CE Engineerings and Chemicals Pvt
Ltd
SIA ACTIVITY
Dec13
8/10/2019 Copy of Hoshin KanrDec2013 (1)
2/19
SIA Monthly Review PPT
Signed Hoshin KanriCo-operation Team Supplier Improvement Activity Plan in ACE Engineering
Quality Goal VECV Team Supplier Team
# To reduce ppm level to 150 PPM by
2014 end
Facilitator Mr Tomochi Katsumata MD & CEO Mr. Pradeep Jain
Leader Mr Vinayak Shanbagh Head-Manuf. Mr. Manoj Ohja
#
Zero defect at customer end
Co-ordinator Mr Yogesh Jagtap Head-Design Mr. Ramkaran Meena
Materials Mr Jeetendra Joshi RQC Mr. Mayur Ajmera#
Continual improvement in process
through Poka-Yoke & Kaizens
QA Ms. Neha Jain In process Quality Mr. Mayur Ajmera
PDD Mr. Amarjeet singh PDI Mr. Mayur Ajmera
Supplier up-gradation Mr. Vinay Singh Tool Room Mr. Rajesh Dixit
Main
Issu
e
Controlled KPI -Ace Engg.
Activity
Watched KPI - Ace Engg. Responsible &
Supporting DepartmentObje
ctive
Name
KPI
Item
s
2009
(Base)
201
2
Tgt. Tgt.
Respons
ibleKPI Items
Base
(2012
Q4)
Target 2013
Respo
nsible2013 2014 Q1 Q2 Q3 Q4 ProdDesig
n
Tool
room
QCpurch
ase
Delivery
Qual
ity
PPM
wise
PPM
Impr
ove
ment
Delivery
PPM
impr
ove
ment
11575 350 200 150 CFT
Start
QRQCIn-house monthly PDI PPM 3747 3000 2500 200 1500
CalibrationIn-house monthly Process
PPM4000 3800 3500 3200 3000
MSA In-coming monthly PPM 1950 1800 1700 1600 1500
5SNo of DOL parts
(Total 68 parts)61 62 63 65 66
ProcessAudit
PDI Execution (% of PDI
followed invoices/Totalinvoices raised)
100 100 100 100 100
Poka Yoke Process audit (No of parts ) 8 3 3 3 3
Layout inspection (No. of
parts)10221 29 19 18
IMTE and Gauge Calibration - - - 8
Tooling validation (Dies, Jigs
& Fixture validation &
Maintenance)
10 0 5 5 5
Poka Yoke 12 3 5 6 6 QS Sign off _ _ 40 28
System audit score 81% 95%
8/10/2019 Copy of Hoshin KanrDec2013 (1)
3/19
SIA Monthly Review PPT
ACE ENGINEERINGS & CHEMICALS PVT.LTD.
Monthly Internal Hoshin Kanri Review MOM with top management
S.
No
.
Date Location Issue Analysis Action Target Dt. Complet
ion Dt
Resp. GY
R
stat
us
1 5/12/13 VECV
Cover plate
assy
rejection
Due to improper adhesiveness of
insert on pp part cover plate assy.
Insert comes out; the adhesive
used acra-bond shows poor
compatibility with the partmaterial.
Adhesive My-T Bond grade
103 is used & tested as per
pull out test.
7/12/13 7/12/13
2 12/12/13 VECV
GSC IA303087- C.C
Dimension is
out by 9-10-
mm due to
which fitment
issue
occurred.
Rejected mould were used byproduction dept, only 2 mould were
OK and rest were rejected due to
which ok & not ok parts were found at
VECV as well as FG Stock. Drilling
done by seeing marking which is very
light due to which c.c varies is also the
source of variation.
Each part checked at
FG,filing,painting,moulding,re
worked with providion of
drilling fixture. New mould to
be provided with pin provision
for further production.
17/12/13 17/12/13Mr.Laxman
Surage
8/10/2019 Copy of Hoshin KanrDec2013 (1)
4/19
SIA Monthly Review PPT
ACE ENGINEERINGS & CHEMICALS PVT.LTD.
Monthly Internal Hoshin Kanri Review MOM with top management
S.
No
.
Date Location Issue Analysis Action Target
Dt.
Complet
ion Dt
Resp. GYR
status
3 22/12/13 vecvGear shift cvr
IA209914 gap
issue.
