+ All Categories
Home > Documents > Copy of Rock Mechanics Lecture Short Version Rev1 [Read-Only]

Copy of Rock Mechanics Lecture Short Version Rev1 [Read-Only]

Date post: 20-Oct-2015
Category:
Upload: enas-al-khawaldeh
View: 25 times
Download: 3 times
Share this document with a friend
Description:
Notes
Popular Tags:
64
Rock Classification for Tunnelling Projects Ian McFeat – Smith Director IMS Tunnel Consultancy Ltd
Transcript
  • Rock Classification for Tunnelling Projects

    Ian McFeat SmithDirector IMS Tunnel Consultancy Ltd

  • Rock Classification for Tunnelling Projects

    Special Design Issues for Tunnel Complexes and Rock Caverns

    Rock Classification for the Selection of Tunnel Support Systems

    Predicting Tunnel Boring Machine (TBM) Performance

    Management and Prediction of Water Inflows

    Tunnelling Costs and Programming

    Risk Assessment

    New Code of Practice for Tunnelling

    Role of Rock Classification for Payment Purposes in Risk SharingContracts

  • Early Form of Rock Classification ?

  • The problem is mathematics is black and white but the real world is grey Albert Einstein

  • Site Investigation

  • Special Design Issues for Tunnel Complexes and Caverns

  • Rock Cavern for Tai Koo MTR Station

  • Impact of major joints / weathered seams on primary support system

  • Modification of lining design philosophy

  • Impact of incorrect on site rock classification on design and construction liability

  • Rock Classification for Selection of Tunnel Support Systems

  • NORWEIGN GEOTECHNICAL INSTITUTES (NGI) Q - SYSTEM

    Q = RQD x Jr x JwJn Ja SRF

    where RQD is the rock quality designationJn is the joint set numberJr represents the joint roughnessJa represents the joint alterationJw is a joint water reduction factorSRF is a stress reduction factor

    Further RQD represents rock block sizeJn

    Jr represents joint shear strengthJa

    And Jw represents active stressSRF

  • Selection of Temporary Supports using Q system

  • Construction of twin 16 18m span tunnels for Eagles Nest Tunnels (Current)

  • Key Issues for Classification of Rock Masses in Tunnelling

    1) Variability of geology /temp supports 2) 3D - RQD assessment? 3) Proportion of blast fractures?

  • CSIR GEOMECHANICS CLASSIFICATION OF JOINTED ROCK MASSES

    System involves measurement, selection of a rating and addition of these for each of the following rock mass parameters:

    INTACT STRENGTH OF ROCK RQD % SPACING OF JOINTS m CONDITION OF JOINTS GROUND WATER

    RATING ADJUSTMENT FOR ADVERSE JOINT ORIENTATIONS

    From the overall rating the following is provided:

    AVERAGE STAND UP TIME COHESION OF ROCK MASS ANGLE OF FRICTION

  • Description of IMS Rock Classes

    IMS DescriptionRock Class

    1 Massive competent rock mass2 Favourable rock mass3 Moderately fractured / weathered rock4 Highly fractured or weathered 5A Fault zones 5B Fault gouge / soils

  • Application of IMS rock classes for preliminary design of Sha Tin Heights tunnel

  • Rock Classification for Estimating Tunnel Boring Machine (TBM) Performance

  • Hong Kongs first TBM project - Open type hard rock Tunnel Boring Machine (TBM)

  • Hong Kongs first TBM projects cable tunnel and double shielded TBM for Tolo Tunnel

  • Hard rock earth pressure balance TBM for tunnelling in mixed face conditions

  • TBM excavated tunnel no effective overbreak and no support required

  • Comparison of support requirements for drill and blast and TBM excavated cable tunnels

  • Use of IMS rock classification for estimating overbreak for different methods of tunnelling

  • Management and Prediction of Water Inflows in Rock Tunnelling

  • Water Inflow Issues for Tai Po to Butterfly Valley Aqueducts

  • Cumulative water inflows experienced in aqueduct

  • Tai Po to Butterfly Valley Large Disseminated Inflows in TBM Drives

  • Large inflows through individual open joints and shear zones

  • Tai Po to Butterfly Aqueduct water inflow at full hydrostatic head (700m)

  • SSDS subaqueous tunnels. Large inflows at full hydrostatic head below urban areas

  • Site measurement of Water Reduction Factor R with time.

  • PREDICTION OF WATER INFLOWS INTO ROCK TUNNELS IN HONG KONG

    METHOD OF PREDICTING INFLOW REDUCTION

    FACTOR (R)

    Water Source Head Factor (Hf) Horizontal Separation (df)

    Size Factor (Sf) Head m/100 (m) Separation df dmm= 1 400

    Source Sea

    Sf 1.0

    Head m

    Hf 0 1.0

    Major Valley/ Reservoir

    0.85 >100 1.0 50 0.65

    Large Valley/ Reservoir

    0.7 100 1.0 100 0.5

    Small River/ Reservoir

    0.5 80 0.8 200 0.29

    Stream 0.3 50 0.5 300 0.13 Ridge 0.1 20 0.2 400 0

    For d = 0 to 400m only Notes : R = Sf x Hf x df with R being dimensionless.

