CLIENT : SAUDI ARABIAN OIL COMPANY ELECTRICAL UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT (NRTLR) – X57 AL-KHODARI AND SONS COMPANY CONTRACT NO. 6600018467, BI-10-03566 / 0009 ENERGIZATION PACKAGE SWITCHRACK X57-SB-SR-001
Transcript

CLIENT :

SAUDI ARABIAN OIL COMPANY

ELECTRICAL

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK

PLANT (NRTLR) – X57

AL-KHODARI AND SONS COMPANYCONTRACT NO. 6600018467, BI-10-03566 / 0009

ENERGIZATION PACKAGE SWITCHRACK X57-SB-SR-001

CLIENT :

SAUDI ARABIAN OIL COMPANY

ELECTRICAL

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH

TERMINAL UNIT (NRTFF) – X56

AL-KHODARI AND SONS COMPANYCONTRACT NO. 6600018467, BI-10-03566 / 0009

ENERGIZATION PACKAGE SWITCHRACK X56-SB-SR-001

SWITCHRACK X56-SB-SR-001

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH

TERMINAL UNIT (NRTFF) – X56

ENERGIZATION PACKAGE

SWITCHRACK X57-SB-SR-001

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK

PLANT (NRTLR) – X57

ENERGIZATION PACKAGE

AL-KHODARI & SONS CO.

ELECTRICAL TIE-IN PACKAGE Tie-in No.: E-006

INDEX

No. Attachment Required

1 Tie-in Approval Sheet Yes

2 Tie-in Walk Through Checklist Yes

3 Tie-in Procedure and Statements Yes

4 Yes

5 Yes

6 Saudi ARAMCO Inspection Checklist & RMAF Yes

Note: To complete the shutdown activities it requires minimum 8 working hours.

Client : SAUDI ARAMCO

Project : Upgrade Waste Water System @ North Riyadh Bulk Plant (NRTLR) - X57

Contract : 6600018467

BI No. : 10-03566

Cable Routing Plan, Electrical Details, Cable Layout, Cable & Conduit Schedule, Cable & Conduit Layout, Electrical One-Line Diagram, Rack Layout

LV Power and Control Cable Insulation Resistance / Megger Test, Continuity Test Report

AL-KHODARI & SONS CO.

Provided Remarks

Yes

Yes

Yes

Yes

Yes

Yes

SAUDI ARAMCO

Upgrade Waste Water System @ North Riyadh Bulk Plant (NRTLR) - X57

6600018467

10-03566

AL-KHODARI & SONS CO.

PRE-COMMISSIONING CERTIFICATE

PLANT NO.: X57C0NTRACT NO.: 6600018467BI / JO NO.: BI-10-03566 / 0009

EQUIPMENT SWITCHRACK X57-SB-SR-001

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

CONTRACTOR REPRESENTATIVE

SIGNATURE & DATE

SAPMT REPRESENTATIVE

SIGNATURE & DATE

SAPID REPRESENTATIVESIGNATURE & DATE

CRDD REPRESENTATIVESIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

AL-KHODARI & SONS CO.

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

AL-KHODARI & SONS CO.

ENERGIZATION CERTIFICATE

PLANT NO.: X56C0NTRACT NO.: 6600018467BI / JO NO.: BI-10-03566 / 0009

EQUIPMENT SWITCHRACK X56-SB-SR-001

CONTRACTOR REPRESENTATIVE

SIGNATURE & DATE

SAPMT REPRESENTATIVE

SIGNATURE & DATE

SAPID REPRESENTATIVESIGNATURE & DATE

CRDD REPRESENTATIVESIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH TERMINAL UNIT

(NRTFF) – X56

The above equipment is mechanically completed. All pre-commissioning checks and final inspections have been carried out satisfactorily.

AL-KHODARI & SONS CO.

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH TERMINAL UNIT

(NRTFF) – X56

The above equipment is mechanically completed. All pre-commissioning checks and final inspections have been carried out satisfactorily.

AL-KHODARI & SONS CO.