It is seen that the gap of 15-25 mm
found after fitment of the part on
line. When checked dimensionally
height found 409-415 mm against 412
mm. Although part as per drawing has
also resulted in gap from chamfer
side.
Sample (3) provided to VECV as
per fitment basis. Waiting for
feedback for changes from
VECV.
5/1/14 TBP vecv
8/10/2019 Copy of Hoshin KanrDec2013 (1)
5/19
SIA Monthly Review PPT
Control KPI
KPI Summary
Months Jan-13 Feb-13March-
13Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13
KPI R Y G R Y G R Y G R Y G R Y G R Y G R Y G R Y G R Y G R Y G R Y G R Y G
Controlle
d0 0 1 1 0 0 0 0 1 0 0 1 1 0 0 0 0 1 1 0 0 0 0 1 0 0 1 0 0 1 1 0 0 0 0 1
Controlled KPI :-
S. No.Main
Issue
Objective
NameKPI Items Status
Targets VS ActualRemark
s13-
Jan
13-
Feb
13-
Mar
13-
Apr
13-
May
13-
Jun13-Jul
13-
Aug
13-
Sep
13-
Oct
13-
Nov
13-
Dec
1.
Delivery
Quality
PPM
wise
PPM
Improveme
nt
Delivery PPM
improvement
TARGET 325 325 325 300 300 300 250 250 250 200 200 200
ACTUAL 49 939 96 39 606 0 756 200 90 79 682 133
8/10/2019 Copy of Hoshin KanrDec2013 (1)
6/19
SIA Monthly Review PPT
Control KPI 1 Pareto & Root Cause analysis with implementation detail
1 1 1
7
9
10
0
2
4
6
8
10
12
Handle Loose Metal Insert
removing
Hinge Inclined DAMAGE BOLT LOOSE PAINT PROBLEM
DEFECT REPEATATION
QUANTITY
8/10/2019 Copy of Hoshin KanrDec2013 (1)
7/19
Customer End Rejection Monitoring from JAN '13-DEC 13
Sno.Item
CodeItem Name Nature of Defects
JAN'13
FEB'13
MAR'13
APR13
MAY'13
JUN'13
JUL'13
AUG'13
SEP'13
OCT'13
NOV'13
Dec;13
Root Cause Action PlanTarget
Date
Statu
s
(RY
G)
1 IA22025
9
PANEL SHIELD
SIDE UPPER RH
DAMAGE 1 NA NA NAG
2 IA22453
5
ASSY. ENGINE
COVER
BOLT LOOSE 9 Pin dia was less in
mold.
Mold scraped which was
found wrong
02-Mar-
13 G
100% of visual inspection
will be done of the bolt
before dispatch & yellow
sticker is pasted on the hinge
if bolt found wrong
01-Mar-
13
G
HANDLE 1 I1)mproper tightening
of the screw
1)Sop prepared for
tightening the screwControl; plan has also been
revised.
2) Checking of handle by
pulling it is also implemented
at the time of PDI
01-Nov-
13
G
3 IA225381
PAD SPRAYSUPPRESSION
CD DIMENSIONNOT OK
3 Drilling fixture verified& found not ok
New drilling fixture madewith hardened bush.
Checking of gauges is done in
every 4 month.
15-Feb-12
G
7 Drilling process is not
adequate .
Punching will be used for the
control of dimension
8/06/13
G
4
IA22360
9
BATTERY COVER
DAMAGE(AIR
BUBBLE AROUND
BUSH
1Air bubble at the time
of molding
Painting process has been
revised , checking being done
at primer stage.
25
may13
g
8/10/2019 Copy of Hoshin KanrDec2013 (1)
8/19
Customer End Rejection Monitoring from JAN '13-DEC 13
Sno
.
Item
CodeItem Name Nature of Defects
JAN'13
FEB'13
MAR'13
APR13
MAY'13
JUN'13
JUL'13
AUG'13
SEP'13
OCT'13
NOV'13
Dec;13
Root Cause Action PlanTarget
Date
Statu
s
(RY
G)
5IA30745
2
AIR CLEANER
COVER ASSY
DAMAGE 2 G
DAMAGE AT
GROMMET2
Crack found at the position of
grommet
Grommet will beassemble in parts at
supplier end
G
2
Previously grommet was fixed
by hand , due to
transportation there are
chances of releasing grommet
from parts.