  • PREDICTION OF WATER INFLOWS INTO ROCK TUNNELS IN HONG KONG

    Prediction of Initial (Ii) and Final Inflows (Fi)

    Ii = R.IF & Fi = R2IF

    IF VALUES FOR IMS ROCK CLASSES (l/min/m)

    IMS Rock Class 1 2 3 4 5 IF values

    High 0.6 1.4 12.2 37 3.8

    l/min/m

    Average

    0.45 1.05 6.55 24 3.1

    Low 0.3 0.7 0.9 11 2.4

  • GUIDE TO GROUND TREATMENT FOR PRE-GROUTING OF ROCK TUNNELS

    Rock mass classification

    IMS Rock Class

    Grouting required Grout material

    1. JOINTED ROCK 1.1 Massive, no joints 1 No grouting N/A 1.2 Very few joints;

    < 0.1 joints/m 1 Spot or targeted grouting MFC, if

    joints >0.5mm; OPC

    1.3 Few joints; < 1 joints/m, 2 joint sets

    2 Limited to continuous MFC

    1.4 Jointed rock; 2 joint sets

    3 Continuous MFC

    1.5 Very jointed rock; 10 joints/m

    4-5A Continuous, closer spacing, in stages

    MFC, UFC

    2. FAULT ZONES 2.1 Zones with clay 5A-5B Displace, wash out/replace,

    compact OPC, MFC

    2.2 Silty zones 5A-5B Penetrate, very close spacing, in stages

    UFC, Chemical

    2.2 Sandy zones 5A-5B Penetrate, close spacing, in stages

    MFC, UFC

    2.3 Gravel zones or sugar cube rock

    5A-5B Penetrate, quick set, in stages OPC, MFC

    2.5 Mixed material 5A-5B Penetrate, displace, compact, replace, in stages, close spacing

    OPC, MFC, UFC, Chemical

    3. REGIONAL STRUCTURAL ZONE

    Depends of size of zone and composition. Often a combination of 1.5 and 2.5 above.

  • Tunnelling Costs and Programming

  • Risks for Tunnelling

  • Risks - rockhead Issues Key risks 1. Defining rockhead? - 5m CDG below 12mof

    competent rock; 2. tunnelling close below rockhead in urban areas

  • Collapse of HK MTR Island Line Tunnels in Hennessy Road,1983

  • Island Line TunnelsKey Risks Rock tunnelling (blasting) in urban areas with low

    rockhead cover ; blast vibrations restrictions ; damage to third parties

  • Athens Metro: Collapses of TBM Tunnels to Street Level

    Key Risk - lack of geological risk management plan

  • Hong Kong MTR large boulders in soft ground

  • Singapore and Hong Kong Key Risk: Failure of Earth Pressure Balance System for tunnelling

    in extreme mixed face conditions; risk to third party property

  • PUBLIC LIABILITY ISSUES

  • EPB EPB

    EPB EPB

    EPB EPB

    EPB

    EPB

    EPB

    EPB

    MEDIUM PRESSURE

    EPBMEDIUM

    PRESSURE EPB

    MEDIUM PRESSURE

    EPB

    MEDIUM PRESSURE

    EPB

    LOW PRESSURE

    EPB

    LOW PRESSURE

    EPB

    LOW PRESS EPB

    OPEN OPEN

    OPENOPEN

    LOW PRESSURE

    EPB

    20 40 60 80 100 SPT

    CLAY

    SILT

    SAND

    GRAVEL

    Slurry or Special Measures

    Slurry or Special Measures

    SLURRY

    SLURRY

    SLURRYSLURRY

    SLURRY

    Special Measures

    SOIL DENSITY

    FILLALLUVIUM

    MARINE SAND COMPLETELY WEATHERED GRANITES

    SOFT / LOOSEVERY FIRM VERY STIFF

    IMS Method of Selecting Face Controlfor Soft Ground TBMs

  • New Joint Code of Practice for Tunnels British Tunnelling Society The Association of British Insurers

  • New Code of Practice for Tunnels

    Client responsible for sufficiency of site investigations

    Geotechnical data forms part of contract

    Geotechnical baseline conditions i.e. rock classification, to bedrawn up by Client or Tenderer

    Geotechnical baseline conditions and used for assessing unexpected geological conditions

    Risk assessment and management at all stages of development of project

    Continuous tracking and mitigation of risks through risk register

    Insurance cover may be suspended or cancelled in event of a breach of code requirements

  • Risk Levels and Action Plans

    Mitigation to be undertaken as resources permit.

