Sq.m 15,463.449
4,722.993 Sq.m 4,762.884
43,315.653 Sq.m 42,262.822
54,198.032 Sq.m 52,918.471
103,675.447 Sq.m 103,391.590
50,410.315 Sq.m 35,318.853
Subtotal = 3.500 m = 334,471.491 Sq.m 312,610.620
Please tick (ü) where necessary;
With Attachment Without Attachment
Jointly Measured By Verified By:
Prepared By: Checked By:KG (PM)
SUBCON KG (SITE SUPERVISOR/ENGINEER)Signature : Signature : Signature Name : Name : Name Designation : Designation : Designation Date : Date : Date
* The JMS’s running no. shall be controlled, recorded and maintain by KGNRC.
CIKAMPEK – PALIMANAN TOLL ROAD PROJECT
REF: CIPAL/JMS/01_____________
Pay Item No :
· STA 92+500 ~ 92+850 = 350 m =
· STA 93+000 ~ 93+200 = 200 m =
· STA 93+200 ~ 93+900 = 700 m =
· STA 91+700 – 91+800 = 100 m =
· STA 91+800 – 92+250 = 450 m =
· STA 92+300 – 92+500 = 200 m =
· STA 93+900 ~ 94+250 = 350 m =
· STA 95+300 ~ 95+400 = 100 m =
· STA 95+400 ~ 96+000 = 600 m =
· STA 96+000 ~ 96+700 = 700 m =
· STA 96+700 ~ 97+400 = 700 m =
· STA 97+400 ~ 97+700 = 300 m =
√
CIPAL/FORM/JMS/NOV 2011/REV.0
JOINT MEASUREMENT SHEET (JMS)
We request your attendance to Joint Measurement to the following works:-Subject: Site Clearing
Date: 02 March 2012 to 10 March 2012Description / Remarks / Sketch
Summary Measurement of Site Clearing
2.01.(01) Clearing and grubbing classified dense field free area and rubber plantation
2.01.(02) Clearing and grubbing classified scattered free area and village area
2.01.(03) Clearing and grubbing classified rice field swampy area, cultivated area and grass field
Please tick (ü) where necessary;
With Attachment Without Attachment
Verified By:
KG (PM)
::::
REF: CIPAL/JMS/01_____________
JOINT MEASUREMENT SHEET (JMS)
We request your attendance to Joint Measurement to the following works:-Subject: Site Clearing
Scope/Location/Structure: STA 91+700 ~ STA 97+975 Date: 02 March 2012 to 10 March 2012Description / Remarks / Sketch
Summary Measurement of Site Clearing
2.01.(01) Clearing and grubbing classified dense field free area and rubber plantation
14,395.628 Sq.m
6,529.877 Sq.m
13,373.088 Sq.m
50,736.334 Sq.m
Subtotal = 1.100 m = 85,034.927 Sq.m
2.01.(02) Clearing and grubbing classified scattered free area and village area
2.01.(03) Clearing and grubbing classified rice field swampy area, cultivated area and grass field
5,190.502 Sq.m
39,048.549 Sq.m
17,569.597 Sq.m
16,340.403 Sq.m
4,722.993 Sq.m
43,315.653 Sq.m
54,198.032 Sq.m
103,675.447 Sq.m
50,410.315 Sq.m
Subtotal = 3.810 m = 334,471.491 Sq.m
Please tick (ü) where necessary;
With Attachment Without Attachment
Jointly Measured By Verified By:
Prepared By: Checked By:KG (PM)
SUBCON KG (SITE SUPERVISOR/ENGINEER)Signature : Signature : Signature Name : Name : Name Designation : Designation : Designation Date : Date : Date
CIKAMPEK – PALIMANAN TOLL ROAD PROJECT
REF: CIPAL/JMS/01_____________
Pay Item No :
· STA 92+500 ~ 92+700 = 200 m =
· STA 92+700 ~ 92+850 = 150 m =
· STA 93+000 ~ 93+200 = 200 m =
· STA 93+200 ~ 93+900 = 700 m =
· STA 91+700 – 91+800 = 100 m =
· STA 91+800 – 92+250 = 450 m =
· STA 92+300 – 92+500 = 200 m =
· STA 93+900 ~ 94+285 = 385 m =
· STA 95+300 ~ 95+400 = 100 m =
· STA 95+400 ~ 96+000 = 600 m =
· STA 96+000 ~ 96+700 = 700 m =
· STA 96+700 ~ 97+400 = 700 m =
· STA 97+400 ~ 97+975 = 575 m =
√
* The JMS’s running no. shall be controlled, recorded and maintain by KGNRC.
CIPAL/FORM/JMS/NOV 2011/REV.0
JOINT MEASUREMENT SHEET (JMS)
We request your attendance to Joint Measurement to the following works:-Subject: Site Clearing
Date: 02 March 2012 to 10 March 2012Description / Remarks / Sketch
Summary Measurement of Site Clearing
2.01.(01) Clearing and grubbing classified dense field free area and rubber plantation
2.01.(02) Clearing and grubbing classified scattered free area and village area
2.01.(03) Clearing and grubbing classified rice field swampy area, cultivated area and grass field
Please tick (ü) where necessary;
With Attachment Without Attachment
Verified By:
KG (PM)
::::
REF: CIPAL/JMS/01_____________