At the time of fixing the
grommet , the adhesive
is also pasted to give
good bonding.
10/08/20
13
G
6IA23018
7
COWL GRILL
CENTER (HCV
FACE COWL)
DAMAGE 1 Handling damage at VECV -- NIL G
C.C OUT
1
Different parts were checked
dimensionally with logo
fitment and found ok at
VECV by our quality person.
It is to be discussed with
the VECV concern
erson that part
rovided is ok but the
mating part could not
meet the dimension.
Sep13 G
C.C OUT 1
It is analyzed that C.C 280 is
observed 277-278mm.While
mounting the logo taking hole
as reference the last pin (215
C.C in part)is coming out of
the part when logo is fitted.
Logo pin also has variation of1 mm in C.C dimension.
Part, tool & mating part
dimensions measured for
rectifying the tool. Tool
sent to tool maker for
modification in c.d of pin
location.0/10/201
3
G
The 2 mm variation in part &
1 mm variation in logo
resulted in problem
Parts provided by filing
the slots as an immediate
action.
7IA22999
0COWL GARNISH
LOGO FITMENT
ISSUE
3
Observed that horse logo
resent at VECV is not fitted
and logo at our end has no
fitment issue.
New mould pin already
implimented and logo
available at VECV is
rought at our end,parts
now send with checking
logo mounting on theart at PDI.
19-Jul G
8/10/2019 Copy of Hoshin KanrDec2013 (1)
9/19
Customer End Rejection Monitoring from JAN '13-DEC 13
Sno. Item Code Item Name Nature of Defects
JAN'13
FEB'13
MAR'13
APR13
MAY'13
JUN'13
JUL'13
AUG'13
SEP'13
OCT'13
NOV'13
Dec;13
Root CauseAction
Plan
Target
Date
Status
(RYG
)
8 IA22385 DASHBOARD PAINT PROBLEM 10
21 out of 24
Dashboards were
found with polythene
impression on it,.
Also there is
problem with the
paint application
which impart thick
layers on the part
which gives
polythene impression
even after proper
curing time.
Holes in the
polythene is done
after proper curing
time, also electric
heaters provide
better curing of part
as compared with
the earlier used gas
furnace oven.
17/07/201
3G
9 IA222215PANEL SHIELD
T/M LOWERDAMAGE 1
Handling damage at
VECV.... NIL G
10 IC322032 Cover Plate Assy. Metal insert removing 5
the adhesive which
we are using is notcompatible to adhere
the metal insert with
ABS .
We are planning to
change our processof joining of metal
insert with ABS8/12/13
G
11 IA302841
ENGINE HOOD
ASSY
Hinge Inclined 1
CD Dimasion of the
hole was found
shifted due to which ,
The hinge found
tilted with respect to
cd dimension
Checking gauge
provided at PDI to
check the hole CD.
Immediat
e G
TOTAL 1 14 2 1 8 0 13 4 1 1 5 1
8/10/2019 Copy of Hoshin KanrDec2013 (1)
10/19SIA Monthly Review PPT
WATCH KPI TRENDS.No. WATCHED KPI
MEASUREJAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
-MENT
1In-house monthly PDI
PPM
TOTAL Qty 64687 52930 66373 76000 80401 75486 74546 59406 37720 54275 27955 61144
REJECTED 242 200 250 253 323 195 390 286 205 208 98 169
ACTUAL 3741 3778 3767 3470 4020 2580 5231 4814 5434 3680 3520 2760
TARGET 3800 3800 3800 2500 2500 2500 2000 2000 2000 1500 1500 1500
2-AIn-house monthly
Process PPM (Molding)
ACTUAL
Activity started from may
-* 2680 3338 8678 2800 2000
TARGET 3500 3500 3200 3200 5000 3000 3000 3000
2-BIn-house monthly
Process PPM (Filing)
ACTUAL
Activity started from september8931 4950 4800 4850
TARGET TBF 5000 5000 5000 5000
2-C
In-house monthly
Process PPM(Painting)
ACTUAL
Activity started from september
11139 8051 9580 6850
TARGET TBF 7000 7000 7000 7000
3In-coming monthly
PPM
ACTUAL 3400 0 0 0 0 0 0 0 0 0 0 0
TARGET 4000 4000 4000 3500 3500 3500 3000 3000 3000 2500 2500 2500
4
No of DOL partsACTUAL
61 61 58 60 62
(Total 68 parts)TARGET
62 62 62 63 63 63 65 65 65 66 66 66
5
PDI Execution (% ofPDI followed
invoices/Total invoices
raised)
No OF PDI 60 55 50 55 51 50 51 60 60 55 55 55
ACTUAL 100 100 100 100 100 100 100 100 100 100 100 100
TARGET 100 100 100 100 100 100 100 100 100 100 100 100
6Process audit (No of
parts )
ACTUALActivity started from may
5 5 3
TARGET 5 5 3
7
Dock audit (No of
parts)
ACTUAL
Activity will start from june
30 10 10 10 10 10 10
TARGET 30 10 10 10 10 10 10
8/10/2019 Copy of Hoshin KanrDec2013 (1)
11/19SIA Monthly Review PPT
S.No. WATCHED KPIMEASURE
-MENTJAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
8
Raw material
inspection plan
ACTUAL
Activity started from
APRIL..