    R4

    Mitigation should be completed before works begin.

    R3

    Work shall not begin until mitigation implementation has been completed and verified.Mitigation should reduce risk to R3 Level

    R2

    Work shall not begin until mitigation implementation has been completed and verified. Mitigation of risk of high priority and risk must be reduced significantly or alternative methods adopted.

    R1

    Action and TimescaleRisk Level

  • The IMS Risk Evaluation System

  • Key Risk Categories

    quality, level of detail and contributionPROGRAMME A delay risk as a percentage of overall programmePROGRAMME B

    commercial risk as a percentage of cost of worksCOMMERCIAL B cost of project relative to available funds and previous worksCOMMERCIAL A quality of contract documents, partnering and risk sharingCONTRACT management systems and site cultureMANAGEMENT for type and scale of works and by contractorPRECEDENCE/ EXPERIENCE ground control requirements, support, and excavation difficultyTUNNELLING METHODS

    including layout, number of working faces, interfaces, ease of access, and spoil disposal

    COMPLEXITY OF WORKS

    robustness of design, quality of specifications and implementation

    DESIGN & SPECIFICATION

    predictability, achievability of watertightness specification and likely impact

    WATER ISSUES classification and variability of conditionsGROUND CONDITIONS adequacy and qualitySITE INVESTIGATION

    proximity to tunnels of adjacent man-made structures and other constraints

    CONSTRAINTS type of terrain and coverTERRAIN

  • Score Forms IV Ground Conditions

    1Highly consistent4Consistent generally easy to predict9Intermediate moderate risk

    16Highly variable high risk

    25Major variations / impossible to predict accurately6 Variability

    1No risk e.g. competent rock tunnel

    4Low risk e.g. consistent soft ground or moderate rock

    9Intermediate e.g. soft ground or variable rock moderate risk

    16Poor e.g. soft ground with boulders / low rockhead cover

    25Very poor e.g. IMS Rock Class 5B, extreme mixed ground; rockhead at tunnel crown; regions of high seismicity; very high in situ stresses

    5 Ground Mass Characterisation

    (rock and soft ground tunnels to be classified using IMS rock or soil classes)

    ScoreRisk EvaluationRisk Type

  • Score Forms V Water Issues

    1No Impact Expected4Low Risk9Intermediate Moderate Risk16High Impact Anticipated25Extreme Risk Major Impact9 Likely Impact of

    Inflows in terms of Ground Movements, Disposal, Tunnel Instability

    1Very Easy to Achieve4Low Risk 9Intermediate Moderate Risk16Difficult to Achieve25Very Unlikely to be Achieved8 Watertightness

    Specifications

    1Consistent or low flows Likely4Small risk 9Intermediate Moderate risk16Difficult variable inflows25No local precedence much uncertainty creating very high risk7 Predictability of

    Inflows

    ScoreRisk EvaluationRisk Type

  • Score Forms XI Contract

    1Client assumes all risks4Risks are allocated to party most able to manage them9Equal client specified distribution of risks

    16Risk sharing occurs but biased in favour of the Client25All risks are transferred to the Contractor27 Risk Sharing1Client participates in partnering and encourages broad involvement4Client actively involved in partnering but lacking experience.9Client passively involved in partnering but lacking experience.

    16Parties accept partnering in principle but reluctant strict focus on contract rather than problem solving

    25Partnering is not allowed strict pursuit of contract conditions. 26 Partnering

    (general attitude towards mutual co-operation)

    1Excellent Quality, Well structured, Clear and Easy to Implement4Good standard 9Just Sufficient Moderate Risk

    16Poor Quality Many Ambiguities25Very Poor, Inappropriate for Job, Allocation of Risks Unclear25 Quality of

    Contract Documents

    ScoreRisk EvaluationRisk Type

  • Re-measurement Risk Sharing Forms of Contract

  • Tunnel for Tolo Effluent Export Scheme HK Governments first TBM project - 7.5 km long tunnel

    completed within budget and 6 months ahead of programme; using double shielded TBM

  • Re-measurement Risk Sharing Contract for Tolo Tunnel:

    Only major risk sharing contract used for tunnelling in HK to date. Payment for geological conditions made on re-measurement of IMS rock classes

  • Re-measurement Risk Sharing Contract for Tolo Tunnel:

    Actual Limit to Governments Risk

  • The Present System

  • Rock Classification for Tunnelling Projects

    Special Design Issues for Tunnel Complexes and Rock Caverns

    Rock Classification for the Selection of Tunnel Support Systems

    Prediction of Tunnel Boring Machine (TBM) Performance

    Prediction and Management of Water Inflows

    Tunnelling Costs and Programming

    Risk Assessment

    New Code of Practice for Tunnelling

    Role of Rock Classification for Payment Purposes in Risk SharingContracts


Recommended