ENERGIZATION CERTIFICATE

PLANT NO.: X57C0NTRACT NO.: 6600018467BI / JO NO.: BI-10-03566 / 0009

EQUIPMENT SWITCHRACK X57-SB-SR-001

CONTRACTOR REPRESENTATIVE

SIGNATURE & DATE

SAPMT REPRESENTATIVE

SIGNATURE & DATE

SAPID REPRESENTATIVESIGNATURE & DATE

CRDD REPRESENTATIVESIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

The above equipment is mechanically completed. All pre-commissioning checks and final inspections have been carried out satisfactorily.

AL-KHODARI & SONS CO.

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

The above equipment is mechanically completed. All pre-commissioning checks and final inspections have been carried out satisfactorily.

ELECTRICAL TIE-IN WALKTHROUGH CHECKLIST

Tie-in No. : E-003

Tapping Point : UPS X56-UPS-001 (MCB #Q103)

Service : RADAR TANK GAUGE (RTG) CONTROL U Location : NORTH RIYADH Date :

SI No. Activity Input Remarks / Reference

1 Tie-in location agreed uponYes

No

2 Shutdown offered by operation …….Days

3 Tie-in work execution duration …….Days

4 Megger & Continuity Test …….Days

Contractor's Representative SAPMT's Representative

Signature Signature

Name Name

Badge No. Badge No.

CRDD's Representative PID's Representative

Signature Signature

Name Name

Badge No. Badge No.

Remarks / Reference

AL-KHODARI & SONS CO.

PROCEDURE AND STATEMENTTIE-IN No. E-006

1.0 Saudi ARAMCO Test Report:

1.1 SATR-P-3203-LV Power & Control Cable Continuity and Megger Insulation Resistance Test1.2 Saudi ARAMCO Pre-Commissioning Form SA-P-040 - Low Voltage Cables

2.0 IFC Drawings:

2.1 VA-338128, SHT-002, REV-00 : CABLE LAYOUT2.2 VA-041027, SHT-001, REV-01D : CABLE LAYOUT2.3 VA-041032, SHT-001, REV-02E : CABLE / CONDUIT LAYOUT2.4 VD-338129, SHT-001, REV-00A : CABLE & CONDUIT SCHEDULE

3.0 Scope:

3.1 The scope of work describes the activities to be performed for the safe performance of "Tie-In" to the Existing Multipurpose Panel X57-PP-004, which will feed power to the new Level Transmitter X57-LIT-1986 on the existing Sanitary Septic Tank, with power cable (PC-8941) and needs termination during shutdown period.

4.0 Safety Requirements:

4.1 Al-Khodari & Sons Co. and Operation Department jointly walk through prior to request for work permit.4.2 Al-Khodari & Sons Co. to obtain work permit from operation department.4.3 Al-Khodari & Sons Co. Safety Officer should be at the shutdown location & should be familiar with the approved shutdown procedure.

Client : SAUDI ARAMCO

Project : Upgrade Waste Water System @ North Riyadh Bulk Plant (NRTLR) - X57

Contract : 6600018467

BI No. : 10-03566

From Existing Multipurpose Panel X57-PP-004 to New Level Transmitter X57-LIT-1986

4.4 Al-Khodari & Sons Co. Safety Officer shall make a brief safety meeting at the work location, prior to start of work.

5.0 Tools & Equipment Required for The Job:

5.1 Terminal Lugs5.2 If necessary Raychem Tube / Termination Kit

5.3 Electrical Tape (Red, Yellow, Blue, White, & Green)5.4 Rubber tape5.5 Bolts, Nuts, Flat Washers, & Lock Washers5.6 Pencil & Pen5.7 Hydraulic Crimping Tools5.8 Adjustable Wrench / Socket Wrench / Torque Wrench5.9 Trouble Lights5.10 Megger Tester5.11 Multimeter/Multi-Tester5.12 Electric Drills5.13 Extension Cord5.14 Splicing Knife5.15 Hacksaw Frame with Blades5.16 Two (2) sets of tool box, etc.