2 2 2
(Third party)TARGET
2 2 2
9Layout inspection
(No. of parts)
ACTUAL 7 7 5 5 10 8 6 9 6 9 8 4
TARGET
7 7 5 5 10 8 6 9 6 9 8 4
10IMTE and Gauge
Calibration
ACTUAL .. 11
TARGET
.. .. .. .. .. .. .. 8
11
Tooling validation
(Dies, Jigs & Fixture
validation &
Maintenance)
ACTUAL
Activity started from may..
3 2 5 3 3 3 3 3
TARGET 3 2 5 3 3 3 3 3
12 Poka YokeACTUAL 1 1 1 1 0 2 0 1 0 2 2 1
TARGET 1 1 1 1 2 2 2 2 2 2 2 2
13 QS Sign offACTUAL
Activity will start from june..0
TARGET 40 26
14 System audit scoreACTUAL 85%
TARGET95%
KPI Summary
Months Jan-13 Feb-13 March-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13
KPI R Y G R Y G R Y G R Y G R Y G R Y G R Y G R Y G R Y G R Y G R Y G R Y G
Watched 0 0 1 1 0 0 0 0 1 0 0 1 1 0 0 0 0 1 1 0 0 0 0 1 6 0 7
8/10/2019 Copy of Hoshin KanrDec2013 (1)
12/19SIA Monthly Review PPT
Open Red KPI Status
S.
No.KPI Month
Red
ParameterReason Root Cause Action
Target
DateResp. Status
1
controlled
g
2
W
atched
Inhouse
RejectionHole Not Clear
During painting
metafill deposition
mistakenly on the
part lead to hole
block.
Painting supervisor
instructed to check part
visually before sending
to PDI. & Clear hole
before proceeding
ImmediateMayur
AjmeraG
8/10/2019 Copy of Hoshin KanrDec2013 (1)
13/19SIA Monthly Review PPT
Road-map status to achieve KPI
KPI Action to achieve the KPI TARGET RESPONSIBILITY
In-house monthly PDI PPM In process improvement & in process
checking June'13 Mr.Mayur Ajmera
In-coming monthly PPMSupplier up gradation through
supplier audit July'13 Mr.R.Patidar
No of DOL parts
100% gauging implementation, And
special focus on repeated issue July'13
Mr.Mayur
Ajmera,Mr.Laxman
Surage and
Mr.Mayaram Sharma
Defect analysis in QRQC Jan'13 Mr. Jasvin S Bhatia
Information of defect to the down
level through involvement of
workers in QRQC Jan'13
Top Management
Process auditStrengthening the QC department June'13 Top Management
Raw material inspection plan Third party involvement for
inspection July'13 Mr.Mayur Ajmera
Tooling validation (Dies, Jigs &
Fixture validation & Maintenance)Validation of drilling fixtures with in
4 months April'13 Mr. Rajan S Patta
Poka Yoke Daily QRQC & Involvement of CFT
team Jan13 Mr. Mayur Ajmera
System audit score
Internal Audit June'13 &July'13 QC & MR
8/10/2019 Copy of Hoshin KanrDec2013 (1)
14/19SIA Monthly Review PPT
Layout StatusS.
No.Month
Comp.
Planed
Comp.
Complet
ed
N. C.
obser
ved
N. C.
Closed
Cumulati
ve Open
N.C.
