Date post: | 20-Oct-2015 |
Category: |
Documents |
Upload: | enas-al-khawaldeh |
View: | 25 times |
Download: | 3 times |
Rock Classification for Tunnelling Projects
Ian McFeat SmithDirector IMS Tunnel Consultancy Ltd
Rock Classification for Tunnelling Projects
Special Design Issues for Tunnel Complexes and Rock Caverns
Rock Classification for the Selection of Tunnel Support Systems
Predicting Tunnel Boring Machine (TBM) Performance
Management and Prediction of Water Inflows
Tunnelling Costs and Programming
Risk Assessment
New Code of Practice for Tunnelling
Role of Rock Classification for Payment Purposes in Risk SharingContracts
Early Form of Rock Classification ?
The problem is mathematics is black and white but the real world is grey Albert Einstein
Site Investigation
Special Design Issues for Tunnel Complexes and Caverns
Rock Cavern for Tai Koo MTR Station
Impact of major joints / weathered seams on primary support system
Modification of lining design philosophy
Impact of incorrect on site rock classification on design and construction liability
Rock Classification for Selection of Tunnel Support Systems
NORWEIGN GEOTECHNICAL INSTITUTES (NGI) Q - SYSTEM
Q = RQD x Jr x JwJn Ja SRF
where RQD is the rock quality designationJn is the joint set numberJr represents the joint roughnessJa represents the joint alterationJw is a joint water reduction factorSRF is a stress reduction factor
Further RQD represents rock block sizeJn
Jr represents joint shear strengthJa
And Jw represents active stressSRF
Selection of Temporary Supports using Q system
Construction of twin 16 18m span tunnels for Eagles Nest Tunnels (Current)
Key Issues for Classification of Rock Masses in Tunnelling
1) Variability of geology /temp supports 2) 3D - RQD assessment? 3) Proportion of blast fractures?
CSIR GEOMECHANICS CLASSIFICATION OF JOINTED ROCK MASSES
System involves measurement, selection of a rating and addition of these for each of the following rock mass parameters:
INTACT STRENGTH OF ROCK RQD % SPACING OF JOINTS m CONDITION OF JOINTS GROUND WATER
RATING ADJUSTMENT FOR ADVERSE JOINT ORIENTATIONS
From the overall rating the following is provided:
AVERAGE STAND UP TIME COHESION OF ROCK MASS ANGLE OF FRICTION
Description of IMS Rock Classes
IMS DescriptionRock Class
1 Massive competent rock mass2 Favourable rock mass3 Moderately fractured / weathered rock4 Highly fractured or weathered 5A Fault zones 5B Fault gouge / soils
Application of IMS rock classes for preliminary design of Sha Tin Heights tunnel
Rock Classification for Estimating Tunnel Boring Machine (TBM) Performance
Hong Kongs first TBM project - Open type hard rock Tunnel Boring Machine (TBM)
Hong Kongs first TBM projects cable tunnel and double shielded TBM for Tolo Tunnel
Hard rock earth pressure balance TBM for tunnelling in mixed face conditions
TBM excavated tunnel no effective overbreak and no support required
Comparison of support requirements for drill and blast and TBM excavated cable tunnels
Use of IMS rock classification for estimating overbreak for different methods of tunnelling
Management and Prediction of Water Inflows in Rock Tunnelling
Water Inflow Issues for Tai Po to Butterfly Valley Aqueducts
Cumulative water inflows experienced in aqueduct
Tai Po to Butterfly Valley Large Disseminated Inflows in TBM Drives
Large inflows through individual open joints and shear zones
Tai Po to Butterfly Aqueduct water inflow at full hydrostatic head (700m)
SSDS subaqueous tunnels. Large inflows at full hydrostatic head below urban areas
Site measurement of Water Reduction Factor R with time.
PREDICTION OF WATER INFLOWS INTO ROCK TUNNELS IN HONG KONG
METHOD OF PREDICTING INFLOW REDUCTION
FACTOR (R)
Water Source Head Factor (Hf) Horizontal Separation (df)
Size Factor (Sf) Head m/100 (m) Separation df dmm= 1 400
Source Sea
Sf 1.0
Head m
Hf 0 1.0
Major Valley/ Reservoir
0.85 >100 1.0 50 0.65
Large Valley/ Reservoir
0.7 100 1.0 100 0.5
Small River/ Reservoir
0.5 80 0.8 200 0.29
Stream 0.3 50 0.5 300 0.13 Ridge 0.1 20 0.2 400 0
For d = 0 to 400m only Notes : R = Sf x Hf x df with R being dimensionless.