6.0 Sequence of Activities Required for The Job :

6.1 Coordinate closely with the Operation and SAPMT prior to shutdown, a short meeting shall be conducted so that everybody is aware on how long the schedule will take and should be agreed by the operation / maintenance / PMT and the contractor.6.2 Al-Khodari & Sons Co. to obtain necessary work permit from Operation / Maintenance.6.3 Operation / Maintenance should be informed that the work is ready in order to proceed with the shutdown.6.4 After shutdown of the requested power supply by ARAMCO Maintenance at existing substation, double check to make sure that no power prior to start of any work, this is for all the equipment involve in the shutdown (Downstream).6.5 After shutdown, warning tagging has to be put by the Operation Department if applicable lock the requested transfer power supply switch (perform Lock-out Tag-out {LOTO} Procedure) . Refer to GI 6.012: Isolation, Lockout and Use of Hold Tags.6.6 Perform continuity testing and Megger testing of cables, note all the reading as per approved QA/QC format and the entire work shall be witnessed by Al-Khodari & Sons Co. and Saudi ARAMCO QC personnel.6.7 After meggering, start cable arrangement in each phase, note that all cable were already prepared as per standard termination procedure (e.g. cutting, crimping, insulating) and ready for connection.6.8 Make sure that all terminal lugs are in position, tightened the bolts with flat washer and lock washer as per standard.6.9 After all activities are completed all QA/QC document should be checked and signed by Al-Khodari & Sons Co., ARAMCO Inspection and Operation / Maintenance Department (if required).6.10 The Operation and Maintenance Department to resume power supply after termination.

7.0 Shutdown / Tie-In Duration :

7.1 A notification will be given to Saudi ARAMCO, thirty (30) days prior on performing the tie-in activities, to plan and prepare for the upcoming shutdown.7.2 To complete the shutdown activities, it may require a minimum of eight (8) working hours.

AL-KHODARI & SONS CO.

1.1 SATR-P-3203-LV Power & Control Cable Continuity and Megger Insulation Resistance Test

3.1 The scope of work describes the activities to be performed for the safe performance of "Tie-In" to the Existing Multipurpose Panel X57-PP-004, which will feed power to the new Level Transmitter X57-LIT-1986 on the existing Sanitary Septic Tank, with power cable (PC-8941) and needs termination during shutdown period.

4.1 Al-Khodari & Sons Co. and Operation Department jointly walk through prior to request for work permit.

4.3 Al-Khodari & Sons Co. Safety Officer should be at the shutdown location & should be familiar with the

Upgrade Waste Water System @ North Riyadh Bulk Plant

From Existing Multipurpose Panel X57-PP-004 to New Level Transmitter X57-LIT-1986

4.4 Al-Khodari & Sons Co. Safety Officer shall make a brief safety meeting at the work location, prior to

6.1 Coordinate closely with the Operation and SAPMT prior to shutdown, a short meeting shall be conducted so that everybody is aware on how long the schedule will take and should be agreed by the

6.3 Operation / Maintenance should be informed that the work is ready in order to proceed with the shutdown.6.4 After shutdown of the requested power supply by ARAMCO Maintenance at existing substation, double check to make sure that no power prior to start of any work, this is for all the equipment involve

6.5 After shutdown, warning tagging has to be put by the Operation Department if applicable lock the requested transfer power supply switch (perform Lock-out Tag-out {LOTO} Procedure) . Refer to GI 6.012: Isolation, Lockout and Use of Hold Tags.6.6 Perform continuity testing and Megger testing of cables, note all the reading as per approved QA/QC format and the entire work shall be witnessed by Al-Khodari & Sons Co. and Saudi ARAMCO QC

6.7 After meggering, start cable arrangement in each phase, note that all cable were already prepared as per standard termination procedure (e.g. cutting, crimping, insulating) and ready for connection.6.8 Make sure that all terminal lugs are in position, tightened the bolts with flat washer and lock washer as

6.9 After all activities are completed all QA/QC document should be checked and signed by Al-Khodari & Sons Co., ARAMCO Inspection and Operation / Maintenance Department (if required).