Reason for open NC
Target
date for
Open N
C
Resp. Remarks
1 Jan-13 7 7 0
2 Feb-13 7 7 1 1 0
3 Mar-13 5 5 0
4 Apr-13 5 5 1 1 0
5 May-13 10 10 2 1 1 Drawing req. from VECV.15 JULY
2013vecv
Horizontal slots
converted to vertical as
per req in air cleaner
cover assy.
6 Jun-13 8 8 1 0 1As per fitment part is ok, but still it is to
verify whether dim variation.
15 JULY
2013
Quality
dept.
7 Jul-13 6 6 0 0
8 Aug-13 9 9 1 1 0
9 Sep-13 6 6 1 1 0
10 Oct-13 9 9 1 0 0
Due to fouling of RH part in mudguard 12
mm trimming of the part has to be done
according to the fitment purpose, But the
LH (IA222296) IS SUPPLIED
ACCORDING TO THE WIDTH GIVEN IN
DRAWING .
15/10/1
3
VECV Mr.
Vinay
Gupta
The drawing has to be
revised according to the
reduced width
11 Nov-13 9 9 0
12 Dec-13 4 4 0
7 7
5 5
10
8
6
9
6
9 9
1
65
4
87
6
8
5
89
0
2
4
6
8
10
12
No. of Parts completed 100% Green Parts
0
1
0
1
2
1
0
1 1 1
00 0 0
1 1
0 0
1 1
0 00
1
00
1 1
0 0 0 0
0
0.5
1
1.5
2
2.5
Total N.C. N.C. Closed Cumm. Pending N.C.
8/10/2019 Copy of Hoshin KanrDec2013 (1)
15/19SIA Monthly Review PPT
In-house PPM Trend
PARETO FOR TOP CONTRIBUTOR
0
1000
2000
3000
4000
5000
6000
INHOUSE PPM TREND
PPM
34
26 2421
5
05
10152025
303540
REJECTED
QUANTITY
TOP CONTRIBUTOR OF DEC'13
In-house Rejection Status
S. No. Part No.
Non-
conformance
Detail
Repeated or
NotRoot Cause ACTION Target date Resp. Status
1 ID206599Hole Not
Clear
R
ep
a
t
e
d
During
painting
metafill
deposition
mistakenly
on the part
lead to hole
block.
Painting
supervisor
instructed to
check part
visually
before
sending to
PDI. & Clear
hole before
proceeding
ImmediateMayur
Ajmera
g
2 IA303087Hole Not
Clear
3 IA218893 Hole Not Clear
8/10/2019 Copy of Hoshin KanrDec2013 (1)
16/19SIA Monthly Review PPT
Improvement plan & status
IMPROVEMENT PLAN 2013
Sl. No Particulars PLAN DETAILS Target Responsibility
1
Quali
tyrelatedimpro
vements
Raw Material Inspection
Third party APRIL '13
Mr. Mayur Ajmera
2
Measurement of Raw
Material at shop floor MAY'13Mr. Abhinav
3
Avoid repeated customer
complaint JUNE'13Mr.Mayur Ajmera
4Dock audit to be conduct
JUNE'13Mr. Jasvin S Bhatia
5
Arrange of all gauges near
the working area. JULY'13
Mr.Jasvin S Bhatia
6
100% Guaging
Implementation of all the
parts JULY'14
Mr.Mayur Ajmera; Mr. Laxman Surage
7
Aim for 0 ppm at
customer end JULY'13Mr. Mayur Ajmera
8
100% will be checked in
layout report. JULY'13Mr.Jasvin S Bhatia
9To achieve quality System
Audit Score 95% AUG'13Mr. Mayur Ajmera
10
Punching Die
Implementation For all
types of mud flap AUG'13
Mr. Nikhil Jain
11
Machine for Dry
Sandering Is to Be Started
For Better Results SEP'13
Mr. Mayur Ajmera
8/10/2019 Copy of Hoshin KanrDec2013 (1)
17/19SIA Monthly Review PPT
POKA YOKE IMPLEMENTATION DEC13
CHECKING GAUGE FOR CD DIMENSION ENGINE HOOD ASSY IA302841
Checking of Hole By qualifying with PIN
CD dimension
8/10/2019 Copy of Hoshin KanrDec2013 (1)
18/19SIA Monthly Review PPT
General Awareness About 5S
Training conducted at our plant regarding general awareness
about 5 S, under the guidance of Mr. Sanjay Agrawal Sir.