PREDICTION OF WATER INFLOWS INTO ROCK TUNNELS IN HONG KONG
Prediction of Initial (Ii) and Final Inflows (Fi)
Ii = R.IF & Fi = R2IF
IF VALUES FOR IMS ROCK CLASSES (l/min/m)
IMS Rock Class 1 2 3 4 5 IF values
High 0.6 1.4 12.2 37 3.8
l/min/m
Average
0.45 1.05 6.55 24 3.1
Low 0.3 0.7 0.9 11 2.4
GUIDE TO GROUND TREATMENT FOR PRE-GROUTING OF ROCK TUNNELS
Rock mass classification
IMS Rock Class
Grouting required Grout material
1. JOINTED ROCK 1.1 Massive, no joints 1 No grouting N/A 1.2 Very few joints;
< 0.1 joints/m 1 Spot or targeted grouting MFC, if
joints >0.5mm; OPC
1.3 Few joints; < 1 joints/m, 2 joint sets
2 Limited to continuous MFC
1.4 Jointed rock; 2 joint sets
3 Continuous MFC
1.5 Very jointed rock; 10 joints/m
4-5A Continuous, closer spacing, in stages
MFC, UFC
2. FAULT ZONES 2.1 Zones with clay 5A-5B Displace, wash out/replace,
compact OPC, MFC
2.2 Silty zones 5A-5B Penetrate, very close spacing, in stages
UFC, Chemical
2.2 Sandy zones 5A-5B Penetrate, close spacing, in stages
MFC, UFC
2.3 Gravel zones or sugar cube rock
5A-5B Penetrate, quick set, in stages OPC, MFC
2.5 Mixed material 5A-5B Penetrate, displace, compact, replace, in stages, close spacing
OPC, MFC, UFC, Chemical
3. REGIONAL STRUCTURAL ZONE
Depends of size of zone and composition. Often a combination of 1.5 and 2.5 above.
Tunnelling Costs and Programming
Risks for Tunnelling
Risks - rockhead Issues Key risks 1. Defining rockhead? - 5m CDG below 12mof
competent rock; 2. tunnelling close below rockhead in urban areas
Collapse of HK MTR Island Line Tunnels in Hennessy Road,1983
Island Line TunnelsKey Risks Rock tunnelling (blasting) in urban areas with low
rockhead cover ; blast vibrations restrictions ; damage to third parties
Athens Metro: Collapses of TBM Tunnels to Street Level
Key Risk - lack of geological risk management plan
Hong Kong MTR large boulders in soft ground
Singapore and Hong Kong Key Risk: Failure of Earth Pressure Balance System for tunnelling
in extreme mixed face conditions; risk to third party property
PUBLIC LIABILITY ISSUES
EPB EPB
EPB EPB
EPB EPB
EPB
EPB
EPB
EPB
MEDIUM PRESSURE
EPBMEDIUM
PRESSURE EPB
MEDIUM PRESSURE
EPB
MEDIUM PRESSURE
EPB
LOW PRESSURE
EPB
LOW PRESSURE
EPB
LOW PRESS EPB
OPEN OPEN
OPENOPEN
LOW PRESSURE
EPB
20 40 60 80 100 SPT
CLAY
SILT
SAND
GRAVEL
Slurry or Special Measures
Slurry or Special Measures
SLURRY
SLURRY
SLURRYSLURRY
SLURRY
Special Measures
SOIL DENSITY
FILLALLUVIUM
MARINE SAND COMPLETELY WEATHERED GRANITES
SOFT / LOOSEVERY FIRM VERY STIFF
IMS Method of Selecting Face Controlfor Soft Ground TBMs
New Joint Code of Practice for Tunnels British Tunnelling Society The Association of British Insurers
New Code of Practice for Tunnels
Client responsible for sufficiency of site investigations
Geotechnical data forms part of contract
Geotechnical baseline conditions i.e. rock classification, to bedrawn up by Client or Tenderer
Geotechnical baseline conditions and used for assessing unexpected geological conditions
Risk assessment and management at all stages of development of project
Continuous tracking and mitigation of risks through risk register
Insurance cover may be suspended or cancelled in event of a breach of code requirements
Risk Levels and Action Plans
Mitigation to be undertaken as resources permit.
R4
Mitigation should be completed before works begin.