7.1 A notification will be given to Saudi ARAMCO, thirty (30) days prior on performing the tie-in activities, to

7.2 To complete the shutdown activities, it may require a minimum of eight (8) working hours.

REQUEST FOR MATERIAL APPROVAL SUBMISSION STATUS

AL-KHODARI & SONS CO. "BULK MATERIALS"

DATE:

DOCUMENT No.:

MR No. REVISION:

S/N DESCRIPTION CCC No. 9 COM No. SUPPLIER MANUFACTURER SAES STD DWG. SAMSS SA-175 FORM

SUBMITTED BY AL-KHODARI & SONS CO. REVIEW & APPROVAL BY ARAMCO APPROVAL & COMMENT

NAME

POSITION

SIGNATURE

DATE

1st SUBMISSION

Electrical Wires and Cables for Power and Lighting System 2nd SUBMISSION

PROJECT: UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT (NRTLR) - X57

CONTRACT No.: 6600018467 BI No. 10-03566

SUBMISSION STATUS

DATE:

DOCUMENT No.:

REVISION:

INSPECTION LEVEL

APPROVAL & COMMENT

1st SUBMISSION

2nd SUBMISSION

NMR FORM

REQUEST FOR MATERIAL APPROVAL SUBMISSION STATUS

AL-KHODARI & SONS CO. "BULK MATERIALS"

Electrical Consumables

DATE:

DOCUMENT No.:

MR No. REVISION:

S/N DESCRIPTION CCC No. 9 COM No. SUPPLIER MANUFACTURER SAES STD DWG. SAMSS SA-175 FORM

SUBMITTED BY AL-KHODARI & SONS CO. REVIEW & APPROVAL BY ARAMCO APPROVAL & COMMENT

NAME

POSITION

SIGNATURE

DATE

1st SUBMISSION

2nd SUBMISSION

PROJECT: UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT (NRTLR) - X57

CONTRACT No.: 6600018467 BI No. 10-03566

SUBMISSION STATUS

DATE:

DOCUMENT No.:

REVISION:

INSPECTION LEVEL

APPROVAL & COMMENT

1st SUBMISSION

2nd SUBMISSION

NMR FORM

REQUEST FOR MATERIAL APPROVAL SUBMISSION STATUS

AL-KHODARI & SONS CO. "BULK MATERIALS"

Electrical Hardwares

DATE:

DOCUMENT No.:

MR No. REVISION:

S/N DESCRIPTION CCC No. 9 COM No. SUPPLIER MANUFACTURER SAES STD DWG. SAMSS SA-175 FORM

SUBMITTED BY AL-KHODARI & SONS CO. REVIEW & APPROVAL BY ARAMCO APPROVAL & COMMENT

NAME

POSITION

SIGNATURE

DATE

1st SUBMISSION

2nd SUBMISSION

PROJECT: UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT (NRTLR) - X57

CONTRACT No.: 6600018467 BI No. 10-03566

SUBMISSION STATUS

DATE:

DOCUMENT No.:

REVISION:

INSPECTION LEVEL

APPROVAL & COMMENT

1st SUBMISSION

2nd SUBMISSION

NMR FORM

REQUEST FOR MATERIAL APPROVAL SUBMISSION STATUS

AL-KHODARI & SONS CO. "BULK MATERIALS"

Steel Conduits and Fittings

DATE:

DOCUMENT No.:

MR No. REVISION:

S/N DESCRIPTION CCC No. 9 COM No. SUPPLIER MANUFACTURER SAES STD DWG. SAMSS SA-175 FORM

SUBMITTED BY AL-KHODARI & SONS CO. REVIEW & APPROVAL BY ARAMCO APPROVAL & COMMENT

NAME

POSITION

SIGNATURE

DATE

1st SUBMISSION

2nd SUBMISSION

PROJECT: UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT (NRTLR) - X57

CONTRACT No.: 6600018467 BI No. 10-03566

SUBMISSION STATUS

DATE:

DOCUMENT No.:

REVISION:

APPROVAL & COMMENT

1st SUBMISSION

2nd SUBMISSION

NMR FORM

INSPECTION LEVEL

REQUEST FOR MATERIAL APPROVAL SUBMISSION STATUS

AL-KHODARI & SONS CO. "BULK MATERIALS"

Misc. Fasteners

DATE:

DOCUMENT No.:

MR No. REVISION:

S/N DESCRIPTION CCC No. 9 COM No. SUPPLIER MANUFACTURER SAES STD DWG. SAMSS SA-175 FORM

SUBMITTED BY AL-KHODARI & SONS CO. REVIEW & APPROVAL BY ARAMCO APPROVAL & COMMENT

NAME

POSITION

SIGNATURE

DATE

1st SUBMISSION

2nd SUBMISSION

PROJECT: UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT (NRTLR) - X57

CONTRACT No.: 6600018467 BI No. 10-03566

SUBMISSION STATUS

DATE:

DOCUMENT No.:

REVISION:

APPROVAL & COMMENT

1st SUBMISSION

2nd SUBMISSION

NMR FORM

INSPECTION LEVEL

AL-KHODARI & SONS CO.

PRE-COMMISSIONING CERTIFICATE

PLANT NO.: X56C0NTRACT NO.: 6600018467BI / JO NO.: BI-10-03566 / 0009

EQUIPMENT OILY WATER SUMP MOTOR X56-GM-0301 A/B

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

CONTRACTOR REPRESENTATIVE

SIGNATURE & DATE

SAPMT REPRESENTATIVE

SIGNATURE & DATE

SAPID REPRESENTATIVESIGNATURE & DATE

CRDD REPRESENTATIVESIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH TERMINAL UNIT

(NRTFF) – X56

AL-KHODARI & SONS CO.

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH TERMINAL UNIT

(NRTFF) – X56

AL-KHODARI & SONS CO.

PRE-COMMISSIONING CERTIFICATE

PLANT NO.: X57C0NTRACT NO.: 6600018467BI / JO NO.: BI-10-03566 / 0009

EQUIPMENT OILY WATER SUMP MOTOR X57-GM-0103 A/B

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

CONTRACTOR REPRESENTATIVE

SIGNATURE & DATE

SAPMT REPRESENTATIVE

SIGNATURE & DATE

SAPID REPRESENTATIVESIGNATURE & DATE

CRDD REPRESENTATIVESIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

AL-KHODARI & SONS CO.

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

OILY WATER SUMP MOTOR X56-GM-0301 A/B

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH

TERMINAL UNIT (NRTFF) – X56

PRE-COMMISSIONING PACKAGE

OILY WATER SUMP MOTOR X57-GM-0103 A/B

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK

PLANT (NRTLR) – X57

PRE-COMMISSIONING PACKAGE

TASK LIGHTINGS

SWITCHRACK X56-SB-SR-001

OILY WATER SUMP X56-D-0301

RICH GASOLINE / DIESEL TANK X56-D-0301

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH

TERMINAL UNIT (NRTFF) – X56

PRE-COMMISSIONING PACKAGE

AL-KHODARI & SONS CO.

PRE-COMMISSIONING CERTIFICATE

PLANT NO.: X56C0NTRACT NO.: 6600018467BI / JO NO.: BI-10-03566 / 0009

EQUIPMENT: TASK LIGHTINGS FOR THE FOLLOWING:SWITCHRACK X56-SB-SR-001,

OILY WATER SUMP X56-D-0301, &RICH GASOLINE / DIESEL TANK X56-D-0301

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

CONTRACTOR REPRESENTATIVE

SIGNATURE & DATE

SAPMT REPRESENTATIVESIGNATURE & DATE

SAPID REPRESENTATIVESIGNATURE & DATE

CRDD REPRESENTATIVESIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH TERMINAL UNIT

(NRTFF) – X56

AL-KHODARI & SONS CO.