R3
Work shall not begin until mitigation implementation has been completed and verified.Mitigation should reduce risk to R3 Level
R2
Work shall not begin until mitigation implementation has been completed and verified. Mitigation of risk of high priority and risk must be reduced significantly or alternative methods adopted.
R1
Action and TimescaleRisk Level
The IMS Risk Evaluation System
Key Risk Categories
quality, level of detail and contributionPROGRAMME A delay risk as a percentage of overall programmePROGRAMME B
commercial risk as a percentage of cost of worksCOMMERCIAL B cost of project relative to available funds and previous worksCOMMERCIAL A quality of contract documents, partnering and risk sharingCONTRACT management systems and site cultureMANAGEMENT for type and scale of works and by contractorPRECEDENCE/ EXPERIENCE ground control requirements, support, and excavation difficultyTUNNELLING METHODS
including layout, number of working faces, interfaces, ease of access, and spoil disposal
COMPLEXITY OF WORKS
robustness of design, quality of specifications and implementation
DESIGN & SPECIFICATION
predictability, achievability of watertightness specification and likely impact
WATER ISSUES classification and variability of conditionsGROUND CONDITIONS adequacy and qualitySITE INVESTIGATION
proximity to tunnels of adjacent man-made structures and other constraints
CONSTRAINTS type of terrain and coverTERRAIN
Score Forms IV Ground Conditions
1Highly consistent4Consistent generally easy to predict9Intermediate moderate risk
16Highly variable high risk
25Major variations / impossible to predict accurately6 Variability
1No risk e.g. competent rock tunnel
4Low risk e.g. consistent soft ground or moderate rock
9Intermediate e.g. soft ground or variable rock moderate risk
16Poor e.g. soft ground with boulders / low rockhead cover
25Very poor e.g. IMS Rock Class 5B, extreme mixed ground; rockhead at tunnel crown; regions of high seismicity; very high in situ stresses
5 Ground Mass Characterisation
(rock and soft ground tunnels to be classified using IMS rock or soil classes)
ScoreRisk EvaluationRisk Type
Score Forms V Water Issues
1No Impact Expected4Low Risk9Intermediate Moderate Risk16High Impact Anticipated25Extreme Risk Major Impact9 Likely Impact of
Inflows in terms of Ground Movements, Disposal, Tunnel Instability
1Very Easy to Achieve4Low Risk 9Intermediate Moderate Risk16Difficult to Achieve25Very Unlikely to be Achieved8 Watertightness
Specifications
1Consistent or low flows Likely4Small risk 9Intermediate Moderate risk16Difficult variable inflows25No local precedence much uncertainty creating very high risk7 Predictability of
Inflows
ScoreRisk EvaluationRisk Type
Score Forms XI Contract
1Client assumes all risks4Risks are allocated to party most able to manage them9Equal client specified distribution of risks
16Risk sharing occurs but biased in favour of the Client25All risks are transferred to the Contractor27 Risk Sharing1Client participates in partnering and encourages broad involvement4Client actively involved in partnering but lacking experience.9Client passively involved in partnering but lacking experience.
16Parties accept partnering in principle but reluctant strict focus on contract rather than problem solving
25Partnering is not allowed strict pursuit of contract conditions. 26 Partnering
(general attitude towards mutual co-operation)
1Excellent Quality, Well structured, Clear and Easy to Implement4Good standard 9Just Sufficient Moderate Risk
16Poor Quality Many Ambiguities25Very Poor, Inappropriate for Job, Allocation of Risks Unclear25 Quality of
Contract Documents
ScoreRisk EvaluationRisk Type
Re-measurement Risk Sharing Forms of Contract
Tunnel for Tolo Effluent Export Scheme HK Governments first TBM project - 7.5 km long tunnel
completed within budget and 6 months ahead of programme; using double shielded TBM
Re-measurement Risk Sharing Contract for Tolo Tunnel:
Only major risk sharing contract used for tunnelling in HK to date. Payment for geological conditions made on re-measurement of IMS rock classes
Re-measurement Risk Sharing Contract for Tolo Tunnel:
Actual Limit to Governments Risk
The Present System
Rock Classification for Tunnelling Projects
Special Design Issues for Tunnel Complexes and Rock Caverns
Rock Classification for the Selection of Tunnel Support Systems
Prediction of Tunnel Boring Machine (TBM) Performance
Prediction and Management of Water Inflows
Tunnelling Costs and Programming
Risk Assessment
New Code of Practice for Tunnelling
Role of Rock Classification for Payment Purposes in Risk SharingContracts