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH TERMINAL UNIT

(NRTFF) – X56

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK

PLANT (NRTLR) – X57

PRE-COMMISSIONING PACKAGE

MOTOR STARTER UNITS 2H & 2L (@ X57-MCC-004) NEW SEWER PUMPS X57-G-0104 A/B

TASK LIGHTINGS

SWITCHRACK X57-SB-SR-001

OILY WATER SUMP X56-D-0103

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK

PLANT (NRTLR) – X57

PRE-COMMISSIONING PACKAGE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK

PLANT (NRTLR) – X57

PRE-COMMISSIONING PACKAGE

MBR MOTOR CONTROL CENTER (X57-SB-MCC-001)

AL-KHODARI & SONS CO.

PRE-COMMISSIONING CERTIFICATE

PLANT NO.: X57C0NTRACT NO.: 6600018467BI / JO NO.: BI-10-03566 / 0009

EQUIPMENT MBR MOTOR CONTROL CENTER (X57-SB-SR-001)

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

CONTRACTOR REPRESENTATIVE

SIGNATURE & DATE

SAPMT REPRESENTATIVESIGNATURE & DATE

SAPID REPRESENTATIVESIGNATURE & DATE

CRDD REPRESENTATIVESIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

AL-KHODARI & SONS CO.

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

(X57-U-0010-A/B)

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK

PLANT (NRTLR) – X57

PRE-COMMISSIONING PACKAGE

MBR 480V UNINTERRUPTIBLE POWER SUPPLY SYSTEM (UPS)

AL-KHODARI & SONS CO.

PRE-COMMISSIONING CERTIFICATE

PLANT NO.: X57C0NTRACT NO.: 6600018467BI / JO NO.: BI-10-03566 / 0009

EQUIPMENT MBR 480V UNINTERRUPTIBLE POWER SUPPLY SYSTEM (UPS)

(X57-U-0010-A/B)

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

CONTRACTOR REPRESENTATIVE

SIGNATURE & DATE

SAPMT REPRESENTATIVESIGNATURE & DATE

SAPID REPRESENTATIVESIGNATURE & DATE

CRDD REPRESENTATIVESIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

AL-KHODARI & SONS CO.

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

120V, 1-Phase Combination Starters

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK

PLANT (NRTLR) – X57

PRE-COMMISSIONING PACKAGE

AL-KHODARI & SONS CO.

PRE-COMMISSIONING CERTIFICATE

PLANT NO.: X57C0NTRACT NO.: 6600018467BI / JO NO.: BI-10-03566 / 0009

EQUIPMENT 120V, 1-PHASE COMBINATION STARTERS

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

CONTRACTOR REPRESENTATIVE

SIGNATURE & DATE

SAPMT REPRESENTATIVESIGNATURE & DATE

SAPID REPRESENTATIVESIGNATURE & DATE

CRDD REPRESENTATIVESIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

AL-KHODARI & SONS CO.

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK PLANT

(NRTLR) – X57

UPGRADE WASTE WATER SYSTEM @ NORTH RIYADH BULK

PLANT (NRTLR) – X57

PRE-COMMISSIONING PACKAGE

MBR 75KVA Dry-Type Transformer (X57-U-0010) & Distribution Panel Board

AL-KHODARI & SONS CO.

PRE- COMMISSIONING CERTIFICATE

PLANT NO.: X51CONTRACT NO.: 6600018467BI / JO NO.: BI-10-03566 / 0009

EQUIPMENT X51-GM-001 (HYDRAULIC POWER PACK)

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

CONTRACTOR REPRESENTATIVE

SIGNATURE & DATE

SAPMT REPRESENTATIVESIGNATURE & DATE

SAPID REPRESENTATIVESIGNATURE & DATE

CRDD REPRESENTATIVESIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ SOUTH RIYADH BULK PLANT

(SRBP)– X51

AL-KHODARI & SONS CO.

The above equipment is mechanically completed and all pre-commissioning checks have been carried out satisfactorily.

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

SIGNATURE & DATE

UPGRADE WASTE WATER SYSTEM @ SOUTH RIYADH BULK PLANT

(SRBP)– X51